0% found this document useful (0 votes)
315 views

Sample Report 1

The document provides a table of contents for a report on an industrial training conducted at PZK Sdn Bhd from July 7th to September 7th, 2014. It includes an introduction describing the period of employment, nature of appointment as a consulting engineer, job location, and supervisor's details. The table of contents outlines 7 chapters covering the background of the company, weekly summary, technical report on a project, discussion, conclusions and references.

Uploaded by

ali
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
315 views

Sample Report 1

The document provides a table of contents for a report on an industrial training conducted at PZK Sdn Bhd from July 7th to September 7th, 2014. It includes an introduction describing the period of employment, nature of appointment as a consulting engineer, job location, and supervisor's details. The table of contents outlines 7 chapters covering the background of the company, weekly summary, technical report on a project, discussion, conclusions and references.

Uploaded by

ali
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 64

TABLE OF CONTENTS

ACKNOWLEDGEMENT 1
ABSTRACT 2
LIST OF FIGURES 3
LIST OF TABLES 4
CHAPTER 1 INTRODUCTION 5
1.1. Period of employment 5
1.2. Nature of appointment 5
1.3. Details of job location 5
1.4. Details of supervisor 6
1.5. Project involved 23
CHAPTER 2 BACKGROUND OF THE COMPANY 25
2.1. Corporate profile 25
2.2. Facilities 25
2.3. List of staffs 26
2.4. Organizational chart 28
2.5. Current list of projects 29
2.6. List of completed projects 33
2.7. Registration 43
2.8. Vision and Mission 43
CHAPTER 3 SUMMARY OF WEEKLY 44
CHAPTER 4 TECHNICAL REPORT 47
4.1. Project Background 47
4.2. Site location 48
4.3 Project site 48
4.4. Problem statement 50
4.5. Objective of the project 50
4.6. Scope of the project 50
4.7. Outcome of the project 51
4.8. Project constrains 51
4.9. Project needs 51
4.10. Design the project 52
CHAPTER 5 DISCUSSION AND RECOMMENDATIONS 56
CHAPTER 6 CONCLUSIONS 61
REFERENCES 62
APPENDICES 63
ACKNOWLEDGEMENT

Special thanks to my supervisor, Mr Noor Rizan Bin Sarmin as a General Manager and also
Head of Department of Civil and Structure, for the tolerance and valuable time sacrifice of his
busy schedule of work to guide me throughout this industrial training.

A big thanks to Mr Mohd Fazly Omar and Miss Azween Bt Md Yusof a Civil Engineer, and
Mrs Yuniza Mohd Fitri, a Project Engineer for the great experience throughout my training
period, because of their guidance, help and plenty of information about the civil and structure
and also infrastructure project.

To the entire staff of PZK Sdn Bhd who has given me a wonderful experience in work as a
team especially in a project that I have assigned during my training. Last but not least, my
gratitude to my dedicated lecturer, En Mohd Azuan Bin Tukiar as an Industrial Training
Coordinator of Faculty of Civil Engineering UiTM Pulau Pinang and Mrs Zuraisah Dollah as
my logbook supervisor for invaluable support.

1|Page
ABSTRACT

As a student of of Bachelor in Engineering (Hos) Civil (Infrastructure), industrial


training must be undertaken in order to meet the requirements of Engineering
Accreditation (EAC) for enable students to graduation. Industrial training purposes
was for disclose to students about the real working world and at the same time as the
initial preparations to students before entering employment. The duration for the
industrial training is nine week start from 7th July 2014 to 7th September 2014.

During the industrial training in PZK Sdn. Bhd., I have been arranged on the
department of civil and structure. Since the company is a consulting firm, most of the
work was for the design management which consist of work such as design by using
software Esteem 9 and Orion and manual design by doing spread sheet in Microsoft
Excel 2010, design checking and others that requires in design management. My main
task during this training is the design of the Masjid Cina that was still in the design
stage.

In addition, there are several times I will also visit the project site to monitor and
control the project Pusat Dakwah dan Tarbiah. I also need to prepare a report for the
project after the site visit. Other than that, I had attended meeting for the project in the
deflection liability period (DLP).

In the industrial training, I also need to do tender document for project Indah Water
Konsortium and also Medini development project. Other than that, I also do the Bill of
Quantities for the project Rancangan Bekalan Air Negeri Selangor Projek Mitigasi
Fasa 2.

Last but not least during this Industrial Training, it helps me to understand the job’s
need and increase my understanding to be more clear and wide in the civil engineering
field.

2|Page
LIST OF FIGURES

Table Description Page


No.
4.1 Site location 48
4.2 Project Site 48
4.3 Location picture 49
4.4 Location picture 49
4.5 Location picture 49
4.6 Step to design the whole structure 53
4.7 The 3D output from the Orion software for the roof 54
layout
4.8 The 3D output from the Esteem 9 for the roof layout 54
4.9 The structure of the Masjid Cina using Orion 55
4.10 Output from the Orion for the beam 55
4.11 Outpit from the Esteem 9 for the beam 55
5.1 The existing Monsoon drain 56
5.2 The existing Monsoon drain at the site project 57
5.3 The new propose Monsoon drain 57
5.4 The existing SYABAS waterpipe 58
5.5 Water reticulation layout plan 58
5.6 The existing IWK pipe 59
5.7 Sewerage layout plan 59

3|Page
LIST OF TABLES

Table Description Page


No.
3.1 Summary of Weekly 44
4.1 The differences between Eurocode and British 52
Standard

4|Page
CHAPTER 1 INTRODUCTION

1.1. PERIOD OF EMPLOYMENT

Employment period specified for this industrial training is nine weeks. The date
started from 7th July 2014 until 7th September 2014. Working hours of PZK Sdn. Bhd.
is 8.30 am to 5.30 pm, Monday to Friday. The lunch hour on Monday to Thursday is
at 1.00 p.m. to 2.00 p.m. While on Friday is 1.00 p.m. until 2.30 pm.

1.2. NATURE OF APPOINTMENT

PZK Company Sdn Bhd is a consulting engineer. Consulting engineers is a company


well versed especially in the field of design. As I undergo industrial training here,
most of the work I do is in the design field such as design using software or manually,
design review and others. For the site management and project management, only the
small number that I did here.

1.3. DETAIILS OF JOB LOCATION

PZK SDN. BHD.


(464305 – D)

CONSULTING ENGINEERING
No 7B Wisma PZK,
Jalan Suarasa 8/3 Lake Valley,
Bandar Tun Hussein Onn,
43200 Cheras,
Selangor Darul Ehsan.
Tel : +603-9076 4869 / 70
Fax : +603-9074 9844
E-mail : [email protected]

5|Page
1.4. DETAILS OF SUPERVISOR

1. Nama : Noor Rizan b. Sarmin


2. Jawatan : Genaral Manager
3. Status kakitangan : Tetap
4. Umur / Tarikh Lahir : 43 Tahun / 11 Jul 1970
5. Warganegara : Malaysia
6. Kelulusan Akademik :

Peringkat Kelulusan Bidang Tahun


Bil. Pengkhususan Nama Institusi
(Ijazah/Sarjana/PhD) Pengajian Dianugerahkan

1. Ijazah Kejuruteraan Civil 1993 Universiti Teknologi Malaysia

7. Keahlian Badan Profesional (sekiranya ada) :

Bil. Nama Badan Profesional No. Keahlian Tarikh Luput Keahlian


1. Registered with Board of Engineer Malaysia 21916A -

6|Page
8. Senarai Nama Projek/Kajian Yang Pernah Dilaksanakan :

Kerajaan/Swasta/Negara Tahun
Peranan/Jawatan
Luar (sekiranya Negara Projek/Projek
Bil. Nama Projek/Kajian Nama Pelanggan Di Dalam
Luar sila Semasa Nilai
Projek/Kajian
Nyatakan nama Negara) Projek

1. Cadangan Pembinaan Tadika Islam Kerajaan Majlis Agama 2013 Pengurus Projek /
di Jalan 1B, Taman Intan Baiduri, Islam Wilayah RM 2,000,000.00 Jurutera Kanan
Kepong 52100 Kuala Lumpur Persekutuan (Rekabentuk)

2. Cadangan Pembinaan Sebuah Kerajaan Jabatan Agama 2013 Pengurus Projek /


Masjid Cina di Jalan Davis Kuala Islam Wilayah RM 100,000,000.00 Jurutera Kanan
Lumpur Persekutuan (Rekabentuk)

3. Cadangan Pembinaan 2 Blok 342 Swasta Udaland Holdings 2013 Pengurus Projek /
Unit Pangsapuri 28 Dan 30 Berhad RM 150,000,000.00 Jurutera Kanan
Tingkat Termasuk 6 Tingkat (Rekabentuk)
Podium Tempat Letak Kereta Dan
Kemudahan Serta Kemudahan
7|Page
Pengawal Di Atas Lot 31677 Fasa
3 Zon 14, Bandar Tun Hussein
Onn, Mukim Cheras, Daerah Hulu
Langat Selangor Darul Ehsan

4. Perlaksanaan Projek Bekalan Air Kerajaan Jabatan 2013 Pengurus Projek /


terawat Pelbagai Sumber Di Kemajuan Orang RM 5,000,000.00 Jurutera Kanan
Perkampungan Asli Pos Lenjang Asli Malaysia (Rekabentuk)
Daerah Kuala Lipis Zone E Negeri
Pahang Tahun 2013

5. Cadangan Pembinaan Rangkaian Kerajaan Kementerian 2011 Pengurus Projek /


Paip Pembentungan Tambahan Tenaga, RM 20,000,000.00 Jurutera Kanan
(Sewer Extension) di Sungai Teknologi Hijau (Rekabentuk)
Kepayang (Bukit Galena), Bukit dan Air
Labu dan Galla Industrial Park), (KeTTHA)
Seremban, Negeri Sembilan.

