Best It Helpdesk Software: Cost Management
Best It Helpdesk Software: Cost Management
Sections
[Reference Material to Study] [What to Study?] [Key Definitions] [Cost Management Processes] [Cost Management Concepts] [Sample Problems] [Sample Problem Answers] [Sample Questions]
[Answers]
The project cost management knowledge area includes processes to ensure that a project is completed on time and within budget. These processes include resource planning and cost budgeting. Each
process has a set of input and a set output. Each process also has a set of tools and techniques that are used to turn the input into output.
- A Guide to the Project Management Body of Knowledge, Chapter 7 (1996 & 2000 edition)
- PMBOK Q&A, PMI
A Guide to the
Project...
$8.99
Shop now
Project Planning, Scheduling & Control, Lewis, James P., 1995, Chapter 10
Project
Planning, ...
$29.90
Shop now
Project Management, A Managerial Approach,, Chapters 5 (pg. 206), 7, 10. Meridith & Mantel
Project
Management:...
$27.45
Shop now
Shop now
Shop now
$36.13
Shop now
What to Study?
The PMBOK phases of Project Cost Management: Resource Planning, Cost Estimating, Cost Budgeting, and Cost Control (Be familiar with Input, Tools and Techniques, and Output for each
phase)
Cost Estimates and Ranges: Order of Magnitude, Budgetary, and Definitive
Earned Value Analysis: BCWP, BCWS, ACWP, EAC, BAC, ETC, CV, SV, CPI, SPI
Cost Estimating Techniques: analogous, parametric, and bottom-up
Present Value and Net Present Value
Straight-Line, Double Declining Depreciation and Sum of Yrs Digits
Key Definitions
Baseline
The original plan plus or minus approved changes.
Budget At Completion (BAC)
The estimated total cost of the project when done.
Budgeted Cost of Work Performed (BCWP)
The sum of the approved cost estimates for activities completed during a given period (usually project-to-date).
Budgeted Cost of Work Scheduled (BCWS)
The sum of the approved cost estimates for activities scheduled to be performed during a given period.
Chart of Accounts
Any numbering system used to monitor project costs by category (e.g., labor, supplies, materials). The project chart of accounts is usually based upon the corporate chart of accounts of the
primary performing organization.
Code of Accounts
Any numbering system used to uniquely identify each element of the WBS.
Contingency Reserve
A separately planned quantity used to allow for future situations which may be planned for only in part ("known unknowns"). Contingency reserves are intended to reduce the impact of missing
cost or schedule objectives. Contingency reserves are normally included in the project's cost and schedule baselines.
Cost Budgeting
Allocating the cost estimates to individual project components.
Cost Control
Controlling changes to the project budget.
Cost Estimating
Estimating the cost of the resources needed to complete project activities.
Cost Performance Index (CPI)
The ratio of budgeted costs to actual costs (BCWP / ACWP). CPI is often used to predict the magnitude of a possible cost overrun using the following formula: original cost estimate/CPI =
projected cost at completion.
Cost Variance (CV)
Any difference between the estimated cost of an activity and the actual cost of that activity. In earned value, CV = BCWP-ACWP.
Earned Value
1. A method for measuring project performance. It compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance is as
planned.
2. The BCWP for an activity or group of activities.
Resource Planning
The process of determining what physical resources and what quantities of each should be used to perform project activities.
Input includes: WBS, historical information, scope statement, resource pool description, and organizational policies.
Methods used:
Expert judgment: consultants, professional and technical associations, industry groups, other units within the performing organization.
Alternatives identification: Any technique such as brainstorming and lateral thinking used to generate different approaches to the project.
Output includes: Resource requirements - a description of what types of resources are required and in what quantities for each element of the WBS.
Cost Estimating:
The process of developing an estimate of the costs of the resources needed to complete project activities.
Input includes: WBS, resource requirements, resource rates, activity duration estimates, historical information, chart of accounts.
Methods used:
Analogous estimating: (top down estimating) Uses the actual cost of a previous similar project as the basis for estimating the cost of the current project. Analogous estimating is frequently
used to estimate total project costs when there is a limited amount of detailed information about the project. (e.g., in the early project phases) It is generally less costly than other estimating
techniques, but it is also generally less accurate. Most reliable when 1) the previous projects are similar in fact and not just in appearance, 2) the individuals or groups preparing estimates
have the needed expertise.
Parametric modeling: Uses project characteristics (parameters) in a mathematical model to predict project costs. Models may be simple or complex. Most reliable when 1) the historical
information used to develop the model was accurate, 2) the parameters used in the model are readily quantifiable, and 3) the model is scalable.
Bottom-up estimating: Involves estimating the cost of individual work items, then summarizing or rolling-up the individual estimates to get a project total. The cost and accuracy of bottom-
up estimating is driven by the size of the individual work items: smaller work items increase both cost and accuracy. The project management team must weigh the additional accuracy
against the additional cost.
Computerized tools: Project management software and spreadsheets can assist with cost estimating.
Output includes: cost estimates, supporting detail, and the cost management plan. The cost management plan describes how cost variances will be managed. It is a subsidiary element of the
overall project plan.
Cost Budgeting
The process of allocating the overall cost estimates to individual work items in order to establish a cost baseline for measuring project performance.
