201105icpstutorialmanual 151228020532
201105icpstutorialmanual 151228020532
NEWPORT BEACH, CA
MAY 1 – 4, 2011
TABLE OF CONTENTS
1.0 INTRODUCTION.....................................................................................1-1
5.0 PT FAILURES.........................................................................................5-1
7.0 SUMMARY..............................................................................................7-1
8.0 REFERENCES........................................................................................8-1
i
1.0 INTRODUCTION
Switching transients associated with circuit breakers have been observed for many
years. Recently this phenomenon has been attributed to a significant number of
transformer failures involving primary circuit breaker switching. These transformer
failures had common contributing factors such as 1) primary vacuum or SF-6
breaker, 2) short cable or bus connection to transformer, and 3) application involving
dry-type or cast coil transformers and some liquid filled.
This tutorial will review these recent transformer failures due to primary circuit
breaker switching transients to show the severity of damage caused by the voltage
surge and discuss the common contributing factors. Next, switching transient
simulations in the electromagnetic transients program (EMTP) will give case studies
which illustrate how breaker characteristics of current chopping and re-strike
combine with critical circuit characteristics to cause transformer failure.
1-1
2.0 CASE STUDY OVERVIEW
2-1
Transformer Failure Due to Circuit Breaker
Induced Switching Transients
Part 1: Case Study Overview
David D. Shipp, PE Thomas J. Dionise, PE
Fellow, IEEE Senior Member, IEEE
Eaton Electrical Group Eaton Electrical Group
130 Commonwealth Dr. 130 Commonwealth Dr.
Warrendale, PA 15086 Warrendale, PA 15086
Presentation Purpose/Summary
• Purpose #1 Safety:
– Alert Design & User Community
– Drive Solutions Through Market Interest
• Unique Case History
– Forensic Evidence
– High Speed Power Quality Capture
• Presentation Summary
– Simplified System Overview
– Forensic Review
– Power Quality Snapshots
– Installed RC Snubber Fix
• Presentation Summary: David Shipp, Eaton
– Phenomenon Detailed Explanation
– Science of RC Snubber Design
Site Specifics
• Utility Service:
– 26kV
– Double Ended Loop Through
• Transformers
– (6) Total
– 26kV Primary, 480V Secondary
– VPI
– 3000kVA AA / 3990 kVA FA
– 150 kVbil
• Switching Device
– Vacuum Circuit Breaker
• Cable
– 35kV, 133% EPR Insulation, 1/3 Concentric Ground
M M
40’ 40’
T-A3 T-B3
CRACs CRACs
80’ Chillers Chillers
80’
T-A2 T-B2
UPS UPS
100’+ To Normal Side 100’+
Of 480vac ATS
T-A1 (Typical) T-B1
OTHER OTHER
Failure/Sequence of Events
• All Transformers Fully Tested:
• Pre-functional: Turns Ratio, Insulation Resistance, etc
• Functional:UPS Full Load Tests, UPS Transient Tests, Data Center
Room Validation Testing
• Final Pull The Plug Test (PTP)
• 4 Electricians “simultaneously” open (4) 26KV vacuum breakers to
simulate a general utility outage.
• All systems successfully transfer to standby generation but:
• Loud Pop heard in Substation Room B
• Relay for VCB feeding TB3 signaling trip
• Decision made to shutdown generator test and investigate issue in
“B” substation room
• 2 Electricians “simultaneously” close (2) 26KV vacuum breakers to
Substation Room “A”
• Transformer TA3 fails catastrophically.
Pre-PTP Condition
26kv Utility “A” 26kv Utility “B”
M M
40’ 40’
T-A3 T-B3
CRACs CRACs
80’ Chillers Chillers
80’
T-A2 T-B2
UPS UPS
100’+ 0.8MW 0.9MW 100’+
T-A1 T-B1
OTHER OTHER
1.5MW 1.3MW
40’ 40’
T-A3 T-B3
CRACs CRACs
80’ Chillers Chillers
80’
40’ 40’
T-A3 T-B3
CRACs CRACs
80’ Chillers Chillers
80’
T-A1 T-B1
OTHER OTHER
Failure #2
Transformer Failure On Energization
Failure #2
Transformer Failure On Energization
Suspected Area
of Initial Flash
Failure #2
Transformer Failure On Energization
Coil to Coil Tap
Burnt Off
Failure #2
Transformer Failure On Energization
Coil to Coil Tap
Burnt Off
Upward Twist
From Lower Blast
Failure #1
Transformer Failure On De-Energization
Flash/Burn Marks
Failure #1
Transformer Failure On De-Energization
Close up of
Flash/Burn Marks
No Coil to Coil
Cable Supports
Some Burn
Marks Match
Point of
Cable Contact
Failure #1
Transformer Failure On De-Energization
Some Burn
Marks Match
Vicinity of Cable
Cable is Undamaged
Unaffected Transformer
Factory Installed
Cable Support
Current Transient: Failure #2
Transformer Energization
Second Transformer
Inrush
AØ
CØ
BØ
Event Initiated
A-B Phase 19,000 amp, 3 Phase
5 Cycle CB Clearing Time
AØ C Phase Shows
2nd Xfmr Load
& Event Duration
CØ
Breaker Induced