8|Page
6. Cadangan Pembangunan Institusi Swasta Koperasi Belia 2011 Pengurus Projek
Pendidikan Agama Sekolah Islam Malaysia RM 14,000,000.00
Rendah Islam (SRI) dan Sekolah Berhad (KBI)
Menengah Islam (SMI) Bandar
Indera Mahkota, Kuantan, Di atas
Tanah Seluas 4 Ekar, Di Bandar
Indera Mahkota, Pahang Darul
Makmur

7. Projek Sistem Bekalan Air Untuk Swasta Perbadanan Aset 2011 Pengurus Projek /
projek Pembangunan Seremban Air Berhad RM 60,000,000.00 Jurutera Kanan
Barat-Selatan Negeri Sembilan (PAAB) (Rekabentuk)
Darul Khusus Pakej 2 :
Membekal dan Memasang Paip
Jenis 'M.S' Bergarispusat Nominal
1200mm, Tangki Sedutan,
Rumah Pam dan Kolam Imbangan
di Bandar Enstek hingga Kawasan
Bandar Sendayan.

9|Page
8. Design a New 25 Mld Saratok Kerajaan Kementerian 2011 Jurutera Kanan
Water Treatment Plant, Saratok, Kemajuan Luar RM 70,000,000.00 (Rekabentuk)
Sarawak Bandar dan
Wilayah

9. Membaikpulih dan Menaiktaraf Kerajaan Air Kelantan Sdn. 2011 Jurutera Kanan
Loji-Loji dan Tangki Air Negeri Bhd. (AKSB) RM 100,000,000.00 (Rekabentuk)
Kelantan

10. Design Works for the Upgrading Kerajaan Dewan 2011 Pengurus Projek /
of Connecting Road Between Bandaraya Kuala RM 17,000,000.00 Jurutera Kanan
Bandar Tasik Permaisuri and Salak Lumpur (Rekabentuk)
Selatan

11. Consultancy Services for the Swasta Petronas 2011 Pengurus Projek /
Construction of Blast Proof Penapisan Melaka RM 6,000,000.00 Jurutera Kanan
Building for Area 3A and 3B Sdn. Bhd. (Rekabentuk)

10 | P a g e
Personnel for PPMSB

12. Projek Bekalan Air Luar Bandar Kerajaan Kementerian 2011 Pengurus Projek /
(BALB) / Estet Tahun 2011, Kemajuan Luar RM 3,000,000.00 Jurutera Kanan
Negeri Selangor Bandar dan (Rekabentuk)
. Wilayah

13. Cadangan Membina dan Swasta Kolej Universiti 2011 Pengurus Projek
Menyiapkan Sebuah Stor Utama, Islam RM 1,000,000.00
Kolej Universiti Islam Antarabangsa
Antarabangsa Selangor (KUIS)

14. Cadangan Membina dan Swasta Bank Perusahaan 2010 Pengurus Projek
Menyiapkan 4 Unit Industri Teres Kecil dan RM 3,000,000.00
2 Tingkat (30' x 158'), 5 Unit Sederhana
Industri Teres 2 Tingkat (30' x Malaysia Berhad
112') 6 Unit Industri Teres 2 (SME Bank)
Tingkat (27' x 112') Di atas Lot PT

11 | P a g e
70839 (Lot Lama PT 10620)
Taman Perusahaan IKS, Seksyen
16 Bandar Baru Bangi, Mukim
Kajang, Daerah Hulu Langat
Selangor untuk Tet. Bank
Perusahaan Kecil dan Sederhana
Malaysia Berhad (SME Bank)

15. Projek Bekalan Air Luar Bandar Kerajaan Kementerian 2010 Pengurus Projek /
(BALB) Tahun 2010 Negeri Kemajuan Luar RM 3,000,000.00 Jurutera Kanan
Selangor Bandar dan (Rekabentuk)
Wilayah

Lembaga
16. Projek Naiktaraf Loji Air Sungai Kerajaan Kemajuan 2010 Pengurus Projek /
Cherul. Terengganu RM 15,000,000.00 Jurutera Kanan
Tengah (Rekabentuk)
(KETENGAH)

12 | P a g e
17. Design and Build Chengal Kerajaan Kementerian 2009 Pengurus Projek /
Lempong Secondary School, Pelajaran RM 23,000,000.00 Jurutera Kanan
Kuantan District, Pahang Darul Malaysia (Rekabentuk)
Makmur

18. Housing Scheme at Pelindung Swasta Uda Land (East) 2009 Pengurus Projek /
Heights, Phase 1, Mukim Kuala Sdn. Bhd. RM 12,000,000.00 Jurutera Kanan
Kuantan, Pahang Darul Makmur (Rekabentuk)

19. Slope Rehabilitation Works at Swasta Syarikat Bekalan 2009 Pengurus Projek /
Syabas Facilities Air Selangor Sdn. RM 2,000,000.00 Jurutera Kanan
Bhd. (SYABAS) (Rekabentuk)

20. Cadangan Pembinaan 4 Unit Kedai Swasta Yayasan Anak 2009 Pengurus Projek /
Pejabat 3 Tingkat Di atas Lot Yatim RM 3,000,000.00 Jurutera Kanan
PT16351 (HSD 69015), Bandar (YAYAKEM) (Rekabentuk
Semenyih, Daerah Hulu Langat,

13 | P a g e
Selangor Darul Ehsan.

21. Proposed Pipe Rehabilitation Swasta Ranhill Engineers 2009 Jurutera Kanan
Works For Year 2009 For The & Constructors RM 10,000,000.00 (Rekabentuk)
State Of Johor Sdn. Bhd.

22. Cadangan Membina dan Kerajaan Kementerian 2008 Pengurus Projek /


Menyiapkan Sebuah Sekolah Pelajaran RM 10,000,000.00 Jurutera Kanan
Kebangsaan Kampung Raja, Malaysia (Rekabentuk)
Daerah Cameron Highlands,
Pahang Darul Makmur

23. Greater Kuantan Water Supply Kerajaan Jabatan Bekalan 2008 Pengurus Projek /
Project Air Pahang RM 14,000,000.00 Jurutera Kanan
- New Kobat Raw Water Pumping (Rekabentuk)
Station
Pakej 8 : Membekal, Memasang,
Mengujiterima dan Mentauliah
Pam Air Mentah Termasuk Kerja-

14 | P a g e
Kerja Elektrikal Serta Membina
dan Menyiapkan Sesebuah
Mukasauk Dan Kerja-Kerja
Berkaitan di Kg. Kobat, Pahang
Darul Makmur

24. Rancangan Bekalan Air Seberang Kerajaan Jabatan Bekalan 2008 Jurutera Kanan
Temerloh Air Pahang RM 35,000,000.00 (Rekabentuk)
Pakej 2 : Membina, Menyiapkan,
Menguji dan Mentauliahkan Kerja-
Kerja Sivil, Mekanikal, Elektrikal
Dan Yang Berkaitan Bagi
Melengkapkan Loji Air Seberang
Temerloh, Pahang Darul Makmur.

25. Rancangan Bekalan Air Seberang Kerajaan Jabatan Bekalan 2008 Jurutera Kanan
Temerloh Air Pahang RM 12,000,000.00 (Rekabentuk)
Pakej 4 : Membina, Menyiapkan,
Menguji dan Mentauliahkan Kerja-

15 | P a g e
Kerja Sivil, Mekanikal, Elektrikal
Dan Yang Berkaitan Untuk Muka
Sauk Loji Air Seberang Temerloh,
Pahang Darul Makmur

26. Hostel Bolcks University Inst. Kerajaan Jabatan Kerja 2008 Pengurus Projek /
Tech. MARA, Terengganu Branch, Raya, Kuala RM 20,000,000.00 Jurutera Kanan
Bukit Besi, Terengganu Lumpur (Rekabentuk)

27. Cadangan Membina dan Kerajaan Universiti 2008 Pengurus Projek /


Menyiapkan 10 Tingkat Bangunan Teknologi RM 18,000,000.00 Jurutera Kanan
Tambahan Fakulti Sains Komputer Malaysia (Rekabentuk)
dan Sistem Maklumat (RMK 9) di
Universiti Teknologi Malaysia,
Skudai, Johor

28. Upgrading Works to Enchance Kerajaan Kementerian 2007 Jurutera Kanan


Security at the Drug Rehabilitation Dalam Negeri RM 5,000,000.00 (Rekabentuk)

16 | P a g e
Centre, Jerantut District, Pahang
Darul Makmur

29. Cadangan Membina 1 unit Banglo Swasta Tn. Hj. Abdul 2006 Pengurus Projek /
2.1/2 Tingkat Di Atas Lot Halim b. Ahmad RM 1,000,000.00 Jurutera Kanan
PT40248, No. 73, Jln Seri Putra (Rekabentuk)
8/1, Bandar Seri Putra Bangi
43000 Kajang, Selangor darul
Ehsan.

