0% found this document useful (0 votes)
63 views10 pages

Cco Sumberagung Andri Ok

This document appears to be a change order form for a water pipeline project in Desa Sumberagung, Magetan Regency, Indonesia. It provides details of the original contract quantities and values compared to the actual work completed. The project involved preliminary works, construction of a water intake tower, and laying of PVC pipelines from the tower to villages. The form lists changes in quantities and associated costs for items like excavation, concrete works, and pipeline materials and installation. Overall it indicates that additional works were done compared to the original contract, resulting in higher total costs for items like concrete, rebar and pipeline materials. The total contract value was increased to account for these changes and completion of the project

Uploaded by

Adi Arch
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
63 views10 pages

Cco Sumberagung Andri Ok

This document appears to be a change order form for a water pipeline project in Desa Sumberagung, Magetan Regency, Indonesia. It provides details of the original contract quantities and values compared to the actual work completed. The project involved preliminary works, construction of a water intake tower, and laying of PVC pipelines from the tower to villages. The form lists changes in quantities and associated costs for items like excavation, concrete works, and pipeline materials and installation. Overall it indicates that additional works were done compared to the original contract, resulting in higher total costs for items like concrete, rebar and pipeline materials. The total contract value was increased to account for these changes and completion of the project

Uploaded by

Adi Arch
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 10

LAMPIRAN BERITA ACARA TAMBAH KURANG

KEGIATAN : PENINGKATAN DISTRIBUSI PENYEDIAAN AIR BAKU


PEKERJAAN : PEMBANGUNAN JARINGAN PIPA AIR MINUM DESA SUMBERAGUNG KECAMATAN PLAOSAN
LOKASI : KAB. MAGETAN
TA : 2018

Nomor VOLUME VOLUME HARGA NILAI


No. Uraian Pekerjaan SAT
Analisa KONTRAK PELAKS TAMBAH KURANG SATUAN ( Rp) KONTRAK ( Rp) PELAKS. ( Rp)
1 2 3 4 5 6 7 8 9 10 11

I. PEKERJAAN PENDAHULUAN
1 Pas papan nama proyek - Ls 1.00 1.00 - - 250,000.00 250,000.00 250,000.00
2 Dokumentasi - Ls 1.00 1.00 - - 250,000.00 250,000.00 250,000.00
3 Uitset dan pengukuran - Ls 1.00 1.00 - - 250,000.00 250,000.00 250,000.00
4 Uji Beton - Ls 1.00 1.00 - - 250,000.00 250,000.00 250,000.00

Jumlah Sub I 1,000,000.00 1,000,000.00


II. PEMBUATAN BTA 1 (1 UNIT)
A PEKERJAAN TANAH
1 Galian Tanah sedalam 1 meter An.B.1 m3 105.90 105.90 - 47,000.00 4,977,300.00 4,977,300.00
2 Urugan tanah kembali An.B.12 m3 3.10 3.10 - - 15,600.00 48,360.00 48,360.00

Sub Total A 5,025,660.00 5,025,660.00


B PEKERJAAN PASANGAN
1 Batu pecah uk. 15/20 cm An.C.2 m2 15.12 15.12 - - 635,800.00 9,613,296.00 9,613,296.00
2 Plesteran 1 Pc : 3 Ps An.E.3 m2 89.56 89.56 - - 44,600.00 3,994,376.00 3,994,376.00

Sub Total B 13,607,672.00 13,607,672.00


C PEKERJAAN BETON
1 Rabat Beton An.G.4 m3 0.45 21.39 20.94 - 674,600.00 303,570.00 14,426,395.21
2 Pas. Beton pondasi, kolom, sloof, dinding, balok, atap (K.175) An.G.5 m3 18.63 18.63 - - 792,200.00 14,758,686.00 14,758,686.00
3 Pembesian An.G.17.a Kg 2,875.28 2,875.28 - - 11,700.00 33,640,776.00 33,640,776.00
4 Begisting Kolom (2x pakai) An.G.20 m2 44.28 44.28 - - 49,600.00 2,196,288.00 2,196,288.00
5 Begisting Sloof (3x pakai) An.G.21 m2 13.12 13.12 - - 34,733.33 455,701.33 455,701.33
6 Begisting Sloof Kopel (3x pakai) An.G.21 m2 4.10 4.10 - - 34,733.33 142,406.67 142,406.67
7 Begisting Balok (3x pakai) An.g.22 m2 3.36 3.36 - - 75,600.00 254,016.00 254,016.00
8 Begisting Dinding (3x pakai) An.G.25 m2 101.68 101.68 - - 149,833.33 15,235,053.33 15,235,053.33
9 Begisting Atap (3x pakai) An.G.24 m2 69.24 69.24 - - 164,000.00 11,355,360.00 11,355,360.00