Switching Transients
Case 1
Hydro Dam, MT 2005
• MV Vac Bkr Replacements Vendor “A”
• 13.8 kV
• 20 feet of cable
• 50 kV BIL (W) ASL Dry Type Txmrs
• Customer Energized before Vendor OK
• Txmr Failed
• No Surge Protection Applied
CASE 2
Cleveland Hospital 3/06
• Vacuum Breakers – Vendor “A” and Vendor
“C”
• 13.8 kV
• 95 kV BIL
• Dry Type Txmr
• 27 feet of Cable
• Bkr Manufacturer Paid to Repair Failed 2500
KVA Txmr
• Surge Protection Added Afterwards
CASE 3
RAILROAD SUBSTATION 11/06
• Vacuum Breaker – Vendor “A”
• 26.4 kV
• 150 kV BIL
• Generic Liquid Filled Rectifier Txmr
• 37 feet of Cable
CASE 4
NJ DATA CENTER 12/06
• 26.4 kV – Vendor “B”
• 4 Txmrs Switched Under Light Load
• 2 Txmrs Failed-1 on Closing/1 on
Opening
• 40 Feet of Cable
• 2 other Txmrs Did Not Fail - 80 Feet of
Cable
• Arresters Were Present
CASE 5
OIL FIELD – AFRICA 6/07
• Vacuum Breaker – Vendor “D”
• 33 kV
• 7 Feet of Cable
• Dry Type Txmr in 36 Pulse VSD
• Arresters Were Applied
• Txmr Failed Upon Energization
CASE 9
Oil Drilling Ship – 6/2002
• Vendor “A” IEC Vac Bkrs in Vendor “D”
Swgr
• 11kV, 60 HZ
• Cast Coil Dry Type IEC VSD Propulsion
Txmr Failed (7500 kVA) – 75 kV BIL?
• < 30 feet of Cable
• Fed from Alternate Bus – Now 80 feet of
Cable
• No further Failures Reported
CASE 11
Hospital – Slide 1
• 13. 8 kV System
• Vendor C Breakers/
Vendor F Txmrs
• 2 Txmrs Failed During
Commissioning
• Differential Relay
Tripped During motor
Starting – under
Highly Inductive Load
CASE 11
Hospital – Slide 2
CASE 11
Hospital – Slide 3
CASE 12
Motor Starter Auto Txmr Failure
• 4160V
• 5000 HP
• Reduced Voltage
Auto Txmr Failed
• Arresters on Wye
Point
• Internal Resonance
• Layer Wound
• Failed Layer to Layer
Current Chop
Current Chop
Current Chop in Vacuum is a Material Problem
Current Chop
• All Types of
Interrupters Chop
Current
• This is not a Unique
Feature of Vacuum
• Closing
• Opening
• Voltage Escalation
• Surge Suppression
Switching Inductive Loads
CLOSING
ENERGY EQUATION
1 2 1
LI CV 2
2 2
OR
L
V I
C
TOTAL VOLTAGE
ANALYSIS
1
NF
2 LC
CASE 3
Waveforms Without Snubbers
CASE 3
Current – Without Snubbers
Ichop
CASE 3
Waveforms With Snubbers
CASE 4
Data Center 12/06
• 26.4 kV
• Vendor “B” Breakers
• 4 Bkrs Switched at Once
• 2 Dry Type Txmrs Failed (40 Ft of
Cable)
• 2 Txmrs Did not Fail (80 Ft of Cable)
• Unfaulted Txmr Winding Failed BIL
@162 kV ( Rated 150 kV)
CASE 4
Data Center, NJ 12/06 - W/O Snubbers
200
150
100
50
-50
-100
-150
-200
0 5 10 15 20 25
CASE 4
Data Center, NJ 12/06-With Snubbers
40
30
20
10
-10
-20
-39 kV
-30
-40
0 5 10 15 20 25
CASE 6
Data Center 2, NJ 12/06
• 13.2 kV
• Vendor “B” Breakers
• 3 MVA Dry Type Txmrs
• 60 ft Cable – Required Snubbers
• 157 ft Cable – Required Snubbers
• No Problem at Startup
CASE 6
13.2 kV SYSTEM – 119 kV @ 678 HZ
CASE 6
WITH SNUBBERS – 33.6 kV @ 236 HZ
CASE 7
Chemical Plant, NC 3/07
• 12.47 kV System
• 20+ Year Old Oil Filled Txmrs
• Vendor “A” Vacuum Bkrs retrofitted on
Primary
• 10 Feet of Cable
• No Problem at Startup
CASE 7
425 kV - 12. 47 kV - 23 kHZ Ring Wave
CASE 7
Added Snubbers – 12.47 kV
CASE 8
DATA CENTER – Indiana 6/07
• 12.47 kV System
• Vendor “A” Breakers
• 270 Feet of Cable
• No Additional Surge Protection
Required
CASE 8
-55 kV at 800 HZ
CASE 11 Hospital
186.9 kV / 2000 HZ
CASE 10 – Snubber
Reduced to 33.8 kV / 368 HZ
MITIGATING TECHNIQUES
• Arresters
• Surge Capacitors
• Snubbers (RC)
• Hybrid / Combinations
• Liquid vs Dry Type
• Electronic Zero Crossing Switching
Lightning
Arrestor
Fuse
Blown Fuse
Viewing Window
Resistor
Capacitor
RC Snubber Installed – Case 4
Resistor
Capacitor
Fuse
Blown
Fuse
Indicator
• Quantifies Problem
• Predict Exposure / Risk
• Select Best / Most Cost Effective
Solution
• Do “What if” Cases
• Verify Results
RECOMMENDATIONS
Conclusion/Next Steps
• This is a System Problem
– Transformer, Cable, Switching Device, Proximity
– Statistical Event , Possible Undetected Failures
• Data Centers Fall into the Highest Risk Category
– High Power Density
– Close Proximities
– Frequent Switching
• Draft IEEE C57.142
– A Guide To Describe The Occurrence and Mitigation Of Switching Transients
Induced By Transformer And Switching Device Interaction
– Does not accurately warn users of all areas of concern
– This case did not meet the areas of concern noted in Draft C57.142
– Need to push for formalization of the standard with new lessons learned
• RC Snubbers
– Transformer Manufacturer appears best positioned to implement the solution
– Limited Cataloged Product (One Manufacturer)
– Not embraced by all transformer manufacturers
– Design Parameters of RC Snubber not clearly defined
• Lives, Property and Uptime are all at risk
QUESTIONS ?
