Load Forecast and Planning
Load Forecast and Planning
1. What is load?
Load can be characterised electrically by: a)size of equipment(MW,KW)b) single
phase or three phase c) voltage level, frequency d) duty cycle –whether continous
or random
Load devices may be: a) Electrical motor drives for industrial purpose or for
traction b) Heating equipment c) lighting equipment d) different electrical
equipments
Loads vary with time in a 24 hour period and may also vary periodically
Plot of variation of load demand with time is called a load curve
LOAD CURVE
P max
Load factor = Pave/Pmax
demand
P average
Period 12 to 7 7 to 9 9 to 11 11 to 1 1 to 4 4 to 10 10 to 12
Load, 20 100 45 70 40 85 30
MW
=1260MWh
Installed capacity ideally should be 100MW plus reserve capacity., say 20%
Peak load= it is the maximum simultaneous ultimate customer demand which occurs at any
period (day,week. Month or year)
Area under the load curve gives the amount of energy supplied to the system
At any instant of time sum of gross consumption of energy should be exactly equal to the sum
of demand of energy plus the losses in the system.
Peak Load: it is the simultaneous maximum demand on the system which may occur at any
period, day, week, month , year.
Voltage conditions are within permissible levels so that the technical losses can be
minimised.
VOLTAGE REGULATION
The voltage drop is indicative of losses in the system. As Indian Electricity Rules provides some
voltage variation limits, these are taken as one of the guiding factors in formulating various
system improvement proposals. The Indian Electricity Rules sets the following limits for various
voltage levels of a system:
TECHNICAL LOSSES
The target levels and maximum tolerable loss levels for each voltage level on the system are
accepted in India as follows:
The ability to forecast the long-term demand for electricity is a fundamental prerequisite
for the development of a secure and economic power system.
The term forecast refers to determination of requirements for the future using a
systematic process of defining future loads in sufficient quantitative detail to permit
important system expansion decisions to be made.
An accurate forecast requires adequate data, for without it, the results of the forecast may
be unreliable.
The demand for electricity depends on a number of socio-economic factors such as
economic growth, industrial production, the new technological developments that
influence the life styles, and also on the Governmental policies.
Prediction of future energy demand requires an intuitive and wise judgment and may call
for revising the estimate at regular intervals to take care of new policies, changes in
socio-economic trends. Thus, the projection may have to consider these changes into
account.
Even with the best information, forecasting is by nature a vague science. It is open
to the occurrence of the unpredictable events that may vary the consumption
pattern. Over estimation of demand may lead to unnecessary investment in
transmission and generation assets. Though in an open and competitive market,
excess generation will tend to force electricity prices down, on the other hand the
excess investment in the infrastructure will impose additional costs to the
consumers.
Under estimation of demand may lead to shortages of supply and infrastructure. In the
electricity market, energy prices would most likely to rise in this scenario, while system
security would be below standard. This may lead to curtailment of economic growth and
deny potential investors. Both extremes are undesirable for the electricity industry and to
the overall economy of the State.
Comprehensive plans has to be prepared for a 5 year period with a perspective plan for
the next 10 years to match with the five year plans of the planning commission.
For preparation of the plan projections or load forecasts for the electricity demand for
short time and long time basis is an essential pre requisite
Depending on the assumptions considered for growth and accuracy of data
compiled from the stakeholders, the forecasts can be made realistic.
More realistic the forecasts more pragmatic will be the Plan formulation as Optimization
of utilization of funds and scarce resources is a necessity
For planning to be effective it should cover the generation sector, transmission sector and
the distribution sector. For every new generating station coming up, the transmission
system has to be studied to examine whether the existing transmission system will be
adequate to evacuate this power and if necessary it would need to be strengthened.
At the same time, there should not be any constraint in the sub transmission or
distribution system also. Actually the generating stations are planned based on the
projected demand of the end users in the distribution system.
The Central Electricity Authority is entrusted with projecting these forecasts in the form
of Electric Power Survey Reports.
An expert committee is formed from representatives of the DISCOMS- private and state
sector, transmission cos, PGCIL, REC, various concerned ministry, experts from TERI
and other economists, Planning commissions etc
A thorough study of the electrical energy statistics such as category wise annual energy
consumption, availability of electricity, no of consumers and connected load, no of
electrified villages, no of energized agriculture pump sets, new plans of large scale
energy intensive industries, captive plants being installed etc are collected from the
concerned utilities of each state and union territory for the last five years The Central
Electricity Authority in close co-ordination with all the power utilities of the different
states of India, makes a comprehensive study based on past trends and projects a load
demand state wise and the entire nation as a whole every five years and prepares the
Electric load survey reports.
The 18th EPS report has been prepared to cater to the 12th annual plan from 2013-
2017 and long term planning upto 2022. Based on these reports the state utilities are to
make their own load flow studies and prepare their business plans for strengthening of the
transmission and distribution network as well as proposals for generating stations. Since
electricity is now governed by The Electricity Act 2003, commercial considerations come
into fore while making the project proposals.
4. FORECASTING METHODS
For forecasting the demand for electricity, many reliable statistical methods have been
developed which are very much effective and efficient in projecting the future demand.
The statistical models adopted are illustrated as below:
a. Trend analysis: Trending methods are widely used as a tool for forecasting which works with
historical data, extrapolating past load growth patterns into future. Trending techniques involve
fitting trend curves to basic historical data adjusted to reflect the growth trend itself.
Finally some critical studies are conducted to examine the condition of overloading or
changes in voltage profile when a breakdown occurs in a line or interconnecting transformer
when regular shutdown for maintenance is being done on one line/transformer. These
criticality studies are very important in system study, to avoid Transmission system failure.
Following are checked for inadequacy of the back up transmission system.
Overloading of transformers.
Overloading of lines.
Requirement of reactive compensation.
Additional load due to normal load growth in the next five years as projected from load growth
of the previous five years of the different categories of consumers
so if one 5mva is replaced by a 10mva, loading will be= 8.88/15=59%. And if both are replaced by
10MVA, then transformers will have loading of 44% only. In the event of outage of the 10MVA
transformer, the 5 MVA transformer will not be able to cater to entire load.
So, S/S Transformer capacity is selected as 2x10MVA considering 100% redundancy to take care
of outage of transformer.
8) =v3x205x(0.432x.85+0.3891x0.526)x20=4060Volts
13) We may consider higher capacity conductor by using ACSR Wolf conductor in place ACSR
Raccoon
15) Voltage Regulation= 3865x100/29135= 13.26%, so the reconductoring will not be effective.
(here resistance of ACSR Wolf= 0.1871 ohm and Reactance of ACSR Wolf= 0.3866ohm)