Sub Total C 78,341,857.33 92,464,682.54


D PEKERJAAN PIPA DAN AKSESORIS
Pengadaan
1 Pipa GI Ø 2" - m' 5.00 5.00 - - 68,000.00 340,000.00 340,000.00
2 Knee GIF 2" - bh 1.00 1.00 - - 35,000.00 35,000.00 35,000.00
3 Seal Tape 25mm - bh 3.00 3.00 - - 4,500.00 13,500.00 13,500.00
4 Besi Tangga LS unit 1.00 1.00 - - 1,500,000.00 1,500,000.00 1,500,000.00
5 Tutup Mainhole LS unit 2.00 2.00 - - 350,000.00 700,000.00 700,000.00
Pemasangan
1 Pipa GI Ø 2" An.P.8 m' 5.00 5.00 - - 5,400.00 27,000.00 27,000.00
2 Knee GIF 2" An.P.10 bh 1.00 1.00 - - 17,000.00 17,000.00 17,000.00
3 Besi Tangga LS unit 1.00 1.00 - - 100,000.00 100,000.00 100,000.00
4 Tutup Mainhole LS unit 2.00 2.00 - - 50,000.00 100,000.00 100,000.00

Sub Total D 2,832,500.00 2,832,500.00


Jumlah Sub II 99,807,689.33 113,930,514.54
III. JARINGAN PERPIPAAN DARI BTA S/D PEMUKIMAN
A PENGADAAN
1 Pipa PVC Moof 6 m' S-10 Ø 2" - m' 2,460.00 448.00 - 2,012.00 18,750.00 46,125,000.00 8,400,000.00
2 Pipa PVC Moof 6 m' S-10 Ø 1,5" - m' 324.00 930.00 606.00 - 15,000.00 4,860,000.00 13,950,000.00
3 Knee PVC Ø 2" - bh 1.00 13.00 12.00 - 5,000.00 5,000.00 65,000.00
4 Reducer 2" x 1,5" - bh 1.00 4.00 3.00 - 28,000.00 28,000.00 112,000.00
5 Tee PVC Ø 1,5" x 1,5" x 1,5" - bh 1.00 1.00 - - 35,000.00 35,000.00 35,000.00
6 Dop PVC Moof Ø 2" - bh 3.00 - - 3.00 29,000.00 87,000.00 -
7 Dop PVC Moof Ø 1,5" - bh 2.00 4.00 2.00 - 21,000.00 42,000.00 84,000.00
8 Lem PVC - bh 5.00 5.00 - - 45,000.00 225,000.00 225,000.00
9 Water Meter Ø 2" - bh 4.00 1.00 - 3.00 5,600,000.00 22,400,000.00 5,600,000.00
10 Stop Kran 2" - bh - 5.00 5.00 - 75,000.00 - 375,000.00