30. Projek Pembinaan Bangunan Kerajaan Jabatan Kerja 2006 Jurutera Kanan
Herbarium di Institut Penyelidikan Raya, Kuala RM 4,000,000.00 (Rekabentuk)
Malaysia (FRIM) Kepong, Lumpur
Selangor

31. Merekabentuk, Membina dan Kerajaan Jabatan Bekalan 2005 Jurutera Kanan
Menyiapkan Kerja Menaiktaraf Air Pahang RM 5,000,000.00 (Rekabentuk)
dan Lain-lain Kerja Berkaitan

17 | P a g e
untuk Loji Pembersih Air Di
Mempateh, Temerloh, Pahang
Darul Makmur

32. Upgrading of Jalan Haji Ahmad, Kerajaan Jabatan Kerja 1997-2005 Jurutera Kanan
Kuantan, Pahang Skop kerja : Raya, Pahang RM 40,000,000.00 (Rekabentuk)

33. Proposed Design For Rural Road Kerajaan Kementerian 2005 Jurutera Kanan
Construction From Kg. Relau To Pembangunan RM 10,000,000.00 (Rekabentuk)
Sg. Punti, Bandar Baharu, Kedah Luar Bandar /
Jabatan Kerja
Raya, Kedah

34. Design of Greater Kuantan Water Kerajaan Jabatan Bekalan 2004 Jurutera Kanan
Supply Phase III Air Pahang RM 2,000,000.00 (Rekabentuk)

18 | P a g e
35. Proposed Factory /Warehouse with Swasta Boustead Sissons 2002 Jurutera Kanan
3 Storey Office Block, Canteen Paints Sdn Bhd RM 10,000,000.00 (Rekabentuk)
and Ancillary Building at Nilai For
Boustead Sissons Paints Sdn. Bhd.
Cost

36. Proposed 7 Block Low Cost Swasta Mutiara Rini Sdn 2001 Jurutera Kanan
Apartment and 4 Block Medium Bhd RM 20,000,000.00 (Rekabentuk)
Cost Apartment at Mutiara
Damansara for Mutiara Rini Sdn.
Bhd.

37. Proposed Government Buildings Swasta Putrajaya Holding 1999 Jurutera Rekabentuk
(Block E2 & E3) Development Sdn Bhd RM 140,000,000.00
Parcel E, Precinct 1, Putrajaya for
Putrajaya Holdings Sdn. Bhd.

19 | P a g e
38. Proposed Institut Kemahiran Belia Kerajaan Kementerian 1998 Pengurus Projek /
Negara at Pagoh Muar Johor For Kerja Raya RM70,000,000.00 Jurutera Rekabentuk
Kementerian Belia dan Sukan.

39. Proposed Institut Kemahiran Belia Kerajaan Kementerian 1998 Jurutera Rekabentuk
Negara at Bachok Kelantan for Kerja Raya RM 60,000,000.00
Kementerian Belia dan Sukan

40. Proposed Housing Scheme at Parit Swasta Sime Darby Land 1997 Jurutera Rekabentuk
Buntar for Sime Darby Land RM 150,000,000.00

41. Proposed Institut Latihan Swasta Petronas 1996 Jurutera Rekabentuk


Perindustrian Petronas at Batu RM 7,000,000.00
Rakit, Terengganu.

20 | P a g e
42. Proposed Design and Built Kerajaan Kementerian 1997 Pengurus Projek /
Sekolah Kebangsaan Batang Pendidikan RM 9,000,000.00 Jurutera Rekabentuk
Berjuntai for Kementerian Malaysia
Pendidikan Malaysia.

43. Proposed Design and Built Kerajaan Kementerian 1997 Jurutera Rekabentuk
Sekolah Kebangsaan Segambut Pendidikan RM 7,000,000.00
Makmur Kuala Lumpur for Malaysia
Kementerian Pendidikan Malaysia.
Kebangsaan Segambut Makmur
Kuala Lumpur for Kementerian
Pendidikan Malaysia.

44. Proposed Housing Scheme at Kerajaan UDA 1995 Jurutera Rekabentuk


Teluk Air Tawar, Seberang Prai RM 40,000,000.00
for Urban Development Authority
(UDA)

21 | P a g e
45. Proposed Malaysian French Kerajaan Majlis Amanah 1994 Jurutera Rekabentuk
Institute at Bangi for Majlis Rakyar (MARA) RM 20,000,000.00
Amanah Rakyat (MARA)

9.Working experience :

Tarikh Mula Tarikh Tamat Bilangan Tahun


Perkhidmatan Perkhidmatan Pengalaman
Bil. Nama Firma Jawatan Dalam Firma
(DD/MM/YYYY) (DD/MM/YYYY) (B-A)
(A) (B)
1 PZK Sdn. Bhd. General Manager 2003 Current 11 Tahun

2 A.SANI & ASSOCIATES Civil & Structural 2001 2003 2 Tahun


SDN. BHD. Engineer
3 WAN HUSIN & Civil & Structural 1993 2001 8 Tahun
ASSOCIATES SDN. Engineer
BHD.
JUMLAH 21 Tahun

22 | P a g e
1.5. PROJECT INVOLVED

a. Cadangan Merekabentuk Dan Membina Masjid Cina Di Atas Lot 1220, Jalan
Devis, Wilayah Perseketuan Kuala Lumpur

b. Projek Naiktaraf Loji Air Sungai Cherul Pakej 2: Membina, Menyiapkan, Menguji
Dan Mentauliah Kerja-Kerja Sivil, Mekanikal Dan Elektrikal Dan Yang Berkaitan
Bagi Melengkapkan Loji Air Sungai Cherul Kemaman, Terengganu Darul Iman.

c. Cadangan Membina Dan Menyiapkan Sebuah Rumah Banglo Dua Tingkat Di No.
16, Jalan Gunung Nuang, Bukit Bandaraya Shah Alam.

d. Cadangan Pembinaan Loji Rawatan Air Ramuan China Kecil.

e. Rancangan Bekalan Air Negeri Selangor. Projek Mitigasi Fasa 2: Skim Rasa.
Projek Pengagihan Semula Kapasiti Rekabentuk Air Terawat Dari Loji Rawatan
Air Sg Selangor Fasa 3 (Ssp 3). Pakej 1 : Membekal & Memasang Paip Jenis
Keluli Lembut (Mild Steel) Bergaris Pusat 100mm & Kerja-Kerja Berkaitan Dari
Batu Arang Ke Bandar Tasik Puteri, Mukim Rawang, Daerah Gombak.

f. Projek Pembangunan Pusat Dakwah Dan Tarbiah Kg. Sungai Merab Tengah Di
Atas Sebahagian Lot 2996, Mukim Dengkil, Daerah Sepang, Selangor.

g. Loji Rawatan Air Sungai Labu, Kampung Lembah Paya Salak Tinggi, Sepang
Selangor.

h. Pakej 2: Kerja-Kerja Membekal Dan Memasang Paip Jenis Keluli Lembut (Mild
Steel, M.S) Bergarispusat Nominal 750 Mm, Membina Dan Menyiapkan Tangki
Imbangan Berkapasiti 30 Ml Serta Kerja-Kerja Sivil, Elektrikal Dan Yang
Berkaitan Di Tangki Imbangan Di Gadong, Seremban Negeri Sembilan Darul
Khusus.

i. Uitm Cawangan Terengganu, Kampus Bukit Besi.

j. Indah Water Konsortium (IWK).


23 | P a g e
k. Sungai Semenyih Water Supply Scheme Asset Replacement Works.

l. Projek Sistem Bekalan Air Untuk Pembangunan Seremban Barat, Negeri


Sembilan.

m. The Proposed Development of Office Towers On Plot B9 At Zone B, Medini


Iskandar Malaysia, Johor Darul Takzim.

24 | P a g e
CHAPTER 2 BACKGROUND OF THE COMPANY

2.1 CORPORATE PROFILE

PZK SDN. BHD., also known as Perunding Zakariah and Kemas is a consultancy
firm that are specializing in the civil and structural consultancy, water treatment plant
and water distribution system to building structures, industrial, management &
planning services. PZK is a 100% Bumiputera and start incorporated in 1995.