3.0 EMTP MODELING & CASE STUDIES
3-1
Transformer Failure Due to Circuit Breaker
Induced Switching Transients
Part 2: EMTP Modeling and Case Studies
David D. Shipp, PE Thomas J. Dionise, PE
Fellow, IEEE Senior Member, IEEE
Eaton Electrical Group Eaton Electrical Group
130 Commonwealth Dr. 130 Commonwealth Dr.
Warrendale, PA 15086 Warrendale, PA 15086
2
2
ATP
3
3
1
Source Model
U RUTIL XUTIL UT
• “3-phase wye cosine”
• Resistance in ohms
• Inductance in mili-Henries UN
• Source Impedance VUTIL
• Z1 and X/R
• Z0 and X/R
SYSTEM SOURCE
AT 13.8 KV
4
4
Cable Model
C1 LCABLE RCABLE C2
• “Pi Model”
• Resistance in ohms
• Inductance in mili-Henries
• Cable charging in micro-Farads
• ½ charging on sending end
• ½ charning on receiving end C/2 C/2
• Multiple pi models in some cases
CABLE
13.8KV
5
5
Breaker Model
• “Switch”
• Time dependent switch
• Open or close at a specific time
• Opens at current zero unless specify otherwise
• Current dependent switch
• Needed for current chopping
• Define current at which to open switch
• Independent Poles (A, B and C independent)
• Data request
VCB
• Vacuum or SF6 breaker nameplate BKR
• Current chop (ask manufacturer)
• Transient Recovery Voltage Ratings – T2, E2 and RRV
6
6
2
Transformer Model
T1 LTRAN RTRAN N:1 T2
• “Three Phase Model”
• Resistance in ohms
• Inductance in mili-Henries
• Magnetizing current
• Winding capacitance
• CH and CL for dry-types
• CHL for oil-filled
• More detailed modeling
• Saturation
• Hysteresis CH CL
• Data Request RLRG
• %Z and X/R, MVA
• BIL
TRANSFORMER
7
7
UN
VUTIL
C/2 C/2 CH CL
RLRG
8
8
Time Step
9
9
3
Switching Transient Simulations
10
10
Ferry Propulsion
Highlights
• 60K passengers per day
• 20M passengers per year
• 4160V distribution
• 3 x 2865kW diesel gens
• 2 x 1865KW forward propulsion motors
• 2 x 1865KW reverse propulsion
11
11
Problem
12
12
4
Ferry - Oneline
Vacuum
Breaker
Short
Cable
Dry-Type
Transformer
Forward Reverse
13
13
15
15
5
Measurements
Transient Overvoltages at Primary of Rectifier Transformer – VCB Closes
16
16
Study Cases
17
17
18
18
6
Case 2 – Valid Model with Snubber
Transformer primary voltage
19
19
Case 3 – Re-ignition
Transient Recovery Voltage (TRV) at VCB
20
20
21
21
7
Case 5 – Current Chop
Transformer primary voltage
V max of 31.9kV > 30kV BIL
Oscillation of 958Hz ~ 1000Hz
22
22
23
23
24
24
8
Summary of Re-Ignition Cases
25
25
Recommendations
26
26
Data Center
Highlights
• Tier III
• LEEDS Certified
• 12.5MVA Capacity
• 13.2KV Ring Bus
27
27
9
Data Center - Oneline
Vacuum
Breaker
Short
Cable
Cast-Coil
Transformer
28
28
29
29
30
30
10
Worst Case – Study Case 13
32
32
33
33
11
Case 14 – 0.25uF surge cap
Load current at 13.2kV VCB
34
34
35
35
36
36
12
Case 15 – snubber 30ohm and 0.25uF
Transformer CSC primary voltage
37
37
IC peak of 7.7A
IB peak of 8.0A
IA peak of 6.8A
38
38
Comparison of Results
No
Snubber
0.25uF
surge cap
Snubber
R=30ohm
C=0.25uF
39
39
13
Measured Transients with Snubber
40
40
Recommendations
41
41
42
42
14
LMF & EAF - Oneline
Vacuum
Breaker
Short
Bus
Existing Oil-Filled
EAF New Transformer
LMF
43
43
UTILITY
4713MVA 3PH SC
9.26 X/R
LMF 138KV
1600A
50/66/83MVA
135.3/26.4KV
7.5%Z
13OHM
SF6 27KV
Breaker SF-6 BREAKER
2000A
Short ALUMINUM
Bus IPS BUS
53FEET
HEAVY DUTY
COPPER PIPE Short
28FEET Bus
LMF XFMR
50/56MVA
25/.53KV Oil-Filled
2.5%Z Furnace
LMF Transformer
New 20MW
LMF
44
44
15
Worst Case Scenarios
46
46
47
47
48
48
16
Case 3 – Open SF6 Breaker
Auto-regulating Transformer primary voltage
49
49
50
50
51
51
17
Case 5 – Highly Inductive Current
Inrush current to LMF transformer
6000A Peak
Inrush
VCB
Closes
VCB
Opens
52
52
53
53
54
54
18
Case 7 – Highly Inductive Current
Inrush current to Auto-Regulating transformer
14000A Peak
Inrush
SF6 CB
Closes
SF6 CB
Opens
55
55
56
56
57
57
19
Summary of Re-Ignition Cases
58
58
Recommendations
59
59
20