Sub Total A 73,807,000.00 28,846,000.00


B PEMASANGAN
1 Pipa PVC Moof 6 m' S-10 Ø 2" An.P.2 m' 2,460.00 - - 2,460.00 3,100.00 7,626,000.00 -
Pipa PVC Moof 6 m' S-10 Ø 2" An.P.11 m' 448.00 448.00 - 18,900.00 - 8,467,200.00
2 Pipa PVC Moof 6 m' S-10 Ø 1,5" An.P.2 m' 324.00 - - 324.00 3,100.00 1,004,400.00 -
Pipa PVC Moof 6 m' S-10 Ø 1,5" An.P.11 m' 930.00 930.00 - 18,900.00 - 17,577,000.00
3 Knee PVC Ø 2" An.P.10 m' 1.00 13.00 12.00 - 17,000.00 17,000.00 221,000.00
4 Reducer 2" x 1,5" An.P.10 m' 1.00 4.00 3.00 - 17,000.00 17,000.00 68,000.00
5 Tee PVC Ø 1,5" x 1,5" x 1,5" An.P.10 m' 1.00 1.00 - - 17,000.00 17,000.00 17,000.00
6 Dop PVC Moof Ø 2" An.P.10 bh 3.00 - - 3.00 17,000.00 51,000.00 -
7 Dop PVC Moof Ø 1,5" An.P.10 bh 2.00 4.00 2.00 - 17,000.00 34,000.00 68,000.00
8 Water Meter Ø 2" LS bh 4.00 - - 4.00 100,000.00 400,000.00 -
9 Stop Kran 2" An.P.10 bh - 5.00 5.00 - 17,000.00 - 85,000.00

Sub Total B 9,166,400.00 26,503,200.00


Jumlah Sub III 82,973,400.00 55,349,200.00
IV. SAMBUNGAN RUMAH
A PENGADAAN DAN PEMASANGAN
1 Water Meter 1/2" - bh 1.00 1.00 - - 100,000.00 100,000.00 100,000.00
2 Stop Kran 1/2" - bh 1.00 1.00 - - 30,000.00 30,000.00 30,000.00
3 Clam Sadle 1/2" - bh 1.00 1.00 - - 25,000.00 25,000.00 25,000.00
4 Kran Air 1/2" - bh 1.00 1.00 - - 10,000.00 10,000.00 10,000.00
5 Pipa PVC AW 1/2" - btg 1.00 1.00 - - 25,000.00 25,000.00 25,000.00
6 Knee PVC 1/2" - bh 6.00 6.00 - - 2,500.00 15,000.00 15,000.00
7 Tee PVC 1/2" - bh 1.00 1.00 - - 3,250.00 3,250.00 3,250.00
8 Sock Drat Dalam 1/2" - bh 6.00 6.00 - - 2,750.00 16,500.00 16,500.00
9 Sock Drat Luar 1/2" - bh 1.00 1.00 - - 2,600.00 2,600.00 2,600.00
10 Seal Tape - bh 2.00 2.00 - - 4,500.00 9,000.00 9,000.00
11 Overlop PVC 1/2" - bh 1.00 1.00 - - 5,500.00 5,500.00 5,500.00
12 Ongkos Pemasangan - Ls 1.00 1.00 - - 65,000.00 65,000.00 65,000.00

Sub Total 306,850.00 306,850.00


Jumlah SR unit 76.00 120.00 44.00 - 306,850.00 23,320,600.00 36,822,000.00
Jumlah Sub IV 23,320,600.00 36,822,000.00

207,101,689.33 JUMLAH KONTRAK 207,101,689.33 JUMLAH TAMBAH


JUMLAH PELAKSANAAN 207,101,714.54 JUMLAH KURANG
SELISIH 25.21 SELISIH
NILAI
KET.
TAMBAH ( Rp) KURANG ( Rp)
12 13 14

- - Tetap
- - Tetap
- - Tetap
- - Tetap

- -

- - Tetap
- - Tetap

- -

- - Tetap
- - Tetap

- -

14,122,825.21 - Tambah
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap

14,122,825.21 -

- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap

- -
14,122,825.21 -

- 37,725,000.00 (Kurang)
9,090,000.00 - Tambah
60,000.00 - Tambah
84,000.00 - Tambah
- - Tetap
- 87,000.00 (Kurang)
42,000.00 - Tambah
- - Tetap
- 16,800,000.00 (Kurang)
375,000.00 - Tambah

9,651,000.00 54,612,000.00

- 7,626,000.00 (Kurang)
8,467,200.00 - Tambah
- 1,004,400.00 (Kurang)
17,577,000.00 - Tambah
204,000.00 - Tambah
51,000.00 - Tambah
- - Tetap
- 51,000.00 (Kurang)
34,000.00 - Tambah
- 400,000.00 (Kurang)
85,000.00 - Tambah

26,418,200.00 9,081,400.00
36,069,200.00 63,693,400.00
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap
- - Tetap

