Sumatra Grid Code - English Version PDF
Sumatra Grid Code - English Version PDF
Grid Code
Sumatra 2007
PT PLN (PERSERO)
ON
system;
power.
Sumatra
Company (Persero).
(Persero)
4
Listrik Negara
PT PLN (Persero)
HAS DECIDED
OF SUMATERA
Article 1
Directors
Article 2
5
Article 3
Code of Sumatra
Article 4
System Grid.
On 28 December 2007
PRESIDENT DIRECTOR
EDDIE WIDIONO S
7
Addresses of
Praise our thanks to the God Allah SWT, who has given the
power.
the future.
INTRODUCTION
Management Code.
be reviewed.
Code
and
b. Members
- Head Office;
Jaringan di Sumatra
development.
as follows:
the dispute.
proposing party
steps as follows:
trouble/occurrence report.
GMC 7.1 Table contents, Introduction and Each Title are not
language
Dispatch.
GMC 7.5 The Word of “in written" in this Grid Code contain
23) and 2 digits for minutes (00 till 59) with the
expression of “hour”
Connection Code - CC
CC 1.0 Objectives
Connection point
Identification
25
Connection Code – CC
CC 1.0 Objectives
that:
Grid
the Grid
26
fulfilled.
following limitation:
275kV + 10%,-10%
150kV + 10%,-10%
66kV + 10%,-10%
20kV + 10%,-10%
27
275 kV 3%
150kV 3%
66kV 3%
20kV 3%
and
868
condition.
defined by CC 2.1
resulting instability;
resulting instability;
0.90 leading.
Unit.
Unit/Sub Unit.
Unit:
Voice - Operational:
- Administrative:
SCADA
Protection Net
network.
CC 3.3.2 Grid User must install, look after and operate two
field work:
and,
Code;
control; and
set of organization
operation
the energize
related equipments
Connection point
or is amounting to:
of Connection point
(power swing);
and,
Table A1.1.
Remarks:
(*) scheme of distance relay use scheme transfer different trip such as
permissive under reach and permissive over reach
non-impedance);
Over-Current.
Grid User.
(rele 81)
protection.
protection.
Metering Code
Connection point
51
Note:
GI: Central Power Station TS: Tele Signaling TM: Tele Metering
TRF: Transformer TSS: single Tele Signaling of TSD: Double Tele Signaling
GENTRF: Generator RCD Transformer: Digital Tele Control of RCA: Analogous Tele
Control
(“x" indication signal which must be reserved for by each extension type
Identification
A HHHHH A HHHHH A AA HH P
A B C
A: figure/number
H: letter
P: number or letter
A HHHH
1 2
follows
1 LANSA 3 BKSAM
ACC_Northern Sumatera
Mariana MRINA
Tarahan TRHAN
Natar NATAR
Baturaja BTRJA
A HHHHP A AA
Medium voltage 1 - 10 kV 1
10—30kv 2
30—60kV 3
90—200kV 5
200—400kV 6
600—1000kV 8
Above 1000 kV 9
A. Generating Center
Conductor Bay 1)
Rail/Busbar BSBAR
Trafo TRFOX2>
Diameter DAMTR
Extension EXTEN3>
Spare SPARE4>
Substation SUBST5>
RTU RTUTS6>
clock.
4 KOPEL 1 07
number 7
HH P
1 2
Circuit Breaker CB
Tap Changer TC
Trafo Voltage VT
BI 2
separator
Rail B.
61
Rail A
Example
formation
A HH A
to 150 kV.
PMT B
62
Example:
Example 1
1 BLVLAN 5 PBKIT3 07 BI 1
Sumatera
5: connected in Grid 1 50 kV
1: Busbar Number 1
Example 2
3 NTRHN 5 DAMTR1 04 CB 1
Sumatera
1: number 1
Example 3
Sumatera
5: voltage 150kV
2: transformer Number 2
Example 4:
2 SKRAK1SKRAK 1 PLTA.3 - MW
15 kV)
Example 5:
Belawan
A3.8
Operating Code – OC
particular level
OC 1.0 Basis
operation
and/or transmission
simultaneous by storm
disconnection
contingency
credible contingency
responsibilities.
examination.
security of System
kV and 66 I
and 66 kV
Grid 150 kV or 66 kV
Regional, if needed
System Security
extinguishing total
periodical;
or condition; and
transmission facility
station
is responsible
related Load
equipments agreed on
effective operation
Unit
frequency
exit
agreement interconnection or
System requirement
Security
responsible in
and
Code
agreement interconnection
Unit/Sub Unit
84
Code
reached by through:
(regulation primary
load
other level
(AGC).