2.2. FACILITIES

PZK engineering software comprises are as follows:-


a. Autocad R14
b. Staad-Pro 2003
c. Esteem Version 6
d. Esteem Version 9
e. Infoworks Version 5
f. EW3D – Road and Earthworks
g. Dra Net – Drainage System
h. Microsoft Project
i. Infoworks
j. Epa Net
k. Orion
l. Autocad LT 2011

25 | P a g e
2.3. LIST OF STAFFS

DESIGNATION QUALIFICATIONS YEARS OF


EXPERIENCE

MANAGING DIRECTOR
Ir, ZAKARIAH KEMAS SALLEH Bsc. Civil Eng. (Salford, U.Kingdom) 32
Msc. Eng. (Newcastle Upon-Tyne, U.K)

EXECUTIVE DIRECTOR
Ir. KAMAL AZWAN ABBAS Bsc. Eng. (Plymouth, U.K) 30

DIRECTOR / HEAD OF DEPARTMENT ELECTRICAL


Ir. SITI MUTRIKAH BT HJ. ABD MOKHSIN Bsc. Eng (Hons) Electrical, UiTM 30

ASSOCIATED DIRECTOR
Ir. MOHD NAZARI BIN HJ. JAFFAR Bsc. Eng (Hons) Mech, UTM 20

GENERAL MANAGER
NOOR RIZAN SARMIN Bsc. Eng. (Hons) in Civil , UTM 21

HEAD OF DEPARTMENT MECHANICAL


ZAHIDIN HARUN Bsc. Eng. (Mechanical) UM 24

ENGINEERS
Ir. MOHAMAD BIN AWANG B. Eng (Hons) in Civil Eng. (UK) 26
AZRUL HAFIZ ABD AZIZ B. Eng (Hons) in Civil & Structural (UKM) 14
MOHD ROSLI AWANG B.Eng (Hons) Electrical 9
AHMAD ZHAFRI B. AHMAD @ AHMAD ZAKI B.Eng (Hons) Civil, UiTM 7
AZWEEN MD YUSOF B.Eng (Hons) Civil, UiTM 7
YUNIZA MOHD FITRI B.Eng (Hons) Civil, USM 7
MOHD FAZLY OMAR B.Eng (Hons) Civil & Environment, UKM 6
MIOR AHMAD AFZAL B. AHMAD MUSTAZA B.Eng (Hons) Mechanical, UiTM 4
MOHD ZULFADHLI JOHARI B.Eng (Hons) Civil, UTP 3
FAHMI AHMAD RASHIDI B.Eng (Hons) Mechanical, UNITEN 2

TECHNICAL ASSISTANTS
SALBIAH LEE Dip. Civil Eng, UiTM 19
MUNAWARAH HJ. MUHAMAD Dip. In Town & Regional Planning, UiTM 23
KAMALRUDDIN ABU BAKAR Dip. Mech. Eng, UTM 11
MOKHTAR JUSUH Dip. Civil. Eng (UTM) 24

26 | P a g e
MORIYAH BT DOL Dip. Drafting 21

ADMINISTRATION
HAMIDAH ABDUL RAHMAN SPM 16
NORAZLINA ZAKARIA SPM 27
MAZZURA MAMAD SPM 8
IMAM WAHYUDI SUHARDI SPM 4

ACCOUNT
SITI HAJAR ABDUL HADI Deg. In Mngt’ Technology (Finance) UTM 6

CLERKS
ROMZI ISMAIL SPM 16

27 | P a g e
2.4. ORGANIZATIONAL CHART

MANAGING DIRECTOR
Ir. ZAKARIAH KEMAS SALLEH
EXECUTIVE DIRECTOR
Ir. KAMAL AZWAN ABBAS BOARD OF
DIRECTOR DIRECTORS
Ir. SITI MUTRIKAH HJ. ABD
MOKHSIN

ASSOCIATED DIRECTOR
Ir. MOHD NAZARI B. HJ. JAFFAR

GENERAL MANAGER
NOOR RIZAN
SARMIN

ENGINEERS C&S M&E BRANCH


MIOR AHMAD AFZAL DEPARTMENT DEPARTMENT

SITI HAJAR ABDUL HADI (Acc. Exec) KUANTAN


HEAD OF DEPARTMENT HEAD OF DEPARTMENT (HOD)
NORAZLINA ZAKARIA (Clerk) HEAD OF DEPARTMENT (HOD) ROMZI BT
(HOD) ELECTRICAL
MAZZURA MAMAD HAMIDAH ABD RAHMAN ISMAIL
NOOR RIZAN SARMIN IR SITI MUTRIKAH HJ ABD MOKHSIN
IMAM WAHYUDI

ASSOCIATED DIRECTOR STRUCTURE / WATER SUPPLY HEAD OF DEPARTMENT (HOD) ENGINEERS


ROAD /
Ir. MOHD NAZARI B. HJ. JAFFAR INFRASTRUCTURE / MECHANICAL MOHD ROSLI
BRIDGE
WASTE WATER ZAHIDIN HARUN AWANG

ENGINEERS
ENGINEERS MOHD ZULFADHLI ENGINEERS
AZWEEN MD YUSOF JOHARI IR MOHAMAD B. AWANG
MOHD FAZLY MOKHTAR JUSOH AHMAD ZHAFRI B. AHMAD ZAKI
OMAR YUNIZA MUHAMMAD FITRI AZRUL HAFIZ ABD AZIZ

DRAFTING
MUNAWARAH MUHAMAD
KAMALRUDDIN B. ABU
BAKAR
MOKHTAR B. JUSOH
MORIYAH DOL
SALBIAH LEE

28 | P a g e
2.5. CURRENT LIST OF PROJECT

WATER TREATMENT PLANT

Item Name of Projects Clients Contract Value


1 Membekal dan Menyiapkan Bekalan Air Terawat Kementerian Kemajuan Luar RM5,000,000.00
Pelbagai Sumber Di Perkampungan Orang Asli, Zon E Bandar Dan Wilayah
Pahang
2 Greater Kuantan Water Supply Project Jabatan Bekalan Air Pahang RM40,000.000.00
- New Kobat Raw Water Pumping Station
Pakej 8 : Membekal, Memasang, Mengujiterima dan
Mentauliah Pam Air Mentah Termasuk Kerja-Kerja
Elektrikal Serta Membina dan Menyiapkan Sesebuah
Mukasauk Dan Kerja-Kerja Berkaitan di Kg. Kobat,
Pahang Darul Makmur

3 Design and Upgrade Thirteen (13) Water Treatment Air Kelantan Sdn. Bhd. RM59,000,000.00
Plant in the State of Kelantan Darul Naim

4 Projek Menaiktaraf Loji Air Sungai Cherul, Kemaman, Lembaga Kemajuan Terengganu RM4,510,999.00
Terengganu Pakej Tengah (KETENGAH) (RE-TENDER)
2 : Membina, Menyiapkan, Menguji dan Mentauliah
Kerja-Kerja Sivil, Mekanikal, Elektrik dan Yang Berkaitan
Bagi Melengkapkan Loji Air Sungai Cherul, Kemaman,
Terengganu

5 Design a New 25 Mld Saratok Water Treatment Plant, Jabatan Bekalan Air Pahang RM13,400,000.00
Saratok, Sarawak

29 | P a g e
6 Projek Sistem Bekalan Air Untuk projek Pembangunan Perbadanan Aset Air Berhad RM50,000,000.00
Seremban Barat-Selatan Negeri Sembilan Darul Khusus (PAAB)
Pakej 2 : Membekal dan Memasang Paip Jenis 'M.S'
Bergarispusat Nominal 1200mm, Tangki Sedutan,
Rumah Pam dan Kolam Imbangan di Bandar Enstek
hingga Kawasan Bandar Sendayan.

BUILDING / STRUCTURES AND HOUSING

Item Name of Projects Clients Contract Value


1 Projek Cadangan Pembinaan Baru Masjid Cina Jalan MAIWP RM20,000,000.00
Davis, Di Wilayah Persekutuan Kuala Lumpur

2 Pemasangan Sistem Elektrik Untuk Menaiktaraf Jalan JKR RM2,605,000.00


Persekutuan FT006 Dari Teluk Kumbar Ke Lapangan
Terbang Antarabangsa Pulau Pinang, Bayan Lepas,
Pulau Pinang.

3 Design And Build Chengal Lempong Secondary School, Kementerian Pelajaran Malaysia RM21,391,600.00
Kuantan District Pahang Darul Makmur for the Ministry of
Education, Malaysia

4 Design On Electrical And ICT Works For UiTM Selangor Jabatan Kerja Raya, Kuala RM126,000,000.00
Branch, Sg. Buloh, Selangor Lumpur

5 Cadangan Perumahan Pelindung Heights (Fasa 1B), Udaland (East Sdn. Bhd.
Mukim Kuala Kuantan, Daerah Kuantan.

6 Cadangan Pembinaan 4 Unit Kedai Pejabat 3 Tingkat Di Yayasan Anak Yatim (YAYAKEM)
atas Lot PT16351 (HSD 69015), Bandar Semenyih, Daerah
Hulu Langat, Selangor Darul Ehsan.

30 | P a g e
7 Cadangan Membina dan Menyiapkan 4 Unit Industri Bank Perusahaan Kecil dan RM16,000,000.00
Teres 2 Tingkat (30' x 158'), 5 Unit Industri Teres 2 Tingkat Sederhana Malaysia Berhad (SME
(30' x 112') 6 Unit Industri Teres 2 Tingkat (27' x 112') Di Bank)
atas Lot PT 70839 (Lot Lama PT 10620) Taman
Perusahaan IKS, Seksyen 16 Bandar Baru Bangi, Mukim
Kajang, Daerah Hulu Langat Selangor untuk Tet. Bank
Perusahaan Kecil dan Sederhana Malaysia Berhad (SME
Bank)

8 Consultancy Services for the Construction of Blast Proof Petronas Penapisan (Melaka)
Building for Area 3A and 3B Personnel for PPMSB Sdn. Bhd.

