BG Pow.r1v8 Complete
BG Pow.r1v8 Complete
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
1
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
86 Additional canopy added 2nd floor 8 days Mon 16/05/16 Thu 26/05/16
87 Erect formwork canopy 5 days Mon 16/05/16 Mon 23/05/16
88 Reinforcing to canopy 3 days Fri 20/05/16 Wed 25/05/16
89 Concrete to canopy 1 day Wed 25/05/16 Thu 26/05/16
90 FRC SF slab 25 days Fri 10/06/16 Tue 19/07/16
91 Deformwork 5 days Wed 3/08/16 Wed 10/08/16
92 Completion of SF Slab 0 days Tue 19/07/16 Tue 19/07/16
93 2nd to Roof 61 days Fri 8/07/16 Thu 6/10/16
94 Setting out 8 days Fri 8/07/16 Thu 21/07/16
95 Blockwall 18 days Thu 14/07/16 Thu 11/08/16
96 Commencement of EF SF Blockwork 0 days Thu 14/07/16 Thu 14/07/16
97 FRC columns 12 days Mon 25/07/16 Thu 11/08/16
98 FRC beam 20 days Wed 27/07/16 Thu 25/08/16
99 FRC Roof slab 24 days Thu 4/08/16 Thu 8/09/16
100 Deformwork 5 days Thu 29/09/16 Thu 6/10/16
101 Completion of EF Roof Slab (100% Milestone Structure com 0 days Thu 8/09/16 Thu 8/09/16
102 Parapet walls Block E & F 15 days Thu 8/09/16 Thu 29/09/16
103 External SAOTA changes and Additional works Block EF 70.6 days Tue 26/04/16 Tue 9/08/16
104 Receive instruction additional/changes bases, columns RC 0 days Tue 26/04/16 Tue 26/04/16
105 Excavate, drill dowel existing bases 7 days Wed 4/05/16 Fri 13/05/16
106 FRC new bases 8 days Fri 13/05/16 Wed 25/05/16
107 FRC new columns, walls etc 6 days Wed 25/05/16 Thu 2/06/16
108 Receive instruction Addition of R.C Wall 0 days Wed 11/05/16 Wed 11/05/16
109 FRC bases RC walls 8 days Thu 26/05/16 Tue 7/06/16
110 FRC RC walls incl doweling to reinforcing 12 days Tue 7/06/16 Fri 24/06/16
111 Complete columns & RC wall to canopy 30 days Fri 24/06/16 Tue 9/08/16
112 Complete external SAOTA 0 days Tue 9/08/16 Tue 9/08/16
113 Wet Trades 234.22 days Tue 12/01/16 Wed 18/01/17
114 Internally 229.22 days Tue 12/01/16 Wed 11/01/17
115 Ground Floor 133.22 days Tue 12/01/16 Tue 2/08/16
116 Partition block wall & risers 12 days Thu 21/04/16 Mon 9/05/16
117 Appointment of Conceal Mixer Supplier 0 days Tue 12/01/16 Tue 12/01/16
118 M&E 1st & 2nd fix 15 days Fri 22/04/16 Fri 13/05/16
119 Preplaster Check 10 days Tue 3/05/16 Tue 17/05/16
120 Render wall & ceilings internal 25 days Thu 5/05/16 Fri 10/06/16
121 SAOTA Changes Block EF Ground Floor Internal (Anne 30.89 days Fri 6/05/16 Wed 22/06/16
122 SAOTA layout/Elevation drawings received 06/05/16 0 days Fri 6/05/16 Fri 6/05/16
123 New details including structural received up to 12/05/1 0 days Thu 12/05/16 Thu 12/05/16
124 Setting out additional opeings, M & E service changes 3 days Tue 10/05/16 Mon 16/05/16
125 Breaking in additional openings, reducing columns, ext 8 days Mon 16/05/16 Thu 26/05/16
126 M & E chasings,rerouting 5 days Wed 25/05/16 Wed 1/06/16
127 FRC additional columns, jambs & cills incl dowling 8 days Wed 1/06/16 Mon 13/06/16
128 Receive instruction close newly broken openings 07/06 0 days Tue 7/06/16 Tue 7/06/16
129 FRC close openings incl dowel, hack 4 days Thu 9/06/16 Wed 15/06/16
130 Complete render following changes 6 days Mon 13/06/16 Wed 22/06/16
131 Completion of EF GF wet works 0 days Tue 2/08/16 Tue 2/08/16
132 1st Floor 58 days Mon 1/08/16 Mon 24/10/16
133 Partition block wall & risers 10 days Tue 2/08/16 Tue 16/08/16
134 M&E 1st & 2nd fix 15 days Mon 1/08/16 Mon 22/08/16
135 Preplaster Check 10 days Wed 10/08/16 Wed 24/08/16
136 SATOA Changes Block EF 1st Floor Internal 20 days Wed 10/08/16 Thu 8/09/16
137 Setting out additional opeings, M & E service changes 3 days Wed 10/08/16 Mon 15/08/16
138 Breaking in additional openings, reducing columns, ext 8 days Thu 11/08/16 Tue 23/08/16
139 M & E chasings,rerouting 5 days Fri 19/08/16 Fri 26/08/16
140 FRC additional columns, jambs & cills incl dowling 8 days Fri 26/08/16 Thu 8/09/16
141 Render wall & ceilings internal 25 days Fri 19/08/16 Mon 26/09/16
142 Completion of EF 1st floor wet works 0 days Mon 24/10/16 Mon 24/10/16
143 2nd Floor 49 days Fri 7/10/16 Wed 11/01/17
144 Partition block wall & risers 12 days Fri 7/10/16 Wed 26/10/16
145 M&E 1st & 2nd fix 12 days Mon 10/10/16 Thu 27/10/16
146 Preplaster Check 10 days Mon 17/10/16 Mon 31/10/16
147 Render wall & ceilings internal 25 days Wed 19/10/16 Tue 29/11/16
148 Completion of EF 2nd floor wet works 0 days Wed 11/01/17 Wed 11/01/17
149 Externally (Block E & F) 65 days Thu 22/09/16 Wed 18/01/17
150 Plaster parapet wall on roof 10 days Thu 22/09/16 Thu 6/10/16
151 Plaster front façade 25 days Fri 30/09/16 Wed 9/11/16
152 Plaster side façade 20 days Fri 28/10/16 Thu 1/12/16
153 Plaster rear facades 25 days Wed 23/11/16 Wed 18/01/17
154 Builders work in connection with services on roof & Screed 20 days Thu 22/09/16 Fri 21/10/16
155 Completion of EF plaster to facades 0 days Wed 18/01/17 Wed 18/01/17
156 Finishes 251 days Tue 5/04/16 Fri 5/05/17
157 Internally 251 days Tue 5/04/16 Fri 5/05/17
158 Ground Floor Block E (G009 & G010) 204 days Tue 5/04/16 Thu 23/02/17
159 Wet Works (ceiling & tiles) 81 days Tue 5/04/16 Tue 2/08/16
160 Appointment of Suspended Ceiling Subcontractor 0 days Fri 13/05/16 Fri 13/05/16
161 Suspended ceiling grid work 12 days Thu 30/06/16 Tue 19/07/16
162 Appointment of Floor and Wall tile Supplier 0 days Tue 5/04/16 Tue 5/04/16
163 Floor & wall tiles 14 days Mon 11/07/16 Tue 2/08/16
164 Finishes Internal 135 days Thu 14/04/16 Fri 28/10/16
165 Commencement of Block E GF Finishes 0 days Thu 16/06/16 Thu 16/06/16
166 Appointment of Painting Subcontractor 0 days Thu 16/06/16 Thu 16/06/16
167 Paint 1st coat 5 days Thu 28/07/16 Fri 5/08/16
168 Appointment of Alumnium Opening Subcontractor 0 days Thu 14/04/16 Thu 14/04/16
169 Aluminium openings 10 days Wed 3/08/16 Wed 17/08/16
170 Suspended Ceilings final 5 days Mon 15/08/16 Mon 22/08/16
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
2
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
171 Appointment of Shopfitting Subcontractor 0 days Wed 20/04/16 Wed 20/04/16
172 Shopfitting installation incl all 10 days Thu 18/08/16 Thu 1/09/16
173 Appointment of Kithcen Fit Out Subcontractor 0 days Mon 2/05/16 Mon 2/05/16
174 Kitchen fit outs 9 days Tue 30/08/16 Tue 13/09/16
175 Appointment of Granite Supplier 0 days Tue 24/05/16 Tue 24/05/16
176 Granite tops 8 days Fri 9/09/16 Wed 21/09/16
177 Appointment of Sanware & Toilet Accessories Supplier 0 days Tue 21/06/16 Tue 21/06/16
178 Sanitary wares & accessories 7 days Mon 19/09/16 Wed 28/09/16
179 Appointment of Light Fitting Supplier 0 days Wed 15/06/16 Wed 15/06/16
180 Electrical accessories & light fittings 8 days Mon 26/09/16 Thu 6/10/16
181 Appointment of Tel/Data/MATV Subcontractor 0 days Wed 27/07/16 Wed 27/07/16
182 TEL/DATA/MATV installation 4 days Tue 4/10/16 Mon 10/10/16
183 Appointment of Shower Door Supplier 0 days Fri 15/07/16 Fri 15/07/16
184 Shower screens 5 days Fri 7/10/16 Mon 17/10/16
185 Snag/De-snag 5 days Mon 17/10/16 Mon 24/10/16
186 Paint final coat 5 days Fri 21/10/16 Fri 28/10/16
187 Complete Block E GF internal 0 days Fri 28/10/16 Fri 28/10/16
188 Terraces Ground Floor 74 days Tue 11/10/16 Thu 23/02/17
189 Paint 1st & 2nd coat 5 days Tue 10/01/17 Tue 17/01/17
190 Waterproofing to terraces 7 days Thu 12/01/17 Mon 23/01/17
191 Apppointment of external tiling 0 days Tue 11/10/16 Tue 11/10/16
192 Terrace tiling 8 days Thu 19/01/17 Thu 2/02/17
193 Timber screens & cladding 7 days Fri 27/01/17 Thu 9/02/17
194 Balustrades 6 days Mon 6/02/17 Tue 14/02/17
195 Paint final coat 4 days Fri 10/02/17 Thu 16/02/17
196 Snag/De-snag 5 days Wed 15/02/17 Thu 23/02/17
197 Complete Block E Terraces GF 0 days Thu 23/02/17 Thu 23/02/17
198 Ground Floor Block F (G011 & G012) 137 days Tue 19/07/16 Thu 2/03/17
199 Wet Works (ceiling & tiles) 21 days Tue 19/07/16 Thu 18/08/16
200 Suspended ceiling grid work 12 days Tue 19/07/16 Fri 5/08/16
201 Floor & wall tiles 14 days Thu 28/07/16 Thu 18/08/16
202 Finishes Internal 63 days Tue 16/08/16 Fri 18/11/16
203 Paint 1st coat 5 days Tue 16/08/16 Tue 23/08/16
204 Aluminium openings 10 days Fri 19/08/16 Fri 2/09/16
205 Suspended Ceilings final 5 days Wed 31/08/16 Thu 8/09/16
206 Shopfitting installation incl all 10 days Mon 5/09/16 Tue 20/09/16
207 Kitchen fit outs 9 days Fri 16/09/16 Thu 29/09/16
208 Granite tops 8 days Tue 27/09/16 Fri 7/10/16
209 Sanitary wares & accessories 7 days Wed 5/10/16 Mon 17/10/16
210 Electrical accessories & light fittings 8 days Wed 12/10/16 Tue 25/10/16
211 TEL/DATA/MATV installation 4 days Fri 21/10/16 Thu 27/10/16
212 Shower screens 5 days Wed 26/10/16 Fri 4/11/16
213 Snag/De-snag 5 days Fri 4/11/16 Mon 14/11/16
214 Paint final coat 5 days Thu 10/11/16 Fri 18/11/16
215 Complete Block F GF internal 0 days Fri 18/11/16 Fri 18/11/16
216 Terraces Ground Floor 28 days Tue 17/01/17 Thu 2/03/17
217 Paint 1st & 2nd coat 5 days Tue 17/01/17 Tue 24/01/17
218 Waterproofing to terraces 7 days Thu 19/01/17 Tue 31/01/17
219 Terrace tiling 8 days Fri 27/01/17 Fri 10/02/17
220 Timber screens & cladding 7 days Tue 7/02/17 Thu 16/02/17
221 Balustrades 6 days Mon 13/02/17 Wed 22/02/17
222 Paint final coat 4 days Mon 20/02/17 Fri 24/02/17
223 Snag/De-snag 5 days Thu 23/02/17 Thu 2/03/17
224 Complete Block F Terraces GF 0 days Thu 2/03/17 Thu 2/03/17
225 First Floor Block E (F109 & F110) 98 days Mon 19/09/16 Tue 7/03/17
226 Wet Works (ceiling & tiles) 24 days Mon 19/09/16 Mon 24/10/16
227 Suspended ceiling grid work 12 days Mon 19/09/16 Wed 5/10/16
228 Floor & wall tiles 14 days Mon 3/10/16 Mon 24/10/16
229 Finishes Internal 63 days Thu 20/10/16 Wed 15/02/17
230 Commencement of Block E FF Finishes 0 days Thu 27/10/16 Thu 27/10/16
231 Paint 1st coat 5 days Thu 20/10/16 Thu 27/10/16
232 Aluminium openings 10 days Tue 25/10/16 Thu 10/11/16
233 Suspended Ceilings 5 days Tue 8/11/16 Wed 16/11/16
234 Shopfitting installation incl all 10 days Mon 14/11/16 Tue 29/11/16
235 Kitchen fit outs 9 days Thu 24/11/16 Thu 8/12/16
236 Granite tops 8 days Tue 6/12/16 Thu 5/01/17
237 Sanitary wares & accessories 7 days Wed 14/12/16 Thu 12/01/17
238 Electrical accessories & light fittings 8 days Tue 10/01/17 Fri 20/01/17
239 TEL/DATA/MATV installation 4 days Wed 18/01/17 Tue 24/01/17
240 Shower screens 5 days Mon 23/01/17 Tue 31/01/17
241 Snag/De-snag 5 days Tue 31/01/17 Thu 9/02/17
242 Paint final coat 5 days Wed 8/02/17 Wed 15/02/17
243 Complete Block E FF internal 0 days Wed 15/02/17 Wed 15/02/17
244 Terraces First Floor 27 days Mon 23/01/17 Tue 7/03/17
245 Paint 1st & 2nd coat 5 days Mon 23/01/17 Tue 31/01/17
246 Waterproofing to terraces 7 days Thu 26/01/17 Wed 8/02/17
247 Terrace tiling 8 days Mon 6/02/17 Thu 16/02/17
248 Timber screens & cladding 7 days Mon 13/02/17 Thu 23/02/17
249 Balustrades 6 days Mon 20/02/17 Tue 28/02/17
250 Paint final coat 4 days Thu 23/02/17 Wed 1/03/17
251 Snag/De-snag 5 days Tue 28/02/17 Tue 7/03/17
252 Complete Block E Terraces FF 0 days Tue 7/03/17 Tue 7/03/17
253 First Floor Block F (F111 & F112) 89 days Fri 7/10/16 Wed 15/03/17
254 Wet Works (ceiling & tiles) 24 days Fri 7/10/16 Wed 16/11/16
255 Suspended ceiling grid work 12 days Fri 7/10/16 Wed 26/10/16
256 Floor & wall tiles 14 days Mon 24/10/16 Wed 16/11/16
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
3
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
257 Finishes Internal 63 days Mon 14/11/16 Thu 9/03/17
258 Commencement of Block F FF Finishes 0 days Mon 21/11/16 Mon 21/11/16
259 Paint 1st coat 5 days Mon 14/11/16 Mon 21/11/16
260 Aluminium openings 10 days Thu 17/11/16 Fri 2/12/16
261 Suspended Ceilings 5 days Wed 30/11/16 Wed 7/12/16
262 Shopfitting installation incl all 10 days Mon 5/12/16 Fri 6/01/17
263 Kitchen fit outs 9 days Thu 15/12/16 Tue 17/01/17
264 Granite tops 8 days Fri 13/01/17 Thu 26/01/17
265 Sanitary wares & accessories 7 days Mon 23/01/17 Mon 6/02/17