(voltage collapse
Frequency
customer
and System
b. synchronous condenser
in CC 2.1 (c)
rating determinable
scheme protection
adequate; or
generating unit
and
voltage collapse
condition
accepted
security.
Lacking of Power if
Regional
(Persero)
minimum requirement
problem
requiring to
Operation Emergency.
notification receiver
activating of ROD
Operation)
100
must be followed
assessment
Sub Unit
transmission
OC
partly blackout.
voltage instability.
of those facilities.
OC
and 66 kV.
to be done.
work performance.
switching device.
the separator.
operable; and
reinstatement.
of the System.
must:
receiving news.
limited to:
immediately);
User.
the issuance;
impact thereof.
limited to:
111
conductor;
receiver; and
OC 10.3 Milestone
a. Instability of system;
limit;
information:
operational communication.
accuracy confirmation.
Network’s User.
Major Consumer.
Consumer.
presented.
b. description of event;
c. duration of event;
the event;
116
power; and
operational condition.
or
need of devices.
P3B Sumatera;
details).
provisional;
withheld);
User.
operation condition;
to.
OC 12.1 Testing
procedure;
unit;
conducted;
agreement.
conducted:
or
123
contains as follows:
a. date of request;
request);
not); or
results.
years thereafter.
protection device;
Agreement.
User.
rescheduling.
installation.
Code;
of the inspection;
inspecting party.
OC 13.1 Application
device manufacturing.
b. Monthly Schedule;
c. Weekly Schedule
d. Daily Dispatch
load need.
problems.
SDC.
SDC.
impediment; and
owner.
blackout;
network configuration;
quality (grid).
on:
month;
one month;
per required;
contract.
river;
production;
reserve margin.
Center.
following purposes:
operation;
regulator or compensator;
informed by PLTA;
distribution.
Schedule
anyway.
covers:
PLTA;
process;
margin.
targets:
environmental needs;
to PLN Enterprise;
transmission;
conducted;
readiness if necessary;
the transmission.
compensator device;
i. identification of operational
characteristic; and
implemented; and
transmission-interconnection only;
unit;
schedule implementation.
changed or not.
schedule.
day.
System operation.
subject to revise.
reserve;
is deemed necessary.
of Daily Schedule
System load.
Re-dispatch covers:
transmission;
generator;
maintenance;
daily dispatch.
release);
Code;
voltage regulation.
shall consider:
generator;
generator unit.
SDC.
Unit/Sub Unit.
System frequency;
Enterprise);
Enterprise;
power.
covering:
System;
of estimated load;
load;
consistent basis.
transmission; and
Schedule.
163
factors/data:
operational schedule;
System;
Schedule:
and
Schedule.
Schedule:
(IC); and
Operational Schedule
Schedule:
Schedule;
Schedule/Pre-dispatch:
following factors:
Schedule;
holidays;
maintenances works.
requirements.
SDCA2 1.4 The Load Control Centre must provide its effort
167
binding.
operations; and
168
generating units;
and “week”;
outage; and
must:
169
considering:
load;
Units/Generating Companies ;
should:
Generating Units/Generating
SDCA2 3.4;
or grids);
outage; and
relevant year.
generating units;
Schedule; and
SDCA2 4.4 On the 4th week for each month of the current
considering:
SDCA2 4.5 By end of the 4th week on each month, the Load
and
following month.
relevant week;
4.4.1; and
schedule; and
Centre must:
following week.
may be neglected.
Units/Generating Companies
178
Synchronizations
overheating.
hours.
units to be synchronized
for synchronization.
conversion, including:
synchronization;
required.
