Collection of Exam Questions
Collection of Exam Questions
J.D. Jansen
E-mail: [email protected]
Contents
NOTE ......................................................................................................................... 1
QUESTIONS .............................................................................................................. 1
13 August 2014 ...................................................................................................................................... 1
Note
These worked exam questions have been taken from exams given in the period 2001-2014.
During these years the contents of the course have gradually changed, and some topics have
been added or removed. Furthermore, some of the notation has changed over the years.
Therefore, old exam questions taken from other sources may lead to confusion and are not
recommended as exercise material.
Questions
13 August 2014
1. Mixed questions:
1.a) In a horizontal well draining a homogeneous reservoir, where do you expect water
coning to occur first, at the toe or at the heel? Why? (½ point)
1.b) The hydraulic head capacity of a centrifugal pump is not influenced by the density
of the liquid. So, why does its power consumption increase with increasing liquid
density (for a given flow rate)? (½ point)
1.c) Why is the water FVF, at a given pressure, increasing with increasing temperatures?
(½ point)
1.d) What are the dimensions of the liquid viscosity number N ? (½ point)
1.e) Why is the slope of the IPR for a gas well near-vertical at atmospheric pressure? (½
point)
1.f) Describe a simple test to check the accuracy of a pressure drop calculation in any
commercial nodal analysis package. Does passing the test imply that the program is
accurate? (½ point)
2. Consider an oil well completed with a 4” tubing producing according to profile A given in
Table 1 below. The reservoir pressure decline is identical for the two cases.
2.a) Profile B corresponds to completing the well with a 3” tubing. Why would profile A
lead to a higher production rate early-on, while profile B leads to a higher
production rate later during the life of the well? Explain your answer with a
schematic nodal analysis plot. (1 point)
2.b) Changing-out the tubing after year 3 costs 2 million $ (discounted). Is this an
economically attractive option at a discount rate of 15% and an oil price of
105 $/bbl. (Start discounting production from year one at the end of year one). What
is the corresponding NPV? (1 point)
3. Multiphase flow:
3.a) Which factors determine the flow regime in a pipe or oil well with multiphase
(gas/oil) flow? (½ point)
3.b) What is the effect of gas slip on upward vertical multiphase flow? What are the
causes of slip? (½ point)
3.c) Calculate the pressure drop per unit length (in SI units) in a vertical oil well with
zero water cut using the Hagedorn and Brown correlation. Consider two cases: with
and without slip. (1 point)
Data:
qo 0.7 ft 3 /s, qg 2.8 ft 3 /s,
d 5 in, e 30 m,
f w 0, o 7 cp, g = 0.01 cp,
o 890 kg/m3 , g 3.7 kg/m3 ,
H g 0.73 (in case of slip),
p 0.5 106 Pa.
2 July 2014
4. Mixed questions
1.a) What is the most important similarity and what is the most important difference
between the volatile oil and black oil models? (½ point)
1.b) What is the difference between the pseudo-reduced and the pseudo-critical
temperature of a hydrocarbon gas mixture? (½ point)
1.c) What are the most important pressure drop mechanisms in a) the near well bore, b)
the converging part of a choke, c) a horizontal gas well, and d) a vertical water
injection well? (½ point)
1.d) Describe two mechanisms that can cause the gas phase in a well to travel faster (on
average) than the oil phase? (½ point)
1.e) Why are lift performance curves of an ESP expressed in terms of head instead of
pressure? (½ point)
1.f) Why is it not possible to distinguish between stable and unstable operation points in
the nodal analysis of a production system based on steady-state equations? (½ point)
5. Consider a dry gas well in a reservoir that can be represented as a circular reservoir
producing under semi-steady state conditions with properties listed in Table 1. Compute
the (approximate) well flow rate at standard conditions if the bottom hole pressure is
lowered to 130 bar. (1 point)
6. Consider a vertical black oil well with properties given in Table 2. All properties
correspond to a depth of 500 ft., except for qg,sc, Rgo, fw, g,sc and o,sc which correspond
to standard conditions.
pfl
pmf ptf
pwf pR
Figure 1: System elements: near-wellbore, well bore, choke and flow line.
6
x 10
3
p - 20 MPa
wf
p
2.5 tf
p
fl
p
mf
2
Pressure p , Pa
1.5
0.5
0
0 0.5 1 1.5 2 2.5
3 -3
Oil flow rate -q , m /s x 10
o,sc
Mp 1 g , sc ZRTabs
2
g f g , sc g , sc
q q
dp ZRTabs 2d MpA
.
Mp g , sc qg , sc ZRTabs 1 1 dZ
2
ds
1
ZRTabs MpA p Z dp
3.a) What does this equation describe? (½ point).
3.b) What is the meaning of the term in the denominator? (½ point).
3.c) Why is the term qg ,sc qg , sc not simply expressed as qg2 , sc ? (½ point).
29 June 2011
1. Mixed questions:
1.a) The steady-state pressure drop over the components of a production system can be
expressed as in general form as
dp dv
g sin f v v v .
ds 2d ds
head loss frictional loss acceleration loss
For a typical oil well, which of the three terms at the right-hand side of this equation
dominate: a. converging choke flow, b. near-well reservoir flow, c. well bore flow?
(½ point).
2. Consider a gas pipeline with properties give in Table 1.
3600
24
3400
22 3200
3000
20
2800
18
0 500 1000 1500 2000 2500 3000 3500 4000
Distance from exit to entrance s, m
Compute the Duns & Ros liquid viscosity number. Use a water cut of 50% and a no-
slip mixing rule. (½ point)
1.e) What is dimension of the Duns & Ros gas velocity number? (½ point)
2. Consider a horizontal flow line between a well head and a production manifold. The
manifold pressure is 8.00 MPa. The flow line pressure just downstream of the well head
choke is 13.1 MPa.
2.a) What should be the minimum pressure upstream of the choke to guarantee critical
flow? (½ point)
2.b) Can the well be operated if the flowing tubing head pressure drops below this
minimum pressure? What changes? (½ point)
2.c) Next, consider the case where the flowing tubing head pressure is 29.4 MPa and the
oil flow rate 691 m3/d. After a half year the flow line pressure has dropped to 11.8
MPa, and the tubing head tubing head pressure to 26.3 MPa, while the oil rate has
been reduced to 619 m3/d for the same choke size. Sketch the choke performance
curves for the two situations and indicate the working points.(1 point)
16 June 2008
1. Consider a well with the following production parameters:
oil rate: 1300 bpd
water cut: 60%
GOR: 200 scf/stbbl
Note: give all your answers in strict SI units.
1.a) What are the surface oil, gas and water rates? (½ point)
1.b) The well is equipped with a well head choke with a bean of 56/64 inch. The flow
line pressure is 100 psi. What is the pressure drop over the choke? (1 point)
1.c) What are the in-situ oil, gas and water rates at the top of the tubing when Bo = 1.07
and Bg = 0.09, and Rs = 6.18 m3/m3? (½ point)
1.d) Why is Bo larger than 1 and Bg much smaller than 1? (½ point)
1.e) What are the Duns & Ros liquid and gas velocity numbers at the top of the tubing if
the tubing ID is 62 mm? Assume that l = 915 kg/m3 and l = 10-2 N/m. (½ point).
1.f) What is the role of these dimensionless numbers in the Hagedorn & Brown method?
(½ point).
31 August 2007
1. You are requested to design the completion of an oil well producing associated gas
containing a small amount of H2S. To avoid corrosion of the tubing you can choose
between two options: 1) To complete the well with an ordinary steel tubing and a
chemicals injection line to permanently inject a small stream of corrosion inhibitor at the
bottom of the well, or 2) to complete the well with corrosion-resistant chromium-steel
tubing. The first solution costs $ 300.000 for the completion (including rig time), has
operating costs associated with the chemicals injection of 0.20 $/bbl, and will last for
about 4 years. Thereafter a workover, taking 0.1 year, will be required to replace the
tubing. The second option costs $ 3.000.000, but will last for the entire 10-year life of the
well.
