Cco Sumberagung Andri Ok
Cco Sumberagung Andri Ok
I. PEKERJAAN PENDAHULUAN
1 Pas papan nama proyek - Ls 1.00 1.00 - - 250,000.00 250,000.00 250,000.00
2 Dokumentasi - Ls 1.00 1.00 - - 250,000.00 250,000.00 250,000.00
3 Uitset dan pengukuran - Ls 1.00 1.00 - - 250,000.00 250,000.00 250,000.00
4 Uji Beton - Ls 1.00 1.00 - - 250,000.00 250,000.00 250,000.00
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- -
- - Tetap
- - Tetap
- -
- - Tetap
- - Tetap
- -
14,122,825.21 - Tambah
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
14,122,825.21 -
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- -
14,122,825.21 -
- 37,725,000.00 (Kurang)
9,090,000.00 - Tambah
60,000.00 - Tambah
84,000.00 - Tambah
- - Tetap
- 87,000.00 (Kurang)
42,000.00 - Tambah
- - Tetap
- 16,800,000.00 (Kurang)
375,000.00 - Tambah
9,651,000.00 54,612,000.00
- 7,626,000.00 (Kurang)
8,467,200.00 - Tambah
- 1,004,400.00 (Kurang)
17,577,000.00 - Tambah
204,000.00 - Tambah
51,000.00 - Tambah
- - Tetap
- 51,000.00 (Kurang)
34,000.00 - Tambah
- 400,000.00 (Kurang)
85,000.00 - Tambah
26,418,200.00 9,081,400.00
36,069,200.00 63,693,400.00
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- -
13,501,400.00 - Tambah
13,501,400.00 -
1 2 3 3 4 5
I. PEKERJAAN PENDAHULUAN
1 Pas papan nama proyek 1.00 Ls
2 Dokumentasi 1.00 Ls
3 Uitset dan pengukuran 1.00 Ls
4 Uji Beton 1.00 Ls
Jumlah Sub I
II. PEMBUATAN BTA 1 (1 UNIT)
A PEKERJAAN TANAH
1 Galian Tanah sedalam 1 meter 24.00 m3 P L T 15.20 m3
V= 10.00 x 1.90 x 0.80 15.20 m3
Sub Total D
Jumlah Sub II
III. PEMBUATAN BTA 2 (1 UNIT)
A PEKERJAAN TANAH
1 Galian Tanah sedalam 1 meter 8.71 m3 P L T 6.40 m3
V= 10.00 x 0.80 x 0.80 6.40 m3
2 Urugan tanah kembali 1.74 m3 1/4 Galian Tanah sedalam 1 meter 1.60 m3
V= 0.25 x 6.40 1.60 m3
Sub Total A
B PEKERJAAN PASANGAN
No. Jenis Pekerjaan Kontrak Sat Perhitungan Vol Pelaks
1 2 3 3 4 5
1 Pas. batu kosong 2.11 m3 P L T 1.60 m3
V= 10.00 x 0.80 x 0.20 1.60 m3
Sub Total B
C PEKERJAAN BETON
1 Cor Beton K100 0.63 m3 P L T 20.94 m3
V= 996.91 x 0.30 x 0.07 20.94 m3
Sub Total C
D PEKERJAAN PENGECATAN
1 Pengecatan Beton 43.89 m2 P L Jml 43.56 m2
luar V= 3.30 x 3.30 x 4.00 43.56 m2
Sub Total D
E PEKERJAAN PIPA DAN AKSESORIS
i PENGADAAN
- Pipa GI Ø 3" 2.40 m'