9 Cadangan Merekabentuk, Membina, Menyiapkan dan Kementerian Pelajaran Malaysia


Menguji Sekolah Menengah Kebangsaan Agama Kuala
Lipis, Mukim Penjom, Daerah Lipis, Pahang Darul
Makmur
10 Cadangan Pembangunan Institusi Pendidikan Agama Koperasi Belia Islam Malaysia
Sekolah Rendah Islam (SRI) dan Sekolah Menengah Berhad (KBI)
Islam (SMI) Bandar Indera Mahkota, Kuantan, Di atas
Tanah Seluas 4 Ekar, Di Bandar Indera Mahkota, Pahang
Darul Makmur

11 Cadangan Membina dan Menyiapkan Sebuah Stor Kolej Universiti Islam


Utama, Kolej Universiti Islam Antarabangsa Selangor Antarabangsa (KUIS)

12 Cadangan Membina Sebuah Masjid Di Bandar Sri Putra, Jabatan Agama Islam Selangor RM9,000,000.00
Bangi (JAIS)

31 | P a g e
ROAD AND BRIDGES

Item Name of Projects Clients Contract Value


Kementerian Pembangunan Luar
Proposed Design For Rural Road Construction From Kg. RM30,000,000.00
1 Bandar / Jabatan Kerja Raya,
Relau To Sg. Punti, Bandar Baharu, Kedah (Pending)
Kedah

Design Works For The Upgrading Of Connecting Road


Dewan Bandaraya, Kuala
2 Between Bandar Tasik Permaisuri And Salak Selatan, RM16,000,000.00
Lumpur
Kuala Lumpur

Dewan Bandaraya, Kuala RM10,000,000.00


3 Proposal Of Beautification And Upgrade Haji Taib Road
Lumpur (Pending)

Projek Penswastaan Lebuhraya bertingkat Sungai Besi Lembaga Lebuhraya Malaysia


4 RM6,000,000.00
Ulu-Klang (Seksyen B - Cheras ke Ulu Klang) (LLM)
Cadangan bagi mengemukakan rekabentuk Alternatif
oleh Projek Delivery Partner (PDP) bagi Projek di bawah
EPP 5 : River of life (ROL), NKEA Greater Kuala Lumpur / Kementerian Tenaga/Teknologi
5 RM300,000,000.00
Klang Valley - Projek Pembinaan Loji Rawatan Hijau dan Air (KeTTHA)
Kumbahan Serantau Batu, Jinjang Kepong, Kuala
Lumpur.

SEWERAGE

Item Name of Projects Clients Contract Value


1 Cadangan Pembinaan Rangkaian Paip Pembentungan Kementerian Tenaga, Teknologi RM20,000,000.00
Tambahan (Sewer Extension) di Sungai Kepayang (Bukit Hijau dan Air (KeTTHA)
Galena), Bukit Labu dan Galla Industrial Park),
Seremban, Negeri Sembilan.

32 | P a g e
2.6. LIST OF COMPLETED PROJECTS

WATER TREATMENT PLANT

Item Name of Projects Clients Contract Value Remarks


1 Kuala Terengganu Water Supply Project Phase III Jabatan Bekalan Air RM54,800,000.00 Completed 2000
Construction, Completion, Testing and Terengganu / Syarikat Air
Commissioning of Kepong II Water Treatment Plant Terengganu Sdn. Bhd.
and Associated Works

2 Design, Build and Finance of Chicha Water Supply ACPI Engineering / Air RM77,000,000.00 Completed 2003
Scheme, Kota Bharu, Kelantan Darul Naim Kelantan Sdn. Bhd.

3 Rancangan Bekalan Air Triang Jabatan Bekalan Air Pahang RM24,911,900.00 Completed 2000
Pakej 1 : Membina dan Menyiapkan Loji Air Baru
Triang dan Kerja-Kerja Lain Berkaitan di Triang, Bera,
Pahang
4 Rancangan Bekalan Air Triang Jabatan Bekalan Air Pahang RM498,800.00 Completed 2001
Pakej 1(a) : Membekal, Memasang dan
Mengujiterima Pam Air Mentah di Mukasauk
Sediada dan Kerja-Kerja Berkaitan di Triang, Bera,
Pahang
5 Rancangan Bekalan Air Triang Jabatan Bekalan Air Pahang RM1,685,698.00 Completed 2001
Pakej 2 : Membina dan Menyiapkan Tangki Air
Tetulang dan Kerja-Kerja Lain Berkaitan di Triang,
Bera, Pahang

33 | P a g e
6 Rancangan Bekalan Air Triang Jabatan Bekalan Air Pahang RM4,636,805.50 Completed 2002
Pakej 3 : Membekal dan Memasang Paip Jenis M.S.
250mm Dia dan Kerja-Kerja Lain Berkaitan di Triang,
Bera, Pahang

7 Rancangan Bekalan Air Triang Jabatan Bekalan Air Pahang RM3,415,970.00 Completed 2002
Pakej 4 : Membekal dan Memasang Paip Jenis M.S.
750mm Dia dan Kerja-Kerja Lain Berkaitan di Triang,
Bera, Pahang

8 Rancangan Bekalan Air Triang Jabatan Bekalan Air Pahang RM3,571,023.14 Completed 2005
Pakej 5 : Membekal dan Memasang Paip Jenis M.S.
750mm Dia dan Kerja-Kerja Lain Berkaitan di Triang,
Bera, Pahang

9 Rancangan Bekalan Air Seberang Temerloh, Jabatan Bekalan Air Pahang RM2,835,341.50 Completed 2005
Temerloh, Pahang
Pakej 1 : Membekal dan Memasang Paip Jenis Mild
Steel dan HDPE Bergaris Pusat Nominal 400mm dia.
Serta Kerja-Kerja Bersangkutan Dari Tangki Air Bukit
Angin ke Hospital Baru, Seberang Temerloh, Pahang
Darul Makmur

10 Rancangan Bekalan Air Seberang Temerloh, Jabatan Bekalan Air Pahang RM9,716,636.99 Completed 2005
Temerloh, Pahang
Pakej 9 : Sebuah Rumah Pam dan Kerja-Kerja
Berkaitan di Tapak Cadangan Loji Air Seberang
Temerloh, Temerloh, Pahang Darul Makmur

34 | P a g e
11 Rancangan Bekalan Air Seberang Temerloh, Jabatan Bekalan Air Pahang RM1,921,235.20 Completed 2005
Temerloh, Pahang
Pakej 10A : Cadangan Membekal dan Memasang
Paip Jenis MS Bergarispusat 400mm Dia. Bagi
Menggantikan Paip AC Sediada Serta Kerja-Kerja
Bersangkutan Dari Jambatan Sultan Abu Bakar ke
Simpang Pulai, Temerloh, Pahang Darul Makmur

12 Rancangan Bekalan Air Seberang Temerloh, Jabatan Bekalan Air Pahang RM2,020,512.00 Completed 2005
Temerloh, Pahang
Pakej 10B : Cadangan Membekal dan Memasang
Paip Jenis MS Bergarispusat 400mm Dia. Bagi
Menggantikan Paip AC Sediada Serta Kerja-Kerja
Bersangkutan Dari Simpang Kg. Paya Pulai ke Tangki
Air Batu 8, Temerloh, Pahang Darul Makmur

13 Rancangan Bekalan Air Greater Kuantan Fasa II Jabatan Bekalan Air Pahang RM13,336,248.00 Completed 1998
Pakej 4A : Membekal, Memasang dan Menguji
Terima Air Mentah Tambahan dan Kerja-Kerja
Berkaitan di Kg. Kobat, Kuantan, Pahang Darul
Makmur
14 Rancangan Bekalan Air Greater Kuantan Fasa II Jabatan Bekalan Air Pahang RM1,334,499.00 Completed 1998
Pakej 4A(i) : Membaikpulih, Memasang dan
Mengujiterima Pam Air Mentah ke Bukit Ubi dan
Kerja-Kerja Berkaitan di Kg. Kobat, Kuantan, Pahang
Darul Makmur.

15 Rancangan Bekalan Air Greater Kuantan Fasa II Jabatan Bekalan Air Pahang RM5,197,842.00 Completed 1998
Pakej 4A(ii) : Kerja-Kerja Membaikpulih Barrage
Gates dan Kerja-Kerja Berkaitan di Kg. Kobat,
Kuantan, Pahang Darul Makmur

35 | P a g e
16 Rancangan Bekalan Air Greater Kuantan Fasa II Jabatan Bekalan Air Pahang RM3,203,030.75 Completed 1998
Pakej 4D : Membina dan Menyiapkan Pusat
Kawalan serta Kerja-Kerja Berkaitan di Kg. Kobat,
Kuantan, Pahang Darul Makmur

17 Rancangan Bekalan Air Greater Kuantan Fasa II Jabatan Bekalan Air Pahang RM6,491,021.00 Completed 1998
Pakej 6B : Memasang Paip Keluli Lembut Bersaiz
900mm, 1200mm dan 1300mm dari Loji Air Semambu
ke Tangki Air Bukit Tg. Putus, Pahang Darul Makmur

18 Rancangan Bekalan Air Greater Kuantan Fasa II Jabatan Bekalan Air Pahang RM2,780,191.00 Completed 1998
Pakej 6C : Memasang Paip Keluli Lembut Bersaiz
1300mm dari Tangki Air Bukit Tg. Putus ke Rumah
Pam KM20, Kuantan, Pahang Darul Makmur

19 Rancangan Bekalan Air Greater Kuantan Fasa II Jabatan Bekalan Air Pahang RM4,488,480.00 Completed 1998
Pakej 6D : Membekal dan Memasang Paip 'Ductile
Iron' Bergarispusat Nominal 400mm dan 450mm Serta
Kerja-Kerja Bersangkutan dari Loji Air Lepar Hilir ke
Kolej Matrikulasi, Kuantan, Pahang Darul Makmur