1.a) Given the production profile in Table 1, an oil price of 40 $/bbl, and a discount rate
of 15%, what is the difference in NPV between the two options? Assign the costs of
the initial completion to year 0, and start oil production and discounting in year 1.
(1 point)
1.b) What are the major uncertainties in your analysis? What would you do to take a
decision about the preferred completion? (½ point)
3 April 2007
1. You are requested to schedule a work over campaign, using one rig, to improve the
productivity of 3 wells through acidizing. The rate, FBHP and PI before acidizing and the
estimated PI after acidizing have been indicated for each well in Table 1.
1.a) Two of wells have been completed in the same reservoir. Which two? (½ point)
1.b) If you have to shut-in a well for a one month period to perform a workover, what
will be the optimal sequence? The three workovers are equally expensive (½ point)
1.c) What is the AOFP of the wells after acidizing? (½ point)
18 August 2006
1. An approximate way to compute the pressure drop in an annular geometry (e.g. between
casing and tubing) makes use of the hydraulic radius concept. The hydraulic radius rh is
defined as the cross-sectional area A, divided by the wetted perimeter Pw, and it is
assumed that conduits with identical hydraulic radii experience identical pressure drops
per unit length. For a circular pipe with inner diameter d the wetted perimeter for internal
flow is simply the perimeter d, and the hydraulic radius therefore becomes
A 4d
1 2
d
rh .
Pw d 4
For a casing-tubing annulus we find
A 4 d c dt
1 2 2
rh ,
Pw dc dt
where dc is the casing’s inner diameter and dt the tubing’s outer diameter. Consider a
vertical oil well with a 5 inch (outer diameter) tubing inside a 6.8 inch (inner diameter)
casing. The well doesn’t flow naturally and is therefore gas lifted. The gas has a specific
gravity of 0.8 and is at a pressure of 1200 psi at the valve inlet which is at 6000 ft depth.
The average temperature is 110 deg. F, and the average friction factor is 0.02. Compute
the annulus pressure at the tubing head for a lift gas flow rate of 100000 scf/d. If you use
an iterative solution method, use a first guess of 800 psi, and do not perform more than
one iteration, i.e. do not perform any of the computations more than once. (2 points)
18 August 2005
1. Mixed questions:
1.b) What are the dimensions of the oil-formation volume factor and the solution gas-oil
ratio and in which field units are they expressed? (½ point)
1.c) What is the difference between steady-state and semi-steady-state reservoir flow?
(½ point)
1.d) What is the NPV of the following cash flow at a discount rate of 15%? (½ point)
Table 1: Cash flow
Year 1 2 3 4 5
6
Cash surplus (10 $) -20 -40 10 20 30
1.e) Why are gas engineering equations sometimes expressed in terms of a real-gas
pseudo pressure? (½ point)
1.g) What is the role of the dimensionless Hagedorn and Brown velocity numbers in the
Mukherjee and Brill multi-phase flow correlation? (½ point)
30 March 2005
1. Consider three pairs of nodal analysis curves in Figure 1 for a choke/flow line/well/near-
well system. The choke is at the manifold (i.e. between the separator and the flow line)
and not at the well head. In each of the pairs the analysis node has been chosen at a
different point. The water cut is 0; the GOR is 50 m3/m3.
1.a) At which point is the analysis node for each pair of curves? (½ point)
1.b) Which system elements correspond to the upstream and downstream pressure drops
for each pair of curves? (½ point)
1.c) What are the pressures in the reservoir and the separator? (½ point)
1.d) What is the gas flow rate of the well? (½ point)
1.e) Sketch how the curves would change if the water cut would increase? (½ point)
6 6
x 10 x 10
6 6
upstream upstream
5 downstream 5 downstream
FTHP ptf , Pa
3 3
2 2
1 1
0 0
0 0.5 1 1.5 2 2.5 3 0 0.5 1 1.5 2 2.5 3
3
Oil flow rate -qo,sc , m /s x 10
-3
Oil flow rate -qo,sc , m 3/s x 10
-3
7
x 10
2.8
upstream
2.7 downstream
2.6
FBHP pwf , Pa
2.5
2.4
2.3
2.2
2.1
0 0.5 1 1.5 2 2.5 3
Oil flow rate -qo,sc , m 3/s x 10
-3
At a point in the well bore where the pressure is 3 MPa and the temperature 80º C
compute the values of the following variables:
2.a) The oil and gas formation volume factors according to the Standing correlations.
(1 point)
2.b) The local oil, gas and water flow rates according to the black oil model. (½ point)
2.c) The liquid hold-up according to the Mukherjee and Brill method using the local
fluid properties given in Table 2. Use a no-slip mixing rule to compute the liquid
properties. (1 point)
2.d) The liquid fraction. Do you expect the result to be higher or lower than the answer
of question 2.c? Give a possible explanation if this is not the case. (½ point)
3. Mixed questions:
3.a) What are the three components of the pressure drop over a well bore? Give an
example of a situation where each of the components is dominant. (½ point)
3.b) What is the essential difference between the black-oil model and volatile oil model?
Which pseudo-components are present in each of the models? (½ point)
4. Consider the following estimates of liquid rates and water cuts of a subsea horizontal well
as a function of time for two geological scenarios.
4.a) Which scenario is more attractive at an oil price of 30$/bbl and a discount rate of
15%? (½ point)
4.b) Scenario 1 has a probability 1/3 of occurring; scenario 2 a probability of 2/3. Each
of the scenarios requires a different completion: Scenario 1 requires completion A,
and scenario 2 completion B. The completions have the same cost, but if the wrong
completion is chosen, the well will produce 30% less over the 9-year period. A
workover is not an option. Which completion is more attractive under these
conditions? (½ point)
4.c) The initial PI of the well is estimated as 110 and 180 bpd/psi for scenario 1 and 2
respectively. An acid treatment prior to completion could improve these values by
20% at a cost of 15 million dollar. The well has a completed length of 1200 m and
the undisturbed permeability is 350 mD for scenario 1 and 600 mD for scenario 2.
Assuming the productivity increase to remain unchanged over the 9-year period,
would you recommend the acid treatment? (½ point)
25 March 2004
1. Consider an oil well producing 2000 bpd of black oil with Rgo = 800 scf/stb and a water
cut of 15 %. The fluid properties are specified as: API gravity: 35 degrees, gas gravity:
0.85, bubble point pressure pb = 533 psi. The black oil parameters can be accurately
described with the Standing correlations, which have been given in field units in the
Appendix below. The reservoir temperature is 200 deg. F. Express all your answers in
field units.
1.a) What is the solution gas-oil ratio at the bubble point pressure? (½ point)
1.b) The reservoir was originally under-saturated but because of depletion the pressure
has dropped to 60 psi below the bubble-point pressure. How much of the produced
gas at this moment is free gas? (½ point)
1.c) What is the volume flow rate of the free gas at the bottom of the well at the current
reservoir pressure and temperature conditions? (Neglect the pressure gradient over
the hight of the reservoir). If you did not obtain the answer to question 1.b) use the
(incorrect) answer 1.0 106 scf/d. Use the Sutton correlations in field units in the
Appendix below. (½ point)
1.d) What is the liquid volume fraction at the bottom of the well at the current reservoir
pressure and temperature? (½ point)
1.e) How much larger is the liquid volume fraction of the well at standard conditions?
(½ point)
2. Consider the nodal analysis curves in Figure 1 for a flow line/choke/well/near-well
system.
