ISC Safety Lore - Issue No3
ISC Safety Lore - Issue No3
September 2018
Issue 3
Introduction
The flare collects a range of gaseous emission and pipes them to a flare stack where the harmful gases
are burnt and then the exhaust is safely discharged to the atmosphere. The flare is a last line of defense
in the safe emergency release system in a refinery or chemical plant. It is used to dispose of purged and
wasted products from refineries, unrecoverable gases emerging with oil from oil wells, vented gases from
blast furnaces, unused gases from coke ovens, and gaseous water from chemical industries.
In the What can I do section below you can see how each of these
elements plays a part.
• Ensure sources of flare blockage are understood contingence plans are developed to address possible
obstructions in the flare systems.
• Ensure rigorous risk assessments have been undertaken prior to jobs of such a high magnitude and potential
hazard such as maintenance of a flare system.
• Make sure that maintenance supervisors have the competence to undertake responsibilities and to perform their
activities to a recognised standard on a sustained basis.
• Develop detailed procedures for drainage and isolation of lines, and opening of pipelines and flanges, and ensure
they are followed.
Process Engineer/Supervisor
• In case of ammonia production facilities, ensure flare systems containing ammonia are segregated from the flare
systems containing carbon dioxide, as the mixing can cause plugging problems.
• In addition to ensuring the permit to work system is used, job specific Task Risk Assessment (TRA) are needed for
higher risk activities. Ensure that deviations from the PTW/TRA are risk assessed prior to execution.
• Supervise and control the work; check that the procedures are always followed. Talk through the hazards and
maintenance procedure with the workforce before issuing a PTW.
• Ensure flare line isolation valves incorporate valve position indicators.
• Process isolation and preparation plan should be clearly documented and checked. Positive isolation and drainage
checks must be performed prior to work commencing.
• Make sure that adequate means of escape in case of an emergency are provided, especially at elevated working
platform. A single egress point is not sufficient in an emergency.
• Prepare an emergency response plan to enable workers to escape or act upon in case of emergency.
• Check that all personal protection equipment that is required for the work is present and fit for purpose. Workers
should wear fireproof suits until the lines are proved safe.
• Check for the presence of residual flammable gas, avoiding a flammable atmosphere. The use of nitrogen to purge
lines should be considered but used with caution. It could cause pyrophoric deposits to dry out, thus increasing
their flammability. Working areas should be drenched in water until open pipes have been blanked or spaded.
• In case of any abnormal situation (leak or rupture etc.) work must be stopped immediately and should not start
again until a thorough inspection if it is safe for work to continue.
Operator
• Make sure that no flammable gas/vapour is left inside the system prior to cold/hot work activities.
• In case of any emergency situation ask the supervisor for further advice on whether the work can be completed or
additional checks are necessary.
• Ensure that relevant PPE is available such as breathing apparatus.
• When completing process isolation and draining, a positive check should be conducted to prove them.
The information included is given in good faith but without any liability on the part of the IChemE or the IChemE Safety Centre.
Contact us at [email protected]