20 Merekabentuk, Membina dan Menyiapkan Kerja Jabatan Bekalan Air Pahang RM7,205,000.00 Completed 2005
Menaiktaraf dan Lain-Lain Kerja Berkaitan Untuk Loji
Pembersih Air Di Mempateh, Temerloh, Pahang Darul
Makmur

21 Study, Design, Upgrading and Additional Water Universiti Teknologi Malaysia RM4,800,000.00 Completed 2000
Reticulation System for UTM Campus, Skudai, Johor
Darul Takzim

36 | P a g e
22 Projek Bekalan Air Chenor, Maran Jabatan Bekalan Air Pahang RM4,357,486.00 Completed 2000
Construction and Completion of Continuous
Microfiltration (CMF) Treatment Plant and Related
Works

23 Upgrading of Kg. New Zealand Water Treatment Jabatan Bekalan Air Pahang RM1,000,000.00 Completed
Plant, Pahang Darul Makmur

24 Upgrading of Bera Treatment Plant, Temerloh, Jabatan Bekalan Air Pahang RM1,000,000.00 Completed
Pahang
25 Membina dan Menyiapkan Projek Bekalan Air Luar Kementerian Pembangunan RM5,000,000.00 Completed 2002
Bandar (BALB) Secara Konsep Bersepadu Bagi Luar Bandar dan Wilayah
Negeri Perak (Pakej 1 - 2001/2002)

26 Membina dan Menyiapkan Projek Bekalan Air Luar Kementerian Pembangunan RM8,950,000.00 Completed 2002
Bandar (BALB) Secara Konsep Bersepadu Bagi Luar Bandar dan Wilayah
Negeri Perak (Pakej 2)

27 Membina dan Menyiapkan Projek Bekalan Air Luar Kementerian Pembangunan RM8,950,000.00 Completed 2003
Bandar (BALB) Secara Konsep Bersepadu Bagi Luar Bandar dan Wilayah
Negeri Perak (Pakej 2)

28 Projek Sistem Bekalan Air Untuk Pembangunan Syarikat Air Negeri Sembilan RM37,507,009.50 Completed 2011
Seremban Barat-Selatan Negeri Sembilan Darul Sdn. Bhd. (SAINS)
Khusus Pakej 1 : Membekal dan
Memasang Paip Jenis 'M.S' Bergarispusat Nominal
1200mm dan Keja-Kerja Bersangkutan Dari Bulatan
Bandar Nilai ke Tangki Sedutan Enstek Fasa II, Negeri
Sembilan Darul Khusus

37 | P a g e
29 Projek Menaiktaraf Loji Air Sungai Cherul, Kemaman, Lembaga Kemajuan RM7,530,206.26
Terengganu Terengganu Tengah
Pakej 1 : Membina, Menyiapkan, Menguji dan (KETENGAH)
Mentauliah Loji Air Sungai Cherul, Kemaman,
Terengganu
Completed 2011
30 Supervision of STATE OF KELANTAN NRW Program Air Kelantan Sdn. Bhd. RM130,000,000.00 Completed 2012
31 Rancangan Bekalan Air Seberang Temerloh Jabatan Bekalan Air Pahang RM38,500,000.00 Completed 2012
Pakej 2 : Membina, Menyiapkan, Menguji dan
Mentauliahkan Kerja-Kerja Sivil, Mekanikal, Elektrikal
Dan Yang Berkaitan Bagi Melengkapkan Loji Air
Seberang Temerloh, Pahang Darul Makmur
32 Rancangan Bekalan Air Seberang Temerloh Jabatan Bekalan Air Pahang RM15,000,000.00 Completed 2012
Pakej 3 : Cadangan Membekal, Memasang,
Menguji dan Mentauliah Paip AIr Mentah Jenis M.S.
Bergarispusat Nominal 700mm dan Paip Air Sisa Jenis
M.S. Bergarispusat Nominal 300mm serta Kerja-Kerja
Bersangkutan dari Muka Sauk ke Loji Air Seberang
Temerloh, Pahang Darul Makmur.

33 Rancangan Bekalan Air Seberang Temerloh Jabatan Bekalan Air Pahang RM13,400,000.00 Completed 2012
Pakej 4 : Membina, Menyiapkan, Menguji dan
Mentauliahkan Kerja-Kerja Sivil, Mekanikal, Elektrikal
Dan Yang Berkaitan Untuk Muka Sauk Loji Air
Seberang Temerloh, Pahang Darul Makmur

BUILDING / STRUCTURES AND HOUSING

Item Name of Projects Clients Contract Value Remarks


1 Design and Supervision of the Construction of Kolej Jabatan Kerja Raya, RM30,000,000.00 Completed 1999
Islam, Jalan Gambang, Kuantan, Pahang Pahang

38 | P a g e
2 The Structural Analysis, Design, Drafting, Specification Jabatan Kerja Raya, RM3,000,000.00 Completed 2000
and Construction Supervision of Proposed Building Pahang
for Wild Life Conservation / Public Awareness - Kuala
Atok
3 The Structural Analysis, Design, Drafting, Specification Jabatan Kerja Raya, RM4,000,000.00 Completed 2000
and Construction Supervision of Proposed Building Pahang
for Wild Life Conservation / Public Awareness -
Lanchang
4 The Structural Analysis, Design, Drafting, Specification Jabatan Kerja Raya, RM3,000,000.00 Completed 2000
and Construction Supervision of Proposed Building Pahang
for Wild Life Conservation / Public Awareness -
Merapoh
5 UIA Medical Campus, Jalan Penjara, Kuantan, Jabatan Kerja Raya, RM23,000,000.00 Completed 2002
Pahang Darul Makmur Pahang

6 Cadangan Membina dan Menyiapkan Masjid Kolej Jabatan Kerja Raya, RM10,000,000.00 Completed 2005
Islam, Pahang Darul Makmur Pahang

7 Cadangan Membina dan Menyiapkan 21 Unit Perbadanan Kemajuan RM2,000,000.00 Completed 2005
Rumah Sesebuah Satu (1) Tingkat di Sebahagian Lot Negeri Selangor (PKNS)
193, Jalan Raja Musa, Daeraha Kuala Selangor,
Selangor Darul Ehsan

8 Projek Cadangan Tapak Perumahan Pegawai LKPP Property Sdn. Bhd. RM3,000,000.00 Completed 2001
Kerajaan Kg. Soi, Kuantan, Pahang Darul Makmur

9 Cadangan Kerja-Kerja Untuk Membina dan Yayasan Basmi Kemiskinan RM313,280.00 Completed 2005
Menyiapkan 4 Buah Asrama Setingkat di atas Lot Selangor
2871, Mukim Hulu Bernam, Daerah Hulu Selangor,
Selangor Darul Ehsan

39 | P a g e
10 Cadangan Membina 1 unit Banglo 2.1/2 Tingkat Di Tn. Hj. Abdul Halim b. RM400,000.00 Completed 2006
Atas Lot PT40248, No. 73, Jalan Seri Putra 8/1, Bandar Ahmad
Seri Putra, Bangi, 43000 Kajang, Selangor Darul Ehsan

11 Projek Pembinaan Bangunan Herbarium di Institut Jabatan Kerja Raya, Kuala RM6,000,000.00 Completed 2006
Penyelidikan Malaysia (FRIM) Kepong, Selangor Lumpur

12 Design and Build Kg. Raja Secondary School at Lot Kementerian Pelajaran RM9,000,000.00 Completed 2009
602, Kg. Raja, Mukim Hulu Telum, Cameron Highlands Malaysia
District, Pahang Darul Makmur for the Ministry of
Education, Malaysia

13 Upgrading Works to Enchance Security At The Drug Kementerian Keselamatan RM3,000,000.00 Completed 2009
Rehabilitation Centre, Jerantut District, Pahang Darul Dalam Negeri
Makmur for Ministry of Internal Affairs, Malaysia

14 Housing Scheme at Pelindung Heights, Phase 1, Uda Land (East) Sdn. Bhd. RM20,000,000.00 Completed 2009
Mukim Kuala Kuantan, Pahang Darul Makmur

15 Hostel Bolcks University Inst. Tech. MARA, Terengganu Jabatan Kerja Raya, Kuala RM28,000,000.00
Branch, Bukit Besi, Terengganu Lumpur Completed
16 Design Works For The Construction of Computer Universiti Teknologi Malaysia RM18,600,000.00
Science & Inform. Tech. Faculty Building for University
Tech. Malaysia, Johor Completed
Cadangan Merekabentuk, Membina dan Jabatan Perumahan RM2,093.228.00 Completed
Menyiapkan 47 Unit Rumah Teres Satu Tingkat Bagi Negara
Program Perumahan Rakyat 9PPR-Dimiliki), Di Bandar
Baru Jerantut, Fasa II, Jerantut, Pahang Darul
17 Makmur.