266 Electrical accessories & light fittings 8 days Tue 31/01/17 Tue 14/02/17
267 TEL/DATA/MATV installation 4 days Fri 10/02/17 Thu 16/02/17
268 Shower screens 5 days Wed 15/02/17 Thu 23/02/17
269 Snag/De-snag 5 days Thu 23/02/17 Thu 2/03/17
270 Paint final coat 5 days Wed 1/03/17 Thu 9/03/17
271 Complete Block F FF internal 0 days Thu 9/03/17 Thu 9/03/17
272 Terraces First Floor 27 days Tue 31/01/17 Wed 15/03/17
273 Paint 1st & 2nd coat 5 days Tue 31/01/17 Thu 9/02/17
274 Waterproofing to terraces 7 days Mon 6/02/17 Wed 15/02/17
275 Terrace tiling 8 days Mon 13/02/17 Fri 24/02/17
276 Timber screens & cladding 7 days Tue 21/02/17 Thu 2/03/17
277 Balustrades 6 days Mon 27/02/17 Tue 7/03/17
278 Paint final coat 4 days Thu 2/03/17 Thu 9/03/17
279 Snag/De-snag 5 days Tue 7/03/17 Wed 15/03/17
280 Complete Block F Terraces FF 0 days Wed 15/03/17 Wed 15/03/17
281 Second Floor Block E (S209 & S210) 85 days Thu 17/11/16 Fri 14/04/17
282 Wet Works (ceiling & tiles) 24 days Thu 17/11/16 Wed 11/01/17
283 Suspended ceiling grid work 12 days Thu 17/11/16 Tue 6/12/16
284 Floor & wall tiles 14 days Fri 2/12/16 Wed 11/01/17
285 Finishes Internal 63 days Mon 9/01/17 Fri 14/04/17
286 Commencement of Block E SF Finishes 0 days Mon 16/01/17 Mon 16/01/17
287 Paint 1st coat 5 days Mon 9/01/17 Mon 16/01/17
288 Aluminium openings 10 days Thu 12/01/17 Fri 27/01/17
289 Suspended Ceilings 5 days Wed 25/01/17 Thu 2/02/17
290 Shopfitting installation incl all 10 days Mon 30/01/17 Wed 15/02/17
291 Kitchen fit outs 9 days Mon 13/02/17 Mon 27/02/17
292 Granite tops 8 days Thu 23/02/17 Tue 7/03/17
293 Sanitary wares & accessories 7 days Fri 3/03/17 Wed 15/03/17
294 Electrical accessories & light fittings 8 days Mon 13/03/17 Fri 24/03/17
295 TEL/DATA/MATV installation 4 days Wed 22/03/17 Tue 28/03/17
296 Shower screens 5 days Mon 27/03/17 Mon 3/04/17
297 Snag/De-snag 5 days Mon 3/04/17 Mon 10/04/17
298 Paint final coat 5 days Fri 7/04/17 Fri 14/04/17
299 Complete Block E SF internal 0 days Fri 14/04/17 Fri 14/04/17
300 Terraces Second Floor 27 days Tue 21/02/17 Mon 3/04/17
301 Paint 1st & 2nd coat 5 days Tue 21/02/17 Tue 28/02/17
302 Waterproofing to terraces 7 days Thu 23/02/17 Mon 6/03/17
303 Terrace tiling & Pool tiling 8 days Thu 2/03/17 Wed 15/03/17
304 Timber screens & cladding 7 days Fri 10/03/17 Wed 22/03/17
305 Balustrades 6 days Thu 16/03/17 Mon 27/03/17
306 Paint final coat 4 days Wed 22/03/17 Tue 28/03/17
307 Snag/De-snag 5 days Mon 27/03/17 Mon 3/04/17
308 Complete Block E Terraces SF 0 days Mon 3/04/17 Mon 3/04/17
309 Second Floor Block F (S211 & S212) 85 days Wed 7/12/16 Fri 5/05/17
310 Wet Works (ceiling & tiles) 24 days Wed 7/12/16 Tue 31/01/17
311 Suspended ceiling grid work 12 days Wed 7/12/16 Thu 12/01/17
312 Floor & wall tiles 14 days Tue 10/01/17 Tue 31/01/17
313 Finishes Internal 63 days Fri 27/01/17 Fri 5/05/17
314 Commencement of Block F SF Finishes 0 days Tue 7/02/17 Tue 7/02/17
315 Paint 1st coat 5 days Fri 27/01/17 Tue 7/02/17
316 Aluminium openings 10 days Thu 2/02/17 Mon 20/02/17
317 Suspended Ceilings 5 days Wed 15/02/17 Thu 23/02/17
318 Shopfitting installation incl all 10 days Tue 21/02/17 Tue 7/03/17
319 Kitchen fit outs 9 days Fri 3/03/17 Fri 17/03/17
320 Granite tops 8 days Wed 15/03/17 Tue 28/03/17
321 Sanitary wares & accessories 7 days Fri 24/03/17 Tue 4/04/17
322 Electrical accessories & light fittings 8 days Fri 31/03/17 Wed 12/04/17
323 TEL/DATA/MATV installation 4 days Mon 10/04/17 Fri 14/04/17
324 Shower screens 5 days Thu 13/04/17 Fri 21/04/17
325 Snag/De-snag 5 days Fri 21/04/17 Fri 28/04/17
326 Paint final coat 5 days Thu 27/04/17 Fri 5/05/17
327 Complete Block F SF internal 0 days Fri 5/05/17 Fri 5/05/17
328 Terraces Second Floor 27 days Wed 15/03/17 Tue 25/04/17
329 Paint 1st & 2nd coat 5 days Wed 15/03/17 Thu 23/03/17
330 Waterproofing to terraces 7 days Fri 17/03/17 Wed 29/03/17
331 Terrace tiling & Pool tiling 8 days Mon 27/03/17 Thu 6/04/17
332 Timber screens & cladding 7 days Mon 3/04/17 Wed 12/04/17
333 Balustrades 6 days Fri 7/04/17 Mon 17/04/17
334 Paint final coat 4 days Wed 12/04/17 Wed 19/04/17
335 Snag/De-snag 5 days Mon 17/04/17 Tue 25/04/17
336 Complete Block F Terraces SF 0 days Tue 25/04/17 Tue 25/04/17
337 Externally & Common areas Block E 110 days Thu 25/08/16 Wed 1/03/17
338 Commencement of Block E Externally & Common areas 0 days Fri 21/10/16 Fri 21/10/16
339 Waterproofing on roof 8 days Fri 21/10/16 Fri 4/11/16
340 M & E Equipments on roof 12 days Mon 31/10/16 Mon 21/11/16
341 Paint 1st & 2nd coat 6 days Mon 16/01/17 Tue 24/01/17
342 Lifts installation including finishes 15 days Fri 28/10/16 Wed 23/11/16
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
4
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
343 Appointment of external stone subcontractor 0 days Thu 25/08/16 Thu 25/08/16
344 Stone cladding 15 days Fri 20/01/17 Wed 15/02/17
345 Composite timber cladding & gates 15 days Fri 20/01/17 Wed 15/02/17
346 Balustrades 10 days Wed 25/01/17 Fri 10/02/17
347 Tiling to main staircases and common areas 10 days Wed 11/01/17 Thu 26/01/17
348 Paint final coat 7 days Wed 8/02/17 Mon 20/02/17
349 Snag/De-snag 7 days Mon 20/02/17 Wed 1/03/17
350 Complete Block E External Finishes & Common areas 0 days Wed 1/03/17 Wed 1/03/17
351 Externally & Common areas Block F 72 days Fri 4/11/16 Wed 15/03/17
352 Commencement of Block F Externally & Common areas 0 days Fri 4/11/16 Fri 4/11/16
353 Waterproofing on roof 8 days Fri 4/11/16 Thu 17/11/16
354 M & E Equipments on roof 12 days Mon 21/11/16 Thu 8/12/16
355 Paint 1st & 2nd coat 6 days Wed 25/01/17 Mon 6/02/17
356 Lifts installation including finishes 18 days Wed 23/11/16 Mon 9/01/17
357 Stone cladding 15 days Wed 15/02/17 Fri 10/03/17
358 Composite timber cladding & gates 15 days Wed 15/02/17 Fri 10/03/17
359 Balustrades 10 days Fri 10/02/17 Mon 27/02/17
360 Tiling to main staircases and common areas 10 days Tue 31/01/17 Thu 16/02/17
361 Paint final coat 7 days Mon 20/02/17 Wed 1/03/17
362 Snag/De-snag 7 days Fri 3/03/17 Wed 15/03/17
363 Complete Block F External Finishes & Common areas 0 days Wed 15/03/17 Wed 15/03/17
364 Block AB 314 days Tue 15/12/15 Mon 8/05/17
365 Structure 189 days Tue 15/12/15 Thu 6/10/16
366 Ground Floor Slab 189 days Tue 15/12/15 Thu 6/10/16
367 FRC beams 18 days Tue 15/12/15 Mon 25/01/16
368 FRC basement slab(GF) inc MEPD conduits 25 days Fri 15/01/16 Fri 26/02/16
369 Completion of basement slab AB (GF) 0 days Fri 26/02/16 Fri 26/02/16
370 Deformwork 5 days Wed 16/03/16 Thu 24/03/16
371 Superstructure 168.55 days Wed 27/01/16 Thu 6/10/16
372 Ground to 1st 152.63 days Wed 27/01/16 Wed 14/09/16
373 Setting out 10 days Thu 11/02/16 Mon 29/02/16
374 Blockwork 24 days Mon 15/02/16 Thu 24/03/16
375 Commencement of AB Blockwork 0 days Mon 15/02/16 Mon 15/02/16
376 Erect tower crane 0 days Tue 23/02/16 Tue 23/02/16
377 FRC columns 14 days Tue 1/03/16 Wed 23/03/16
378 FRC beams 18 days Fri 4/03/16 Thu 31/03/16
379 FRC 1st Floor slab inc MEPD conduits 24 days Wed 9/03/16 Thu 14/04/16
380 Completion of AB 1st floor slab (Milestone 50% structu 0 days Thu 14/04/16 Thu 14/04/16
381 SOATA RHS Changes Block AB 152.63 days Wed 27/01/16 Wed 14/09/16
382 Receive dwgs and reply to EFI 0 days Sat 16/04/16 Sat 16/04/16
383 Add adidional RHS 24/03/16 & 11/04/16 0 days Thu 24/03/16 Thu 24/03/16
384 Receive instructions abortive bases/columns 0 days Fri 29/04/16 Fri 29/04/16
385 Procure and manufacture additional RHS 35 days Wed 27/01/16 Thu 24/03/16
386 Receive instruction modifications to RHS GL L 0 days Thu 9/06/16 Thu 9/06/16
387 Modifications to RHS 10 days Fri 10/06/16 Fri 24/06/16
388 FWK, Reinf, Cast new bases, columns, walls GL L 14 days Wed 1/06/16 Wed 22/06/16
389 Receive new instruction RC Wall & dowel reinforc 0 days Tue 17/05/16 Tue 17/05/16
390 FRC RC wall base 3 days Wed 18/05/16 Mon 23/05/16
391 FRC RC wall & dowel reinforcing & waterproof 7 days Mon 23/05/16 Wed 1/06/16
392 Backfill to U/S terraces 4 days Thu 7/07/16 Wed 13/07/16
393 FRC terraces GF 7 days Thu 28/07/16 Tue 9/08/16
394 Installation of RHS to 1st floor 4 days Tue 9/08/16 Mon 15/08/16
395 FRC terraces 1st floor 8 days Mon 15/08/16 Thu 25/08/16
396 Complete 1st floor terraces 0 days Thu 25/08/16 Thu 25/08/16
397 Deformwork terraces 1st floor 3 days Thu 8/09/16 Wed 14/09/16
398 Continuation of Ground to 1st works 5 days Thu 28/04/16 Thu 5/05/16
399 Deformwork 5 days Thu 28/04/16 Thu 5/05/16
400 1st to 2nd 103 days Tue 29/03/16 Fri 26/08/16
401 Setting out 5 days Mon 2/05/16 Mon 9/05/16
402 Blockwork 24 days Mon 2/05/16 Mon 6/06/16
403 FRC columns 14 days Fri 13/05/16 Fri 3/06/16
404 FRC beams 16 days Mon 16/05/16 Wed 8/06/16
405 Appointment of Pool & Water Feature Equipment Supp 0 days Tue 29/03/16 Tue 29/03/16
406 Appointment pool lights 0 days Fri 1/04/16 Fri 1/04/16
407 Additional changes 2nd floor slab (tender to latest 6 days Fri 13/05/16 Mon 23/05/16
408 General changes as per marked up drawing 6 days Fri 13/05/16 Mon 23/05/16
409 Complete additional changes to block EF 2nd floo 0 days Mon 23/05/16 Mon 23/05/16
410 Additional canopy added 2nd floor 8 days Thu 7/07/16 Wed 20/07/16
411 Erect formwork canopy 5 days Thu 7/07/16 Thu 14/07/16
412 Reinforcing to canopy 3 days Wed 13/07/16 Tue 19/07/16
413 concrete to canopy 1 day Tue 19/07/16 Wed 20/07/16
414 FRC 2nd floor slab inc MEPD conduits 24 days Thu 30/06/16 Thu 4/08/16
415 Completion FRC 2nd floor slab inc MEPD conduits AB 0 days Thu 4/08/16 Thu 4/08/16
416 Deformwork 5 days Fri 19/08/16 Fri 26/08/16
417 2nd to Roof 48 days Thu 28/07/16 Thu 6/10/16
418 Setting out 5 days Thu 28/07/16 Thu 4/08/16
419 Blockwork 18 days Fri 29/07/16 Thu 25/08/16
420 FRC columns 12 days Tue 9/08/16 Thu 25/08/16
421 FRC beams 16 days Wed 10/08/16 Thu 1/09/16
422 FRC roof slab inc MEPD conduits 24 days Thu 11/08/16 Wed 14/09/16
423 Completion of AB Roof slab (Milestone Structure) 0 days Wed 14/09/16 Wed 14/09/16
424 Dismantle tower crane and remove from site 0 days Wed 14/09/16 Wed 14/09/16
425 Deformwork 5 days Thu 29/09/16 Thu 6/10/16
426 Parapet walls & 2nd floor pools Block AB 15 days Wed 7/09/16 Thu 29/09/16
427 External SAOTA changes and Additional works Block A 100.71 days Fri 29/04/16 Mon 26/09/16
428 Receive instruction additional/changes bases, columns 0 days Fri 29/04/16 Fri 29/04/16
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
5
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
429 Excavate, drill dowel existing bases 7 days Mon 9/05/16 Wed 18/05/16
430 FRC new bases (link to EF, current 35 %) 8 days Wed 25/05/16 Tue 7/06/16
431 FRC new columns, walls etc 6 days Tue 7/06/16 Wed 15/06/16
432 Receive instruction Addition of R.C Wall at GL A/7' 0 days Tue 17/05/16 Tue 17/05/16
433 FRC bases RC walls 8 days Tue 7/06/16 Fri 17/06/16
434 FRC RC walls incl doweling to reinforcing 12 days Fri 17/06/16 Wed 6/07/16
435 Receive instruction additional/changes bases, columns 0 days Fri 29/04/16 Fri 29/04/16
436 Abortive works break stub columns 2 days Mon 2/05/16 Wed 4/05/16
437 FRC circular columns 5 days Wed 4/05/16 Wed 11/05/16
438 Receive instruction floating platform 0 days Tue 7/06/16 Tue 7/06/16
439 Backfill 5 days Wed 6/07/16 Wed 13/07/16
440 FRC floating platform works 30 days Fri 12/08/16 Mon 26/09/16
441 Complete columns & RC wall to canopy 30 days Thu 21/07/16 Fri 2/09/16
442 Complete external SAOTA 0 days Fri 2/09/16 Fri 2/09/16
443 Wet Trades 162 days Thu 5/05/16 Fri 20/01/17
444 Internally 155 days Thu 5/05/16 Wed 11/01/17
445 Basement 60 days Thu 15/09/16 Thu 15/12/16
446 Basement block and wet works 40 days Thu 15/09/16 Wed 16/11/16
447 Render common stairs 20 days Wed 16/11/16 Thu 15/12/16
448 Ground Floor 72.22 days Thu 5/05/16 Fri 19/08/16