- -
13,501,400.00 - Tambah
13,501,400.00 -

JUMLAH TAMBAH 63,693,425.21


JUMLAH KURANG 63,693,400.00
SELISIH 25.21
BACK UP VOLUME
KEGIATAN : PENINGKATAN DISTRIBUSI PENYEDIAAN AIR BAKU
PEKERJAAN : PEMBANGUNAN JARINGAN PIPA AIR MINUM DESA SUMBERAGUNG KECAMATAN PLAOSAN
LOKASI : KAB. MAGETAN
TA : 2018

No. Jenis Pekerjaan Kontrak Sat Perhitungan Vol Pelaks

1 2 3 3 4 5
I. PEKERJAAN PENDAHULUAN
1 Pas papan nama proyek 1.00 Ls
2 Dokumentasi 1.00 Ls
3 Uitset dan pengukuran 1.00 Ls
4 Uji Beton 1.00 Ls

Jumlah Sub I
II. PEMBUATAN BTA 1 (1 UNIT)
A PEKERJAAN TANAH
1 Galian Tanah sedalam 1 meter 24.00 m3 P L T 15.20 m3
V= 10.00 x 1.90 x 0.80 15.20 m3

2 Urugan tanah kembali 1.40 m3 P L T 1.00 m3


V= 10.00 x 0.50 x 0.20 1.00 m3
Sub Total A
B PEKERJAAN PASANGAN
1 Pas. batu aanstampeng. 12.52 m3 P L atas L bawah T 10.54 m3
V= 11.00 x 0.70 x 0.20 1.54 m3
V= 10.00 x 0.30 + 0.70 x 1.80 9.00 m3
2
2 Pas. batu belah 1 pc : 3 psr 10.65 m3 P L atas L bawah T 8.80 m3
V= 11.00 x 0.30 + 0.70 x 1.60 8.80 m3
2
3 Urugan batu kricak uk 5/7 cm 1.40 m3 P L T 1.40 m3
V= 10.00 x 0.70 x 0.20 1.40 m3

4 Plesteran 1 pc : 3 psr (dalam) 18.81 m2 P L 17.60 m2


V= 11.00 x 1.60 17.60 m2

5 Siaran 10.26 m2 P L 10.00 m2


V= 10.00 x 1.00 10.00 m2
Sub Total B
C PEKERJAAN BETON
1 Pas. Beton pondasi plat, kolom, ring, plat (K.175) 1.83 m3 P L T Jml 2.71 m3
footplat V = 0.50 x 0.50 x 0.15 x 4.00 0.15 m3
kolom V = 1.65 x 0.15 x 0.15 x 4.00 0.15 m3
ring balok V = 23.10 x 0.15 x 0.25 x 1.00 0.87 m3
plat V = 10.00 x 1.55 x 0.10 x 1.00 1.55 m3

2 Pembesian 241.99 kg P Jml btg Kg Jml 440.30 kg


footplat V = 1.30 x 12.00 x 0.62 x 4.00 38.47 kg
kolom V = 2.15 x 4.00 x 0.62 x 4.00 21.21 kg
V = 0.55 x 16.00 x 0.62 x 4.00 21.70 kg
ring balok V = 23.10 x 4.00 x 0.62 x 1.00 56.96 kg
V = 0.75 x ### x 0.62 x 1.00 106.81 kg
plat V = 10.00 x 16.00 x 0.62 x 1.00 98.64 kg
V = 1.55 x ### x 0.62 x 1.00 96.51 kg

3 Begesting ring datar (2x pakai) 13.20 m2 P L Jml 9.24 m2


V= 23.10 x 0.40 x 1.00 9.24 m2

4 Begesting kolom (3x pakai) 4.32 m2 P L Jml 3.96 m2


V= 1.65 x 0.60 x 4.00 3.96 m2

5 Begesting plat (3x pakai) 4.00 m2 P L Jml 15.50 m2


V= 10.00 x 1.55 x 1.00 15.50 m2
Sub Total C
D LAIN - LAIN
1 Tutup Manhole 1.00 bh

Sub Total D
Jumlah Sub II
III. PEMBUATAN BTA 2 (1 UNIT)
A PEKERJAAN TANAH
1 Galian Tanah sedalam 1 meter 8.71 m3 P L T 6.40 m3
V= 10.00 x 0.80 x 0.80 6.40 m3

