Which Form NB
Which Form NB
A Comparison of
The Various FIDIC Forms
and
Other Procurement Systems
1
1
A Brief Outline of FIDIC
FIDIC - Federation Internationale des
Ingenieurs - Conseils
Founded in 1913 in Ghent , Belgium by the
national associations of consulting engineers
of Belgium, France & Switzerland
Has grown to represent associations from
over 84 countries worldwide
Secretariat is located in Geneva, Switzerland
Contd./2
3 of 40 Cornerstone/Which’F Copyright NGB
2
2
A Brief Outline of FIDIC (contd.)
First standard form of contract published in
1957
– It was the first edition of the Red Book for civil
engineering works in the international field
– Since then FIDIC has become known outside the
engineering profession for its standard forms of
contract
The Red Book was followed by the Yellow
Book for Electrical and Mechanical Works
including erection on site Contd./4
5 of 40 Cornerstone/Which’F Copyright NGB
3
3
A Brief Outline of FIDIC (contd.)
First Edition of the Green Book – Short Form of
Contract – Agreement,
g , General Conditions,, Rules
for Adjudication and Notes for Guidance;
The 1999 Red Book – Conditions of Contract for
Construction, (for Building and Engineering Works,
Designed by the Employer) – General Conditions,
Guidance for the Preparation of the Particular
Conditions, Forms of Tender, Contract Agreement,
and Dispute Adjudication Agreement, 29,775 words;
4
4
Other Developments since 1999
The Harmonised Multilateral Development
Banks Form of Contract, 1st Ed. 2005, 3rd Ed.
2010
The Dredging & Reclamation Works, in 2006
The most important development is the
introduction of the DBO “Gold Book” in 2008
The FIDIC DBO Guide, December 2011
The Subcontract Form for the 1999 Red
Book, December 2011
FIDIC Procurement Procedures Guide, 2011
9 of 40 Cornerstone/Which’F Copyright NGB
5
5
Model Services Agreement
The White Book
Updated
4th Edition - 9.2006
Red Book, 4th Ed. 1992 New Red where the DAB is Adhoc & the
Engineer acts as the DAB
Red Book, 4th Ed. With New Red where the DAB is Standing & the
Suppl. 1996 Board is Independent & Impartial
6
6
Usual contractual arrangements in a construction project
Employer
or Owner
Engineer Contractor
Sub-contractors
Other Suppliers
pp
Consultants
Manufacturers
Direct contract
Indirect relationship
7
7
1. The allocation of the
essential functions found in
the project and particularly
the design function
8
8
The Allocation of Functions (cont.)
– Designer
» Sketch design
» Preliminary design
» Final design
– Manager and coordinator of various design functions
– Contractor
– Sub--contractor, supplier and manufacturer
Sub
– Project Manager** & Safety Controller
– Supervisor
– Certifier
– Adjudicator
– Operator
17 of 40 Cornerstone/Which’F Copyright NGB
9
9
The Allocation of Risks &Liability
Law of contract allocates risks to contracting parties.
Standard Forms affirm that allocation or re-
re-allocate
risks to another contracting part or third party.
For Civil Engineering Construction the following
concepts must be borne in mind:
– The meaning and significance of “Risk”;
– Not all undesirable events can be perceived and
identified; and
– Whilst risks generally imply undesirable consequences,
in certain circumstances desirable as well as undesirable
consequence may occur
19 of 40 Cornerstone/Which’F Copyright NGB
DEFINITIONS:
z RISK: ‘ The combined effect of the
probability , or frequency, of occurrence of
a defined hazard and the magnitude of the
consequences of the occurrence. ’
– B.S. 4778, 1991.
Australia/New Zealand Risk Management
Standard AS/NZ 3951: 1995: hazard is
replaced by event, which includes positive
as well as negative consequences.
10
10
DEFINITIONS:
HAZARD: ‘A situation that could
occur during the lifetime of a product,
system or plant that has the potential
for human injury, damage to property,
damage to the environment, or
economic loss’.
PROBABILITY OF OCCURRENCE : A
statistical term representing the likelihood
of a certain hazard occurring.
11
11
If risks are not allocated by law or
the terms of the contract then courts
adjudicate using following questions:
12
12
THE FUNCTION OF THE CONTRACT
– “It is a function of a contract to define upon whom
the various risks of an enterprise shall fall, and it
was decided that the Contractor should only price
for those risks which an experienced contractor
could be expected to foresee at the time of tender
tender.. ..
– It is the right and the duty of the Employer to decide and by
his Engineer, to design and specify that which is to be done
without hindrance
hindrance.. It is the duty of the Contractor to do
what the Contract required to be done, as designed and
specified by the Engineer, but, subject to any specific
requirement in the contract, it is his right and duty to decide
the manner in which he will do it.it.
– If there are to be exceptional cases ...............”
...............”
25 of 40 Cornerstone/Which’F Copyright NGB
Risks in Performance
Responsibility towards others & self
Liability
y ((amount,, period
p & scope)
p )
Indemnity
Insurance
13
13
Duties & Obligations are set out
in the Contract
Risks exist
throughout the Contract
Injury
j y or Delay
y in
Damage performance
Responsibility is
allocated
In accordance with
14
14
RISKS IN CONSTRUCTION
Risks of Loss or
D
Damage
g Economic & Time Risks
Go to next
Employer’s Risks Contractor’s Risks
slide
( Specified ) ( All Others )
P.I. P.&E.
C.A.R. T.P.L. E. L. Excess D.I.C.
L.
NGB
Copyright
Non-
Delay Patent Defects Performance
15
15
Economic & Time Risks
Numbers in Yellow refer to ICE & Green to FIDIC Red Book, 4th Ed.
Numbers in blue refer to FIDIC New Red Book, 1999 NGB
Copyright
The Unexpected
happens
more frequently
than
you think !
16
16
Risks
17
17
Management, Timing & Method
of Remuneration
When allocating risks and functions, the
promoter or employer should consider:
– Management and method of valuing work
done and its payment
– Is he prepared to share risks with other
parties
ti
– Extent of such sharing
35 of 40 Contd./2
Cornerstone/Which’F Copyright NGB
18
18
Management, Timing & Method of
Remuneration (Contd./2)
19
19
Check List for choice of Form of Contract
Choice of the type of the project to be procured;
Choice of design and whether or not it has an
exclusive
l i nature;
t
Checking of how and when payment is made;
Certainty and the amount of final cost of the project;
Method of tendering;
Control duringg construction; and
The possibility or probability of having a variation
or change in the works after entering into the
Contract.
39 of 40 Cornerstone/Which’F Copyright NGB
Table No. 1
20
20