449 Partition block wall & risers 12 days Thu 5/05/16 Tue 24/05/16
450 M&E 1st & 2nd fix 25 days Tue 14/06/16 Thu 21/07/16
451 Preplaster Check 15 days Tue 14/06/16 Wed 6/07/16
452 SAOTA Changes Block AB Ground Floor Internal (Anne 34.89 days Fri 6/05/16 Tue 28/06/16
453 SAOTA layout/Elevation drawings received 06/05/16 0 days Fri 6/05/16 Fri 6/05/16
454 New details including structural received up to 12/05/1 0 days Thu 12/05/16 Thu 12/05/16
455 Setting out additional opeings, M & E service changes 3 days Thu 12/05/16 Tue 17/05/16
456 Breaking in additional openings, reducing columns, ext 8 days Tue 31/05/16 Fri 10/06/16
457 M & E chasings,rerouting 5 days Thu 9/06/16 Thu 16/06/16
458 FRC additional columns, jambs & cills incl dowling 8 days Wed 15/06/16 Tue 28/06/16
459 Receive instruction close newly broken openings 07/06 0 days Tue 7/06/16 Tue 7/06/16
460 FRC close openings incl dowel, hack 4 days Wed 15/06/16 Tue 21/06/16
461 Render wall & ceilings internal 24 days Thu 16/06/16 Fri 22/07/16
462 Completion of AB GF Floor wet trades 0 days Fri 19/08/16 Fri 19/08/16
463 1st Floor 50 days Thu 18/08/16 Mon 31/10/16
464 Partition block wall & risers 10 days Fri 19/08/16 Fri 2/09/16
465 M&E 1st & 2nd fix 15 days Thu 18/08/16 Thu 8/09/16
466 Preplaster Check 10 days Fri 26/08/16 Fri 9/09/16
467 Render wall & ceilings internal 26 days Tue 30/08/16 Thu 6/10/16
468 Completion of AB 1st Floor wet trades 0 days Mon 31/10/16 Mon 31/10/16
469 2nd Floor 49 days Fri 7/10/16 Wed 11/01/17
470 Partition block wall & risers 12 days Fri 7/10/16 Wed 26/10/16
471 M&E 1st & 2nd fix 12 days Mon 10/10/16 Thu 27/10/16
472 Preplaster Check 10 days Fri 14/10/16 Mon 31/10/16
473 Render wall & ceilings internal 25 days Tue 18/10/16 Mon 28/11/16
474 Completion of AB 2nd Floor wet trades 0 days Wed 11/01/17 Wed 11/01/17
475 Externally (Block AB) 67 days Thu 22/09/16 Fri 20/01/17
476 Plaster parapet wall on roof 10 days Mon 26/09/16 Mon 10/10/16
477 Plaster front façade 25 days Tue 4/10/16 Mon 14/11/16
478 Plaster side façade 20 days Thu 3/11/16 Fri 2/12/16
479 Plaster rear facades 25 days Fri 25/11/16 Fri 20/01/17
480 Builders work in connection with services on roof & Screed 20 days Thu 22/09/16 Thu 20/10/16
481 Complete Plaster AB External facades 0 days Fri 20/01/17 Fri 20/01/17
482 Finishes 178.78 days Wed 20/07/16 Mon 8/05/17
483 Internally 178.78 days Wed 20/07/16 Mon 8/05/17
484 Basement 80 days Wed 30/11/16 Thu 20/04/17
485 Finishes 30 days Wed 30/11/16 Thu 2/02/17
486 Make good to basement floor 20 days Thu 23/03/17 Thu 20/04/17
487 Ground Floor Block B ( G003 & G004) 132.78 days Wed 20/07/16 Mon 27/02/17
488 Wet Works (ceiling & tiles) 21 days Wed 20/07/16 Fri 19/08/16
489 Suspended ceiling grid work 12 days Wed 20/07/16 Mon 8/08/16
490 Floor & wall tiles 14 days Mon 1/08/16 Fri 19/08/16
491 Finishes Internal 63 days Wed 17/08/16 Mon 21/11/16
492 Commencement of Block B GF Finishes 0 days Wed 24/08/16 Wed 24/08/16
493 Paint 1st coat 5 days Wed 17/08/16 Wed 24/08/16
494 Aluminium openings 10 days Mon 22/08/16 Mon 5/09/16
495 Suspended Ceilings 5 days Thu 1/09/16 Fri 9/09/16
496 Shopfitting installation incl all 10 days Wed 7/09/16 Wed 21/09/16
497 Kitchen fit outs 9 days Mon 19/09/16 Fri 30/09/16
498 Granite tops 8 days Wed 28/09/16 Mon 10/10/16
499 Sanitary wares & accessories 7 days Thu 6/10/16 Tue 18/10/16
500 Electrical accessories & light fittings 8 days Thu 13/10/16 Wed 26/10/16
501 TEL/DATA/MATV installation 4 days Mon 24/10/16 Fri 28/10/16
502 Shower screens 5 days Thu 27/10/16 Mon 7/11/16
503 Snag/De-snag 5 days Mon 7/11/16 Tue 15/11/16
504 Paint final coat 5 days Mon 14/11/16 Mon 21/11/16
505 Complete Block B GF internal 0 days Mon 21/11/16 Mon 21/11/16
506 Terraces Ground Floor 28 days Thu 12/01/17 Mon 27/02/17
507 Paint 1st & 2nd coat 5 days Thu 12/01/17 Thu 19/01/17
508 Waterproofing to terraces 7 days Mon 16/01/17 Wed 25/01/17
509 Terrace tiling 8 days Mon 23/01/17 Tue 7/02/17
510 Timber screens & cladding 7 days Mon 30/01/17 Mon 13/02/17
511 Balustrades 6 days Wed 8/02/17 Thu 16/02/17
512 Paint final coat 4 days Tue 14/02/17 Tue 21/02/17
513 Snag/De-snag 5 days Mon 20/02/17 Mon 27/02/17
514 Complete Block B Terraces GF 0 days Mon 27/02/17 Mon 27/02/17
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
6
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
515 Ground Floor Block A (G001 & G002) 121.78 days Fri 12/08/16 Mon 6/03/17
516 Wet Works (ceiling & tiles) 21 days Fri 12/08/16 Tue 13/09/16
517 Suspended ceiling grid work 12 days Fri 12/08/16 Tue 30/08/16
518 Floor & wall tiles 14 days Tue 23/08/16 Tue 13/09/16
519 Finishes Internal 63 days Fri 9/09/16 Wed 14/12/16
520 Commencement of Block A GF Finishes 0 days Fri 16/09/16 Fri 16/09/16
521 Paint 1st coat 5 days Fri 9/09/16 Fri 16/09/16
522 Aluminium openings 10 days Wed 14/09/16 Wed 28/09/16
523 Suspended Ceilings 5 days Mon 26/09/16 Mon 3/10/16
524 Shopfitting installation incl all 10 days Thu 29/09/16 Thu 13/10/16
525 Kitchen fit outs 9 days Tue 11/10/16 Tue 25/10/16
526 Granite tops 8 days Fri 21/10/16 Fri 4/11/16
527 Sanitary wares & accessories 7 days Mon 31/10/16 Mon 14/11/16
528 Electrical accessories & light fittings 8 days Wed 9/11/16 Tue 22/11/16
529 TEL/DATA/MATV installation 4 days Fri 18/11/16 Thu 24/11/16
530 Shower screens 5 days Wed 23/11/16 Thu 1/12/16
531 Snag/De-snag 5 days Thu 1/12/16 Thu 8/12/16
532 Paint final coat 5 days Wed 7/12/16 Wed 14/12/16
533 Complete Block A GF internal 0 days Wed 14/12/16 Wed 14/12/16
534 Terraces Ground Floor 28 days Thu 19/01/17 Mon 6/03/17
535 Paint 1st & 2nd coat 5 days Thu 19/01/17 Thu 26/01/17
536 Waterproofing to terraces 7 days Mon 23/01/17 Thu 2/02/17
537 Terrace tiling 8 days Mon 30/01/17 Tue 14/02/17
538 Timber screens & cladding 7 days Thu 9/02/17 Tue 21/02/17
539 Balustrades 6 days Wed 15/02/17 Fri 24/02/17
540 Paint final coat 4 days Wed 22/02/17 Tue 28/02/17
541 Snag/De-snag 5 days Mon 27/02/17 Mon 6/03/17
542 Complete Block A Terraces GF 0 days Mon 6/03/17 Mon 6/03/17
543 First Floor Block B (F103 & F104) 92 days Mon 26/09/16 Mon 6/03/17
544 Wet Works (ceiling & tiles) 24 days Mon 26/09/16 Mon 31/10/16
545 Suspended ceiling grid work 12 days Mon 26/09/16 Wed 12/10/16
546 Floor & wall tiles 14 days Mon 10/10/16 Mon 31/10/16
547 Finishes Internal 63 days Thu 27/10/16 Thu 23/02/17
548 Commencement of Block B FF Finishes 0 days Mon 7/11/16 Mon 7/11/16
549 Paint 1st coat 5 days Thu 27/10/16 Mon 7/11/16
550 Aluminium openings 10 days Thu 3/11/16 Fri 18/11/16
551 Suspended Ceilings 5 days Wed 16/11/16 Wed 23/11/16
552 Shopfitting installation incl all 10 days Mon 21/11/16 Mon 5/12/16
553 Kitchen fit outs 9 days Thu 1/12/16 Thu 15/12/16
554 Granite tops 8 days Tue 13/12/16 Thu 12/01/17
555 Sanitary wares & accessories 7 days Tue 10/01/17 Thu 19/01/17
556 Electrical accessories & light fittings 8 days Tue 17/01/17 Fri 27/01/17
557 TEL/DATA/MATV installation 4 days Wed 25/01/17 Tue 31/01/17
558 Shower screens 5 days Mon 30/01/17 Thu 9/02/17
559 Snag/De-snag 5 days Thu 9/02/17 Thu 16/02/17
560 Paint final coat 5 days Wed 15/02/17 Thu 23/02/17
561 Complete Block B FF internal 0 days Thu 23/02/17 Thu 23/02/17
562 Terraces First Floor 27 days Fri 20/01/17 Mon 6/03/17
563 Paint 1st & 2nd coat 5 days Fri 20/01/17 Fri 27/01/17
564 Waterproofing to terraces 7 days Tue 24/01/17 Tue 7/02/17
565 Terrace tiling 8 days Tue 31/01/17 Wed 15/02/17
566 Timber screens & cladding 7 days Fri 10/02/17 Wed 22/02/17
567 Balustrades 6 days Thu 16/02/17 Mon 27/02/17
568 Paint final coat 4 days Wed 22/02/17 Tue 28/02/17
569 Snag/De-snag 5 days Mon 27/02/17 Mon 6/03/17
570 Complete Block B Terraces FF 0 days Mon 6/03/17 Mon 6/03/17
571 First Floor Block A (F101 & F102) 88 days Wed 12/10/16 Fri 17/03/17
572 Wet Works (ceiling & tiles) 23 days Wed 12/10/16 Fri 18/11/16
573 Suspended ceiling grid work 12 days Wed 12/10/16 Mon 31/10/16
574 Floor & wall tiles 14 days Wed 26/10/16 Fri 18/11/16
575 Finishes Internal 63 days Wed 16/11/16 Fri 10/03/17
576 Commencement of Block A FF Finishes 0 days Wed 23/11/16 Wed 23/11/16
577 Paint 1st coat 5 days Wed 16/11/16 Wed 23/11/16
578 Aluminium openings 10 days Mon 21/11/16 Mon 5/12/16
579 Suspended Ceilings 5 days Thu 1/12/16 Fri 9/12/16
580 Shopfitting installation incl all 10 days Wed 7/12/16 Tue 10/01/17
581 Kitchen fit outs 9 days Fri 6/01/17 Thu 19/01/17
582 Granite tops 8 days Tue 17/01/17 Fri 27/01/17
583 Sanitary wares & accessories 7 days Wed 25/01/17 Wed 8/02/17
584 Electrical accessories & light fittings 8 days Mon 6/02/17 Thu 16/02/17
585 TEL/DATA/MATV installation 4 days Tue 14/02/17 Tue 21/02/17
586 Shower screens 5 days Mon 20/02/17 Mon 27/02/17
587 Snag/De-snag 5 days Mon 27/02/17 Mon 6/03/17
588 Paint final coat 5 days Fri 3/03/17 Fri 10/03/17
589 Complete Block A FF internal 0 days Fri 10/03/17 Fri 10/03/17
590 Terraces First Floor 27 days Mon 6/02/17 Fri 17/03/17
591 Paint 1st & 2nd coat 5 days Mon 6/02/17 Mon 13/02/17
592 Waterproofing to terraces 7 days Wed 8/02/17 Mon 20/02/17
593 Terrace tiling 8 days Wed 15/02/17 Tue 28/02/17
594 Timber screens & cladding 7 days Thu 23/02/17 Mon 6/03/17
595 Balustrades 6 days Wed 1/03/17 Thu 9/03/17
596 Paint final coat 4 days Mon 6/03/17 Fri 10/03/17
597 Snag/De-snag 5 days Thu 9/03/17 Fri 17/03/17
598 Complete Block A Terraces FF 0 days Fri 17/03/17 Fri 17/03/17
599 Second Floor Block B (S02) 85 days Thu 17/11/16 Fri 14/04/17
600 Wet Works (ceiling & tiles) 24 days Thu 17/11/16 Wed 11/01/17
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
7
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
601 Suspended ceiling grid work 12 days Thu 17/11/16 Mon 5/12/16
602 Floor & wall tiles 14 days Thu 1/12/16 Wed 11/01/17
603 Finishes Internal 63 days Mon 9/01/17 Fri 14/04/17
604 Commencement of Block B SF Finishes 0 days Mon 16/01/17 Mon 16/01/17
605 Paint 1st coat 5 days Mon 9/01/17 Mon 16/01/17
606 Aluminium openings 10 days Thu 12/01/17 Thu 26/01/17
607 Suspended Ceilings 5 days Tue 24/01/17 Tue 31/01/17
608 Shopfitting installation incl all 10 days Fri 27/01/17 Wed 15/02/17
609 Kitchen fit outs 9 days Mon 13/02/17 Mon 27/02/17
610 Granite tops 8 days Thu 23/02/17 Tue 7/03/17
611 Sanitary wares & accessories 7 days Fri 3/03/17 Tue 14/03/17
612 Electrical accessories & light fittings 8 days Fri 10/03/17 Fri 24/03/17
613 TEL/DATA/MATV installation 4 days Wed 22/03/17 Tue 28/03/17
614 Shower screens 5 days Mon 27/03/17 Mon 3/04/17
615 Snag/De-snag 5 days Mon 3/04/17 Mon 10/04/17
616 Paint final coat 5 days Fri 7/04/17 Fri 14/04/17
617 Complete Block B SF internal 0 days Fri 14/04/17 Fri 14/04/17
618 Terraces Second Floor 72 days Thu 17/11/16 Tue 28/03/17
619 Paint 1st & 2nd coat 5 days Tue 14/02/17 Wed 22/02/17
620 Waterproofing to terraces 7 days Thu 16/02/17 Tue 28/02/17
621 Appointment pool tiling 0 days Thu 17/11/16 Thu 17/11/16
622 Terrace tiling & Pool tiling 8 days Fri 24/02/17 Wed 8/03/17
623 Timber screens & cladding 7 days Fri 3/03/17 Tue 14/03/17
624 Balustrades 6 days Thu 9/03/17 Mon 20/03/17
625 Paint final coat 4 days Tue 14/03/17 Wed 22/03/17
626 Snag/De-snag 5 days Mon 20/03/17 Tue 28/03/17
627 Complete Block B Terraces SF 0 days Tue 28/03/17 Tue 28/03/17
628 Second Floor Block A (S01) 85 days Thu 8/12/16 Mon 8/05/17
629 Wet Works (ceiling & tiles) 24 days Thu 8/12/16 Tue 31/01/17
630 Suspended ceiling grid work 12 days Thu 8/12/16 Fri 13/01/17
631 Floor & wall tiles 14 days Wed 11/01/17 Tue 31/01/17
632 Finishes Internal 63 days Fri 27/01/17 Mon 8/05/17
633 Commencement of Block A SF Finishes 0 days Wed 8/02/17 Wed 8/02/17
634 Paint 1st coat 5 days Fri 27/01/17 Wed 8/02/17
635 Aluminium openings 10 days Mon 6/02/17 Tue 21/02/17
636 Suspended Ceilings 5 days Thu 16/02/17 Fri 24/02/17
637 Shopfitting installation incl all 10 days Wed 22/02/17 Wed 8/03/17