2.a) Which point has been chosen as the analysis node? (½ point)
2.b) What are the reservoir and manifold pressures? (½ point)
2.c) What is the PI of the well? (½ point)
2.d) What is the oil flow rate of the well? (½ point)
2.e) What are the pressure drops over the four system elements? (½ point)
2.f) Is the choke operating in the critical regime? (½ point)
2.g) Explain the shape of the tubing intake curve? (½ point)
6 6
x 10 x 10
6 6
3 3
2 2
1 1
0 0
0 1 2 3 4 5 0 1 2 3 4 5
3
Oil flow rate -qo,sc , m /s x 10
-3
Oil flow rate -qo,sc , m 3/s x 10
-3
7 7
x 10 x 10
3.2 3.2
Flowing bottom-hole pressure pwf , Pa
2.8 2.8
2.6 2.6
2.4 2.4
2.2 2.2
0 1 2 3 4 5 0 1 2 3 4 5
Oil flow rate -qo,sc , m 3/s x 10
-3
Oil flow rate -qo,sc , m 3/s x 10
-3
4.a) Consider the low-rate gas well in Figure 3.4 in the lecture notes. The well is connected
to the production facilities through a horizontal flow line with an inside diameter of 78
mm and a roughness of 20 10-3 mm. There is no wellhead choke and you may neglect
any pressure drop over the well head valves. How long can the flow line to the facilities
be if the pressure at the manifold is not allowed to drop below 180 bar? The manifold
temperature is 20 °C. (1 point)
Appendix for 25 March 2004 – Correlations in field units
Standing correlation for bubble point pressure
LF R I 0.83
OP
18.2 MG J
100.00091 T
14
p
pb
MNH K g 100.0125 API
. .
PQ
Standing correlation for solution GOR
p pb : Rs g
LMFG p 14. IJ10 0.0125 API 0.00091T
OP
1.2048
NH 18.2 K Q .
o 1.25 T
1.2
p pb : Bo 0.9759 12 105 Rs .
g
Note the use of o rather than API in this expression.
Sutton correlations for pseudo critical properties
R| p . g 3.6 2g ,
756.8 1310
S|T pc
19 June 2003
1. Figure 1 displays two choke performance curves in combination with two tubing
performance curves.
1.a) The tubing performance curves correspond to water cuts of fw = 0.0 and fw = 0.2; the
choke performance curves correspond to dch = 48/64 inch and dch = 72/64 inch.
Match the letters in the legend of Figure 1 to the correct water cut or choke diameter
(½ point).
1.b) If the downstream pressure at the choke equals 4.7 105 Pa, which of the
choke/tubing combinations A/B, A/D, C/B and C/D are not operating in the critical
regime? (Use a rule of thumb) (½ point).
1.c) Sketch the choke performance curves for the flow in the non-critical choke regimes
in Figure 1. (½ point)
1.d) If it is required to choke back the well when the water cut has reached a value of
0.2, what is the minimum flow rate at which you can still expect stable flow? (Use
the ‘practical’ minimum, not the theoretical minimum). (½ point)
1.e) The four curves in Figure 1 have been generated for Rgo = 60 m3/m3. Sketch how the
curves would change qualitatively if the GOR would be somewhat higher. The
flowing bottomhole pressure remains above the bubble point at all times. Explain
the trends. (1 point)
6
x 10
2
A
1.8 B
C
1.6 D
Flowing tubinghead pressure ptf , Pa
1.4
1.2
0.8
0.6
0.4
0.2
0
0 0.5 1 1.5 2 2.5 3
Oil flow rate -qo,sc , m 3/s x 10
-3
2.c) Consider the use of a well bore flow simulator to generate lift tables for a reservoir
simulator. Assume that oil properties in the reservoir remain constant during
production. Which of the following parameters need to be varied in the well bore
simulator to create a lift table? Briefly explain your answers. (½ point)
A: TR
B: Rgo
C: fw
D: Bo
25 March 2002
1. A 3000 m deep, vertical gas well produces dry gas with a density at standard conditions
of 0.95 kg m-3. The tubing inside diameter is 0.062 m, and the tubing roughness
30 10-6 m. The well is equipped with surface and down hole pressure and temperature
gauges. The flowing bottom hole and tubing head temperatures and pressures are 120 and
30 ºC, and 15 and 3.0 MPa respectively. The reservoir was initially at hydrostatic
conditions, but has been depleted, such that the pressure has dropped 12.0 MPa. The
water gradient is 10.6 kPa m-1. The gas viscosity is 12 10-6 Pa s.
1.a) What is the current static bottom hole pressure? (½ point)
1.b) What are the average values along the well for the flowing pressure, temperature
and Z-factor? Use linear interpolation. (1 point)
1.c) What is the flow rate? (1½ point).
Hint: if you take fav = 0.015 as an initial guess for the average friction factor, no
iteration should be necessary.
1.d) We could also compute the answer through numerical integration, e.g. with the aid
of MATLAB. Why would that probably give a more accurate result? (½ point)
2. A separator handles 25000 stb d-1 of liquid with a water cut of 80% and a producing GOR
of 1300 scf stb-1. It has a working pressure of 270 psig. A well is connected to this
separator through a 32/64 inch choke, a short flow line and a manifold. The combined
flow line-manifold pressure drop is 40 psi at a liquid flow rate of 1800 stb d-1. The tubing
head pressure gauge shows a value of 635 psig. It is known that the well produces from
an under-saturated reservoir with a bubble-point GOR of 735 scf stb-1, a gas gravity of
0.78 and an oil gravity of 38 deg API.
2.a) What are the gas, oil and water flow rates through the separator, and what is its
working pressure, all expressed in SI units? (½ point)
2.b) Demonstrate that the choke operates in the critical regime. (Use a rule of thumb.)
Why is that an advantage? (½ point)
2.c) What are the producing GLR, the producing GOR and the water cut of the well?
Use the Gilbert choke model to compute the GLR. (1 point)
2.d) What are the gas and liquid volume fractions just below the choke? Assume that no
gas dissolves in the oil, that the oil is incompressible and that Z = 1. Would the
liquid hold-up be higher or lower than the liquid volume fraction? Why? (½ point)
2.e) If the Duns-Ros liquid and gas velocity numbers equal Nlv = 9.01 and Ngv = 8.73,
and the liquid viscosity number Nl = 0.005, what is the liquid hold-up according to
the Brill and Mukherjee multi-phase flow model? Note that > 0. (½ point)
3. Figure 1 below depicts a pressure intake curve and four IPRs for the same deep offshore
sub-sea well but under different conditions. Two of the IPRs relate to the current reservoir
pressure, the other two to the estimated reservoir pressure in the last year of production of
the field, which is five years from now. Also, two IPRs relate to a well with a severe skin,
as is the current situation, whereas the other two relate to the well after partial removal of
the skin with the aid of an acid wash.
7500
7000
Flowing bottom-hole pressure pwf , psi
6500
6000
5500
5000
4500
4000
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Oil flow rate qo,sc , bbl/d
Figure 1: Intake pressure curve and four inflow performance relationships for the same well,
but under different conditions.
3.a) What are the current static bottom hole pressure and the pressure after 5 years?
What are the current production rates (with and without acid stimulation) and the
rates after 5 years? (½ point)
3.b) Assuming a linear drop in production rate during the five year period, an oil price of
17 $/bbl and a discount rate of 15%, what is the NPV of the produced oil for the
base case (i.e. without acid stimulation)? (1 point)
3.c) If the acid stimulation would cost 4.5 106 $, would you recommend it? (1 point)
26 June 2001
1. Figure 1 depicts a vertical well penetrating a reservoir containing gas, oil and water. The
aquifer is hydrostatic. The atmospheric pressure is 100 kPa. The oil has a 30° API gravity,
and the water gradient is 0.45 psi/ft. The top perforations are 50 ft below the GOC. Total
perforation height is 100 ft.
1.a) What is the pressure at the gas-oil contact (GOC) in SI units? (½ point)
1.b) If the FBHP at the top perforation equals 12.8 MPa and the specific PI equals 1.25
bpd/(psi ft), what is the inflow rate in SI units? Assume that the pressure at the
GOC is just below the bubble point pressure such that we can use the single-phase
PI. (½ point)
1.c) If the drawdown doubles, will the inflow rate double also? Explain your answer.