4.0 MOTOR STARTING AUTOTRANSFORMER CASE STUDY
4-1
Medium Voltage Reduced Voltage Autotransformer
Starter Failures
– Explaining The Unexplained –
Arthur J. Smith III, Member IEEE Larry Farr, Senior Member IEEE
Vice President Principal Engineer
Waldemar S. Nelson and Co. Inc. Eaton Electrical
New Orleans, LA Asheville NC
TODAY’S AGENDA
• Background
• Investigation
• Testing 1988
• Findings
•Testing 2002-03
• Findings
• Solution
• Conclusions
• Background
1
Background
Background
2
Background
Failures Were Occurring Worldwide
• North Sea Platform 12kV starters failed multiple
times. Problems solved with single phase
autotransformers.
• 20,000 hp-15kV starter in British Columbia failed
four times until surge arresters from the Zero tap to ground
were installed.
• South America 2400 volt failed multiple times.
• Gulf of Mexico – Multiple 5kV starter failures
• IEC 60470 Clause 6.102.7 Change-over Ability Test
• Off the West Coast of Africa – Multiple 5kV starter failures
Background
What Happened?
Zero Tap Circuit to Ground
3 Inches !!
Background
Failure Modes
Telescoping Coils
Layer to Layer
3
Background
High Voltage Flashover
Tap to Tap Over the Surface
Background
High Voltage Flashover
Coil to Ground
Background
High Voltage Flashover
Layer to Layer Failure
4
Background
High Voltage Flashover
Zero-tap Circuit to Ground
Background
Telescoping Coils
• S and R Conducting Simultaneously
• Flashover of S with R Closed
Background
5
Medium Voltage Reduced Voltage Autotransformer
Starter Failures
– Explaining The Unexplained –
• Background
• Investigation
• Testing 1988
Testing
Initial Testing
Testing
Initial Testing
6
Testing
Initial Testing
Testing
• Background
• Investigation
• Testing 1988
• Findings
7
Findings
Design Modifications
• Changed Design to Three Coil Three
Legged Autotransformer
• Changed Control Circuit to Include a
Transition on Current Below 125%
FLA
• HOWEVER, Failures Continued at
a Rate of Two to Three a Year !
Findings
Findings
8
Medium Voltage Reduced Voltage Autotransformer
Starter Failures
– Explaining The Unexplained –
• Background
• Investigation
• Testing 1988
• Findings
• Testing 2002-03
Additional Testing
Additional Testing
Dielectric Withstand
Two Layers of .005 Nomex 14kV rms for 60 Secs.
9
Additional Testing
Partial Discharge
Additional Testing
November, December and January
Belmont, North Carolina
Additional Testing
A Closer Look
10
Additional Testing
February
Arden, North Carolina
• Background
• Investigation
• Testing 1988
• Findings
• Testing 2002-03
• Findings
Findings
Issue Found !
11
Findings
Current Flat During Voltage Escalation
Findings
When Reignition Occurs
Findings
Each Burst
70,000 Volts/Micro Sec
Each Burst
70,000 Volts/Micro Sec
12
Medium Voltage Reduced Voltage Autotransformer
Starter Failures
– Explaining The Unexplained –
• Background
• Investigation
• Testing 1988
• Findings
• Testing 2002-03
• Findings
• Solution
Solution
Solution
With Surge Arresters
12-13,000 Volts at 12-18 amps for 800 Micro Sec
13
Medium Voltage Reduced Voltage Autotransformer
Starter Failures
– Explaining The Unexplained –
• Background
• Investigation
• Testing 1988
• Findings
• Testing 2002-03
• Findings
• Solution
• Conclusions
Conclusions
Conclusions
• When 6 kV distribution surge arresters are
installed on a 4,160 volt circuit from the 0%
tap to ground, the voltage is clamped to 13
kV without the resultant high dv/dt across
the transformer coil regardless of transition
current
• Vacuum contactor autotransformer
starters and starter retrofits require
surge arresters even if no problems
were encountered with air break
contactors
14
Conclusions
• The 15kV Autotransformer Starter in
British Columbia was set on the 55%
tap. The starter used MV Circuit
Breakers. Therefore all
autotransformer starters need surge
arrestors zero tap to ground or across
the VI,s.