638 Kitchen fit outs 9 days Mon 6/03/17 Mon 20/03/17
639 Granite tops 8 days Wed 15/03/17 Wed 29/03/17
640 Sanitary wares & accessories 7 days Mon 27/03/17 Wed 5/04/17
641 Electrical accessories & light fittings 8 days Mon 3/04/17 Thu 13/04/17
642 TEL/DATA/MATV installation 4 days Tue 11/04/17 Mon 17/04/17
643 Shower screens 5 days Fri 14/04/17 Fri 21/04/17
644 Snag/De-snag 5 days Fri 21/04/17 Tue 2/05/17
645 Paint final coat 5 days Fri 28/04/17 Mon 8/05/17
646 Complete Block A SF internal 0 days Mon 8/05/17 Mon 8/05/17
647 Terraces Second Floor 72 days Thu 12/01/17 Thu 4/05/17
648 Paint 1st & 2nd coat 5 days Fri 24/03/17 Fri 31/03/17
649 Waterproofing to terraces 7 days Tue 28/03/17 Thu 6/04/17
650 Appointment pool tiling 0 days Thu 12/01/17 Thu 12/01/17
651 Terrace tiling & Pool tiling 8 days Tue 4/04/17 Fri 14/04/17
652 Timber screens & cladding 7 days Tue 11/04/17 Thu 20/04/17
653 Balustrades 6 days Mon 17/04/17 Tue 25/04/17
654 Paint final coat 4 days Thu 20/04/17 Thu 27/04/17
655 Snag/De-snag 5 days Tue 25/04/17 Thu 4/05/17
656 Complete Block A Terraces SF 0 days Thu 4/05/17 Thu 4/05/17
657 Externally & Common areas Block B 65 days Fri 28/10/16 Tue 28/02/17
658 Commencement of Block B Externally & Common areas 0 days Thu 10/11/16 Thu 10/11/16
659 Waterproofing on roof 8 days Thu 10/11/16 Wed 23/11/16
660 M & E Equipments on roof 12 days Mon 21/11/16 Thu 8/12/16
661 Paint 1st & 2nd coat 6 days Wed 18/01/17 Thu 26/01/17
662 Lifts installation including finishes 18 days Fri 28/10/16 Mon 28/11/16
663 Stone cladding 15 days Tue 24/01/17 Mon 20/02/17
664 Composite timber cladding, pergolas & gates 15 days Tue 24/01/17 Mon 20/02/17
665 Balustrades 10 days Tue 24/01/17 Fri 10/02/17
666 Tiling to main staircases and common areas 10 days Mon 16/01/17 Mon 30/01/17
667 Paint final coat 7 days Tue 7/02/17 Thu 16/02/17
668 Snag/De-snag 7 days Thu 16/02/17 Tue 28/02/17
669 Complete Block B External Finishes & Common areas 0 days Tue 28/02/17 Tue 28/02/17
670 Externally & Common areas Block A 62 days Wed 23/11/16 Fri 17/03/17
671 Commencement of Block A Externally & Common areas 0 days Wed 23/11/16 Wed 23/11/16
672 Waterproofing on roof 8 days Wed 23/11/16 Mon 5/12/16
673 M & E Equipments on roof 12 days Thu 8/12/16 Fri 13/01/17
674 Paint 1st & 2nd coat 6 days Thu 26/01/17 Wed 8/02/17
675 Lifts installation including finishes 18 days Mon 28/11/16 Thu 12/01/17
676 Stone cladding 15 days Mon 20/02/17 Mon 13/03/17
677 Composite timber cladding, pergolas & gates 15 days Mon 20/02/17 Mon 13/03/17
678 Balustrades 10 days Fri 10/02/17 Mon 27/02/17
679 Tiling to main staircases and common areas 10 days Tue 31/01/17 Mon 20/02/17
680 Paint final coat 7 days Fri 24/02/17 Tue 7/03/17
681 Snag/De-snag 7 days Tue 7/03/17 Fri 17/03/17
682 Complete Block A External Finishes & Common areas 0 days Fri 17/03/17 Fri 17/03/17
683 Block CD 317.8 days Mon 11/01/16 Thu 25/05/17
684 Structure 192.8 days Mon 11/01/16 Tue 25/10/16
685 RC Ramp Walls Changes to Block D (EOT3) 32 days Tue 19/04/16 Mon 6/06/16
686 Receive all information complete 0 days Tue 19/04/16 Tue 19/04/16
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
8
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
687 Excavate and compact 1 day Wed 20/04/16 Thu 21/04/16
688 Extend blinding 1 day Thu 21/04/16 Fri 22/04/16
689 Setting out 1 day Fri 22/04/16 Mon 25/04/16
690 FRC base RC Wall 2 days Mon 25/04/16 Wed 27/04/16
691 FRC RC Wall (2 sides) (dowel as per EFI) 4 days Wed 27/04/16 Tue 3/05/16
692 FRC GF basement slab above RC Wall 4 days Mon 2/05/16 Fri 6/05/16
693 Complete basement slab D 0 days Fri 6/05/16 Fri 6/05/16
694 Deformwork 0 days Tue 24/05/16 Tue 24/05/16
695 Ground to 1st Floor 20 days Fri 6/05/16 Mon 6/06/16
696 Block work 4 days Fri 6/05/16 Thu 12/05/16
697 FRC Columns 3 days Tue 10/05/16 Fri 13/05/16
698 FRC 1st Floor slab actual cast date 6 days Wed 11/05/16 Thu 19/05/16
699 Deformwork 1 day Fri 3/06/16 Mon 6/06/16
700 Completion of 1st floor slab actual cast date 0 days Thu 19/05/16 Thu 19/05/16
701 Ground Floor Slab 52 days Mon 11/01/16 Fri 1/04/16
702 FRC beams 17 days Mon 11/01/16 Mon 8/02/16
703 FRC basement slab(GF) inc MEPD conduits 24 days Wed 27/01/16 Tue 8/03/16
704 Completion of basement slab CD (GF) 0 days Tue 8/03/16 Tue 8/03/16
705 Deformwork 5 days Fri 25/03/16 Fri 1/04/16
706 Superstructure 181.35 days Wed 27/01/16 Tue 25/10/16
707 Ground to 1st 159.04 days Wed 27/01/16 Thu 22/09/16
708 Setting out 6 days Tue 23/02/16 Thu 3/03/16
709 Blockwork 23 days Wed 24/02/16 Wed 30/03/16
710 Commencement of CD Blockwork 0 days Wed 24/02/16 Wed 24/02/16
711 Erect tower crane 0 days Mon 29/02/16 Mon 29/02/16
712 FRC columns 14 days Tue 8/03/16 Tue 29/03/16
713 FRC beams 16 days Thu 10/03/16 Mon 4/04/16
714 FRC 1st Floor slab inc MEPD conduits 23 days Fri 11/03/16 Fri 15/04/16
715 Completion of CD 1st floor slab (50% Milestone) 0 days Fri 15/04/16 Fri 15/04/16
716 SOATA RHS Changes Block CD 159.04 days Wed 27/01/16 Thu 22/09/16
717 Receive dwgs and reply to EFI 0 days Sat 16/04/16 Sat 16/04/16
718 Add adidional RHS 24/03/16 & 11/04/16 0 days Thu 24/03/16 Thu 24/03/16
719 Receive instructions abortive bases/columns 0 days Fri 29/04/16 Fri 29/04/16
720 Procure and manufacture additional RHS 35 days Wed 27/01/16 Thu 24/03/16
721 Receive instruction modifications to RHS GL L 0 days Thu 9/06/16 Thu 9/06/16
722 Modifications to RHS 10 days Fri 10/06/16 Fri 24/06/16
723 FWK, Reinf, Cast new bases, columns, walls GL L & A 14 days Mon 13/06/16 Fri 1/07/16
724 Receive new instruction RC Wall & dowel reinforcing 0 days Tue 17/05/16 Tue 17/05/16
725 FRC RC wall base 3 days Wed 18/05/16 Mon 23/05/16
726 FRC RC wall & dowel reinforcing & waterproof 7 days Mon 23/05/16 Wed 1/06/16
727 Backfill to U/S terraces 4 days Tue 26/07/16 Mon 1/08/16
728 FRC terraces GF 7 days Mon 1/08/16 Wed 10/08/16
729 Installation of RHS to 1st floor 4 days Wed 17/08/16 Tue 23/08/16
730 FRC terraces 1st floor 8 days Tue 23/08/16 Mon 5/09/16
731 Complete 1st floor terraces 0 days Mon 5/09/16 Mon 5/09/16
732 Deformwork terraces 1st floor 3 days Mon 19/09/16 Thu 22/09/16
733 Continuation of Ground to 1st 5 days Fri 29/04/16 Fri 6/05/16
734 Deformwork 5 days Fri 29/04/16 Fri 6/05/16
735 1st to 2nd 72.8 days Fri 20/05/16 Mon 5/09/16
736 Setting out 7 days Tue 31/05/16 Thu 9/06/16
737 Blockwork 24 days Thu 2/06/16 Thu 7/07/16
738 FRC columns 15 days Wed 15/06/16 Thu 7/07/16
739 FRC beams 16 days Fri 17/06/16 Tue 12/07/16
740 Additional changes 2nd floor slab (tender to latest revi 5 days Fri 20/05/16 Fri 27/05/16
741 General changes as per marked up drawing 5 days Fri 20/05/16 Fri 27/05/16
742 Complete additional changes to block EF 2nd floor 0 days Fri 27/05/16 Fri 27/05/16
743 Additional canopy added 2nd floor 8 days Mon 25/07/16 Thu 4/08/16
744 Erect formwork canopy 5 days Mon 25/07/16 Mon 1/08/16
745 Reinforcing to canopy 3 days Fri 29/07/16 Wed 3/08/16
746 Concrete to canopy 1 day Wed 3/08/16 Thu 4/08/16
747 FRC 2nd floor slab inc MEPD conduits 24 days Fri 8/07/16 Fri 12/08/16
748 Completion of CD SF slab 0 days Fri 12/08/16 Fri 12/08/16
749 Deformwork 5 days Mon 29/08/16 Mon 5/09/16
750 2nd to Roof 53 days Tue 9/08/16 Tue 25/10/16
751 Setting out 7 days Tue 9/08/16 Fri 19/08/16
752 Blockwork 18 days Fri 12/08/16 Thu 8/09/16
753 FRC columns 12 days Tue 23/08/16 Thu 8/09/16
754 FRC beams 18 days Thu 25/08/16 Tue 20/09/16
755 FRC roof slab inc MEPD conduits 24 days Tue 30/08/16 Tue 4/10/16
756 Completion of CD Roof slab (Milestone Structure) 0 days Tue 4/10/16 Tue 4/10/16
757 Dismantle tower crane and remove from site 0 days Tue 4/10/16 Tue 4/10/16
758 Deformwork 5 days Tue 18/10/16 Tue 25/10/16
759 Parapet walls & 2nd floor pools Block AB 15 days Tue 27/09/16 Tue 18/10/16
760 External SAOTA changes and Additional works Block CD 108.71 days Fri 29/04/16 Thu 6/10/16
761 Receive instruction additional/changes bases, columns RC 0 days Fri 29/04/16 Fri 29/04/16
762 Excavate, drill dowel existing bases 7 days Mon 9/05/16 Wed 18/05/16
763 FRC new bases 8 days Tue 7/06/16 Fri 17/06/16
764 FRC new columns, walls etc 6 days Fri 17/06/16 Mon 27/06/16
765 Receive instruction Addition of R.C Wall at GL A/7' 0 days Tue 17/05/16 Tue 17/05/16
766 FRC bases RC walls 8 days Fri 17/06/16 Thu 30/06/16
767 FRC RC walls incl doweling to reinforcing 12 days Thu 30/06/16 Tue 19/07/16
768 Receive instruction additional/changes bases, columns RC 0 days Fri 29/04/16 Fri 29/04/16
769 Abortive works break stub columns 2 days Mon 2/05/16 Wed 4/05/16
770 FRC circular columns 5 days Wed 11/05/16 Wed 18/05/16
771 Receive instruction floating platform 0 days Tue 7/06/16 Tue 7/06/16
772 Backfill 5 days Tue 19/07/16 Tue 26/07/16
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
9
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
773 FRC floating platform works 30 days Wed 24/08/16 Thu 6/10/16
774 Complete columns & RC wall to canopy 30 days Wed 3/08/16 Thu 15/09/16
775 Complete external SAOTA 0 days Thu 15/09/16 Thu 15/09/16
776 Wet Trades 173.47 days Fri 6/05/16 Fri 10/02/17
777 Internally 172.47 days Fri 6/05/16 Thu 9/02/17
778 Basement 60 days Tue 4/10/16 Mon 23/01/17
779 Basement render works 40 days Tue 4/10/16 Mon 5/12/16
780 Render common stairs 20 days Mon 5/12/16 Mon 23/01/17
781 Ground Floor 81.67 days Fri 6/05/16 Mon 5/09/16
782 Partition block wall & risers 12 days Mon 20/06/16 Thu 7/07/16
783 M&E 1st & 2nd fix 18 days Tue 5/07/16 Mon 1/08/16
784 Preplaster Check 18 days Tue 5/07/16 Mon 1/08/16
785 SAOTA Changes Block CD Ground Floor Internal (Anne 43.89 days Fri 6/05/16 Mon 11/07/16
786 SAOTA layout/Elevation drawings received 06/05/16 0 days Fri 6/05/16 Fri 6/05/16
787 New details including structural received up to 12/05/1 0 days Thu 12/05/16 Thu 12/05/16
788 Setting out additional opeings, M & E service changes 3 days Thu 12/05/16 Tue 17/05/16
789 Breaking in additional openings, reducing columns, ext 8 days Mon 6/06/16 Thu 16/06/16
790 M & E chasings,rerouting 5 days Wed 15/06/16 Thu 23/06/16
791 FRC additional columns, jambs & cills incl dowling 8 days Wed 29/06/16 Mon 11/07/16
792 Receive instruction close newly broken openings 07/06 0 days Tue 7/06/16 Tue 7/06/16
793 FRC close openings incl dowel, hack 4 days Fri 17/06/16 Thu 23/06/16
794 Render wall & ceilings internal 24 days Mon 11/07/16 Tue 16/08/16
795 Completion of CD GF Floor wet trades 0 days Mon 5/09/16 Mon 5/09/16
796 1st Floor 49 days Tue 30/08/16 Mon 14/11/16
797 Partition block wall & risers 11 days Tue 30/08/16 Wed 14/09/16
798 M&E 1st & 2nd fix 15 days Tue 30/08/16 Tue 20/09/16
799 Preplaster Check 10 days Wed 7/09/16 Wed 21/09/16
800 Render wall & ceilings internal 25 days Fri 9/09/16 Mon 17/10/16
801 Completion of CD 1st Floor wet trades 0 days Mon 14/11/16 Mon 14/11/16
802 2nd Floor 49 days Tue 8/11/16 Thu 9/02/17
803 Partition block wall & risers 12 days Tue 8/11/16 Fri 25/11/16
804 M&E 1st & 2nd fix 12 days Wed 9/11/16 Mon 28/11/16
805 Preplaster Check 10 days Wed 16/11/16 Wed 30/11/16
806 Render wall & ceilings internal 25 days Fri 18/11/16 Fri 13/01/17
807 Completion of CD 2nd Floor wet trades 0 days Thu 9/02/17 Thu 9/02/17
808 Externally (Block CD) 67 days Tue 11/10/16 Fri 10/02/17
809 Plaster parapet wall on roof 10 days Thu 13/10/16 Thu 27/10/16
810 Plaster front façade 25 days Fri 21/10/16 Thu 1/12/16
811 Plaster side façade 20 days Wed 23/11/16 Wed 11/01/17
812 Plaster rear facades 25 days Thu 15/12/16 Fri 10/02/17
813 Builders work in connection with services on roof & Screed 20 days Tue 11/10/16 Mon 14/11/16
814 Complete Plaster CD External facades 0 days Fri 10/02/17 Fri 10/02/17
815 Finishes 181.8 days Wed 3/08/16 Thu 25/05/17
816 Internally 181.8 days Wed 3/08/16 Thu 25/05/17
817 Basement 80 days Mon 9/01/17 Thu 11/05/17
