Osp Flow Gbpa

This document outlines the steps to configure an outsourced production process in Oracle, including: 1) defining inventory items, resources, departments, bills of materials, and routings; 2) creating a blanket purchase agreement for outsourced items; 3) running workflows to automatically generate approved supplier lists and sourcing rules on agreement approval; and 4) releasing a discrete job to trigger requisition and purchase order creation for outsourced item procurement.

Uploaded by

Venkat
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views10 pages

Osp Flow Gbpa

This document outlines the steps to configure an outsourced production process in Oracle, including: 1) defining inventory items, resources, departments, bills of materials, and routings; 2) creating a blanket purchase agreement for outsourced items; 3) running workflows to automatically generate approved supplier lists and sourcing rules on agreement approval; and 4) releasing a discrete job to trigger requisition and purchase order creation for outsourced item procurement.

Uploaded by

Venkat
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 10

1. Create OSP item & Finished Goods Item. Assign them to required inventory organizations.

Navigation Inventory Responsibility--> Items--> Master Items.


2. Define Resources

Navigation : Manufacturing and Distribution Manager Responsibility


Bills Of Materials (BOM)-->Routings--> Resources

3. Define Departments & Assign the Resource to Department.

BOM-->Routings--> Departments
4. Create BOM

BOM--> Bills--> Bills

5. Create Routing

BOM--> Routings--> Routings


6. Create Global Blanket Purchase Agreement (GBPA) for OSP Item using OSP line type.
Purchasing Responsibility > Buyer Work Center > Agreements.
7. Enable the controls to create ASL and Sourcing Rule automatically when approving the GBPA.
8. GBPA is approved.
Purchasing Responsibility > Purchase Order Summary > Query the PO and check the Approval
Status.

9. Run the Workflow Background Process for “PO Approval” with Process Deferred as “Yes”.
Requests > Submit Request > Workflow Background Process.
10. Now check ASL is created for the OSP Item.
Navigation : Purchasing Responsibility > Supply Base > Approved Supplier List

11. Check the Sourcing Rule and Sourcing Rule Assignment.


Navigation : Purchasing Responsibility > Supply Base > Sourcing Rules
Navigation : Purchasing Responsibility > Supply Base > Assign Sourcing Rules

12. Create a Discrete Job.


Navigation : Manufacturing and Distribution Manager Responsibility
WIP--> Discrete--> Discrete Jobs
13. Release the Job.

14. Check the Requisition import is triggered.


Requests > View Request
15. Check the Requisition created. Standard PO is created automatically from requisition using
Create Document workflow.
Navigation : Purchasing Responsibility
Requisition Summary > Query for the OSP item with creation Date condition

16. Check the PO created is in Approved status.


Purchasing Responsibility > Purchase orders > Purchase Orders