(½ point)
1.d) A second well is drilled in the reservoir to maintain reservoir pressure through water
injection. The well is completed with a 3 in. tubing and perforated 100 ft below the
OWC. Calculate the hydrostatic and frictional pressure drop over the well in SI units
for an injection rate of 1500 bpd. Assume that w = 1020 kg m-3, w = 0.0127 cp, and
that the tubing has a roughness of 0.003 in. (1 point)
gas
GOC @ 4050 ft TVD
oil
OWC @ 4250 ft TVD
water
Table 2: Production profile and cash flow analysis for a conventional well drilled in
year 1.
Year Oil rate Yearly Cash in Cash out Cash Cash Cum.
(bpd) prod. (106 $) (106 $) flow flow disc.
6 6
(10 bbl) (10 $) @ 15% cash
(106 $) flow
(106 $)
1 6.00 -6.00 -5.22 -5.22
2 5000 1.825 18.25 18.25 13.80 8.58
3 4800 1.752 17.52 17.52 11.52 20.10
4 2500 0.913 9.13 9.13 5.22 25.32
5 1900 0.694 6.94 6.94 3.45 28.77
6 1400 0.511 5.11 5.11 2.21 30.98
7 1000 0.365 3.65 3.65 1.37 32.35
8 700 0.256 2.56 2.56 0.84 33.19
9 500 0.183 1.83 1.83 0.52 33.71
10 400 0.146 1.46 1.46 0.36 34.07
11 350 0.128 1.28 1.28 0.28 34.35
12 300 0.110 1.10 1.10 0.21 34.55
13 300 0.110 1.10 1.10 0.18 34.73
14 300 0.110 1.10 1.10 0.16 34.89
15 300 0.110 1.10 1.10 0.14 35.02
16 300 0.110 1.10 1.10 0.12 35.14
17 300 0.110 1.10 1.10 0.10 35.24
18 300 0.110 1.10 1.10 0.09 35.33
19 300 0.110 1.10 1.10 0.08 35.41
20 300 0.110 1.10 1.10 0.07 35.48
Appen
ndix for 26
6 June 200
01 – Gradiient curves
26 March 2001
1. Figure 1 depicts a nodal analysis graph for the bottom of the tubing of a dry oil well for
various values of the producing GOR Rgo.
1.a) Why is the IPR curved? (½ point)
1.b) Sketch a graph of the flow rate qo of a producing well as function of Rgo. What is the
optimum GOR? (½ point)
1.c) What causes the decrease in qo,sc for values of Rgo below or above the optimum?
(½ point)
1.d) If the gas gravity g = 0.85 and you have no further information on the gas
composition, what are the approximate pseudo-critical temperatures and pressures?
(½ point)
1.e) If the reservoir temperature TR = 150 C, what is the surface gas rate expressed at
bottom hole conditions for a GOR of 200 m3/m3? (1 point).
1.f) Is the answer from 1.e) the same rate as the local gas rate from the reservoir into the
well. If not, is the actual rate higher or lower. Explain your answer. (½ point)
pwf (kPa)
50000
45000
40000
Rgo = 200 m3/m3
35000
Rgo = 400 m3/m3
30000 Rgo =50 m3/m3
25000
Rgo = 100 m3/m3
20000
15000
10000
5000
IPR
0
0.00 100.00 200.00 300.00 400.00 500.00
qo,sc (m3/d)
Answers
13 August 2014
1. Mixed questions
1.a) At the heel, because the pressure drop over the well bore will result in a higher draw
down at the heel than at the toe.
1.b) Generating a given hydraulic head for an increasing liquid density corresponds to
generating an increasing pressure drop. To generate an increasing pressure drop at a
given flow rate requires an increasing power (i.e. energy consumption per unit
time).
1.c) Mainly because water expands with increasing temperatures. Also somewhat
because of increasing gas solubility.
1.d) Dimensionless.
1.e) Because the p-V relationship for gas (mixtures) is (near-)hyperbolic with a vertical
asymptote at zero pressure. (½ point)
1.f) A simple test is to perform the pressure drop calculation top-down, and thereafter,
starting from the result, repeat the calculation bottom-up (or vice-versa), and then
verify that the result of the latter is close to the starting value of the former. Passing
the test is a good check of the discretization error in the numerical integration. It is
as necessary but not a sufficient condition for accuracy, because many other factors
may influence the accuracy.
2. Oil well with different tubing sizes.
2.a) Initially the larger tubing size leads to a higher production because it has the lowest
friction. Later, when the reservoir pressure drops, the intersection shifts to the left.
In this area of the tubing intake curve slip starts to play a more important role. A
smaller tubing size, although it increases the friction, reduces the slip and the
corresponding liquid hold up and head losses, and therefore may result in a higher
production. See the schematic figure below.
25.5
3”
Flowing bottom hole pressure
25
24.5
24
4”
23.5
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2
Oil flow rate -3
x 10
Figure schematically illustrating the benefit of a smaller tubing size when the reservoir
pressure drops.
3. Multiphase flow:
3.a) Gas-liquid ratio, gas and liquid velocities, fluid properties (densities, viscosities,
interfacial tensions etc.), well or pipeline inclination.
3.b) In upward flow, gas travels faster than liquid and, consequently, liquid hold-up
occurs. The main reason is buoyancy caused by the difference in density between
gas and liquid; in addition, gas has a tendency to concentrate at the center of the
pipe, where the fluid velocity is higher than at the boundaries.
3.c) Transform to strict SI units and compute auxiliary variables:
ms vms d
N Re 4.11106 , with the aid of the Moody chart: f ms 0.015,
ms
dp ms dp
f ms vms vms 878 Pa/m, ms g 2384 Pa/m,
ds fric 2d ds grav
ms vsg vm dp Ek , D dp dp
Ek , D 0.0238, 80 Pa/m,
p ds acc 1 Ek , D ds fric ds grav
dp
3342 Pa/m.
ds
Calculation without slip:
mn g g o o 0.0014 Pa s, mn g g o o 181 kg/m3 ,
mn vmn d
N Re 127702, with the aid of the Moody chart: f ms 0.018,
mn
dp mn dp
f mn vmn vmn 785 Pa/m, ns g 1775 Pa/m,
ds fric 2d ds grav
mn vsg vmn dp Ek , D dp dp
Ek , D 0.0177, 46 Pa/m,
p ds acc 1 Ek , D ds fric ds grav
dp
2606 Pa/m.
ds
2 July 2014
1. Mixed questions
1.a) The most important similarity is that both models describe hydrocarbon behavior
with the aid of two pseudo components (typically gas and oil at stock tank
conditions). The most important difference is that in the black oil model, the gas
pseudo component can be present in the liquid phase, but the liquid pseudo
component cannot be present in the gas phase, whereas in the volatile oil model
both pseudo components can be present in both phases.
1.b) The pseudo-critical temperature of a hydrocarbon gas mixture is the temperature
above which the mixture is in the dense phase, i.e. above which it is not possible to
distinguish the difference between a gas and a liquid phase. The pseudo-reduced
.
2.2 10 50
12
1200 3
19.3 106 7.2 103 130 105 ln 4
0.2 4
328 m3 /s.
3. 3.a) In SI units the variables become:
62.3103
2
d2
A 0.00305 m2 ,
4 4
such that the superficial and mixture velocities follow as
qg 0.0008
v sg 0.264 m/s ,
A 0.00305
ql 0.0014
vsl 0.429 m/s .
A 0.00305
The dimensionless groups then become
l 754
Nlv vsl 4 0.429 4 4.32 ,
g gl 9.81 0.08
l 754
N gv vsg 4 0.264 4 2.66 ,
g gl 9.81 0.08
g l 9.81 754
Nd d 62.3103 61.9 ,
gl 0.08
g 9.81
N l 4 6.43 103 4 0.080 .
l 754 0.08
3 3
gl
3.d) In an oil production well the gas often slips through the oil, in which case the oil is
held up and occupies a larger cross sectional area than it would do when it would be
flowing without slip between the phases. The oil is never flowing faster than the gas,
so the liquid hold up will never be smaller than the liquid fraction (i.e. the no-slip
liquid hold-up).