818 Finishes 30 days Mon 9/01/17 Fri 24/02/17
819 Make good to basement floor 20 days Tue 11/04/17 Thu 11/05/17
820 Ground Floor Block C (F105 & F106) 134.8 days Wed 3/08/16 Wed 15/03/17
821 Wet Works (ceiling & tiles) 22 days Wed 3/08/16 Mon 5/09/16
822 Suspended ceiling grid work 12 days Wed 3/08/16 Mon 22/08/16
823 Floor & wall tiles 14 days Tue 16/08/16 Mon 5/09/16
824 Finishes Internal 63 days Wed 31/08/16 Mon 5/12/16
825 Commencement of Block CD GF Finishes 0 days Wed 7/09/16 Wed 7/09/16
826 Paint 1st coat 5 days Wed 31/08/16 Wed 7/09/16
827 Aluminium openings 10 days Mon 5/09/16 Tue 20/09/16
828 Suspended Ceilings 5 days Fri 16/09/16 Fri 23/09/16
829 Shopfitting installation incl all 10 days Wed 21/09/16 Wed 5/10/16
830 Kitchen fit outs 9 days Mon 3/10/16 Fri 14/10/16
831 Granite tops 8 days Wed 12/10/16 Tue 25/10/16
832 Sanitary wares & accessories 7 days Thu 20/10/16 Thu 3/11/16
833 Electrical accessories & light fittings 8 days Fri 28/10/16 Mon 14/11/16
834 TEL/DATA/MATV installation 4 days Wed 9/11/16 Wed 16/11/16
835 Shower screens 5 days Tue 15/11/16 Tue 22/11/16
836 Snag/De-snag 5 days Tue 22/11/16 Tue 29/11/16
837 Paint final coat 5 days Mon 28/11/16 Mon 5/12/16
838 Complete Block CD GF internal 0 days Mon 5/12/16 Mon 5/12/16
839 Terraces Ground Floor 27 days Tue 31/01/17 Wed 15/03/17
840 Paint 1st & 2nd coat 5 days Tue 31/01/17 Thu 9/02/17
841 Waterproofing to terraces 7 days Mon 6/02/17 Thu 16/02/17
842 Terrace tiling 8 days Tue 14/02/17 Mon 27/02/17
843 Timber screens & cladding 7 days Wed 22/02/17 Fri 3/03/17
844 Balustrades 6 days Tue 28/02/17 Wed 8/03/17
845 Paint final coat 4 days Fri 3/03/17 Thu 9/03/17
846 Snag/De-snag 5 days Wed 8/03/17 Wed 15/03/17
847 Complete Block CD Terraces GF 0 days Wed 15/03/17 Wed 15/03/17
848 Ground Floor Block D 130.8 days Mon 22/08/16 Wed 29/03/17
849 Wet Works (ceiling & tiles) 23 days Mon 22/08/16 Fri 23/09/16
850 Suspended ceiling grid work 12 days Mon 22/08/16 Wed 7/09/16
851 Floor & wall tiles 14 days Fri 2/09/16 Fri 23/09/16
852 Finishes Internal 63 days Wed 21/09/16 Fri 13/01/17
853 Commencement of Block D GF Finishes 0 days Wed 28/09/16 Wed 28/09/16
854 Paint 1st coat 5 days Wed 21/09/16 Wed 28/09/16
855 Aluminium openings 10 days Mon 26/09/16 Mon 10/10/16
856 Suspended Ceilings 5 days Thu 6/10/16 Thu 13/10/16
857 Shopfitting installation incl all 10 days Tue 11/10/16 Wed 26/10/16
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
10
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
858 Kitchen fit outs 9 days Fri 21/10/16 Tue 8/11/16
859 Granite tops 8 days Fri 4/11/16 Thu 17/11/16
860 Sanitary wares & accessories 7 days Tue 15/11/16 Thu 24/11/16
861 Electrical accessories & light fittings 8 days Tue 22/11/16 Fri 2/12/16
862 TEL/DATA/MATV installation 4 days Wed 30/11/16 Wed 7/12/16
863 Shower screens 5 days Mon 5/12/16 Tue 13/12/16
864 Snag/De-snag 5 days Tue 13/12/16 Mon 9/01/17
865 Paint final coat 5 days Fri 6/01/17 Fri 13/01/17
866 Complete Block D GF internal 0 days Fri 13/01/17 Fri 13/01/17
867 Terraces Ground Floor 27 days Wed 15/02/17 Wed 29/03/17
868 Paint 1st & 2nd coat 5 days Wed 15/02/17 Thu 23/02/17
869 Waterproofing to terraces 7 days Mon 20/02/17 Wed 1/03/17
870 Terrace tiling 8 days Mon 27/02/17 Thu 9/03/17
871 Timber screens & cladding 7 days Mon 6/03/17 Wed 15/03/17
872 Balustrades 6 days Fri 10/03/17 Mon 20/03/17
873 Paint final coat 4 days Wed 15/03/17 Wed 22/03/17
874 Snag/De-snag 5 days Mon 20/03/17 Wed 29/03/17
875 Complete Block D Terraces GF 0 days Wed 29/03/17 Wed 29/03/17
876 First Floor C 98 days Wed 5/10/16 Fri 24/03/17
877 Wet Works (ceiling & tiles) 24 days Wed 5/10/16 Mon 14/11/16
878 Suspended ceiling grid work 12 days Wed 5/10/16 Fri 21/10/16
879 Floor & wall tiles 14 days Wed 19/10/16 Mon 14/11/16
880 Finishes Internal 63 days Wed 9/11/16 Mon 6/03/17
881 Commencement of Block CD FF Finishes 0 days Thu 17/11/16 Thu 17/11/16
882 Paint 1st coat 5 days Wed 9/11/16 Thu 17/11/16
883 Aluminium openings 10 days Tue 15/11/16 Tue 29/11/16
884 Suspended Ceilings 5 days Fri 25/11/16 Fri 2/12/16
885 Shopfitting installation incl all 10 days Wed 30/11/16 Thu 15/12/16
886 Kitchen fit outs 9 days Mon 12/12/16 Fri 13/01/17
887 Granite tops 8 days Wed 11/01/17 Mon 23/01/17
888 Sanitary wares & accessories 7 days Thu 19/01/17 Mon 30/01/17
889 Electrical accessories & light fittings 8 days Thu 26/01/17 Thu 9/02/17
890 TEL/DATA/MATV installation 4 days Tue 7/02/17 Tue 14/02/17
891 Shower screens 5 days Fri 10/02/17 Tue 21/02/17
892 Snag/De-snag 5 days Tue 21/02/17 Tue 28/02/17
893 Paint final coat 5 days Mon 27/02/17 Mon 6/03/17
894 Complete Block CD FF internal 0 days Mon 6/03/17 Mon 6/03/17
895 Terraces First Floor 27 days Fri 10/02/17 Fri 24/03/17
896 Paint 1st & 2nd coat 5 days Fri 10/02/17 Tue 21/02/17
897 Waterproofing to terraces 7 days Wed 15/02/17 Mon 27/02/17
898 Terrace tiling 8 days Thu 23/02/17 Tue 7/03/17
899 Timber screens & cladding 7 days Thu 2/03/17 Mon 13/03/17
900 Balustrades 6 days Wed 8/03/17 Thu 16/03/17
901 Paint final coat 4 days Mon 13/03/17 Fri 17/03/17
902 Snag/De-snag 5 days Thu 16/03/17 Fri 24/03/17
903 Complete Block CD Terraces FF 0 days Fri 24/03/17 Fri 24/03/17
904 First Floor D 90 days Thu 27/10/16 Thu 6/04/17
905 Wet Works (ceiling & tiles) 22 days Thu 27/10/16 Fri 2/12/16
906 Suspended ceiling grid work 10 days Thu 27/10/16 Wed 16/11/16
907 Floor & wall tiles 14 days Mon 14/11/16 Fri 2/12/16
908 Finishes Internal 63 days Wed 30/11/16 Tue 28/03/17
909 Commencement of Block D FF Finishes 0 days Wed 7/12/16 Wed 7/12/16
910 Paint 1st coat 5 days Wed 30/11/16 Wed 7/12/16
911 Aluminium openings 10 days Mon 5/12/16 Mon 9/01/17
912 Suspended Ceilings 5 days Thu 5/01/17 Thu 12/01/17
913 Shopfitting installation incl all 10 days Tue 10/01/17 Tue 24/01/17
914 Kitchen fit outs 9 days Fri 20/01/17 Mon 6/02/17
915 Granite tops 8 days Tue 31/01/17 Wed 15/02/17
916 Sanitary wares & accessories 7 days Fri 10/02/17 Thu 23/02/17
917 Electrical accessories & light fittings 8 days Tue 21/02/17 Fri 3/03/17
918 TEL/DATA/MATV installation 4 days Wed 1/03/17 Tue 7/03/17
919 Shower screens 5 days Mon 6/03/17 Mon 13/03/17
920 Snag/De-snag 5 days Mon 13/03/17 Mon 20/03/17
921 Paint final coat 5 days Fri 17/03/17 Tue 28/03/17
922 Complete Block D FF internal 0 days Tue 28/03/17 Tue 28/03/17
923 Terraces First Floor 27 days Fri 24/02/17 Thu 6/04/17
924 Paint 1st & 2nd coat 5 days Fri 24/02/17 Fri 3/03/17
925 Waterproofing to terraces 7 days Tue 28/02/17 Thu 9/03/17
926 Terrace tiling 8 days Tue 7/03/17 Fri 17/03/17
927 Timber screens & cladding 7 days Tue 14/03/17 Fri 24/03/17
928 Balustrades 6 days Mon 20/03/17 Thu 30/03/17
929 Paint final coat 4 days Fri 24/03/17 Fri 31/03/17
930 Snag/De-snag 5 days Thu 30/03/17 Thu 6/04/17
931 Complete Block D Terraces FF 0 days Thu 6/04/17 Thu 6/04/17
932 Second Floor C 85 days Thu 15/12/16 Mon 15/05/17
933 Wet Works (ceiling & tiles) 24 days Thu 15/12/16 Thu 9/02/17
934 Suspended ceiling grid work 12 days Thu 15/12/16 Fri 20/01/17
935 Floor & wall tiles 14 days Wed 18/01/17 Thu 9/02/17
936 Finishes Internal 63 days Tue 7/02/17 Mon 15/05/17
937 Commencement of Block C SF Finishes 0 days Wed 15/02/17 Wed 15/02/17
938 Paint 1st coat 5 days Tue 7/02/17 Wed 15/02/17
939 Aluminium openings 10 days Fri 10/02/17 Tue 28/02/17
940 Suspended Ceilings 5 days Fri 24/02/17 Fri 3/03/17
941 Shopfitting installation incl all 10 days Wed 1/03/17 Wed 15/03/17
942 Kitchen fit outs 9 days Mon 13/03/17 Tue 28/03/17
943 Granite tops 8 days Thu 23/03/17 Wed 5/04/17
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
11
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
944 Sanitary wares & accessories 7 days Mon 3/04/17 Wed 12/04/17
945 Electrical accessories & light fittings 8 days Mon 10/04/17 Thu 20/04/17
946 TEL/DATA/MATV installation 4 days Tue 18/04/17 Mon 24/04/17
947 Shower screens 5 days Fri 21/04/17 Fri 28/04/17
948 Snag/De-snag 5 days Fri 28/04/17 Tue 9/05/17
949 Paint final coat 5 days Mon 8/05/17 Mon 15/05/17
950 Complete Block C SF internal 0 days Mon 15/05/17 Mon 15/05/17
951 Terraces Second Floor 59 days Thu 2/02/17 Thu 4/05/17
952 Paint 1st & 2nd coat 10 days Thu 2/02/17 Tue 21/02/17
953 Waterproofing to terraces 15 days Wed 15/02/17 Thu 9/03/17
954 Terrace tiling & Pool tiling 15 days Tue 7/03/17 Thu 30/03/17
955 Timber screens & cladding 10 days Fri 24/03/17 Mon 10/04/17
956 Balustrades 10 days Wed 5/04/17 Wed 19/04/17
957 Paint final coat 7 days Fri 14/04/17 Tue 25/04/17
958 Snag/De-snag 7 days Mon 24/04/17 Thu 4/05/17
959 Complete Block C Terraces SF 0 days Thu 4/05/17 Thu 4/05/17
960 Second Floor D 81 days Fri 20/01/17 Thu 25/05/17
961 Wet Works (ceiling & tiles) 22 days Fri 20/01/17 Mon 27/02/17
962 Suspended ceiling grid work 12 days Fri 20/01/17 Thu 9/02/17
963 Floor & wall tiles 14 days Thu 2/02/17 Mon 27/02/17
964 Finishes Internal 62 days Wed 22/02/17 Thu 25/05/17
965 Commencement of Block D SF Finishes 0 days Wed 1/03/17 Wed 1/03/17
966 Paint 1st coat 5 days Wed 22/02/17 Wed 1/03/17
967 Aluminium openings 10 days Fri 24/02/17 Fri 10/03/17
968 Suspended Ceilings 5 days Wed 8/03/17 Wed 15/03/17
969 Shopfitting installation incl all 10 days Mon 13/03/17 Wed 29/03/17
970 Kitchen fit outs 9 days Fri 24/03/17 Fri 7/04/17
971 Granite tops 8 days Wed 5/04/17 Mon 17/04/17
972 Sanitary wares & accessories 7 days Thu 13/04/17 Mon 24/04/17
973 Electrical accessories & light fittings 8 days Thu 20/04/17 Wed 3/05/17
974 TEL/DATA/MATV installation 4 days Fri 28/04/17 Mon 8/05/17
975 Shower screens 5 days Fri 5/05/17 Fri 12/05/17
976 Snag/De-snag 5 days Fri 12/05/17 Fri 19/05/17
977 Paint final coat 5 days Thu 18/05/17 Thu 25/05/17
978 Complete Block D SF internal 0 days Thu 25/05/17 Thu 25/05/17
979 Terraces Second Floor 59 days Tue 21/02/17 Fri 19/05/17
980 Paint 1st & 2nd coat 10 days Tue 21/02/17 Tue 7/03/17
981 Waterproofing to terraces 15 days Thu 2/03/17 Fri 24/03/17
982 Terrace tiling & Pool tiling 15 days Wed 22/03/17 Thu 13/04/17
983 Timber screens & cladding 10 days Mon 10/04/17 Mon 24/04/17
984 Balustrades 10 days Wed 19/04/17 Thu 4/05/17
985 Paint final coat 7 days Fri 28/04/17 Thu 11/05/17
986 Snag/De-snag 7 days Wed 10/05/17 Fri 19/05/17
987 Complete Block D Terraces SF 0 days Fri 19/05/17 Fri 19/05/17
988 Externally & Common areas C 70 days Mon 14/11/16 Fri 17/03/17
989 Commencement of Block C Externally & Common areas 0 days Mon 14/11/16 Mon 14/11/16
990 Waterproofing on roof 8 days Mon 14/11/16 Thu 24/11/16
991 M & E Equipments on roof 12 days Tue 22/11/16 Thu 8/12/16
992 Paint 1st & 2nd coat 6 days Wed 8/02/17 Mon 20/02/17
993 Lifts installation including finishes 15 days Mon 21/11/16 Mon 12/12/16
994 Stone cladding 35 days Wed 18/01/17 Tue 14/03/17
995 Composite timber cladding, pergolas & gates 15 days Wed 15/02/17 Thu 9/03/17
996 Balustrades 10 days Thu 9/02/17 Mon 27/02/17
997 Tiling to main staircases and common areas 10 days Thu 9/02/17 Mon 27/02/17
998 Paint final coat 7 days Mon 27/02/17 Wed 8/03/17
999 Snag/De-snag 7 days Wed 8/03/17 Fri 17/03/17
1000 Complete Block C External Finishes & Common areas 0 days Fri 17/03/17 Fri 17/03/17
1001 Externally & Common areas D 84 days Tue 6/12/16 Wed 3/05/17
1002 Commencement of Block D Externally & Common areas 0 days Tue 6/12/16 Tue 6/12/16
1003 Waterproofing on roof 8 days Tue 6/12/16 Fri 6/01/17
1004 M & E Equipments on roof 12 days Thu 15/12/16 Fri 20/01/17
1005 Paint 1st & 2nd coat 6 days Mon 20/02/17 Tue 28/02/17
1006 Lifts installation including finishes 15 days Mon 12/12/16 Mon 23/01/17
1007 Stone cladding 35 days Fri 10/03/17 Wed 3/05/17
1008 Composite timber cladding, pergolas & gates 15 days Fri 24/02/17 Fri 17/03/17
1009 Balustrades 10 days Tue 21/02/17 Tue 7/03/17
1010 Tiling to main staircases and common areas 10 days Mon 27/02/17 Mon 13/03/17