Characteristic.
thermal generators:
unit synchronization;
synchronization;
output power;
process;
power, in Rp/MWh;
‘ready-heat’ condition;
synchronize;
load;
load cost;
ready condition;
condition.
184
characteristic.
time;
a. Operator’s names;
performance.
immediately implemented:
start at 14:00”;
13:30:
Synchronization.
notification time:
follows:
generator Unit;
is:
10:20”; or
12:00”; and
12:00”.
in some ways.
power”;
voltage”.
191
Settlement Code - SC
for energy.
SC 1.0 Introduction
Procurement Agreement.
(Persero).
Regional Unit.
as contract management.
prevail.
as follows:
superiors; and
195
Meter Reading;
Regional Unit
Regional Units;
following conditions:
performance; and
be included:
and
interconnection point.
SC 8.0 Others
Metering Code – MC
a. kWh import;
b. kWh export;
c. kVArh import;
d. kVArh export;
to generator).
MC 1.2 Accuracy
a. Instrument Transformer
Standard 185.
2.3.2.2.
Meter).
MC 2.3.2.2.
a. Instrument Transformer
Standard 185.
2.3.2.2.
Meter).
2.3.2.2.
points.
condition).
2 minutes; ,and
MC 2.1 Meter
bidirectional meters:
transformer)
MC 2.2.1 Each and every Grid User must install at least one
metering.
such meter.
power.
MC 2.3.2 Communication
terminal blocks.
parties:
dc-batteries source;
variation is ± 10%.
kiosk.
MC 2.5 Ownership
entered in database.
211
month.
a. Disorder data;
b. Incomplete data;
MC 3.0 Commissioning
212
connection;
are:
c. Attachment of seals.
time interval:
to be borne by owner.
Agreement).
actions.
related parties;
meters owner.
parties.
attendance parties.
seals.
conditions:
testing;
Sumatra’s location;
Meter equipments.
information:
Metering Code.
Users;
requirements in MC 1.2.1.
MC 9.0 Others
sections:
This section explains the data needs for the technical design
223
dispatch target.
Small generators 1, 2
Consumers
of P3B Sumatera
DRC 3.1 Each Network User must submit the required data in
Code.
DRC 3.4 Network Users may request the Load Control Plant to
Network User does not submit the required data, then the Load
action does not exempt the Network User from its obligation to
not required.
Data
Description Unit Value
Item
Generator
rpm
1.2 Resistances
unit
unit
unit
unit
unit
unit
Xd’’ unit
unit
unit
unit
unit
unit
unit
unit
unit
Data
Description Unit Value
Item
Xdsat unit
Xd’’sat unit
unit
unit
Td’’
Tq’’
unit
Coil unit
Coil unit
unit
Capacity
Generation
Data
Description Unit Value
Item
RPM
unit
unit
Vspp
Tvm
P3Bi
Signal Urmax
Signal Urmin
Constant Tst1
Constant Tst2
Terminal Voltage Kc
232
excitation KP
Data
Description Unit Value
Item
kaom unit
Measurement Taom
Kafe unit
Measurement Tafe
Kape unit
unit
unit
Transducer Tp
Droop bpf
unit
Constant Tip
234
Tr
unit
unit
Data
Description Unit Value
Item
ippc
unit
Constant Tm
Tvr
unit
Gain Vn
Tn
Change
(GT) Thp
unit
unit
unit
Constant Kmbr
TW
Data
Description Unit Value
Item
Tl
unit
unit
unit
Data Submission
Description
Item Format
1.14 Charts
data
data
data
data
diagrams
238
diagrams
function of
time
1.17 Excitation
rated
Data
Description Unit Value
Item
Generator unit
of Generator unit
form:
Data Submission
Description
Item Format
units
fitted)
function
shaft stiffness
241
1 of 3)
Data
Description Unit Value
Item
thermal unit)
Output
3.4.1 Monday xx
hours
hours
3.4.3 Saturday xx
hours
hours
3.5.2 Friday xx
hours
hours
3.6 Flexibility
day)
2 of 3)
Data
Description Unit Value
Item
Shutdown)
minute period
244
diagram form:
Data Submission
Description
Item Format
3.10 Flexibility
of Offload data
3 of 3)
Data
Description Unit Value
Item
3.14 Flexibility
Data
Description Unit Value
Item
Voltage
Withstand Voltage
246
4.5 Grounding
motors contribution
Data
Description Unit Value
Item
points:
connection point
connection point
100 MVA)
unit
unit
unit
248
Data Submission
Description
Item Format
4.10 Grounding
1 of 2)
Data
Description Unit Value
Item
cable
item
disturbances
changer trafo
250
reactors
capacitors
Load types
power 7 years
(controlled
251
rectifiers,
big motor,
etc)
step
power
power
Additional Rules
operational reference.