- Pipa GI Ø 2" 12.00 m'
-Valve Socket 3" 1.00 bh
-Knee GIP 3" 4.00 bh
-Knee GIP 2" 6.00 bh
-Gate Valve 3" 1.00 bh
-Stop Kran 2" 1.00 bh
-Filter Tusen dia. 3" 1.00 bh
-Seal Tape 25 mm 30.00 bh
-Tangga besi hollow uk 30 x 30 1.00 bh
-Tutup manhole plat baja tebal 30 mm 60 x 60 cm 2.00 bh
-Water Meter Induk 2" 2.00 bh
Sub Total i
ii PEMASANGAN
- Pipa GI Ø 3" 2.40 m'
- Pipa GI Ø 2" 12.00 m'
-Valve Socket 3" 1.00 bh
-Knee GIP 3" 4.00 bh
-Knee GIP 2" 6.00 bh
-Gate Valve 3" 1.00 bh
No. Jenis Pekerjaan Kontrak Sat Perhitungan Vol Pelaks
1 2 3 3 4 5
-Stop Kran 2" 1.00 bh
-Filter Tusen dia. 3" 1.00 bh
-Seal Tape 25 mm 30.00 bh
-Tangga besi hollow uk 30 x 30 1.00 bh
-Tutup manhole plat baja tebal 30 mm 60 x 60 cm 2.00 bh
-Water Meter Induk 2" 2.00 bh
Sub Total i
Sub Total E
Jumlah Sub III
IV. JARINGAN PERPIPAAN DARI BTA S/D PERMUKIMAN
A PENGADAAN
1 Pipa PVC Moof 6 m' S-10 Ø 3 1,680.00 m'
2 Pipa PVC Moof 6 m' S-10 Ø 2 1,150.00 m'
3 Pipa PVC Moof 6 m' S-10 Ø 0,5 1,500.00 m'
4 Pipa GI Medium SNI (6m) Ø 3" 75.00 m'
5 Flange Las 3" 46.00 bh
6 Pak Karet 3" 11.00 bh
7 Baut Mur 5/8" x 7 cm (3") 88.00 bh
8 Flange Spigot PVC 3" 4.00 bh
9 Flange Socket PVC 3" 3.00 bh
10 Gate Valve 3" 1.00 bh
11 Tee PVC 3" 1.00 bh
12 Lem PVC 5.00 bh
Sub Total A
B PEMASANGAN
1 Pipa PVC Moof 6 m' S-10 Ø 3 1,680.00 m'
2 Pipa PVC Moof 6 m' S-10 Ø 2 1,150.00 m'
3 Pipa PVC Moof 6 m' S-10 Ø 0,5 1,500.00 m'
4 Pipa GI Medium SNI (6m) Ø 3" 75.00 m'
5 Pengelasan Flange dia 3" 2,166.60 bh
6 Flange Spigot PVC 3" 4.00 bh
7 Flange Socket PVC 3" 3.00 bh
8 Gate Valve 3" 1.00 bh
9 Tee PVC 3" 1.00 bh
Sub Total B
C PEKERJAAN PENYANGGA PIPA GI 3"
1 Pas. batu belah 1 pc : 3 psr 0.67 m3
2 Plesteran 1 pc : 3 psr 3.60 m2
3 Acian 3.60 m2
Sub Total C
Jumlah Sub IV
V. SAMBUNGAN RUMAH (452 UNIT)
A PENGADAAN DAN PEMASANGAN
1 Water Meter 1/2" 1.00 bh
2 Stop Kran 1/2" 1.00 bh
3 Clam Sadle 1/2" 1.00 bh
4 Kran Air 1/2" 1.00 bh
5 Pipa PVC AW 1/2" 1.00 btg
6 Knee PVC 1/2" 6.00 bh
7 Tee PVC 1/2" 1.00 bh
8 Sock Drat Dalam 1/2" 6.00 bh
9 Sock Drat Luar 1/2" 1.00 bh
10 Seal Tape 2.00 bh
11 Overlop PVC 1/2" 1.00 bh
12 Ongkos Pemasangan 1.00 ls
Sub Total
Jumlah SR
Jumlah Sub V
Total Sub I + II + III + IV + V
Pipa PVC Moof 6m S 12,5 Ø 3
Pipa PVC Moof 6m S 12,5 Ø 2
Pipa PVC Moof 6m S 12,5 Ø 1,5