1011 Paint final coat 7 days Thu 9/03/17 Mon 20/03/17
1012 Snag/De-snag 7 days Mon 20/03/17 Fri 31/03/17
1013 Complete Block D External Finishes & Common areas 0 days Wed 3/05/17 Wed 3/05/17
1014 Block GH 310 days Mon 25/01/16 Fri 26/05/17
1015 Structure 185 days Mon 25/01/16 Thu 27/10/16
1016 Ground Floor Slab 51 days Mon 25/01/16 Thu 14/04/16
1017 FRC beams 18 days Mon 25/01/16 Wed 24/02/16
1018 FRC basement slab(GF) inc MEPD conduits 24 days Wed 10/02/16 Fri 18/03/16
1019 Completion of basement slab GH (GF) 0 days Fri 18/03/16 Fri 18/03/16
1020 Deformwork 5 days Wed 6/04/16 Thu 14/04/16
1021 Superstructure 182.55 days Wed 27/01/16 Thu 27/10/16
1022 Ground to 1st 176.04 days Wed 27/01/16 Tue 18/10/16
1023 Setting out 10 days Mon 7/03/16 Tue 22/03/16
1024 Blockwork 24 days Wed 9/03/16 Thu 14/04/16
1025 Commencement of GH Blockwork 0 days Wed 9/03/16 Wed 9/03/16
1026 Erect tower crane 0 days Tue 15/03/16 Tue 15/03/16
1027 FRC columns 14 days Wed 23/03/16 Wed 13/04/16
1028 FRC beams 18 days Fri 25/03/16 Thu 21/04/16
1029 FRC 1st Floor slab inc MEPD conduits 24 days Wed 30/03/16 Wed 4/05/16
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
12
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
1030 Completion of GH 1st floor slab 0 days Wed 4/05/16 Wed 4/05/16
1031 Deformwork 5 days Wed 18/05/16 Thu 26/05/16
1032 SOATA RHS Changes Block GH 176.04 days Wed 27/01/16 Tue 18/10/16
1033 Receive dwgs and reply to EFI 0 days Sat 16/04/16 Sat 16/04/16
1034 Add adidional RHS 24/03/16 & 11/04/16 0 days Thu 24/03/16 Thu 24/03/16
1035 Receive instructions abortive bases/columns 0 days Fri 29/04/16 Fri 29/04/16
1036 Procure and manufacture additional RHS 35 days Wed 27/01/16 Thu 24/03/16
1037 Receive instruction modifications to RHS GL L 0 days Thu 9/06/16 Thu 9/06/16
1038 Modifications to RHS 10 days Fri 10/06/16 Fri 24/06/16
1039 FWK, Reinf, Cast new bases, columns, walls GL L & A 14 days Wed 22/06/16 Tue 12/07/16
1040 Receive new instruction RC Wall & dowel reinforcing 0 days Tue 17/05/16 Tue 17/05/16
1041 FRC RC wall base 3 days Wed 18/05/16 Mon 23/05/16
1042 FRC RC wall & dowel reinforcing & waterproof 7 days Mon 23/05/16 Wed 1/06/16
1043 Backfill to U/S terraces 4 days Thu 18/08/16 Wed 24/08/16
1044 FRC terraces GF 7 days Thu 1/09/16 Mon 12/09/16
1045 Installation of RHS to 1st floor 4 days Mon 12/09/16 Fri 16/09/16
1046 FRC terraces 1st floor 8 days Fri 16/09/16 Wed 28/09/16
1047 Complete 1st floor terraces 0 days Wed 28/09/16 Wed 28/09/16
1048 Deformwork terraces 1st floor 3 days Thu 13/10/16 Tue 18/10/16
1049 1st to 2nd 76 days Mon 23/05/16 Fri 9/09/16
1050 Setting out 5 days Mon 23/05/16 Mon 30/05/16
1051 Blockwork 24 days Wed 8/06/16 Wed 13/07/16
1052 FRC columns 14 days Wed 22/06/16 Wed 13/07/16
1053 FRC beams 18 days Thu 23/06/16 Thu 21/07/16
1054 Additional changes 2nd floor slab (tender to latest revi 43.43 days Tue 7/06/16 Wed 10/08/16
1055 General changes as per marked up drawing 5 days Tue 7/06/16 Tue 14/06/16
1056 Complete additional changes to block EF 2nd floor 0 days Tue 14/06/16 Tue 14/06/16
1057 Additional canopy added 2nd floor 8 days Thu 28/07/16 Wed 10/08/16
1058 Erect formwork canopy 5 days Thu 28/07/16 Thu 4/08/16
1059 Reinforcing to canopy 3 days Wed 3/08/16 Tue 9/08/16
1060 Concrete to canopy 1 day Tue 9/08/16 Wed 10/08/16
1061 FRC 2nd floor slab inc MEPD conduits 24 days Thu 14/07/16 Fri 19/08/16
1062 Completion of GH SF slab 0 days Fri 19/08/16 Fri 19/08/16
1063 Deformwork 5 days Fri 2/09/16 Fri 9/09/16
1064 2nd to Roof 49 days Wed 17/08/16 Thu 27/10/16
1065 Setting out 5 days Wed 17/08/16 Wed 24/08/16
1066 Blockwork 18 days Thu 18/08/16 Tue 13/09/16
1067 FRC columns 12 days Fri 26/08/16 Tue 13/09/16
1068 FRC beams 16 days Tue 30/08/16 Thu 22/09/16
1069 FRC roof slab inc MEPD conduits 24 days Wed 31/08/16 Wed 5/10/16
1070 Completion of GH Roof slab 0 days Wed 5/10/16 Wed 5/10/16
1071 Dismantle tower crane and remove from site 0 days Wed 5/10/16 Wed 5/10/16
1072 Deformwork 5 days Wed 19/10/16 Thu 27/10/16
1073 Parapet walls & 2nd floor pools Block GH 15 days Wed 28/09/16 Wed 19/10/16
1074 External SAOTA changes and Additional works Block GH 116.71 days Fri 29/04/16 Wed 19/10/16
1075 Receive instruction additional/changes bases, columns RC 0 days Fri 29/04/16 Fri 29/04/16
1076 Excavate, drill dowel existing bases 7 days Mon 9/05/16 Wed 18/05/16
1077 FRC new bases 8 days Fri 17/06/16 Wed 29/06/16
1078 FRC new columns, walls etc 6 days Wed 29/06/16 Thu 7/07/16
1079 Receive instruction Addition of R.C Wall at GL A/7' 0 days Tue 17/05/16 Tue 17/05/16
1080 FRC bases RC walls 8 days Thu 30/06/16 Tue 12/07/16
1081 FRC RC walls incl doweling to reinforcing 12 days Tue 12/07/16 Mon 1/08/16
1082 Receive instruction additional/changes bases, columns RC 0 days Fri 29/04/16 Fri 29/04/16
1083 Abortive works break stub columns 2 days Mon 2/05/16 Wed 4/05/16
1084 FRC circular columns 5 days Wed 18/05/16 Wed 25/05/16
1085 Receive instruction floating platform 0 days Tue 7/06/16 Tue 7/06/16
1086 Backfill 5 days Mon 1/08/16 Mon 8/08/16
1087 FRC floating platform works 30 days Mon 5/09/16 Wed 19/10/16
1088 Complete columns & RC wall to canopy 30 days Mon 15/08/16 Tue 27/09/16
1089 Complete external SAOTA 0 days Tue 27/09/16 Tue 27/09/16
1090 Wet Trades 176.67 days Fri 6/05/16 Thu 16/02/17
1091 Internally 173.67 days Fri 6/05/16 Mon 13/02/17
1092 Basement 60 days Wed 5/10/16 Tue 24/01/17
1093 Basement render works 40 days Wed 5/10/16 Wed 7/12/16
1094 Render common stairs 20 days Wed 7/12/16 Tue 24/01/17
1095 Ground Floor 86.67 days Fri 6/05/16 Mon 12/09/16
1096 Partition block wall & risers 12 days Fri 8/07/16 Wed 27/07/16
1097 M&E 1st & 2nd fix 20 days Mon 11/07/16 Wed 10/08/16
1098 Preplaster Check 20 days Mon 11/07/16 Wed 10/08/16
1099 SAOTA Changes Block GH Ground Floor Internal (Anne 45.89 days Fri 6/05/16 Wed 13/07/16
1100 SAOTA layout/Elevation drawings received 06/05/16 0 days Fri 6/05/16 Fri 6/05/16
1101 New details including structural received up to 12/05/1 0 days Thu 12/05/16 Thu 12/05/16
1102 Setting out additional opeings, M & E service changes 3 days Thu 26/05/16 Tue 31/05/16
1103 Breaking in additional openings, reducing columns, ext 8 days Fri 10/06/16 Thu 23/06/16
1104 M & E chasings,rerouting 5 days Wed 22/06/16 Wed 29/06/16
1105 FRC additional columns, jambs & cills incl dowling 8 days Fri 1/07/16 Wed 13/07/16
1106 Render wall & ceilings internal 24 days Tue 19/07/16 Tue 23/08/16
1107 Completion of GH GF Floor wet trades 0 days Mon 12/09/16 Mon 12/09/16
1108 1st Floor 51 days Tue 6/09/16 Wed 23/11/16
1109 Partition block wall & risers 10 days Wed 7/09/16 Thu 22/09/16
1110 M&E 1st & 2nd fix 15 days Tue 6/09/16 Wed 28/09/16
1111 Preplaster Check 10 days Fri 16/09/16 Fri 30/09/16
1112 Render wall & ceilings internal 25 days Tue 20/09/16 Wed 26/10/16
1113 Completion of GH 1st Floor wet trades 0 days Wed 23/11/16 Wed 23/11/16
1114 2nd Floor 49 days Wed 9/11/16 Mon 13/02/17
1115 Partition block wall & risers 12 days Wed 9/11/16 Mon 28/11/16
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
13
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
1116 M&E 1st & 2nd fix 12 days Thu 10/11/16 Tue 29/11/16
1117 Preplaster Check 10 days Thu 17/11/16 Thu 1/12/16
1118 Render wall & ceilings internal 25 days Mon 21/11/16 Mon 16/01/17
1119 Completion of GH 2nd Floor wet trades 0 days Mon 13/02/17 Mon 13/02/17
1120 Externally (Block GH) 69 days Wed 12/10/16 Thu 16/02/17
1121 Plaster parapet wall on roof 10 days Tue 18/10/16 Fri 4/11/16
1122 Plaster front façade 25 days Thu 27/10/16 Wed 7/12/16
1123 Plaster side façade 20 days Mon 28/11/16 Mon 16/01/17
1124 Plaster rear facades 25 days Mon 9/01/17 Thu 16/02/17
1125 Builders work in connection with services on roof & Screed 20 days Wed 12/10/16 Tue 15/11/16
1126 Complete Plaster GH External facades 0 days Thu 16/02/17 Thu 16/02/17
1127 Finishes 178 days Thu 11/08/16 Fri 26/05/17
1128 Internally 178 days Thu 11/08/16 Fri 26/05/17
1129 Basement 80 days Tue 10/01/17 Fri 12/05/17
1130 Finishes 30 days Tue 10/01/17 Mon 27/02/17
1131 Make good to basement floor 20 days Wed 12/04/17 Fri 12/05/17
1132 Ground Floor Block H 131 days Thu 11/08/16 Fri 17/03/17
1133 Wet Works (ceiling & tiles) 22 days Thu 11/08/16 Mon 12/09/16
1134 Suspended ceiling grid work 12 days Thu 11/08/16 Mon 29/08/16
1135 Floor & wall tiles 14 days Tue 23/08/16 Mon 12/09/16
1136 Finishes Internal 63 days Thu 8/09/16 Wed 14/12/16
1137 Commencement of Block H GF Finishes 0 days Fri 16/09/16 Fri 16/09/16
1138 Paint 1st coat 5 days Thu 8/09/16 Fri 16/09/16
1139 Aluminium openings 10 days Tue 13/09/16 Wed 28/09/16
1140 Suspended Ceilings final 5 days Mon 26/09/16 Mon 3/10/16
1141 Shopfitting installation incl all 10 days Thu 29/09/16 Thu 13/10/16
1142 Kitchen fit outs 9 days Tue 11/10/16 Tue 25/10/16
1143 Granite tops 8 days Thu 20/10/16 Fri 4/11/16
1144 Sanitary wares & accessories 7 days Mon 31/10/16 Mon 14/11/16
1145 Electrical accessories & light fittings 8 days Wed 9/11/16 Tue 22/11/16
1146 TEL/DATA/MATV installation 4 days Fri 18/11/16 Thu 24/11/16
1147 Shower screens 5 days Wed 23/11/16 Wed 30/11/16
1148 Snag/De-snag 5 days Wed 30/11/16 Thu 8/12/16
1149 Paint final coat 5 days Wed 7/12/16 Wed 14/12/16
1150 Complete Block H GF internal 0 days Wed 14/12/16 Wed 14/12/16
1151 Terraces Ground Floor 27 days Mon 6/02/17 Fri 17/03/17
1152 Paint 1st & 2nd coat 5 days Mon 6/02/17 Mon 13/02/17
1153 Waterproofing to terraces 7 days Wed 8/02/17 Mon 20/02/17
1154 Terrace tiling 8 days Wed 15/02/17 Tue 28/02/17
1155 Timber screens & cladding 7 days Thu 23/02/17 Mon 6/03/17
1156 Balustrades 6 days Wed 1/03/17 Thu 9/03/17
1157 Paint final coat 4 days Mon 6/03/17 Fri 10/03/17
1158 Snag/De-snag 5 days Thu 9/03/17 Fri 17/03/17
1159 Complete Block H Terraces GF 0 days Fri 17/03/17 Fri 17/03/17
1160 Ground Floor Block G 127 days Mon 29/08/16 Thu 30/03/17
1161 Wet Works (ceiling & tiles) 24 days Mon 29/08/16 Mon 3/10/16
1162 Suspended ceiling grid work 12 days Mon 29/08/16 Wed 14/09/16
1163 Floor & wall tiles 14 days Mon 12/09/16 Mon 3/10/16
1164 Finishes Internal 63 days Thu 29/09/16 Mon 23/01/17
1165 Commencement of Block G GF Finishes 0 days Thu 6/10/16 Thu 6/10/16
1166 Paint 1st coat 5 days Thu 29/09/16 Thu 6/10/16
1167 Aluminium openings 10 days Tue 4/10/16 Tue 18/10/16
1168 Suspended Ceilings final 5 days Fri 14/10/16 Fri 21/10/16
1169 Shopfitting installation incl all 10 days Wed 19/10/16 Mon 7/11/16
1170 Kitchen fit outs 9 days Thu 3/11/16 Thu 17/11/16
1171 Granite tops 8 days Tue 15/11/16 Fri 25/11/16
1172 Sanitary wares & accessories 7 days Wed 23/11/16 Fri 2/12/16
1173 Electrical accessories & light fittings 8 days Wed 30/11/16 Tue 13/12/16
1174 TEL/DATA/MATV installation 4 days Fri 9/12/16 Thu 15/12/16
1175 Shower screens 5 days Wed 14/12/16 Tue 10/01/17
1176 Snag/De-snag 5 days Tue 10/01/17 Tue 17/01/17
1177 Paint final coat 5 days Mon 16/01/17 Mon 23/01/17
1178 Complete Block G GF internal 0 days Mon 23/01/17 Mon 23/01/17
1179 Terraces Ground Floor 27 days Thu 16/02/17 Thu 30/03/17
1180 Paint 1st & 2nd coat 5 days Thu 16/02/17 Fri 24/02/17
1181 Waterproofing to terraces 7 days Tue 21/02/17 Thu 2/03/17
1182 Terrace tiling 8 days Tue 28/02/17 Fri 10/03/17
1183 Timber screens & cladding 7 days Tue 7/03/17 Fri 17/03/17
1184 Balustrades 6 days Mon 13/03/17 Thu 23/03/17
1185 Paint final coat 4 days Fri 17/03/17 Fri 24/03/17
1186 Snag/De-snag 5 days Thu 23/03/17 Thu 30/03/17
1187 Complete Block G Terraces GF 0 days Thu 30/03/17 Thu 30/03/17
1188 First Floor Block H 94 days Fri 14/10/16 Thu 30/03/17
1189 Wet Works (ceiling & tiles) 24 days Fri 14/10/16 Wed 23/11/16
1190 Suspended ceiling grid work 12 days Fri 14/10/16 Fri 4/11/16
1191 Floor & wall tiles 14 days Mon 31/10/16 Wed 23/11/16
1192 Finishes Internal 63 days Mon 21/11/16 Wed 15/03/17