2 Urugan tanah kembali 1.74 m3 1/4 Galian Tanah sedalam 1 meter 1.60 m3
V= 0.25 x 6.40 1.60 m3

3 Urugan Pasir bawah lantai 1.08 m3 P L T 0.53 m3


V= 2.30 x 2.30 x 0.10 0.53 m3

Sub Total A
B PEKERJAAN PASANGAN
No. Jenis Pekerjaan Kontrak Sat Perhitungan Vol Pelaks

1 2 3 3 4 5
1 Pas. batu kosong 2.11 m3 P L T 1.60 m3
V= 10.00 x 0.80 x 0.20 1.60 m3

2 Pas. batu kali 1 : 3 6.86 m3 P L atas L bawah T 6.55 m3


V= 11.20 x 0.50 + 0.80 x 0.90 6.55 m3
2
3 Pasangan Dinding 1/2 bata 1 : 3 Sekat. 8.25 m2 P T 6.00 m2
V= 2.00 x 3.00 6.00 m2

4 Plesteran 1 : 3 16.50 m2 P L Jml 15.96 m2


Luar/Pondasi V= 3.30 x 0.30 x 4.00 3.96 m2
Dalam/Skat V= 2.00 x 3.00 x 2.00 12.00 m2

5 Acian Beton 87.12 m2 P L Jml 79.56 m2


Luar V= 3.30 x 3.30 x 4.00 43.56 m2
Dalam V= 3.00 x 3.00 x 4.00 36.00 m2

Sub Total B
C PEKERJAAN BETON
1 Cor Beton K100 0.63 m3 P L T 20.94 m3
V= 996.91 x 0.30 x 0.07 20.94 m3

2 Cor Beton K175 9.97 m3 P L T Jml 9.38 m3


beton lantai V = 3.30 x 3.30 x 0.20 2.18 m3
beton dinding V = 3.30 x 3.00 x 0.15 x 4.00 5.94 m3
balok induk V = 3.30 x 0.20 x 0.15 0.10 m3
balok anak V = 3.30 x 0.15 x 0.15 0.07 m3
plat atap V = 3.30 x 3.30 x 0.10 1.09 m3

3 Pembesian 1,679.07 kg P Jml btg Kg Jml ### kg


lantai V= 3.30 x 22.00 x 0.62 x 4.00 179.03 kg
dinding V= 3.30 x 20.00 x 0.62 x 8.00 325.51 kg
3.30 x 22.00 x 0.62 x 8.00 358.06 kg
balok induk V= 3.30 x 4.00 x 0.62 8.14 kg
0.60 x 22.00 x 0.22 2.93 kg
balok anak V= 3.30 x 4.00 x 0.62 8.14 kg
0.50 x 22.00 x 0.22 2.44 kg
plat atap V= 3.30 x 22.00 x 0.62 x 4.00 179.03 kg

4 Begesting pondasi 2x pakai 1.08 m2 P L Jml 2.64 m2


V= 3.30 x 0.20 x 4.00 2.64 m2

5 Begesting dinding 3x pakai 2.17 m2 P L Jml 75.60 m2


luar V= 3.30 x 3.00 x 4.00 39.60 m2
dalam V= 3.00 x 3.00 x 4.00 36.00 m2

6 Begesting balok 3x pakai 0.39 m2 P L Jml 3.30 m2


V= 3.30 x 0.55 x 1.00 1.82 m2
V= 3.30 x 0.45 x 1.00 1.49 m2

7 Begesting plat atap 3x pakai 0.39 m2 P L Jml 10.32 m2


V= 3.00 x 3.00 x 1.00 9.00 m2
V= 3.30 x 0.10 x 4.00 1.32 m2

Sub Total C
D PEKERJAAN PENGECATAN
1 Pengecatan Beton 43.89 m2 P L Jml 43.56 m2
luar V= 3.30 x 3.30 x 4.00 43.56 m2