4a) 3 106 20
10
23 10 Pa
6 6
shift
4b) Intersection with pmf curve at 1MPa gives 2.3 103 m3 s .
6
x 10
3
p - 20 MPa
wf
p
2.5 tf
p
fl
p
mf
2
Pressure p , Pa
1.5
0.5
0
0 0.5 1 1.5 2 2.5
Oil flow rate -q , m3/s x 10
-3
o,sc
6
x 10
3
p - 20 MPa
wf
p
2.5 tf
p
fl
p
mf
2
Pressure p , Pa
1.5
0.5
0
0 0.5 1 1.5 2 2.5
Oil flow rate -q , m3/s x 10
-3
o,sc
29 August 2012
1.a) Friction.
1.b) Because the pressure drop along the well results in a higher drawdown at the heel
than at the toe.
1.c) Because of the slip between the liquid and gas phases.
4 July 2012
1.a) i) acceleration.
ii) friction.
iii) gravity.
iv) friction.
1.b) Frictionless flow.
1.c) Because flow in the diverging part is not frictionless.
1.d) The difference between gas and mixture velocity.
2. As a first guess, use a simple average wellbore temperature (70+120)/2 = 95° C.
The bubble point pressure then becomes (using a Standing correlation)
716 175 0.83 100.0016495
pb 125 10
3
1.4 29 MPa.
0.98
1768 873
10
This corresponds to a distance from the manifold equal to 2900 m and therefore to a
depth of 2900 – 1500 = 1400 m. This is close enough to the middle of the well to
justify the average temperature.
2.a) The steady state pressure drop in a vertical single-phase gas well.
2.b) The effect of acceleration.
2.c) To account for the flow direction (positive: injection; negative: production).
29 June 2011
1.a) a. acceleration losses; b. friction losses; c. head losses.
= 2.5 × 10-4;
g,sc,av = 1.1× 10-5 Pa s (from Dempsey chart for g at atmospheric pressure);
f = 2.0 (from Dempsey chart for gas viscosity ratio);
g,av = 2.2× 10-5 Pa s;
NRe,av = 3.1 × 107;
fav = 0.015 (from Moody chart);
k1 = -1.6 × 10-5;
k2 = 4.9 × 1010;
pin = 26.8 MPa which is close enough to the numerical result.
30 June 2010
1.a) s and t.
1.b) I = mass in per unit time. II = mass out per unit time. III = mass accumulated per
unit time.
A v
1.c) 0.
s
p pout in
1.d) Ideal gas law: constant . Therefore: out . Furthermore, from 1.c):
pin
Ain in vin Ain vin pin 0.30 2.5 0.22
A v constant . Therefore: vout 1.92 m/s.
Aout out Aout pout 0.86 0.10
11 June 2009
1.a) qg , sc 100 50 5000 scf; qw, sc 100 0.2 (1 0.2) 25 bpd.
1.b) A 38.48 in 2 2.483 104 m 2 ;
ql 0.65 ft 3 /s = 0.018 m3 /s; qg 1.16 ft 3 /s = 0.033 m3 /s;
vsl ql A 0.0169 ft/s 74 m/s; vsg qg A 0.0301 ft/s 132 m/s .
1.c) vl vsl H l 148 m/s; vg vsg (1 H l ) 265 m/s .
1.d) l 0.5 1020 0.5 790 905 kg/m3 ;
l 0.5 0.35 103 0.5 0.70 103 0.53 103 Pa s ;
l 0.5 0.040 0.5 0.008 0.024 N/m ;
N l 0.52 103 (9.81 (905 0.0243 ))0.25 0.0028 .
1.e) Dimensionless.
2.a) 1.7 13.1 22.3 MPa . Note: the factor 1.7 is approximate.
2.b) Yes. In that case the upstream pressure will be influenced by the downstream
pressure.
2.c) 1.7 11.8 20.0 MPa
ptf , MPa 30
25
20
15
10
0
0 200 400 600 800
qo,sc, m3/d
16 June 2008
1.a) Rgo = 35.6 m3/m3.
qo_sc = 0.0024 m3/s.
qg_sc = 35.6 × 0.0024 = 0.0854 m3/s.
qw_sc = [0.6 / (1 – 0.6)] × 0.0024 = 0.0036 m3/s.
1.b) pfl = 0.6894 × 106 Pa.
dch = 0.0222 m.
Assume critical flow. Use e.g. the Gilbert correlation:
0.546
0.0852
5.61 0.0024+0.0036
ptf 3.75 1010 0.0024 0.0036 1.01105
2.52 103 0.0222
1.89
3 April 2007
1.a) The productivity index J is defined as qo,sc = J ´ (pR – pwf), from which we obtain for
the reservoir pressure: pR = pwf qo,sc/J. The reservoir pressure in the three wells
follows as: 1: 4500 psi, 2: 4004 psi and 3: 4000 psi. Apparently well 2 and 3 produce
from the same reservoir.
1.b) The improvement in oil production for each of the three wells follows from:
qo,sc = (Jnew – Jold) ´ (pR – pwf). We find for the three wells: 1: 1200 bpd, 2: 2128 bpd
and 3: 1736 bpd. The optimal sequence is therefore 2, 3, 1.
1.c) The absolute open flowing potential (AOFP) follows from qAOFP = Jnew ´ pR. The
values for the three wells are: 1: 18 ´ 103 bpd, 2: 120 ´ 103 bpd and 3: 24 ´ 103 bpd.
18 August 2006
1) dt,o = 5 × 0.0254 = 0.1270 m.
dc,i = 6.8 × 0.0254 = 0.1727 m.
A = ¼ (0.17272 0.12702) = 10.76 × 10-3 m2.
Pw = (0.1727 + 0.1270) = 0.9416 m.
rh = 10.76 × 10-3 / 0.9416 = 0.0114 m.
A circular pipe has a hydraulic radius rh = ¼ d. An equivalent circular pipe therefore
has a diameter deq = 4 × 0.0114 = 0.0457 m.
g = 0.8 × 1.23 = 0.984 kg/m3
ptf = 800 × 6895 = 5.516 × 106 Pa.
pvalve = 1200 × 6895 = 8.274 × 106 Pa.
pav = (5.516 + 8.274) × 106 /2 = 6.895 × 106 Pa.
Tav,abs = (110 32) / 1.8 = 43.3 C = 43.3 + 273 = 316 K.
1.d) In gas engineering we generally deal with a nonlinear relationship between flow rate
and pressure drop. Use of a real-gas pseudo-pressure allows the use of the linear
pressure drop equations for liquid flow to describe the nonlinear pressure drop in gas
flow.
1.e) The Hagedorn and Brown velocity numbers are used in the Mukherjee and Brill
correlation to determine the flow regime and the liquid hold-up.
30 March 2005
1.a) Top left: node between the choke and the flow line (pmf).
Top right: node between the flow line and the top of the tubing (ptf = pfl).
Bottom left: node between the bottom of the tubing and the near-well reservoir (pwf).
pmf
ptf = pfl Flow line Choke psep
Well
Near
pwf well bore pR
1.b) Top left: upstream: reservoir + tubing + flow line; downstream: choke.
Top right: upstream: reservoir + tubing; downstream: flow line + choke.
Bottom left: upstream: reservoir; downstream: tubing + flow line + choke.
1.c) pR = 28 MPa. psep = 1 MPa.
1.d) qo,sc = 2.6 10-3 m3/s. qg,sc = 50 2.6 10-3 = 130 10-3 m3/s.
1.e) See figure below.