1193 Commencement of Block H FF Finishes 0 days Mon 28/11/16 Mon 28/11/16
1194 Paint 1st coat 5 days Mon 21/11/16 Mon 28/11/16
1195 Aluminium openings 10 days Thu 24/11/16 Fri 9/12/16
1196 Suspended Ceilings 5 days Wed 7/12/16 Wed 14/12/16
1197 Shopfitting installation incl all 10 days Mon 12/12/16 Fri 13/01/17
1198 Kitchen fit outs 9 days Wed 11/01/17 Tue 24/01/17
1199 Granite tops 8 days Fri 20/01/17 Thu 2/02/17
1200 Sanitary wares & accessories 7 days Mon 30/01/17 Mon 13/02/17
1201 Electrical accessories & light fittings 8 days Thu 9/02/17 Wed 22/02/17
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
14
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
1202 TEL/DATA/MATV installation 4 days Mon 20/02/17 Fri 24/02/17
1203 Shower screens 5 days Thu 23/02/17 Thu 2/03/17
1204 Snag/De-snag 5 days Thu 2/03/17 Thu 9/03/17
1205 Paint final coat 5 days Wed 8/03/17 Wed 15/03/17
1206 Complete Block H FF internal 0 days Wed 15/03/17 Wed 15/03/17
1207 Terraces First Floor 27 days Thu 16/02/17 Thu 30/03/17
1208 Paint 1st & 2nd coat 5 days Thu 16/02/17 Fri 24/02/17
1209 Waterproofing to terraces 7 days Tue 21/02/17 Thu 2/03/17
1210 Terrace tiling 8 days Tue 28/02/17 Fri 10/03/17
1211 Timber screens & cladding 7 days Tue 7/03/17 Fri 17/03/17
1212 Balustrades 6 days Mon 13/03/17 Thu 23/03/17
1213 Paint final coat 4 days Fri 17/03/17 Fri 24/03/17
1214 Snag/De-snag 5 days Thu 23/03/17 Thu 30/03/17
1215 Complete Block H Terraces FF 0 days Thu 30/03/17 Thu 30/03/17
1216 First Floor Block G 89 days Fri 4/11/16 Mon 10/04/17
1217 Wet Works (ceiling & tiles) 24 days Fri 4/11/16 Mon 12/12/16
1218 Suspended ceiling grid work 12 days Fri 4/11/16 Wed 23/11/16
1219 Floor & wall tiles 14 days Mon 21/11/16 Mon 12/12/16
1220 Finishes Internal 63 days Thu 8/12/16 Tue 4/04/17
1221 Commencement of Block G FF Finishes 0 days Thu 15/12/16 Thu 15/12/16
1222 Paint 1st coat 5 days Thu 8/12/16 Thu 15/12/16
1223 Aluminium openings 10 days Tue 13/12/16 Mon 16/01/17
1224 Suspended Ceilings 5 days Thu 12/01/17 Thu 19/01/17
1225 Shopfitting installation incl all 10 days Tue 17/01/17 Tue 31/01/17
1226 Kitchen fit outs 9 days Fri 27/01/17 Tue 14/02/17
1227 Granite tops 8 days Fri 10/02/17 Thu 23/02/17
1228 Sanitary wares & accessories 7 days Tue 21/02/17 Thu 2/03/17
1229 Electrical accessories & light fittings 8 days Tue 28/02/17 Fri 10/03/17
1230 TEL/DATA/MATV installation 4 days Wed 8/03/17 Tue 14/03/17
1231 Shower screens 5 days Mon 13/03/17 Wed 22/03/17
1232 Snag/De-snag 5 days Wed 22/03/17 Wed 29/03/17
1233 Paint final coat 5 days Tue 28/03/17 Tue 4/04/17
1234 Complete Block G FF internal 0 days Tue 4/04/17 Tue 4/04/17
1235 Terraces First Floor 27 days Tue 28/02/17 Mon 10/04/17
1236 Paint 1st & 2nd coat 5 days Tue 28/02/17 Tue 7/03/17
1237 Waterproofing to terraces 7 days Thu 2/03/17 Mon 13/03/17
1238 Terrace tiling 8 days Thu 9/03/17 Thu 23/03/17
1239 Timber screens & cladding 7 days Fri 17/03/17 Wed 29/03/17
1240 Balustrades 6 days Fri 24/03/17 Mon 3/04/17
1241 Paint final coat 4 days Wed 29/03/17 Tue 4/04/17
1242 Snag/De-snag 5 days Mon 3/04/17 Mon 10/04/17
1243 Complete Block G Terraces FF 0 days Mon 10/04/17 Mon 10/04/17
1244 Second Floor Block H 85 days Thu 5/01/17 Tue 16/05/17
1245 Wet Works (ceiling & tiles) 24 days Thu 5/01/17 Mon 13/02/17
1246 Suspended ceiling grid work 12 days Thu 5/01/17 Mon 23/01/17
1247 Floor & wall tiles 14 days Thu 19/01/17 Mon 13/02/17
1248 Finishes Internal 63 days Thu 9/02/17 Tue 16/05/17
1249 Commencement of Block H SF Finishes 0 days Thu 16/02/17 Thu 16/02/17
1250 Paint 1st coat 5 days Thu 9/02/17 Thu 16/02/17
1251 Aluminium openings 10 days Tue 14/02/17 Wed 1/03/17
1252 Suspended Ceilings final 5 days Mon 27/02/17 Mon 6/03/17
1253 Shopfitting installation incl all 10 days Thu 2/03/17 Fri 17/03/17
1254 Kitchen fit outs 9 days Tue 14/03/17 Wed 29/03/17
1255 Granite tops 8 days Mon 27/03/17 Thu 6/04/17
1256 Sanitary wares & accessories 7 days Tue 4/04/17 Thu 13/04/17
1257 Electrical accessories & light fittings 8 days Tue 11/04/17 Fri 21/04/17
1258 TEL/DATA/MATV installation 4 days Wed 19/04/17 Tue 25/04/17
1259 Shower screens 5 days Mon 24/04/17 Wed 3/05/17
1260 Snag/De-snag 5 days Wed 3/05/17 Wed 10/05/17
1261 Paint final coat 5 days Tue 9/05/17 Tue 16/05/17
1262 Complete Block H SF internal 0 days Tue 16/05/17 Tue 16/05/17
1263 Terraces Second Floor 27 days Tue 28/03/17 Mon 8/05/17
1264 Paint 1st & 2nd coat 5 days Tue 28/03/17 Tue 4/04/17
1265 Waterproofing to terraces 7 days Thu 30/03/17 Mon 10/04/17
1266 Terrace tiling & Pool tiling 8 days Thu 6/04/17 Tue 18/04/17
1267 Timber screens & cladding 7 days Thu 13/04/17 Mon 24/04/17
1268 Balustrades 6 days Wed 19/04/17 Fri 28/04/17
1269 Paint final coat 4 days Mon 24/04/17 Tue 2/05/17
1270 Snag/De-snag 5 days Fri 28/04/17 Mon 8/05/17
1271 Complete Block H Terraces SF 0 days Mon 8/05/17 Mon 8/05/17
1272 Second Floor Block G 82 days Fri 20/01/17 Fri 26/05/17
1273 Wet Works (ceiling & tiles) 22 days Fri 20/01/17 Mon 27/02/17
1274 Suspended ceiling grid work 12 days Fri 20/01/17 Fri 10/02/17
1275 Floor & wall tiles 14 days Mon 6/02/17 Mon 27/02/17
1276 Finishes Internal 62 days Thu 23/02/17 Fri 26/05/17
1277 Commencement of Block G SF Finishes 0 days Thu 2/03/17 Thu 2/03/17
1278 Paint 1st coat 5 days Thu 23/02/17 Thu 2/03/17
1279 Aluminium openings 10 days Mon 27/02/17 Mon 13/03/17
1280 Suspended Ceilings final 5 days Thu 9/03/17 Fri 17/03/17
1281 Shopfitting installation incl all 10 days Tue 14/03/17 Thu 30/03/17
1282 Kitchen fit outs 9 days Tue 28/03/17 Mon 10/04/17
1283 Granite tops 8 days Thu 6/04/17 Tue 18/04/17
1284 Sanitary wares & accessories 7 days Fri 14/04/17 Tue 25/04/17
1285 Electrical accessories & light fittings 8 days Fri 21/04/17 Fri 5/05/17
1286 TEL/DATA/MATV installation 4 days Wed 3/05/17 Tue 9/05/17
1287 Shower screens 5 days Mon 8/05/17 Mon 15/05/17
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
15
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
1288 Snag/De-snag 5 days Mon 15/05/17 Mon 22/05/17
1289 Paint final coat 5 days Fri 19/05/17 Fri 26/05/17
1290 Complete Block G SF internal 0 days Fri 26/05/17 Fri 26/05/17
1291 Terraces Second Floor 27 days Tue 4/04/17 Mon 15/05/17
1292 Paint 1st & 2nd coat 5 days Tue 4/04/17 Tue 11/04/17
1293 Waterproofing to terraces 7 days Thu 6/04/17 Mon 17/04/17
1294 Terrace tiling & Pool tiling 8 days Thu 13/04/17 Tue 25/04/17
1295 Timber screens & cladding 7 days Thu 20/04/17 Wed 3/05/17
1296 Balustrades 6 days Thu 27/04/17 Mon 8/05/17
1297 Paint final coat 4 days Wed 3/05/17 Tue 9/05/17
1298 Snag/De-snag 5 days Mon 8/05/17 Mon 15/05/17
1299 Complete Block G Terraces SF 0 days Mon 15/05/17 Mon 15/05/17
1300 Externally & Common areas Block H 77 days Tue 15/11/16 Fri 31/03/17
1301 Commencement of Block H Externally & Common areas 0 days Tue 15/11/16 Tue 15/11/16
1302 Waterproofing on roof 8 days Tue 15/11/16 Fri 25/11/16
1303 M & E Equipments on roof 12 days Wed 23/11/16 Mon 12/12/16
1304 Paint 1st & 2nd coat 6 days Tue 14/02/17 Thu 23/02/17
1305 Lifts installation including finishes 15 days Tue 22/11/16 Wed 14/12/16
1306 Stone cladding 15 days Tue 21/02/17 Tue 14/03/17
1307 Composite timber cladding, pergolas & gates 15 days Tue 21/02/17 Tue 14/03/17
1308 Balustrades 10 days Thu 23/02/17 Thu 9/03/17
1309 Tiling to main staircases and common areas 10 days Mon 13/02/17 Tue 28/02/17
1310 Paint final coat 7 days Thu 9/03/17 Wed 22/03/17
1311 Snag/De-snag 7 days Wed 22/03/17 Fri 31/03/17
1312 Complete Block H External Finishes & Common areas 0 days Fri 31/03/17 Fri 31/03/17
1313 Externally & Common areas Block G 76 days Fri 25/11/16 Tue 11/04/17
1314 Commencement of Block G Externally & Common areas 0 days Fri 25/11/16 Fri 25/11/16
1315 Waterproofing on roof 8 days Fri 25/11/16 Thu 8/12/16
1316 M & E Equipments on roof 12 days Mon 5/12/16 Wed 11/01/17
1317 Paint 1st & 2nd coat 6 days Thu 23/02/17 Fri 3/03/17
1318 Lifts installation including finishes 15 days Wed 14/12/16 Tue 24/01/17
1319 Stone cladding 15 days Wed 1/03/17 Fri 24/03/17
1320 Composite timber cladding, pergolas & gates 15 days Wed 1/03/17 Fri 24/03/17
1321 Balustrades 10 days Fri 3/03/17 Mon 20/03/17
1322 Tiling to main staircases and common areas 10 days Mon 27/02/17 Mon 13/03/17
1323 Paint final coat 7 days Wed 22/03/17 Fri 31/03/17
1324 Snag/De-snag 7 days Fri 31/03/17 Tue 11/04/17
1325 Complete Block G External Finishes & Common areas 0 days Tue 11/04/17 Tue 11/04/17
1326 External Works Blocks A, B, C & D 184 days Tue 26/07/16 Fri 19/05/17
1327 Common Pools 158 days Thu 4/08/16 Thu 20/04/17
1328 Structure 98 days Thu 4/08/16 Wed 18/01/17
1329 Excavation and Formation 15 days Thu 4/08/16 Fri 26/08/16
1330 Blinding 10 days Fri 19/08/16 Fri 2/09/16
1331 MEP 1st Fix base 10 days Wed 31/08/16 Wed 14/09/16
1332 FRC Base 30 days Wed 7/09/16 Thu 20/10/16
1333 MEP 1st Fix walls 30 days Thu 29/09/16 Wed 16/11/16
1334 FRC Wall 50 days Thu 13/10/16 Wed 18/01/17
1335 Wet Trades 35 days Wed 11/01/17 Tue 7/03/17
1336 MEP Second Fix 10 days Wed 11/01/17 Wed 25/01/17
1337 water Test 10 days Wed 25/01/17 Mon 13/02/17
1338 Plaster to pool 20 days Mon 6/02/17 Tue 7/03/17
1339 Finishes 40 days Tue 21/02/17 Thu 20/04/17
1340 Pool Tiling 40 days Tue 21/02/17 Thu 20/04/17
1341 Complete common pool 0 days Thu 20/04/17 Thu 20/04/17
1342 Daybeds & Planters 144 days Fri 26/08/16 Fri 21/04/17
1343 Substructure 46 days Fri 26/08/16 Fri 4/11/16
1344 Setting out 10 days Fri 26/08/16 Fri 9/09/16
1345 Excavation for bases 15 days Fri 2/09/16 Mon 26/09/16
1346 Blinding 7 days Fri 9/09/16 Wed 21/09/16
1347 FRC bases 10 days Mon 19/09/16 Mon 3/10/16
1348 MEP First Fix 5 days Thu 29/09/16 Thu 6/10/16
1349 Columns 12 days Mon 3/10/16 Wed 19/10/16
1350 Backfill 7 days Wed 12/10/16 Fri 21/10/16
1351 Casting of Surface Bed 10 days Tue 18/10/16 Fri 4/11/16
1352 Superstructure 38 days Wed 26/10/16 Thu 12/01/17
1353 Ground to First 38 days Wed 26/10/16 Thu 12/01/17
1354 Columns 15 days Wed 26/10/16 Mon 21/11/16
1355 MEP 1st and 2nd fix 5 days Mon 14/11/16 Mon 21/11/16
1356 FRC Beams 10 days Thu 17/11/16 Thu 1/12/16
1357 FRC Slab with conduits 20 days Thu 24/11/16 Thu 12/01/17
1358 Finishes (Internal + External) 74 days Mon 12/12/16 Fri 21/04/17
1359 Plaster 25 days Thu 26/01/17 Wed 8/03/17
1360 Stone Walls 30 days Wed 8/03/17 Fri 21/04/17
1361 Appointment of shade sails 0 days Mon 12/12/16 Mon 12/12/16
1362 Paint 1st coat 10 days Wed 1/03/17 Wed 15/03/17
1363 Complete daybeds & Planters 0 days Fri 21/04/17 Fri 21/04/17
1364 Security Post 82 days Mon 3/10/16 Mon 27/02/17
1365 Substructure 12 days Mon 3/10/16 Wed 19/10/16
1366 Fixed start 0 days Mon 3/10/16 Mon 3/10/16
1367 Setting out 2 days Mon 3/10/16 Wed 5/10/16
1368 Excavate for footing and bases 2 days Tue 4/10/16 Thu 6/10/16
1369 Trim & compact 1 day Wed 5/10/16 Thu 6/10/16
1370 Blinding 1 day Wed 5/10/16 Thu 6/10/16
1371 FRC footing & bases 3 days Wed 5/10/16 Mon 10/10/16
1372 Foundation blockwork 3 days Fri 7/10/16 Wed 12/10/16
1373 FRC tie columns 2 days Tue 11/10/16 Thu 13/10/16
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
16
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
1374 Backfill & compact to u/side of surface bed 2 days Wed 12/10/16 Fri 14/10/16
1375 MEPD sleeves/pipes under surface bed 3 days Wed 12/10/16 Mon 17/10/16
1376 Soil poisoning & DPM sheet 1 day Fri 14/10/16 Mon 17/10/16
1377 FRC GF surface beds 4 days Thu 13/10/16 Wed 19/10/16
1378 Completion of surface bed 0 days Wed 19/10/16 Wed 19/10/16
1379 Superstructure 30 days Wed 19/10/16 Tue 6/12/16
1380 Blockwork 7 days Wed 19/10/16 Fri 28/10/16
1381 FRC columns 7 days Tue 25/10/16 Mon 7/11/16
1382 FRC beams 7 days Fri 28/10/16 Thu 10/11/16
1383 FRC 1st Floor slab inc MEPD conduits 7 days Mon 7/11/16 Fri 18/11/16