• Care must be taken so the Metal Oxide
arrestors do not conduct near normal
operating voltages.
15
5.0 PT FAILURES
5-1
Transformer Failure Due to Circuit Breaker
Induced Switching Transients
Part 4: Potential Transformer Failures
David D. Shipp, PE Thomas J. Dionise, PE
Fellow, IEEE Senior Member, IEEE
Eaton Electrical Group Eaton Electrical Group
130 Commonwealth Dr. 130 Commonwealth Dr.
Warrendale, PA 15086 Warrendale, PA 15086
Case Studies
2
2
CASE 12
Midwest Data Center
3
3
1
CASE 12
Midwest Data Center
4
4
CASE 12
Midwest Data Center
5
5
CASE 12
Closing From Generator Source – 300 kW Load
6
6
2
CASE 12
Opening From Generator Source – 300 kW Load
7
7
CASE 12
Primary Measurements - 300 kW Load Opening
8
8
CASE 12
Primary Measurements – Snubbers + 300 KW Load
9
9
3
CASE 12 - Closing
Primary Measurements - 300 kW Load
10
10
11
11
PT Failure – Example 13
12
12
4
CASE 13
Switching Transient 1st Failure
13
13
14
14
Oscillation continues
beyond ¼ cycle
Transient followed by
high frequency ring
5
PT - test without snubber (zoom view)
Recorded Volts/Amps/Hz Zoomed Detail: 04/27/2011 19:21:07.855.770.000 - 04/27/2011 19:21:07.857.283.100
12000
10000
8000
6000
4000
2000
0
Volts
-2000
-4000
-6000
High frequency
-8000
effects – 50kHz
-10000
-12000 11.27kVpeak
-14000
nominal
-16000
Magnitude -18000
effects – 1800 1900 2000 2100 2200 2300 2400 2500 2600 2700
Time 04/27/2011 19:21:07.854000 + us
2800 2900 3000 3100 3200
17.5kV
• Magnitude is not the only problem
• High frequency as well as high magnitude
• Overtime both will damage PT 16
16
• Overshoot to 12.25kVpeak
• Lower frequency oscillation
• Oscillation very well damped 17
17
10000
4000
2000
Volts
-2000
-4000
-6000
-8000
-10000
-12000
11.27kVpeak
Low Magnitude nominal
2800 3000 3200 3400 3600 3800 4000 4200 4400 4600 4800
12.25kV Time 04/27/2011 20:09:12.580000 + us
6
PT saturation on VCB opening
measured
simulated
19
19
20
20
21
21
7
6.0 SNUBBER PERFORMANCE MEASUREMENTS
6-1
Transformer Failure Due to Circuit Breaker
Induced Switching Transients
Part 5: Snubber Performance Measurements
David D. Shipp, PE Thomas J. Dionise, PE
Fellow, IEEE Senior Member, IEEE
Eaton Electrical Group Eaton Electrical Group
130 Commonwealth Dr. 130 Commonwealth Dr.
Warrendale, PA 15086 Warrendale, PA 15086
• Data Center
• Purpose of Measurements
• Test procedures
• Medium voltage measurements
• Selecting a meter
• Using voltage dividers
• Safety concerns
• Data Center challenges
2
2
3
3
1
Data Center
Highlights
• Tier III
• LEEDS Certified
• 12.5MVA Capacity
• 13.2KV Ring Bus
4
4
Vacuum
Breaker
Short
Cable
Cast-Coil
Transformer
5
5
6
6
2
RC Snubber at MVS - Typical
Cast Coil
3750KVA
Transformer
200 A
Disconnect to
RC Snubber transformer
13.8 kV
0.25 microFarad
30 ohm
7
7
Snubber Specs
13.8 kV
0.25 microFarad
30 ohm
8
8
Test Procedure
3
Measurement Equipment
10
10
11
11
12
12
4
Voltage Divider Connections
13
13
14
14
CT Connections
15
15
5
Initial view of events
Energize De-energize
(see zoom) (see zoom)
16
16
17
17
• No transient on opening
• Well damped
18
18
6
Other Tests – transformer natural frequencies
• Sweep Frequency Response Analysis (SFRA)
Impedance
Phase Angle
Frequency 19
19
Summary
21
21
7
7.0 SUMMARY
7-1
Transformer Failure Due to Circuit Breaker
Induced Switching Transients
Summary
David D. Shipp, PE Thomas J. Dionise, PE
Fellow, IEEE Senior Member, IEEE
Eaton Electrical Group Eaton Electrical Group
130 Commonwealth Dr. 130 Commonwealth Dr.
Warrendale, PA 15086 Warrendale, PA 15086
2
2
3
3
1
Predicting Transients – EMTP Simulations
UN
VUTIL
C/2 C/2 CH CL
RLRG
Surge
Cap
5
5
6
6
2
8.0 REFERENCES
Switching Transients
8-1
IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 47, NO. 2, MARCH/APRIL 2011 707
TABLE I
H ISTORY OF T RANSFORMER FAILURES R ELATED TO
P RIMARY VACUUM B REAKER S WITCHING
TABLE II
C URRENT C HOP V ERSUS C ONTACT M ATERIAL
Fig. 9. Simplified electrical distribution system for Tier III data center.