6 6
x 10 x 10
6 6
upstream upstream
5 downstream 5 downstream
Manifold pressure pmf , Pa
increased f w increased f w
4 4
FTHP ptf , Pa
3 3
2 2
1 1
0 0
0 0.5 1 1.5 2 2.5 3 0 0.5 1 1.5 2 2.5 3
Oil flow rate -qo,sc , m 3/s x 10
-3
Oil flow rate -qo,sc , m 3/s x 10
-3
7
x 10
2.8
upstream
2.7 downstream
increased f w
2.6
FBHP pwf , Pa
2.5
2.4
2.3
2.2
2.1
0 0.5 1 1.5 2 2.5 3
Oil flow rate -qo,sc , m 3/s x 10
-3
2.a)
716 20 0.83 100.0016480
pb 125 10 3
1.4 4.06 MPa .
1.05 10
1768 870
8 106 3.0 106 1.4 101768 870 0.0016480
1.05 1.2048
Rs = 14.1 m3/m3.
716
1.2
Bo 0.9759 12 105 160 15 1.05 870 2.25 80 40 1.09 m3/m3.
p pc 5218 103 734 103 1.05 16.4 103 0.982 4.43 106 Pa,
Tpc ,abs 94.0 157.9 1.05 27.2 1.052 230 K .
3 106 80 273.15
pR , pr 0.68 and TR , pr 1.54 .
4.43 10 6
230
With the Standing-Katz chart: Z = 0.94.
100 103 (80 273.15) 0.94
Bg 0.038 m3/m3
3 10 (15 273.15) 1.00
6
0.6
2.b) qw, sc 3 103 4.5 103 m3/s ,
1 0.6
qg , sc 20 3 103 60 103 m3/s .
qg 0.038 0.038 14.1 0 60 0.7
q 0 1.09 0 3.0 10 3.3 103
3
o
qw 4.5 4.5
0 0 1
2.c) l = 3.3 / 7.8 813 + 4.5 / 7.8 1010 = 927 kg/m3
l = 3.3 / 7.8 5 10-3 + 4.5 / 7.8 0.35 10-3 = 2.3 10-3 Pa s
gl = 3.3 / 7.8 0.008 + 4.5 / 7.8 00.04 = 0.027 N/m
vsg = 0.7 10-3 / (¼ 0.078 2) = 0.14 m/s
vsl = (3.3 + 4.5) 10-3 / (¼ 0.078 2) = 1.62 m/s
Ngv = 0.14 (927 / (9.81 0.027))1/4 = 1.1 (See Brill & Mukherjee, p.29)
Nlv = 1.62 (927 / (9.81 0.027))1/4 = 12.6
Nl = 2.3 10-3 (9.81 / (927 0.0273))1/4 = 0.011
Hl = exp {(–0.380113 + 0.129875 – 0.119788 + 2.343227 0.0112)
[(1.1 0.475686)/(12.6 0.288657) ] } = 0.83. (See Brill & Mukherjee, p.45)
2.d) l = (3.3 + 4.5) / (0.7 + 3.3 + 4.5) = 0.91. For uphill flow Hl should always be larger
than l. In this case the Mukherjee and Brill correlation is in error, i.e. we have used
parameter values that are apparently outside the limit of validity of the empirical results
of Mukherjee and Brill. (Note: If you would have answered that you mistrusted your
own results that would also have been considered a correct answer).
3.a) Gravity forces, friction forces and acceleration forces. Gravity forces dominate in oil
wells, in particular at low rates. Friction forces dominate in high-rate gas wells.
Acceleration forces hardly ever dominate, except in a blow-out situation where the exit
velocity may reach the speed of sound.
3.b) In the volatile oil model oil (or condensate) can dissolve in gas, which is not the case in
the black oil model. (Note: in both models gas can dissolve in oil.) In both models the
two pseudo components are the gas phase and the oil phase at standard conditions.
4.a) Scenario 2 is more attractive; see tables below.
Scenario 1
year ql,1 fw,1 qo,1 F1 Fdisc,1
(bpd) () (bpd) (M$/a) (M$/a)
1 22200 0.0 22200 243 211
2 20000 0.0 20000 219 166
3 17900 0.0 17900 196 129
4 15900 0.0 15900 174 100
5 14000 0.1 12600 138 69
6 12200 0.2 9760 107 46
7 10500 0.4 6300 69 26
8 8900 0.7 2670 29 10
9 7400 0.8 1480 16 5
760
Scenario 2
year ql,2 fw,2 qo,2 F2 Fdisc,2
(bpd) () (bpd) (M$/a) (M$/a)
1 27600 0.00 27600 302 263
2 25300 0.00 25300 277 209
3 23100 0.10 20790 228 150
4 21000 0.30 14700 161 92
5 19000 0.50 9500 104 52
6 17100 0.80 3420 37 16
7 15300 0.85 2295 25 9
8 13600 0.85 2040 22 7
9 12000 0.85 1800 20 6
804
4.b) EMV completion A: 1/3 760 + 2/3 0.7 804 = 629 million $
EMV completion B: 2/3 804 + 1/3 0.7 760 = 714 million $
Completion B is more attractive.
4.c) Yes. The gain (20% of 714 million $) is much more than the costs (15 million $).
25 March 2004
éæ 533 ù
1.2048
ö
1.a) Rsb = 0.85´ êçç +1.4÷÷÷100.0125´35-0.00091´200 ú = 107 scf/stb
êëèç18.2 ø úû
éæ 533 - 60 ù
1.2048
ö
1.b) Rs = 0.85´ êçç +1.4÷÷÷100.0125´35-0.00091´200 ú = 93 scf/stb
êëèç 18.2 ø úû
2.f) ptf / pfl = (2.9 106) / (0.9 106) = 3.2. This ratio is high enough to ensure critical
flow.
2.g) The graph has a minimum around 0.3 10-3 m3/s. To the right of the minimum, friction
forces dominate which increase for increasing flow rates. To the left of the minimum,
gravity forces dominate which increase for decreasing flow rates. This is because at
decreasing flow rates the liquid hold-up increases as a result of an increasing slip of the
gas phase through the liquid phase.
6 6
x 10 x 10
6 6
4 4
fl
3 3
2 2
1 1
pmf
0 0
0 1 2 3 4 5 0 1 2 3 4 5
7 7
x 10 x 10
3.2 3.2
, Pa
pR
wf
3 3
Flowing bottom-hole pressurep
2.8 2.8
2.6 2.6
2.4 2.4
2.2 2.2
0 1 2 3 4 5 0 1 2 3 4 5
c) 3
Oil flow rate -qo,sc , m /s x 10
-3
d) Oil flow rate -qo,sc , m 3/s x 10
-3
3a) It is attractive to delay the shutdown to next year as follows from a cashflow analysis
for the two scenarios:
3b) The major costs in installing gas-lift is usually the cost for compressors. If the tubings
of the production wells have already been equipped with gaslift mandrels, installing the
gas lift valves only involves wireline operations which are relatively inexpensive. If the
tubings have not been equipped with mandrels, a complete workover of the wells is
required which is a costly operations.
s ,
2k 2
if we take sˆ 0 at the manifold. Take an ‘engineering guess’ for the average values:
fav = 0.002 (highly turbulent flow, relative roughness = 0.02/78 = 0.00025; see Moody
chart), Z = 1 (close to atmospheric pressure), Tav = 25 C (mid-in between Ttf and Tmf).
Therefore:
8´1´8314´(25 + 273)´ 0.002´ 0.952 ´ 4.312
k2 = = 1.04´109 Pa 2 m ,
p ´ 0.078 ´ 23.55´ 0.95
2 5
s
19.2 10 18.0 10
6 2 6 2
21500 m,
2 1.04 109
which is much longer than a normal flow line would be in practice. Apparently there is
scope to reduce the flow line diameter and/or to produce for a long time until the FTHP
has dropped significantly.
19 June 2003
1.a) Assuming all other parameters to remain constant, a higher water cut will result in a
lower tubing head pressures for a given flow rate, and a smaller choke diameter will
result in a higher tubing head pressure for a given flowrate. Therefore: A: fw = 0.0 , B:
dch = 72/64 inch, C: fw = 0.2 and D: dch = 48/64 inch.