1384 Deformwork 2 days Fri 2/12/16 Tue 6/12/16
1385 Finishes (Internal + External) 40 days Tue 6/12/16 Mon 27/02/17
1386 Finishes & snag 40 days Tue 6/12/16 Mon 27/02/17
1387 Complete Security Post Security Post 0 days Mon 27/02/17 Mon 27/02/17
1388 Transformer Room 50 days Thu 1/09/16 Wed 16/11/16
1389 Fixed start 0 days Thu 1/09/16 Thu 1/09/16
1390 Structure 15 days Thu 1/09/16 Thu 22/09/16
1391 Wet Trade 15 days Thu 22/09/16 Fri 14/10/16
1392 Finishes 25 days Thu 6/10/16 Wed 16/11/16
1393 Complete Transformer Room 0 days Wed 16/11/16 Wed 16/11/16
1394 Ramps to basements 25 days Tue 11/10/16 Mon 21/11/16
1395 Structure 10 days Tue 11/10/16 Tue 25/10/16
1396 Wet Trade 5 days Tue 25/10/16 Fri 4/11/16
1397 Finishes 10 days Fri 4/11/16 Mon 21/11/16
1398 Complete Ramps to Basement 0 days Mon 21/11/16 Mon 21/11/16
1399 Site Works 118 days Tue 26/07/16 Thu 9/02/17
1400 External Services including stormwater 118 days Tue 26/07/16 Thu 9/02/17
1401 Complete External Services Site Works 0 days Thu 9/02/17 Thu 9/02/17
1402 Hard Landscape 119 days Mon 10/10/16 Tue 2/05/17
1403 Appointment of paving subcontractor 0 days Mon 10/10/16 Mon 10/10/16
1404 Paving slabs & Parking 70 days Fri 9/12/16 Fri 14/04/17
1405 Appointment of external walling subcontractor 0 days Tue 24/01/17 Tue 24/01/17
1406 Other finishes 30 days Wed 15/03/17 Tue 2/05/17
1407 Complete Hard Landscaping 0 days Tue 2/05/17 Tue 2/05/17
1408 Soft Landscape 148 days Fri 16/09/16 Fri 19/05/17
1409 Appointment of Landscape Subcontractor 0 days Fri 16/09/16 Fri 16/09/16
1410 Top soil 15 days Tue 24/01/17 Mon 20/02/17
1411 Irrigation 25 days Fri 10/02/17 Wed 22/03/17
1412 External light 25 days Mon 13/03/17 Wed 19/04/17
1413 Planting 25 days Wed 12/04/17 Fri 19/05/17
1414 Appointment of external lights 0 days Mon 16/01/17 Mon 16/01/17
1415 Appointment of signage subcontractor 0 days Wed 18/01/17 Wed 18/01/17
1416 Place external lights 12 days Thu 27/04/17 Tue 16/05/17
1417 Complete Soft Landscaping 0 days Fri 19/05/17 Fri 19/05/17
1418 Final Handover of Works 463.61 days Mon 7/09/15 Tue 5/09/17
1419 Bulk Earthworks 0 days Mon 7/09/15 Mon 7/09/15
1420 Completion of basement excavation 0 days Mon 7/09/15 Mon 7/09/15
1421 Common Basement (AB, CD, GH) 122 days Wed 13/01/16 Fri 15/07/16
1422 Completion of common basement floor slab (Milestone 13/01/16) 0 days Wed 13/01/16 Wed 13/01/16
1423 Completion of basement retaining walls 0 days Thu 25/02/16 Thu 25/02/16
1424 Completion of basement incl waterproofing to retaining walls 0 days Fri 15/07/16 Fri 15/07/16
1425 Block EF 302.22 days Wed 13/01/16 Fri 5/05/17
1426 Structure 158.22 days Wed 13/01/16 Thu 8/09/16
1427 Completion foundations to underside surfacebed (Milestone 13/01/16 0 days Wed 13/01/16 Wed 13/01/16
1428 Completion of surface bed 0 days Thu 21/01/16 Thu 21/01/16
1429 Completion of FF Slab 0 days Mon 28/03/16 Mon 28/03/16
1430 Completion of SF Slab 0 days Tue 19/07/16 Tue 19/07/16
1431 Completion of Roof Slab (Milestone Structure) 0 days Thu 8/09/16 Thu 8/09/16
1432 Wet Works 101 days Tue 2/08/16 Wed 18/01/17
1433 Completion of GF wet works 0 days Tue 2/08/16 Tue 2/08/16
1434 Completion of 1st floor wet works 0 days Mon 24/10/16 Mon 24/10/16
1435 Completion of 2nd floor wet works 0 days Wed 11/01/17 Wed 11/01/17
1436 Completion of plaster to facades 0 days Wed 18/01/17 Wed 18/01/17
1437 Finishes Block E 96 days Fri 28/10/16 Fri 14/04/17
1438 Complete Block E GF internal 0 days Fri 28/10/16 Fri 28/10/16
1439 Complete Block E Terraces GF 0 days Thu 23/02/17 Thu 23/02/17
1440 Complete Block E FF internal 0 days Wed 15/02/17 Wed 15/02/17
1441 Complete Block E Terraces FF 0 days Tue 7/03/17 Tue 7/03/17
1442 Complete Block E SF internal 0 days Fri 14/04/17 Fri 14/04/17
1443 Complete Block E Terraces SF 0 days Mon 3/04/17 Mon 3/04/17
1444 Complete Block E External Finishes & Common areas 0 days Wed 1/03/17 Wed 1/03/17
1445 Finishes Block F 97 days Fri 18/11/16 Fri 5/05/17
1446 Complete Block F GF internal 0 days Fri 18/11/16 Fri 18/11/16
1447 Complete Block F Terraces GF 0 days Thu 2/03/17 Thu 2/03/17
1448 Complete Block F FF internal 0 days Thu 9/03/17 Thu 9/03/17
1449 Complete Block F Terraces FF 0 days Wed 15/03/17 Wed 15/03/17
1450 Complete Block F SF internal 0 days Fri 5/05/17 Fri 5/05/17
1451 Complete Block F Terraces SF 0 days Tue 25/04/17 Tue 25/04/17
1452 Complete Block F External Finishes & Common areas 0 days Wed 15/03/17 Wed 15/03/17
1453 Block AB 276 days Fri 26/02/16 Mon 8/05/17
1454 Structure 136 days Fri 26/02/16 Wed 14/09/16
1455 Completion of basement slab (GF) 0 days Fri 26/02/16 Fri 26/02/16
1456 Completion of FF slab 0 days Thu 14/04/16 Thu 14/04/16
1457 Completion of SF slab 0 days Thu 4/08/16 Thu 4/08/16
1458 Completion of Roof slab (Milestone Structure) 0 days Wed 14/09/16 Wed 14/09/16
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
17
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
1459 Wet Trades 89.78 days Fri 19/08/16 Fri 20/01/17
1460 Completion of GF Floor wet trades 0 days Fri 19/08/16 Fri 19/08/16
1461 Completion of 1st Floor wet trades 0 days Mon 31/10/16 Mon 31/10/16
1462 Completion of 2nd Floor wet trades 0 days Wed 11/01/17 Wed 11/01/17
1463 Complete Plaster External facades 0 days Fri 20/01/17 Fri 20/01/17
1464 Finishes Block B 82.78 days Mon 21/11/16 Fri 14/04/17
1465 Complete GF internal 0 days Mon 21/11/16 Mon 21/11/16
1466 Complete Terraces GF 0 days Mon 27/02/17 Mon 27/02/17
1467 Complete FF internal 0 days Thu 23/02/17 Thu 23/02/17
1468 Complete Terraces FF 0 days Mon 6/03/17 Mon 6/03/17
1469 Complete SF internal 0 days Fri 14/04/17 Fri 14/04/17
1470 Complete Terraces SF 0 days Tue 28/03/17 Tue 28/03/17
1471 Complete External Finishes & Common areas 0 days Tue 28/02/17 Tue 28/02/17
1472 Finishes Block A 80.78 days Wed 14/12/16 Mon 8/05/17
1473 Complete GF internal 0 days Wed 14/12/16 Wed 14/12/16
1474 Complete Terraces GF 0 days Mon 6/03/17 Mon 6/03/17
1475 Complete FF internal 0 days Fri 10/03/17 Fri 10/03/17
1476 Complete Terraces FF 0 days Fri 17/03/17 Fri 17/03/17
1477 Complete SF internal 0 days Mon 8/05/17 Mon 8/05/17
1478 Complete Terraces SF 0 days Thu 4/05/17 Thu 4/05/17
1479 Complete External Finishes & Common areas 0 days Fri 17/03/17 Fri 17/03/17
1480 Block CD 282.8 days Tue 8/03/16 Thu 25/05/17
1481 Structure 142.8 days Tue 8/03/16 Tue 4/10/16
1482 Completion of basement slab (GF) 0 days Tue 8/03/16 Tue 8/03/16
1483 Completion of FF slab 0 days Fri 15/04/16 Fri 15/04/16
1484 Completion of SF slab 0 days Fri 12/08/16 Fri 12/08/16
1485 Completion of Roof slab (Milestone Structure) 0 days Tue 4/10/16 Tue 4/10/16
1486 Wet Trades 91.8 days Mon 5/09/16 Fri 10/02/17
1487 Completion of GF Floor wet trades 0 days Mon 5/09/16 Mon 5/09/16
1488 Completion of 1st Floor wet trades 0 days Mon 14/11/16 Mon 14/11/16
1489 Completion of 2nd Floor wet trades 0 days Thu 9/02/17 Thu 9/02/17
1490 Complete Plaster External facades 0 days Fri 10/02/17 Fri 10/02/17
1491 Finishes Block C 91.8 days Mon 5/12/16 Mon 15/05/17
1492 Complete GF internal 0 days Mon 5/12/16 Mon 5/12/16
1493 Complete Terraces GF 0 days Wed 15/03/17 Wed 15/03/17
1494 Complete FF internal 0 days Mon 6/03/17 Mon 6/03/17
1495 Complete Terraces FF 0 days Fri 24/03/17 Fri 24/03/17
1496 Complete SF internal 0 days Mon 15/05/17 Mon 15/05/17
1497 Complete Terraces SF 0 days Thu 4/05/17 Thu 4/05/17
1498 Complete External Finishes & Common areas 0 days Fri 17/03/17 Fri 17/03/17
1499 Finishes Block D 85.8 days Fri 13/01/17 Thu 25/05/17
1500 Complete GF internal 0 days Fri 13/01/17 Fri 13/01/17
1501 Complete Terraces GF 0 days Wed 29/03/17 Wed 29/03/17
1502 Complete FF internal 0 days Tue 28/03/17 Tue 28/03/17
1503 Complete Terraces FF 0 days Thu 6/04/17 Thu 6/04/17
1504 Complete SF internal 0 days Thu 25/05/17 Thu 25/05/17
1505 Complete Terraces SF 0 days Fri 19/05/17 Fri 19/05/17
1506 Complete External Finishes & Common areas 0 days Wed 3/05/17 Wed 3/05/17
1507 Block GH 276 days Fri 18/03/16 Fri 26/05/17
1508 Structure 136 days Fri 18/03/16 Wed 5/10/16
1509 Completion of basement slab (GF) 0 days Fri 18/03/16 Fri 18/03/16
1510 Completion of FF slab 0 days Wed 4/05/16 Wed 4/05/16
1511 Completion of SF slab 0 days Fri 19/08/16 Fri 19/08/16
1512 Completion of AB Roof slab (Milestone later as agreed additional bloc 0 days Wed 5/10/16 Wed 5/10/16
1513 Wet Trades 90 days Mon 12/09/16 Thu 16/02/17
1514 Completion of GF Floor wet trades 0 days Mon 12/09/16 Mon 12/09/16
1515 Completion of 1st Floor wet trades 0 days Wed 23/11/16 Wed 23/11/16
1516 Completion of 2nd Floor wet trades 0 days Mon 13/02/17 Mon 13/02/17
1517 Complete Plaster External facades 0 days Thu 16/02/17 Thu 16/02/17
1518 Finishes H 87 days Wed 14/12/16 Tue 16/05/17
1519 Complete GF internal 0 days Wed 14/12/16 Wed 14/12/16
1520 Complete Terraces GF 0 days Fri 17/03/17 Fri 17/03/17
1521 Complete FF internal 0 days Wed 15/03/17 Wed 15/03/17
1522 Complete Terraces FF 0 days Thu 30/03/17 Thu 30/03/17
1523 Complete SF internal 0 days Tue 16/05/17 Tue 16/05/17
1524 Complete Terraces SF 0 days Mon 8/05/17 Mon 8/05/17
1525 Complete External Finishes & Common areas 0 days Fri 31/03/17 Fri 31/03/17
1526 Finishes G 81 days Mon 23/01/17 Fri 26/05/17
1527 Complete GF internal 0 days Mon 23/01/17 Mon 23/01/17
1528 Complete Terraces GF 0 days Thu 30/03/17 Thu 30/03/17
1529 Complete FF internal 0 days Tue 4/04/17 Tue 4/04/17
1530 Complete Terraces FF 0 days Mon 10/04/17 Mon 10/04/17
1531 Complete SF internal 0 days Fri 26/05/17 Fri 26/05/17
1532 Complete Terraces SF 0 days Mon 8/05/17 Mon 8/05/17
1533 Complete External Finishes & Common areas 0 days Tue 11/04/17 Tue 11/04/17
1534 External Works Blocks A, B, C & D 108.64 days Wed 16/11/16 Fri 19/05/17
1535 Complete common pool 0 days Thu 20/04/17 Thu 20/04/17
1536 Complete daybeds & Planters 0 days Fri 21/04/17 Fri 21/04/17
1537 Complete Security Post 0 days Mon 27/02/17 Mon 27/02/17
1538 Complete Transformer Room 0 days Wed 16/11/16 Wed 16/11/16
1539 Complete Ramps to Basement 0 days Mon 21/11/16 Mon 21/11/16
1540 Complete External Services Site Works 0 days Thu 9/02/17 Thu 9/02/17
1541 Complete Hard Landscaping 0 days Tue 2/05/17 Tue 2/05/17
1542 Complete Soft Landscaping 0 days Fri 19/05/17 Fri 19/05/17
1543 Sectional Completion 46.99 days Wed 12/04/17 Tue 20/06/17
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
18
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS R1V8
ID Task Name Duration Start Finish 15 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S
1544 Final M & E T & C & Snag and Desnag E 20 days Wed 12/04/17 Thu 11/05/17
1545 Final M & E T & C & Snag and Desnag F 20 days Wed 3/05/17 Wed 31/05/17
1546 Final M & E T & C & Snag and Desnag B 20 days Fri 14/04/17 Mon 15/05/17
1547 Final M & E T & C & Snag and Desnag A 20 days Fri 5/05/17 Fri 2/06/17
1548 Final M & E T & C & Snag and Desnag C 20 days Mon 8/05/17 Mon 5/06/17
1549 Final M & E T & C & Snag and Desnag D 20 days Fri 19/05/17 Fri 16/06/17
1550 Final M & E T & C & Snag and Desnag H 20 days Thu 11/05/17 Thu 8/06/17
1551 Final M & E T & C & Snag and Desnag G 20 days Tue 23/05/17 Tue 20/06/17
1552 Final M & E T & C & Snag and Desnag Common Basement 15 days Thu 18/05/17 Thu 8/06/17
1553 Final M & E T & C & Snag and Desnag External Works 20 days Mon 22/05/17 Mon 19/06/17
1554
1555 Sectional Completion 0 days Tue 20/06/17 Tue 20/06/17
1556
1557 Works completion works (no change in date!) 53.01 days Wed 21/06/17 Tue 5/09/17
1558 Works completion works 53 days Wed 21/06/17 Tue 5/09/17
1559 Works Completion 0 days Tue 5/09/17 Tue 5/09/17
UPDATED:13 July 2016 Task Progress Summary Rolled Up Critical Task Rolled Up Progress External Tasks Group By Summary
REVISION: 1 VERSION: 8 Critical Task Milestone Rolled Up Task Rolled Up Milestone Split Project Summary Deadline
19