0% found this document useful (0 votes)
469 views

Formwork Check List

This document provides a quality assurance checklist for formwork construction on column elements of a proposed primary learning resource center. The checklist includes 7 items to inspect before pouring concrete, such as ensuring proper supports, alignment, water tightness and cleanliness. Another 7 items are included to inspect after pouring concrete, like dimensions, verticality and provision of cover blocks. Space is allocated for comments and signatures of the contractor's and consultant's engineers to approve the inspections.

Uploaded by

nadun
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
469 views

Formwork Check List

This document provides a quality assurance checklist for formwork construction on column elements of a proposed primary learning resource center. The checklist includes 7 items to inspect before pouring concrete, such as ensuring proper supports, alignment, water tightness and cleanliness. Another 7 items are included to inspect after pouring concrete, like dimensions, verticality and provision of cover blocks. Space is allocated for comments and signatures of the contractor's and consultant's engineers to approve the inspections.

Uploaded by

nadun
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CONSTRUCTION OF PROPOSED PRIMARY LEARNING RESOURCE

CENTER AT CATHEDRAL BOYS SCHOOL COLOMBO 13


Client :
Consultant : Central engineering Organization (Western Province)

QUALITY ASSUARANCE & QUALITY CONTROLLING DOCUMENT


Check list no: Date:
FORMWORK CHECK LIST

Structure Columns - Schedule commencement

Date : Element :

Signature Remark & Signature


No Item Description
(contractor) (consultant)
Initial preparation (Chipping &
1 Cleaning) OK Yes No
Setting out OK Yes/No
2 Setting out
Leveling OK Yes/No
Pre concreting

Supports Adequate Yes/No


3 Supports & Verticality
Verticality OK Yes/No
Alingments OK Yes/No
4 Alignment & Dimentions
Dimentions OK Yes/No
5 Water Tightness Adequate Yes No
6 Rigidity of supports Adequate Yes No
7 Marking of concrete level OK Yes No
8 Cleanliness of pour area OK Yes No
1 Dimensions OK Yes No
2 Supports OK Yes No
3 Verticality OK Yes No
4 Provision of cover blocks Adequate Yes No
5 Provision of MEP Works OK Yes No
Arrangements to access for
6 inspection area-ladders and Adequate Yes No
platform
Date for removal of supports &
7 any other comments

Comment note 1 :

Comment note 2 :

Comment note 3 :

Comment note 4 :

……………………………. ………………………………
Engineer - Contractor Engineer - Consultant