1.b) To operate in the critical regime, the upstream pressure of the choke should be at least
about 1.7 times the downstream pressure: 1.7 4.7 105 = 8.0 105 Pa. Only
combination B/C does therefore not operate in the critical regime.
1.c) The choke performance curves for non-critical flow start from the downstream pressure
p2 = 4.7 105 Pa and are tangent to the “critical” choke performance curves at the
upstream pressure p1 = 8.0 105 Pa.
6
x 10
2
A
1.8 B
C
1.6 D
Flowing tubinghead pressure ptf , Pa
1.4
1.2
0.8
0.6
4.7
0.4
0.2
0
0 0.5 1 1.5 2 2.5 3
Oil flow rate -qo,sc , m 3/s x 10
-3
1.d) The practical minimum corresponds to the flowrate where the tubing performance curve
becomes horizontal: qo,sc = -0.5 10-3 m3/s. Although operating points to the left of this
value can remain stable in theory, a very small disturbance may result in wellbore
instability or dying of the well.
1.e) The tubing performance curves shift upwards, because the additional gas in the tubing
results in a reduced hydrostatic head and therefore in a higher flowing tubing head
pressure. Because the flowing bottom hole pressure is above the bubble point, the near-
wellbore pressure drop is not influenced by the higher GOR. The choke performance
curves also somewhat shift upward, because the increased amount of gas flowing
through the choke results in an increased pressure drop over the choke, and therefore in
a higher flowing tubing head pressure.
6
x 10
2
A
1.8 B
C
1.6 D
Flowing tubing head pressure ptf , Pa
1.4
1.2
0.8
0.6
0.4
0.2
0
0 0.5 1 1.5 2 2.5 3
3 -3
Oil flow rate -qo,sc , m /s x 10
2.a) The Hagedorn and Brown correlation is only valid for vertical wells, whereas the
Mukerjee and Brill correlation can also cope with deviated and horizontal wells.
2.b) The liquid hold-up is always higher than the liquid fraction. This is caused by slip of the
gas through the liquid.
2.c) A: no; does not vary during production
B: yes; production parameter – does vary
C: yes; production parameter – does vary
D: no, fluid property – does not vary
25 March 2002
1.a) pws pR g w ztot pdepl 10.6 103 3000 12.0 106 19.8 106 Pa
Twf Tth
120 30
1.b) Tav 75 o C
2 2
pwf pth 15 106 3 106
pav 9 106 Pa
2 2
With the aid of the Sutton correlations:
p pc 4.51106 Pa and Tpc 219.2 K
pav 9 106 T 75 273
p pr ,av =2.00 and Tpr , av av =1.59
p pc 4.51 10 6
Tpc 219.2
With the aid of the Standing-Katz chart: Zav = 0.86
1.c) M 23.55 g,sc 23.55 0.95 22.37 kg kmol-1
av = -/2 rad (Note: is the pipeline inclination; the wellbore inclination = 0 rad)
s = 3000 m
æ k ö k¢
pwf = ççç pth 2 + 2 ÷÷÷ exp (2k1s ) - 2 = exp (2k1s ) pth 2 + éë exp (2k1s ) -1ùû 2 qg , sc qg , sc
k
è k1 ÷ø k1 k1
and therefore
2
pwf - exp (2k1s ) ptf 2
qg , sc = -
¢
éexp (2k1s ) -1ù k2
ë ûk
1
=- = -4.47 m3s-1
é exp ( 2´ 0.88´10-4 ´3000) -1ù 1.33´10
9
ëê ûú 0.88´10-4
The average flow rates and densities along the well now follow as:
p T Z 1´105 ´ (75 + 273)´ 0.86
qg ,av = sc av , abs av qq , sc = ´-4.47 = -0.051 m s -1
pavTsc , abs Z sc 9´106 ´ (15 + 273)´1
r g , sc qg , sc 0.95´(-4.47)
r g ,av = = = 82.5 kg m -3
qg ,av -0.051
Check the friction factor:
4 r g ,av qg ,av 4 82.5´ 0.051
N Re ,av = = = 7.3´106
p mg d p 12´10-6 ´ 0.062
With the aid of the Moody friction factor chart we find that for NRe,av = 7.3 106 and
= 0.48 10-3, the friction factor fav is indeed about equal to 0.015, so no iteration is
needed. Therefore the answer remains qg,sc = m3 s-1 = 103 m3 d-1.
1.d) Because most variables in the analysis are functions of along-hole depth s, which can be
taken correctly into account in the numerical solution, whereas the analytical
approximation uses average values.
2.a) Oil: 0.2 25000 = 5000 stb/d; 1.590 10-1 5000 = 795 m3/d = 9.20 10-3 m3/s.
Water: 0.8 25000 = 20000 stb/d; 1.590 10-1 20000 = 3180 m3/d = 36.8 10-3
m3/s.
Gas: 1300 0.2 25000 = 6.5 106 scf/d; 2.832 10-2 6.5e6 = 184 103 m3/d =
2.13 m3/s.
Pressure: 6.895 103 (270 + 14.7) = 1.96 106 Pa
2.b) pth = 635 +14.7 = 650 psia
psep = 270 +14.7 = 285 psia
pfl = psep + p = 285 + 40 = 325 psig
pth / pfl = 650 / 325 = 2.0. The upstream/downstream pressure ratio exceeds 1.7 which
implies critical flow. This has the advantage that downstream disturbances do not
propagate into the well.
ER
B
F dch
C
B
1 p D C
Rgl 1 F dch
E Aql , sc
1
1 635 14.7 14.7 1.89 0.546
1.00 32 355 scf stb -1
1.00 10.0 1800
The reservoir is undersaturated. Therefore there is no gas cap and the producing GOR
Rgo is equal to the bubble point GOR Rsb = 735 scf stb-1.
Gas flow rate: qg,sc = Rgl ql,sc = 355 1800 = 639 103 scf d-1
Oil flow rate: qo,sc = qg,sc / Rgo = 639 103 / 735 = 869 stb d-1
Water flow rate: qw,sc = ql,sc - qo,sc = 1800 - 869 = 931 stb d-1
Water cut: fw = qw,sc / ql,sc = 931 / 1800 = 0.52
2.d) Liquid flow rate at tubing head pressure is equal to flowrate at standard conditions (no
1.590 101
gas dissolves). Expressed in scf: ql 1800 10116 scf d -1
2.831102
Gas flow rate at tubing head pressure:
p 14.7
qg ,th sc qg , sc 639 103 = 15 103 scf d -1
pth 635 14.7
ql 10116
l 0.40
ql qg 10116 15 103
g 1 l 1 0.40 0.60
The liquid hold-up will be higher than the liquid fraction because of the occurrence of
slip between the liquid and the gas.
2.e) The Mukerjee and Brill liquid hold-up prediction is given by:
L FN
H exp McC C sin C sin C N hG
C5
I OP ,
l
MN 1 2
HN 3
2
4 l
2 gv
C6
lv
JK PQ
where the coefficients C1 to C6 are specified for upward flow as
C1 -0.380113
C2 0.129875
C3 -0.119788
C4 2.343227
C5 0.475686
C6 0.288657
The angle = /2. The liquid hold-up therefore follows as Hl = 0.58. This is much
higher than the liquid fraction calculated under 2.d) (l = 0.40).
3.c) The NPV of the additional produced oil after stimulation, can be computed as shown
the table below, and amounts to 11 million $. Therefore the acid stimulation is
attractive. In fact, the additional production pays for the stimulation after two years, and
the discount analysis could have been stopped thereafter.
26 June 2001
1.a) API = 30° => o = 876.16 kg/m3.
gw = 45 psi/ft => w = 1037.61 kg/m3.
zOWC = 4250 ft = 1295.40 m.
ho = 4250 – 4050 = 200 ft = 60.96 m.
pOWC = zOWC w g + patm = 1295.40 1037.61 9.81 + 100000 = 13.29 106
Pa.
pGOC = pOWC – ho o g =13.29 106 – 60.96 876.16 9.81 = 12.77 106 Pa.