40 | P a g e
Cadangan Merekabentuk, Membina dan Jabatan Perumahan RM6,700.000.00 Completed
Menyiapkan 150 Unit Rumah Teres 1 Tingkat Bagi Negara
Program Perumahan Rakyat (PPR-Dimiliki), Di Kg.
18 Hijrah, Kuantan, Pahang Darul Makmur.
Cadangan Merekabentuk, Membina dan Jabatan Perumahan RM6,337,500.00 Completed
Menyiapkan 150 Unit Rumah Teres Bagi Program Negara
Perumahan Rumah Rakyat (PPR-Dimiliki), Di Kg. Sri
19 Jaya, Maran, Pahang Darul Makmur
Cadangan Merekabentuk, Membina dan Jabatan Perumahan RM7,155,000.00 Completed
Menyiapkan Rmah Kos Rendah Bagi Program Negara
Perumahan Rakyat (PPR-Dimiliki), Di Kampung Baru
20 Gambang, Kuantan, Pahang Darul Makmur.
Cadangan Merekabentuk, Membina dan Jabatan Perumahan RM3,664.754.90 Completed
Negara
Menyiapkan 100 Unit Rumah Teres 1 tingkat bagi
Program Perumahan Rakyat (PPR-Dimiliki), Di Kg. Ibol
21 Tunggal, Jerantut, Pahang Darul Makmur.

ROAD AND BRIDGES

Item Name of Projects Clients Contract Value Remarks


1 Upgrading of Jalan Haji Ahmad, Kuantan, Pahang Jabatan Kerja Raya, RM11,500,000.00 Completed 1997
Pahang
2 Upgrading of Jalan Kg. Limau Purut to Kg. Kerambit, Jabatan Kerja Raya, RM6,170,000.00 Completed 2001
District of Lipis, Pahang Pahang

3 Design of New Kg. Bak-Bak Bridge, Maran, Pahang Jabatan Kerja Raya, RM8,000,000.00 Completed 1999
Pahang
4 Design of New Kg. Lada Bridge, Maran, Pahang Jabatan Kerja Raya, RM2,000.000.00 Completed 1997
Pahang
5 Upgrading of Jambatan Serangkam and Jalan Kg. Jabatan Kerja Raya, RM1,000,000.00 Completed 1997
Bak-Bak, Maran, Pahang Pahang

41 | P a g e
6 Upgrading of Jalan Sg. Musang KM 18 - KM 22, Jabatan Kerja Raya, RM5,690,000.00 Completed 2001
Kemaman, Terengganu Terengganu

7 Upgrading of Jalan Penjara and Jalan Makbar, Jabatan Kerja Raya, RM4,600,000.00 Completed 2002
Kuantan, Pahang Pahang

8 Upgrading of Jalan Binjai ke Paman Melalui Paya Jabatan Kerja Raya, RM8,000.000.00 Completed 2001
Seratus, Kemaman Terengganu

9 Design of Jalan Sg. Muntoh / Kg. Chennah Bridge, Jabatan Kerja Raya, Negeri RM1,700,000.00 Completed 1998
Daerah Jelebu, Negeri Sembilan Sembilan

SEWERAGE

Item Name of Projects Clients Contract Value Remarks


1 Kerja-Kerja Pemasangan Paip Pembentungan Pasdec Putra Sdn. Bhd. RM957,814.80 Completed 2009
Utama dan Pembinaan Stesyen Pam Serta Kerja-
Kerja Berkaitan di Bandar Putra, Kuantan, Pahang
Darul Makmur. (Pakej 8A2)
2 Kerja-Kerja Pemasangan Paip Pembentungan Pasdec Putra Sdn. Bhd. RM560,000.00 Completed 2009
Utama dan Pembinaan Stesyen Pam Serta Kerja-
Kerja Berkaitan di Bandar Putra, Kuantan, Pahang
Darul Makmur. (Pakej 8A3)

42 | P a g e
2.7. REGISTRATION

a. Kementerian Kewangan Malaysia


No. Rujukan Pendaftaran : 465-00000724
Tempoh : 29/06/2011 - 28/06/2014

b. Board of Engineers Malaysia


No. Perakuan: 1400-1300-BC-598

c. Uda Holding Sdn Bhd.


No. pendaftaran: 8902/1/JUR/185/97(60)

d. MIEL (Malaysian Industrial Estates Berhad)


No Rujukan Pendaftaran. : CS, PM-014

e. Dewan Bandaraya.
Surat rujukan (27)dlm.DBKL/JPEKS/04-1/19JId.6

2.8. VISION AND MISSION

Vision

Strive for excellence in engineering.

Missions

a. To ensure that creativity in engineering design does not impose an


expenditure penalization but most certainly gives cost expediency.
b. Our design’s philosophy is firmly established on equipping simple, cost-
effective and readily-build explication, innovative, simple, tried and proven
techniques whenever obtainable.
c. Delivering our services in a timely, efficient and professional manner.
d. Assigning competent project team in design and servicing our clients.
e. Application of Information Communication Technology in our work
processes.
f. Providing continuous training to our employees at all levels.

43 | P a g e
CHAPTER 3 SUMMARY OF WEEKLY

Week Date Activities

i. Briefing about the company


ii. Assign in a civil and structure soil
investigation department.
iii. Folding drawing paper from A1 size to
A4 size step by step.
iv. Study the drawing from architecture
drawing to structural drawing.
1 7th – 11th July 2014
v. Design the beam size manually and do
the spread sheet in Microsoft Excel.
vi. Check as built drawing and structural
drawing.
vii. Do a report for a sewerage system.
viii. Design the load for roof as slab and also
design slab.

i. Continue to design the slab for the roof


manually.
ii. Design the simply supported beam and
2 14th – 18th July 2014
continuously beam for the roof
manually.
iii. Prepare the checklist of tender proposal.

i. Complete the quotation document for


3 21th – 25th July 2014 engineering survey and utilities
detection and mapping.

ii. Design the column by manually and do

44 | P a g e
the spread sheet.

iii. Calculate the bill of quantities of


contract or tender.

iv. Design flow of water using MWA


design.

4 28th July – 1st August 2014 i. Design the pile capacity.

i. Complete the certificate of refunds.


ii. Understand the form agreement and
conditions contract in the contract
document.
iii. Preparing the bill of quantities in the
th th
5 4 -8 August 2014 contract document.
iv. Preparing the tender document.
v. Site visit to update the progress work.
vi. Site visit raw water treatment plant to
use the same system but more
upgraded.

i. Understand the design of concrete mix.


ii. Understand how to take sample of
th th
6 11 -15 August 2014 material.
iii. Understand how to do hydraulic test.
iv. Folded drawing paper to A4 size.

i. Attend meeting for defect liability


7 18th -22th August 2014 period (DLP) at Loji Cherul.
ii. Attend meeting for repair damage and

45 | P a g e
to get the certificate of making Good
Practice (CMGD) foe project UiTM
Bukit Besi.
iii. Examine material use at the site.
iv. Attend briefings for Esteem 9.
v. Attend tender briefing for Indah Water
Konsortium (IWK).
vi. Understand the raw water treatment
plant process.
vii. Design carbon plant using Esteem 9.

i. Understand water sampling system.


ii. Draw the Pasar Seni Linkway using
AutoCAD.
iii. Understand the consultancy agreement.
8 25th -29th August 2014 iv. Preparing the tender document for the
Indah Water Konsortium (IWK).
v. Design the upper roof beam layout plan
using Esteem 9 and Orion.

i. Continue to prepare the Indah Water


consortium (IWK) tender.

9 1st – 5th September 2014


ii. Site visit for know the exact location for
the new project.
iii. Prepare tender document for project
Medini.

Table 3.1 Summary of Weekly

46 | P a g e
CHAPTER 4 TECHNICAL REPORT

4.1. PROJECT BACKGROUND

The proposed construction of the Masjid Cina Muslim in the Wilayah Perseketuan
have been received by MAIWP in 2000 from the Yayasan/NGOS to be used as the
center of coordination of activities and the welfare of Chinese Muslims. The project
site on 4.6 acres (1.88 hectares) above Lot 1220, section 62, Jalan Davis, Kuala
Lumpur has been identified for the development of the proposed new construction
Chinese Mosque. This site is being proposed has been agreed by the Prime Minister,
Datuk Seri Najib Tun Razak to the construction of a Chinese Mosque complex, and
the Islamic culture. New construction of the mosque is to provide convenience and
comfort to carry out religious activities for the Muslim community in the surrounding
area.
Project Name : Cadangan Membina Masjid Cina Di Atas Lot 1220, Seksyen 62,
Jalan Davis, Kuala Lumpur.
Start Project : 21 September 2014
End Project : 2018
Project Value : RM 130,000,000.00
Project Stage : Design stage

47 | P a g e
4.2. SITE LOCATION

The site location located at Jalan Davis meeting at Jalan Kg. Pandan with Jalan
Changkat Tambi Dollah.

Figure 4.1: Site Location

4.3 PROJECT SITE

Figure 4.2: Project Site

48 | P a g e
Figure 4.3: Location Picture

Figure 4.4: Location Picture

Figure 4.5: Location Picture

49 | P a g e
4.4. PROBLEM STATEMENT

a. As a national agenda for uniting race was Chinese Muslim.


b. Make the missionary activities of the Coordination Center of the Chinese Welfare
Muslim.
c. Build an iconic mosque which focuses on the characteristics of the Chinese.
d. As a gift to the Chinese community that contributed to the country's economy.
e. As a tourist attraction.
f. Meet the needs of the local community in line with the development of the project
Tun Razak Exchange (TRX)

4.5. OBJECTIVE OF THE PROJECT

a. The realization of the hopes and aspirations of the country's leadership in line with
the National Agenda of the country in which the concept proposed is going to be a
landmark of Kuala Lumpur City and the center of Islamic Da'wah activities and
tourist attractions.
b. To provide national recognition to the Chinese community that contributes to the
economy and development through Islamic Da'wah mosque design featuring
Chinese culture.

