Transformer
Transformer
July, 2012
This goal for this month’s paper is to provide a basic understanding of tests
performed on each liquid filled transformer. The following standards detail the
general construction requirements as well as the specific tests which the transformer
must be subjected to.
These standards define “routine” tests that are performed on all transformers as well
as “type” tests which are performed on each unique design.
Routine tests:
1. Winding Resistance
2. Ratio, Polarity and Phase Relation
3. Core Loss and Exciting Current
4. Load Loss and Impedance
5. Induced Potential
6. Applied Potential (Hi-Pot)
7. Production Line Impulse Test
8. Insulation Resistance
9. Insulation Power Factor
10. Leak (pressure) Test
Type Tests:
1. Full ANSI impulse Voltage Test
2. Temperature rise test
3. Short Circuit Test
Type tests are performed on new designs and are required to insure that the
general design parameters are sufficient to insure reliable service. Pacific Crest
Pacific Crest Transformers
300 West Antelope Road – Medford, Oregon 97503
Tel : (541) 826 – 2113 Fax : (541) 826 - 8847
Transformers performs ANSI impulse and temperature rise tests in house while short
circuit tests are performed by an independent test laboratory.
2
The first 6 routine tests listed above are those typically performed as customer
“Factory witness tests”. Following is a brief description of each as well as the PCT
pass criteria.
SETUP: A digital Wheatstone or Kelvin bridge is used to apply a very low DC current
to each of the HV and LV windings which returns the result in ohms. The low current
is necessary to insure against heating of the windings which would lead to false
readings due to an increase in resistance.
PASS CRITERIA:
The variation in resistance measurements between phases of the same winding shall
not exceed the limits specified by the transformer manufacturer.
PURPOSE: To verify the voltage ratio of each coil in the transformer under test by
checking the turns ratio of the HV and LV windings and (2) to verify that the
windings are connected correctly to provide the specified primary to secondary
vector relationship.
SETUP: A ratiometer is used to perform this test. This equipment connects to each
phase of the HV and LV winding and via the application of a very low voltage
determines the ratio of the high voltage windings to the low voltage windings. These
values are compared to those supplied from Engineering.
3
PASS CRITERIA:
Ratio: Compute ratio tolerances from nominal transformer rated voltages.
Maximum tolerances from calculated ratio = ±0.5%.
Vector Relationship: A correct ratio will verify the desired vector relationship,
or polarity. A test that yields no ratio at all or one that is far different than the
calculated ratio may indicate a connection problem in the transformer under
test.
Note: A large difference between exciting current readings while ratioing
different coils of a transformer may indicate a problem such as a turn-to-turn
short.
PURPOSE: To measure no load loss (core loss) and excitation current, and verify that
these values are within acceptable tolerance of the calculated values. This will
confirm that the core design (i.e. cross-sectional area and lamination thickness) is
adequate to handle the required flux density, and that the cores were properly
assembled.
PASS CRITERIA:
Core loss shall not exceed design value by more than 10%.
Maximum excitation current:
wound core 2%
stacked core 5%
4
If tested core loss exceeds maximum allowance, another test shall be made at 110%
of rated secondary voltage, and the resulting data shall be submitted to a design
engineer for review.
PURPOSE: To determine, by test and calculation, load losses and total losses of a
transformer under test. Also, to determine the impedance voltage of the
transformer, expressed as a percentage of the rated primary voltage, from which
may be calculated the winding currents under short circuit conditions. The losses
obtained from this test combined with the core loss data validates if the transformer
tank and radiators are sufficient to allow for proper cooling.
SETUP: The LV terminals are shorted together. The HV terminals are connected to a
variable AC voltage source. Voltage is than applied to the HV and increased until
such time that rated current is reached. The voltage and wattage is recorded and
compared to data supplied by Engineering.
5
PASS CRITERIA:
Tested total losses shall not exceed design losses by more than 6%. The limits of
tested impedance are ±7.5% of specified impedance. Losses or impedance values
that exceed limits should be submitted to engineering for review.
PURPOSE: To verify coil and lead insulation levels by inducing the transformer
under test to twice its rated voltage at high frequency for 7200 cycles. This test
verifies turn to turn and layer to layer insulation, as well as lead to lead insulation
within the high voltage and low voltage lead assemblies.
SETUP: This test is performed using a high frequency generator (180 HZ). Since
frequency and inductive reactance are inversely proportional, the double voltage
required for this test is made possible because the core does not saturate.
PASS CRITERIA:
There should be no collapse or pull down of the test voltage. Smoke and bubbles
from coils or lead assemblies may also indicate an insulation failure.
SETUP: During this test, each winding is shorted out by connecting its bushings
together. The ANSI specified voltage is then applied to the winding under test with
the other windings connected to ground. No voltage is induced in the winding under
test or magnetic flux induced in the core; hence the insulation between turns or
between layers in the winding under test is not stressed.
6
PASS CRITERIA:
Failure of a winding is indicated by loss of test voltage and/or test set circuit breaker
tripping. Failure can also be indicated by smoke and bubbles from coils or lead
assemblies, or by an audible thump from inside the tank.
Tests 7 through 10 as listed above are not normally witnessed (for various reasons),
but test data is available upon request at the time of the Factory Witness Test.
SETUP: The transformer under test is connected to the impulse generator. Each
phase of each winding (HV and LV) is subjected to a voltage level dependent on the
BIL (basic insulation level) of the winding under test. The impulse generator is made
up of a number of capacitors that are charged in parallel to a level that when
discharged in series will combine to achieve the required test voltage. The image of
the voltage surge through each winding is captured on an oscilloscope.
PASS CRITERIA:
There should be no significant differences between voltage traces, displayed on the
oscilloscope, from any HV bushing. Particular attention should be paid to the wave
shape and voltage decay rate after the peak voltage of each voltage trace. Failure
may also be indicated by an audible thump from the transformer tank, or by smoke
and bubbles from coils or lead assemblies.
7
8. Insulation resistance
(“Megger”)
PURPOSE: Insulation resistance tests are made to determine the insulation resistance
from individual windings to ground or between individual windings. This test will
determine the condition of the insulation and that proper internal clearances have
been met and maintained. This test is performed as a routine test on 501kVA and
larger transformers.
PASS CRITERIA:
Insulation resistance measurements shall not be less than the minimum limits
specified by the transformer manufacturer.
The ratio of power dissipated in the insulation in watts to the product of the
effective voltage and current in volt-amperes when tested with a sinusoidal voltage.
This test is used to give an indication of the condition (dryness) of the transformer
8
insulation. There are no established limits for acceptable power factor readings in
the transformer standards. A power factor value of 1.0% or less for distribution
transformers is generally used as an acceptable value.
PASS CRITERIA:
UNIT HAS PASSED if no leaks are found and pressure remains constant (or does not
drop more than expected with consideration of temperature differences) after a
minimum of twelve (12) continuous hours under pressure.
UNIT HAS FAILED if a leak is found or if the pressure drops more than expected.
If leaks are detected, repair the transformer as needed. If the pressure drops more
than expected, investigate tank seams, handholes, cover mounted bushings, etc., to
determine where the leak is located and repair the transformer as needed.