1.b) htop = 50 ft = 15.24 m.
pws = pGOC + htop o g = 12.77 106 + 15.24 876.16 9.81 = 12.90 106 Pa.
p = pws – pwf = 12.90 106 – 12.80 106 = 0.10 106 Pa.
J = Js hperf = 1.25 100 = 125 bpd/psi = 125 2.669 10-10 = 3.34 10-8
m s Pa-1.
3 -1
0.0762 5
2.a) Expressed in field units, the Gilbert model for a choke operating in the critical regime
is given by
Rgl0.546
p1 10.00 ql , sc 1.89
14.7 ,
d ch
from which we can derive that
1 1
p 14.7 1.89 0.564 486 14.7 14.7 1.89 0.564
Rgl 1 d ch 96 1500 scf stb .
10.00 q
l , sc 10.00 5000
Note that the upstream pressure p1 has been expressed in psia and the choke diameter
d in 1/64th of an inch.
The well produces dry oil, and therefore Rgo = Rgl = 1500 scf/stb. Because the choke is
just operating in the critical regime, we know that p1 = 1.7 p2, and therefore that
p2 = p1 / 1.7 = (486 + 14.7) / 1.7 = 295 psia.
2.b) With the aid of the gradient curve:
Select 486 psig at the horizontal axis.
Go down to the line for 1500 scf/stb.
Go left to the vertical axis and read off the “reference depth”: 3600 ft.
Go down 11000 ft to the “reference depth” of 3600 + 11000 = 14600 ft.
Go right to the line for 1500 scf/stb.
Go up to the horizontal axis and read off the pressure: 2240 psig.
2.c) p = pws – pwf = 2280 – 2240 = 40 psig.
J = qo,sc / p = 5000 / 40 = 125 bpd/psi.
2.d) pwf,new = pws – qnew / J = 2280 – 3000 / 125 = 2256 psig.
With the aid of the gradient curve:
3.a) The discounted reduction in expenditure due to the use of smart wells is depicted in
the table below, and the total amounts to 7.64 million. Furthermore, for three wells the
production is one year accelerated which implies
a small gain in production at the end of the project which can be quantified as
3 0.08 = 0.24 million $, and, much more importantly,
a one-year discount reduction on the total production of three wells (minus the
contribution from the last year because the wells only produce for 18 years). The
discounted value of the total production of a single well can be quantified as 35.41
+ 5.22 = 40.63 million $ as can be inferred from the last column in Table 2. (The
total discounted cashflow in year 20 of 35.41 million $ is composed of a total
discounted production value (total cash-in) of 40.63 million $ minus the
discounted cash-out in year 1 (total cash-out) of 5.22 million). The required value
of the one-year discount reduction on the total production of three wells can
therefore be quantified as 3 (40.63 1.15) – 3 40.63 = 18.28 million $.
The total differential cumulative discounted cash flow (differential NPV) is therefore
0.24 + 18.28 – (–7.64) = 26.16 million $, which represents a substantial increase in
the project’s NPV.
Differential expenditure
Year Expenditure Expenditure Differential Discounted
conventional smart wells expenditure differential
wells (106 $) (106 $) expenditure
(106 $) (106 $)
1 -12 9 -3 -2.61
2 -18 27 9 6.81
3 -18 - -18 -11.84
Total -48 36 -12 -7.64
3.b) In the worst case, failure would occur in year 1, because then it would cause the
maximum reduction in production over the life of the field. The corresponding
discounted loss in revenues would be 35.48 + 5.22 = 40.70 million $ (Note that a
smart well produces twice as much as a conventional well). Failure in year 2 would
result in a loss of (35.41 + 5.22) / 1.15 = 35.33. The chance of experiencing no well
failure is 50%. The chance of experiencing a well failure in year 1 is 0.25 50%, and
of a well failure in year 2: 0.75 50%. The total risk-weighted differential NPV is
therefore 0.50 26.16 + 0.25 0.50 (26.16 – 40.70) + 0.75 0.50 (26.16 –
35.33) = 7.82. Even with a 50% chance of failure of one of the wells, the use of smart
wells would therefore still be attractive.
26 March 2001
1.a) Because the well is producing from a reservoir below bubble point pressure. The gas
changes the relative permeability for the oil phase.
Note: this curve was produced with the aid of the Vogel relationship for gas-liquid
inflow performance.
1.b) The optimum GOR is around 100 m3/m3. The graph will look something like:
3
qo,sc (m /d)
230
220
210
200
190
180
170
160
0 50 100 150 200 250 300 350 400 450
Rgo (m3/m3)
1.c) At the optimum value of Rgo the sum of the hydrostatic head and the friction is at its
lowest possible value. For values of Rgo below the optimum the increase in
hydrostatic head exceeds the decrease in friction. Above the optimum the increase in
friction exceeds the decrease in hydrostatic head.
1.d) The gas density at standard conditions follows as
g , sc g air ,sc 0.85 1.23 1.05 kg/m3 .
With the aid of the Sutton correlation (see Appendix B of the lecture notes) we find:
p pc 5218 103 734 103 1.05 16.4 103 1.052 4429 kPa ,
Tpc , abs 94.0 157.9 1.05 27.2 1.052 230 K .
1.e) At surface the gas is at standard conditions: p = 100 kPa, T = 15+173 = 288 K, and
Z = 1.0 Therefore a volume of one m3 gas at surface contains an amount of
pV 100000 1
n 41.8 mol .
ZRTabs 1 8.314 288
The bottom hole pressure at a GOR of 200 m3/m3 is read from Figure 1 in the exam
paper as 18000 kPa. The reservoir temperature in absolute units is Tabs = 150 + 273 =
423 K. The pseudo reduced pressure and temperature follow as
p 18000 T 423
p pr 4.1 and Tpr abs 1.8 .
p pc 4429 Tpc 230
With the aid of the standing-Katz chart we find that Z = 0.92. Therefore the gas-
formation volume factor is given by
qg pscTabs Z 100 103 423 0.92
Bg 0.0075 .
qg , sc pTsc , abs Z sc 1800 103 288 1
The surface oil rate at a GOR of 200 m3/m3 is about 200 m3/d; see Figure 1 of the
exam paper. The gas rate is therefore 200 200 = 40000 m3/d. Expressed at bottom
hole conditions this becomes:
qg qg , sc Bg 40000 0.0075 300 m3 d .
1.f) No. The local gas rate at the bottom of the hole is lower because a part of the gas is
in solution in the oil.
2.a) Water production. During the first six years, the well produced dry oil at an almost
constant rate, but as of year seven, the well started to produce water which replaced
the oil.
Note: The well has produced at almost the same gross liquid rate during its entire
life. This is most likely a result of surface facilities constraints, or possibly from a
restriction on the flow rate to avoid sand production or erosion. The well is not
operating on lift constraint, because otherwise the gross flow rate would have
dropped after the start of the water production.
2.b) A differential cash flow analysis for year 19 gives a cumulative cash flow of about
4.7 million $; see the table below. The re-perforation is therefore very attractive,
even at a low oil price of 12.5 $/bbl.
Note: a full discount analysis is not necessary because already in the first year the
profits exceed the investment.
2.c) The producing GOR of the well remains nearly constant at about 500 scf/stb during
the life of the well; see the figure below. Therefore the well produces associated gas
at a nearly constant level. There is no sign of free gas production, which would have
caused an increase in GOR.
Note: GOR figures often fluctuate much stronger, not in the least because oil and gas
measurements during production testing often have a low accuracy ( 5% is a very
good measurement. Errors up to tens of percents do frequently occur.)
520
515
510
505
500
GOR (scf/stb)
495
490
485
480
475
470
0 2 4 6 8 10 12 14 16 18 20
year
References
Beggs, H.D., 1991: Production optimisation using NODAL analysis, Oil and Gas Consultants
International Publications, Tulsa.