4.6. SCOPE OF THE PROJECT

a. Main block of the Mosque – 5000 people


b. Staff Quarters Block – 10 units
c. Retail space/Booth – 6 units
d. Tower
e. Square (Open Page)/Wakaf
f. Garbage House space
g. Other requirements:-TNB Sub Station-Basement Parking (278 lots)-Gateway-
Playground (2 units)-Office Space-Hall-Class Library
h. Landscape infrastructure works

50 | P a g e
4.7. OUTCOME OF THE PROJECT

a. The development of Chinese Mosque with its commitment is also believed capable
of giving the benefit of the Muslim community in Malaysia in line with the
Government’s, ‘Rakyat Didahulukan Pencapaian Diutamakan”.
b. Increase understanding of new converts.
c. Convey the message that Islam is a universal religion.
d. Meet the needs of a place of worship for the surrounding area.
e. Added another icon/national tourism destinations

4.8. PROJECT CONSTRAINS

a. Existing service – water pipes, Sewerage, drainage.


b. Traffic systems – the location of the site close to the main road/one-way streets.
c. China's architectural needs original – expertise employees, material needs to be
imported.
d. Soil-limestone (limestone formations)/high water table.
e. Monsoon Drain stinks/Overflow.
f. Rain water harvesting/roof designs.

4.9. PROJECT NEEDS

a. Have the characteristics of Chinese architecture.


b. To accommodate a total of about 5,000 people.
c. Provide sufficient parking.
d. Comply with local authority – IBS, RWH, OSD etc.
e. Have an elevator for the disable people and funeral.
f. Build Tower pagoda.

51 | P a g e
4.10 DESIGN THE PROJECT

This project is in design stage which is the second stage for project development. For
this project design stage, it has three type of design that are civil and structural design,
pipeline design and mechanical and electrical design. As a civil engineering student, I
have been assigned to design the civil and structural design for this Masjid Cina
project.

From the architectural drawing given, know that this building have three floor. Two
floors for the quarters and the basement is the parking lot. For the quarters each floor
have five unit of house that means the total of the quarters is 10 units. The important
thing when design is knows the usage of the design areas.

There are manual design and software design. First design is design using manual.
This mean, all the manual calculation need to design in the spreadsheet using
Microsoft Excel. This is because the spreadsheet will be easier because the
spreadsheet can be calculate in the big range and can solve all the formula by itself.
Other than that, the spreadsheet can be reuse by change the certain value which can be
said the time for manual design will be lesser.

The issue when design this project both for manual or software are in the industrial or
this company is still using British Standard while in the university is use Eurocode for
the design. There are differences for British Standard and Eurocode in the design.

Eurocode British Standard


Calculate the basic phenomenon Calculate element type (beam, slab)
(flexure, shear, deflection)
Concrete cylinder strength as the basis Concrete cube strength as the basis
design calculation. design calculation.
Can use high strength concrete without The strength concrete is limited
been limited
The concrete strut angle can be change Only fixed at 45ºC
in shear calculation.
Table 4.1: The differences between Eurocode and British Standard

52 | P a g e
The advantages of using Eurocode are:
a. Can include more shear links.
b. Reduce reinforcement requirements.
c. Saving the materials about 5% to 10% on the applied load to structure due to
reduce the formula:
Eurocode: 1.35gk + 1.5qk
British Standard: 1.4gk + 1.6qk

Although the manual calculation is in Eurocode, the certain value need to changed
follow the British Standard such as characteristic of steel, fyk which is for Eurocode is
500N/mm2 change to 460N/mm2. While for the characteristic for concrete, fck is
change to 35A N/mm2 which is the title aqua concrete better in resist the water.

Figure 4.6: Step To Design the Whole Structures

Each of the elements needs to calculate from the design load until the deflection. For
this Masjid Cina project there will different at truss because the roof not use truss but
use slabs to design.

Step to design Slab:


a. Durability, Fire and Bond Requirement
b. Nominal Cover
c. Design Load
d. Bending Moment and Shear
e. Crack Check.

Step to design beam


a. Nominal cover
b. Design Load
c. Bending Moment and Shear
d. Design Main Reinforcement

53 | P a g e
e. Design Shear Reinforcement
f. Deflection Check
g. Crack Check

Purpose of this manual design is actually to check the with the software ouput.
Software that is used for design this project is Orion and Esteem 9. After using the
software there will be output in the AutoCad file that are full with the detailing of the
structure.

Figure 4.7: The 3D output from the Orion Software for the Roof Layout

Figure 4.8: The 3D output from The Esteem 9 for the Roof Layout

54 | P a g e
Figue 4.9: The Structure of the Masjid Cina using Orion

Figure 4.10: Output from the Orion for the Beam

Figure 4.11: Output from the Esteem9 for the Beam

55 | P a g e
CHAPTER 5 DISCUSSIONS & RECOMMENDATIONS

Every project in the world may have the problem at least one. For this Masjid Cina
project the problem mostly come from the existing utilities at the site. The three
problems for this design stage are existing monsoon drain, Indah Water Konsotium
(IWK) pipe and Syarikat Bekalan Air Selangor (SYABAS) pipe crossing the site.

a. Existing Monsoon Drain


Existing Monsoon Drain is under the supervision of the DBKL.The Monsoon
drain built more than 30 years and sometimes produce bad smell/less pleasant.
The DBKL say that Monsoon drain flows to the Sungai Kepayang.

Figure 5.1: The Existing Monsoon Drain

56 | P a g e
Figure 5.2: The Existing Monsoon Drain at the Site Project

In order to overcome this problem, the existing Monsoon drain is proposed to


move to the site boundry. Monsoon drain to be constructed is covered and from
the type of cast in-situ and the box culvert. The pile size of 200 x 200mm will be
used as the basis of the proposed site of the monsoon drain.

Figure 5.3: The New Propose Monsoon Drain

57 | P a g e
b. Existing SYABAS Water Pipe
There is a water pipe SYABAS at the existing project. Existing pipe is the pipe
type of Asbestos Cement (A. C) 200mm diameter.

Figure 5.4: The Existing SYABAS water pipe

The existing water pipe size 200mm type of Asbestos Cement (AC) within the
proposed project site is proposed to be moved in the Street outside the site. Water
pipe size is 200mm Mild Steel proposed for removal of the pipe. For new pipes
will be installed, the pipe 150mm diameter Mild Steel will be used. Total
estimated water use was 277000 liters per day.

Figure 5.5: Water Reticulation Layout Plan

c. Existing Sewage IWK Pipe


There are existing sewage pipe at the site of the proposed project. Existing pipe
diameter are 525 mm, 375mm, and 750mm.

58 | P a g e
Figure 5.6: The Existing IWK pipe

The existing IWK pipe intended to be moved on the road outside the site. Pipe
jacking method will be used for the removal of existing sewage pipe. The pipe
that will be used is the size 375mm and 525 mm types of Reinforced Concrete pipe
is connected to the existing 750mm. The new Sewage Pipe installation based on
hydraulic design and planning arrangements to design the network pipe culverts
accordance with Standard ' Malaysia M.S. 1228: 1991 Code of Practice for Design
and Installation of Sewerage Systems ' and based on ' Malaysian Sewerage
Industry Guidelines Third Edition Volume III '. The formula that will be used is
the Formula Manning's. For the installation of sewage pipes in the area of the
proposed site, 225mm-sized VCP pipes will be installed. Total estimated
Population is 2555 PE.

Figure 5.7: Sewerage Layout Plan

59 | P a g e
There are recommendations for this Masjid Cina project:
a. Change the cast insitu box culvert to precast box culvert because of cost
savings, speed up the construction and construction quality are easily
controlled.
b. Implement trafic impact assesment (TIA) to comply with the requirements of
the Local Authority.
c. Review the cost of road and drainage (ACDC and Traffic Light) to get a more
accurate estimate of costs and comply with the requirements of the Local
Authority.

60 | P a g e
CHAPTER 6 CONCLUSION

During 9 week of industrial training I have gain lot of experience. I have learned
managed and understand the way of project being done from the beginning until it
complete. The most things that I learned were about about design in the designing
stage. Other than that, I can well communicate with other people through the
presentation or meeting that I involved.

Furthermore I also was exposed to the real life of civil engineer. During the practical I
can understand more the theory that I learn during the lectures and can apply it when
do my work. I also can easily discuss with the staff if I had a problem during
completed my works. We also sometimes exchange the idea together during the
meeting and the staff sometimes uses my opinions. This makes me comfortable to
work with them.

As the conclusion, the Industrial Training have bring many benefits to me to learn not
only the theory but also the practical that are mostly difference from what I have
learned in the lectures.

61 | P a g e
REFERENCES

i. Company Profile, PZK Sdn Bhd.


ii. Mr Noor Rizan Bin Sarmin, General Manager.
iii. Mr Mohd Fazly Omar, Civil Engineer.
iv. Miss Azween Bt Md Yusof, Civil Engineer.
v. Mrs Yuniza Mohd Fitri, Civil Engineer.
vi. Mr Mohd Azuan Bin Tukiar, Industrial Training Coordinator of Faculty of
Civil Engineering UiTM Pulau Pinang.
vii. Design Appendix.
viii. Eurocode BS EN 1990-2002.
ix. Eurocode BS EN 1992-1-1-2004.
x. Eurocode BS EN 1991-1-1-2002.
xi. Lecture Note RC Design.

62 | P a g e

You might also like