D. Borderline Case
It is important to note that not all applications involving
primary switching of transformers using vacuum breakers re-
quire snubbers. The large majority of applications do not re-
quire snubbers. Switching transient studies are conducted to
determine when snubbers are needed. In this paper, the cases
were selected to show different situations requiring snubbers.
For the system shown in Fig. 9, the results were border-
line; therefore, a snubber was still applied for reliability pur-
poses. The Fig. 9 system is a Tier III data center with two
24.9-kV incoming lines, two 12.5-MVA 25/13.2-kV transform-
ers, a 13.2-kV ring bus, two 2250-KW generators, and six
3750-kV cast-coil transformers.
Data centers fall into the highest risk categories because of
their high load density, close proximities of circuit components,
highly inductive transformers (high-efficiency designs), and
frequent switching. The critical parameters for the Fig. 9 system
are vacuum circuit breakers, 90-kV-BIL transformers, and cable Fig. 10. TOV initiated by current chop during de-energization of cast-coil
lengths ranging from 109 to 249 ft. For the cable of 109 ft, the transformer with and without snubber.
results of opening the vacuum breaker with current chopping of
both within acceptable limits. Finally, field measurements were
8 A are shown in Fig. 10. The TOV is as high as 123 kVpeak
taken after the snubber was installed to ensure that the snubbers
on phase A which exceeds the transformer BIL of 95 kV.
performed as designed. The field test setup for the snubber
The TOV exhibits a significant dc offset because there is very
performance measurements is discussed in Section IV. The
little resistance in the highly inductive circuit. The oscillation
field measurements showed that the snubber limited the TOV
frequency of 969 Hz is slightly less than the acceptable limit.
within acceptable limits.
A snubber is required to reduce the peak below 95-kV BIL.
The results of adding a snubber are shown in Fig. 10. Note
E. Case of Switching a Highly Inductive Circuit
the significant reduction in the dc offset. The resistor in the
snubber provides the reduction in dc offset as well as damping. Now, consider the vacuum breaker switching of a highly
The peak is reduced to 28.6 kV and an oscillation of 215 Hz, inductive circuit, such as the starting current of a large grinder
SHIPP et al.: TRANSFORMER FAILURE DUE TO CIRCUIT-BREAKER-INDUCED SWITCHING TRANSIENTS 713
Fig. 12. TOV during de-energization of LMF transformer with and without
snubber protection.
TABLE IV
C URRENT C HOP AND R EIGNITION C ASES FOR LMF T RANSFORMER S WITCHING
Fig. 17. 15-kV snubber visual indication (glow tubes) and continuity verifi-
cation (current sensors).
Fig. 18. Snubber with (left) three-phase and (right) single-phase surge capac-
consider the location of the switching transient source when de- itors for 13.8-kV paper mill application.
veloping the custom design layout of the protective equipment.
Abrupt changes in the electrical path should be avoided. A low
inductive reactance ground path should be designed, using non-
inductive ceramic resistors and flat tin braided copper ground
conductors. The minimum clearances of live parts must meet or
exceed the phase-to-phase and phase-to-ground clearances of
NEC Table 490.24. The enclosure should be designed to meet
the requirements of IEEE Standard C37.20.2 1999. When the
enclosure is mounted greater than 10 ft from the equipment to
be protected, NEC tap rules may apply to the cable size required
and additional circuit protective devices may be required.
R EFERENCES
[1] ANSI/IEEE, A Guide to Describe the Occurrence and Mitigation of Switch-
ing Transients Induced by Transformer and Switching Device Interaction.
C57.142-Draft.
[2] D. Shipp and R. Hoerauf, “Characteristics and applications of various arc
interrupting methods,” IEEE Trans. Ind. Appl., vol. 27, no. 5, pp. 849–861,
Sep./Oct. 1991.
[3] Standard for AC High-Voltage Generator Circuit Breakers on a Symmetri-
cal Current Basis, C37.013-1997, 1997.
[4] Application Guide for Transient Recovery Voltage for AC High-Voltage
Circuit Breakers, C37.011-2005, 2005.
[5] D. Durocher, “Considerations in unit substation design to optimize reliabil-
Fig. 20. Snubber performance measurement setup for 15-kV transformer ity and electrical workplace safety,” presented at the IEEE IAS Electrical
using high bandwidth voltage dividers. Safety Workshop, Memphis, TN, 2010, Paper ESW2010-3.