254
Appendix A
Schedule Summary
B. Network Management
months)
weeks)
days)
Operation
2.2).
2.3)
Regulating Center
(SDCA 1.3.0).
B. Network Management
3.1)
3.1)
4.5)
SDC 5.6)
preparation of Minutes by
Statement of Energy
Transaction to Electrical
no issue in respect of
Statement of Energy
if there is no issue in
(SC 2.3).
260
(Glossary)
Device/Equipment it is tool/device/equipment
to produce, to arrange or
Nasional Amerika)
Grid.
outside
Control, it is computerization
facility arranging
user
could be synchronized.
than 2 days
as reserve capacity.
as rotation/hot reserve
component.
result of multiplication
be transformed to be sparkle,
electric field/magnetic of
losses of reactive on
transmitting facility. It is
or megaVars (MVAr).
Generation PLN/Electrical
requirement/load, through
procedures.
linear characteristic of
nominal frequency.
in a time period.
in GJ/MWh or kCal/kWh
Electrotechnical Commission
for maintenance
implementation.
conductor in a voltage of 66
components.
or MVA.
droop characteristic of 5%
generating unit.
in responding dispatch
instruction
conditions
or it is expected that is it
time periods
normal operation, it is
declared in MW/Minutes.
seconds
comfort of customer
Center
Transformer
facilities in service
operation whether it is
would be declared in
availability in evaluated
periods.
threatened condition.
system
appointed/assigned by P3B
271
preparedness, application,
procedure.
P3B Sumatera.
established).
Lithography Handwriting
of synchronized format,
terminated format.
in Sumatera Island
deliberately (either
automatically or manually)
consumer)
could be produced to be
maintained.
maintained.
System
terminal voltage.
voltage.
land
Thursday.
an incident on a person
purchaser.
units as expected by
Generation PLN/Electrical
breaker (CB).
276
in respective connection
point.
switching Grid
setting price
period
277
customer
weekly period.
additional of Generator in
projection
transformer conductor/cable in
the system.
(voltage aid)
of connection to be conducted.
to display it in Load
system
to be served or to be
fulfilled.
kV.
in Sumatera system
system user
equipments) generating
power.
down.
frequency of Grid.
281
Number: 149.K/DIR/2006
REGARDING
POWER SYSTEM
(Company).
282
Enterprise;
Company).
(Company).
public company;
Number 141.K/DIR/2005;
HEREBY DECIDES
SYSTEM
DISTRIBUTION
TRANSMISSION DEVELOPMENT
- DEPUTY DIRECTOR OF
DISTRIBUTION DEVELOPMENT
- DEPUTY DIRECTOR OF
GENERATION DEVELOPMENT
PLAN
- DEPUTY DIRECTOR OF
GENERATION COMPETITION
MANAGEMENT
Sumatera P3B
Sumbagut Generation
Sumbagsel Generation
Area
Riau Area
S2JB Area
Lampung Area
Pikitring
Sumatera: Secretary
Installation Development
Sumatera: Secretary
Pikitring: Member
DDTRS: Member
DDTRS: Member
DDTRS: Member
& Implementation
Chairman
Area: Member
Area: Member
Member
Member
Member
Member
Kilsel: Member
Settlement
Office: Chairman
Sumatera: Secretary
Member
Area: Member
Area: Member
288
Member
Code Team:
d. Data Requirement
official duties.
(Company).
Stipulated in Jakarta
PRESIDENT DIRECTOR
[Signed]
EDDIE WIDIONO S.