Sub Total D
E PEKERJAAN PIPA DAN AKSESORIS
i PENGADAAN
- Pipa GI Ø 3" 2.40 m'
- Pipa GI Ø 2" 12.00 m'
-Valve Socket 3" 1.00 bh
-Knee GIP 3" 4.00 bh
-Knee GIP 2" 6.00 bh
-Gate Valve 3" 1.00 bh
-Stop Kran 2" 1.00 bh
-Filter Tusen dia. 3" 1.00 bh
-Seal Tape 25 mm 30.00 bh
-Tangga besi hollow uk 30 x 30 1.00 bh
-Tutup manhole plat baja tebal 30 mm 60 x 60 cm 2.00 bh
-Water Meter Induk 2" 2.00 bh

Sub Total i
ii PEMASANGAN
- Pipa GI Ø 3" 2.40 m'
- Pipa GI Ø 2" 12.00 m'
-Valve Socket 3" 1.00 bh
-Knee GIP 3" 4.00 bh
-Knee GIP 2" 6.00 bh
-Gate Valve 3" 1.00 bh
No. Jenis Pekerjaan Kontrak Sat Perhitungan Vol Pelaks

1 2 3 3 4 5
-Stop Kran 2" 1.00 bh
-Filter Tusen dia. 3" 1.00 bh
-Seal Tape 25 mm 30.00 bh
-Tangga besi hollow uk 30 x 30 1.00 bh
-Tutup manhole plat baja tebal 30 mm 60 x 60 cm 2.00 bh
-Water Meter Induk 2" 2.00 bh

Sub Total i
Sub Total E
Jumlah Sub III
IV. JARINGAN PERPIPAAN DARI BTA S/D PERMUKIMAN
A PENGADAAN
1 Pipa PVC Moof 6 m' S-10 Ø 3 1,680.00 m'
2 Pipa PVC Moof 6 m' S-10 Ø 2 1,150.00 m'
3 Pipa PVC Moof 6 m' S-10 Ø 0,5 1,500.00 m'
4 Pipa GI Medium SNI (6m) Ø 3" 75.00 m'
5 Flange Las 3" 46.00 bh
6 Pak Karet 3" 11.00 bh
7 Baut Mur 5/8" x 7 cm (3") 88.00 bh
8 Flange Spigot PVC 3" 4.00 bh
9 Flange Socket PVC 3" 3.00 bh
10 Gate Valve 3" 1.00 bh
11 Tee PVC 3" 1.00 bh
12 Lem PVC 5.00 bh

Sub Total A
B PEMASANGAN
1 Pipa PVC Moof 6 m' S-10 Ø 3 1,680.00 m'
2 Pipa PVC Moof 6 m' S-10 Ø 2 1,150.00 m'
3 Pipa PVC Moof 6 m' S-10 Ø 0,5 1,500.00 m'
4 Pipa GI Medium SNI (6m) Ø 3" 75.00 m'
5 Pengelasan Flange dia 3" 2,166.60 bh
6 Flange Spigot PVC 3" 4.00 bh
7 Flange Socket PVC 3" 3.00 bh
8 Gate Valve 3" 1.00 bh
9 Tee PVC 3" 1.00 bh

Sub Total B
C PEKERJAAN PENYANGGA PIPA GI 3"
1 Pas. batu belah 1 pc : 3 psr 0.67 m3
2 Plesteran 1 pc : 3 psr 3.60 m2
3 Acian 3.60 m2

Sub Total C
Jumlah Sub IV
V. SAMBUNGAN RUMAH (452 UNIT)
A PENGADAAN DAN PEMASANGAN
1 Water Meter 1/2" 1.00 bh
2 Stop Kran 1/2" 1.00 bh
3 Clam Sadle 1/2" 1.00 bh
4 Kran Air 1/2" 1.00 bh
5 Pipa PVC AW 1/2" 1.00 btg
6 Knee PVC 1/2" 6.00 bh
7 Tee PVC 1/2" 1.00 bh
8 Sock Drat Dalam 1/2" 6.00 bh
9 Sock Drat Luar 1/2" 1.00 bh
10 Seal Tape 2.00 bh
11 Overlop PVC 1/2" 1.00 bh
12 Ongkos Pemasangan 1.00 ls

Sub Total
Jumlah SR
Jumlah Sub V
Total Sub I + II + III + IV + V
Pipa PVC Moof 6m S 12,5 Ø 3
Pipa PVC Moof 6m S 12,5 Ø 2
Pipa PVC Moof 6m S 12,5 Ø 1,5

You might also like