Visuth Lorch received the B.S.E.E. degree from Bill G. MacFarlane (S’70–M’72) received the
Chulalongkorn University, Bangkok, Thailand, in B.S.E.E. degree from The Pennsylvania State Uni-
1973, and the M.S. degree in electric power engi- versity, University Park, in 1972.
neering from Oregon State University, Corvallis, in He began his career in 1972 with Dravo Corpo-
1976, where he was also a Ph.D. candidate and was ration, Pittsburgh, PA, as a Power System Design
inducted as a member of the Phi Kappa Phi Honor Engineer supporting this engineering/construction
Society. During his Ph.D. studies, he developed the company with expertise in the design and construc-
Short Circuit, Load Flow, and Two-Machine Tran- tion of material handling systems, chemical plants,
sient Stability programs. The Load Flow program pulp and paper mills, steel facilities, ore benefaction,
has been used in the undergraduate power system mine design, and computer automation systems. He
analysis class. He also prepared a Ph.D. thesis on the provided full electrical design services in heavy in-
Load Flow program using the third-order Taylor’s series iterative method. dustrial applications, primarily in the steelmaking and coal-preparation-related
In 1981, he joined Westinghouse Electric Corporation, Pittsburgh, PA. He sectors. His responsibilities included client and vendor liaison and supervision
was responsible for conduction power system studies, including short circuit, of engineers, designers, and drafters. From 1978 to 2003, he was a principal
protective device coordination, load flow, motor starting, harmonic analysis, Process Controls Systems Engineer with Bayer Corporation, Pittsburgh. He
switching transient, and transient stability studies. He also developed the Pro- provided design and specification of instrumentation and control systems for
tective Device Evaluation program on the main frame Control Data Corporation chemical processes. He configured programmable logic controller and distrib-
supercomputer. In 1984, he joined the Bangkok Oil Refinery, Thailand, where uted control systems. He was a Corporate Technical Consultant for power
his primary responsibility was to design the plant electrical distribution system distribution systems. He had been the principal Electrical Engineer on many
as well as the protection scheme for the steam turbine cogeneration facility. He major projects with Bayer Corporation. He joined the Electrical Services and
was also responsible for designing the plant automation, including the digital Systems Division, Eaton Corporation, Warrendale, PA, in 2004. At Eaton,
control system for the plant control room. In 1986, he rejoined Westinghouse he has been involved in a 230-kV substation design, ground grid design for
Electric Corporation. He performed power system studies and developed the substations, as well as in short circuit, protective device coordination, load flow,
Short Circuit and Protective Device Evaluation programs for the personal and arc-flash hazard analysis studies. He has also done power factor correction
computer. In 1998, he joined the Electrical Services and Systems Division, and harmonics studies to resolve power quality issues.
Eaton Corporation, Warrendale, PA, where he is currently a Senior Power
Systems Engineer in the Power Systems Engineering Department. He performs
a variety of power system studies, including switching transient studies using
the electromagnetic transients program for vacuum breaker/snubber circuit
applications. He continues to develop Excel spreadsheets for quick calculation
for short circuit, harmonic analysis, soft starting of motors, capacitor switching
transients, dc fault calculation, etc.
Vacuum Circuit Breaker Transients
During Switching of an LMF Transformer
Abstract— Switching transients associated with circuit breakers Frequent switching operations have been enabled by the
have been observed for many years. With the wide-spread development of the vacuum switch. The vacuum switch has
application of vacuum breakers for transformer switching, been designed for hundreds of operations in a day, for long life
recently this phenomenon has been attributed to a significant and low maintenance. With the advantages of the vacuum
number of transformer failures. Vacuum circuit breaker switch, also come the disadvantages of switching transient
switching of electric arc furnace and ladle melt furnace overvoltages. Depending on the characteristics of the vacuum
transformers raises concern because of their inductive currents. switch and the power system parameters, these switching
High frequency transients and overvoltages result when the transient overvoltages can be of significant magnitude and
vacuum breaker exhibits virtual current chop and multiple re-
frequency to cause transformer failure. High frequency
ignitions. This paper will present a detailed case study of
vacuum breaker switching of a new ladle melt furnace
transients and overvoltages result when the vacuum breaker
transformer involving current chopping and re-strike simulations exhibits virtual current chop and multiple re-ignitions.
using the electromagnetic transients program. A technique that According to statistics compiled by one insurance company [1],
involves a combination of surge arresters and snubbers will be the application of vacuum switches has resulted in numerous
applied to the ladle melt furnace to show the switching transients failures of arc furnace transformers. These failures rates have
can be successfully mitigated. Additionally, some practical been reduced by the application of surge arresters, surge
aspects of the physical design and installation of the snubber will capacitors and damping resistors [2]. The transients produced
be discussed. by the vacuum circuit breaker switching of an LMF
transformer and their mitigation are the focus of this paper.
Keywords- Switching Transients, vacuum breakers, SF-6
breakers, LMF transformer, EMTP simulations, surge arresters, A. The LMF Circuit of Interest
RC snubbers.
Consider the new LMF circuit of Fig. 1 that consists of a 50
MVA, 135/26.4 kV power transformer, a 2000 A SF-6
I. INTRODUCTION breaker, a 56 MVA, 27/10 kV auto-regulating transformer, a
Electric Arc Furnaces (EAF) are used widely in the steel 1200 A vacuum breaker and a 50 MVA, 25/0.53 kV furnace
industry in the production of carbon steel and specialty steels. transformer. The SF-6 circuit breaker is separated by 53 feet
The Ladle Melt Furnace (LMF) maintains the temperature of from the auto-regulating transformer. The vacuum circuit
liquid steel after tapping the EAF and facilitates changes in the breaker is separated by 28 feet from the LMF transformer. The
alloy composition through additives. In both cases, the furnace normal configuration (1) consists of the new LMF and the
transformer is a critical component of the furnace circuit that is existing 4EAF operating in parallel. One alternate
exposed to severe duty. The demands of the melt cycle may configuration (2) of the LMF circuit consists of 4OCB and
result in extensive damage to the furnace transformer due to 4EAF out-of-service with 4LTC in standby-service. A second
electrical failures in the transformer. With advances in alternate configuration (3) of the LMF circuit consists of LMF
technology and metallurgy, the operation of arc furnaces today LTC out-of-service with 4LTC switched on-line to source the
is significantly different. Heats of 4 to 5 hours with periods of LMF. Each of these three possible configurations of the LMF
moderate loading have been reduced to 3 to 4 hours with circuit was considered. Of the three, the normal configuration
consistently high loading. Accompanying the shorter heats of results in the shortest bus length between the vacuum breaker
sustained loading are many more switching operations. and the LMF transformer. The normal configuration also
Combined, these factors impose thermal and electrical stresses results in the shortest bus length between the SF-6 breaker and
on the transformer. the LMF transformer.
UTILITY
4713MVA 3PH SC
II. SWITCHING TRANSIENTS SIMULATIONS
9.26 X/R
Switching transients simulations were conducted in the
138KV electromagnetic transients program (EMTP) to investigate the
1600A possible failure of the new LMF transformer due to transient
50/66/83MVA overvoltages during the circuit switching of the new vacuum
135.3/26.4KV and SF-6 circuit breakers. The LMF circuit model developed
7.5%Z
13OHM
NC
27KV
NC
in EMTP consisted of the source, breaker, cable and
4OCB SF-6 BREAKER
transformer. The cable was represented by a Pi model
2 2000A 2000A consisting of the series impedance and half of the cable
ALUMINUM charging at each end. In some cases, multiple Pi models are
IPS BUS
53FEET
used to represent the cable. The vacuum or SF-6 breaker was
NC NO represented by a switch with different models for opening
NO NC
XFER BUS
(current chop), re-strike (excessive magnitude of TRV), re-
4AUTO LTC 3 1
AUTO LTC ignition (excessive frequency of TRV) and closing (pre-strike).
56MVA 56MVA
27-10KV 2 27-10KV The three phase transformer model consisted of the leakage
NC NO
3.3%Z 3.3%Z impedance, magnetizing branch, winding capacitances from
XFER BUS NC high-to-ground and low-to-ground. For oil filled transformers,
1700A 3
VACUUM BREAKER
1200A
the oil acts like a dielectric so the high-to-low capacitance was
HEAVY DUTY modeled. Two worst-case switching scenarios involving the
COPPER PIPE
28FEET
2000 A SF-6 breaker and the 1200 A vacuum breaker were
EAF XFMR LMF XFMR
simulated: 1) current chop by the breaker on de-energization of
2 50/56MVA 50/56MVA the LMF transformer and 2) re-ignition following opening of
25/.53KV 25/.53KV
2.5%Z 2.5%Z the breaker during energization of the LMF transformer. Also,
4EAF LMF the surge arrester was not modeled to show worst case.
38MW 20MW
(EXISTS) (NEW)
was reduced from 1,100 μsec to 230 μsec as shown below as T2 (μsec) 16 63
RRRV
shown in Fig. 8. This advantage alone does not justify the 5
Open,
Reignition IC 6 N (kV/μsec) 13.6 1.127 U
installation of an RC snubber at the primary of the auto- E2 32.7 71
Open, No T2 99.4 63
regulating transformer. A surge arrester at the primary of the 6 Reignition IC 6 Y RRRV 0.3293 1.127 A
auto-regulating transformer is adequate. Open, No
E2
T2
29.4
75
136
106
7 IO Reignition 6 N RRRV 0.3923 1.127 A
This results of the switching transient study of the LMF E2 29.4 136
operation during re-ignition conditions are summarized in 8 IO
Open, No
Reignition 6 Y
T2
RRRV
75
0.3923
106
1.127 A
Table IV. The re-ignition was simulated for either the 1200 A Notes: U = unnacceptable. A = acceptable. 1 = current chop on breaker opening. IO = Initially open. IC = initially closed.
A. RC Snubber Ratings
The specifications for the RC snubber circuit are given in
Fig. 9. The resistor average power rating at 40 °C is 1000 W
and the peak energy rating is 17,500 joules. This RC snubber
circuit, which has the same ratings as the one presently
installed at the 3EAF, provides adequate mitigation of the
voltage transients produced by either the vacuum breaker or
Case 8 – Voltage waveform With Snubber SF-6 breaker and simplifies the inventory of spare parts, i.e.
only one type of resistor and capacitor must be stocked.
LMF TX
50/56
MVA
R
100OHM SA
36kV Rating
C 29kV MCOV
0.15uF
REFERENCES