Input includes: cost estimates, WBS, and project schedule.
Methods used: cost estimating tools and techniques.
Output includes: Cost baseline - a time-phased budget used to measure and monitor cost performance. It is developed by summing estimated costs by period and is usually displayed in the form
of an S-curve.
Cost Control
Estimates
Order of Magnitude
Range: -25% + 75%
An approximate estimate made without detailed data
Used during the initial evaluation of the project (Concept)
Other terms: SWAG, feasibility, conceptual, ball park
Budget
Range: -10% + 25%
Used to establish the funds required for the project (Development)
Also used to obtain approval for the project
Other terms: appropriations
Definitive
Range: -5% + 10%
Prepared from well defined specifications, data, drawings, etc.
Used for bid proposals, bid evaluations, contract changes, extra work, legal claims, permit and government approvals.
Cost Estimating involves developing an assessment of how much it will cost the performing organization to provide the product or service.
Pricing is a business decision -- how much the performing organization will charge for the product or service.
Project Cost Management is primarily concerned with the cost of the resources needed to complete the project.
A broader view of Project Cost Management is Life Cycle Costing.
Life Cycle Costing includes acquisition, operating, maintenance, and disposal costs.
Project Cost Management should consider the effect of project decisions on the cost of using the project product. (i.e., limiting the number of design reviews may reduce the cost of the
project but increase the product maintenance costs and customer operating costs.)
Cost Types
Sunk Costs: A historical or expended cost. Since the cost has been expended, we no longer have control over the cost. Sunk costs are not included when determining alternative courses of action.
Fixed Costs: Nonrecurring costs that do not change based on the number of units.
Variable Costs: Costs that rise directly with the size of the project.
Indirect Costs: Costs that are part of the overall organization's cost of doing business and are shared among all the current projects.
Opportunity Costs: The cost of choosing one alternative and, therefore, giving up the potential benefits of another alternative.
Direct Costs: Costs incurred directly by a specific project.
Depreciation
Straight-line Method: Takes an equal credit during each year of the useful life of an asset.
Accelerated Method: Writes off the expense even faster than straight-line.
Double-declining balance
Sum-of-the-years digits
__M _
PV =
(1 + r)**t
M = amount of payment t years from now
r = interest rate (also called discount rate)
Benefit-cost ratio (BCR) = PV of revenue/PV of costs Target Revenue should be at least 1.3X the cost
IRR: Internal Rate of Return - the percentage rate that makes the present value of costs equal to the present value of benefits.
Sample Problems
Given the following problem and assume today's date is Jun. 30.:
Work Unit Completion Date Budget ($M) Work Performed ($M) Actual Cost ($M)
A Jan. 31 10 10 12
B Feb. 28 5 4 5
C Mar. 31 6 8 8
D May 12 15 13 12
E Jun. 30 20 20 30
F Jul. 18 3 0 0
G Aug. 30 35 0 0
H Sep. 22 22 0 0
I Oct. 29 22 0 0
J Nov. 30 9 0 0
1. What is the net present value of an annual income flow of $1600 at 10% over the next 3 years?
2. What is the present value of $1000 at 12% at the end of 5 years?
3. Given the following:
A. Calculate the present value of both revenue and cost assuming a 10% interest rate.
B. Calculate the benefit-cost ratio.
C. Based on the BCR and profitability alone, would you do this project?
Depreciation
A. Calculate the present value of both revenue and cost assuming a 10% interest rate.
B. Calculate the benefit-cost ratio. BCR = PV(r)/PV(c)
3 BCR = 148,672/117,833 = 1.26 -
C. Based on the BCR and profitability alone, would you do this project?
Depends on who you ask. PMF class teaches "no". Should be 1.3 x cost before considering.
Depreciation
Sample Questions
There are 74 questions related to project cost management. Simply click the 'All Questions' link in order to go to them.
[All Questions]
Go to Specific Question
Following is a list of the questions and the general subject of the question. Click the number in order to go directly to that question.
Answers
[All Answers]
Go to Specific Answer
[1] [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] [12] [13] [14] [15] [16] [17] [18] [19] [20] [21] [22] [23] [24] [25] [26] [27] [28] [29] [30] [31] [32] [33] [34] [35] [36] [37] [38] [39] [40] [41] [42]
[43] [44] [45] [46] [47] [48] [49] [50] [51] [52] [53] [54] [55] [56] [57] [58] [59] [60] [61] [62] [63] [64] [65] [66] [67] [68] [69] [70] [71] [72] [73] [74]
[Integration] [Scope] [Cost] [Time] [Quality] [Human Resources] [Communications] [Risk] [Procurement]
DONATIONS
...(Almost) everything on Yancy.Org is TOTALLY FREE. I plan to keep it that way as long as possible. However, it does take a lot of time and costs to maintain the site. If you find the
site useful and can make a donation to offset the cost, it would be greatly appreciated. Donations of any size are welcome. (even $1 is appreciated). It's all a matter of the heart.
Donations are accepted via PayPal. To donate, simply click the 'PayPal' button and complete the form.
Richard Yancy
c/o Yancy.Org
344 Maple Ave. West
PMB283
Vienna, VA 22180
U.S.A.
E-Mail: [email protected]
URL: http://www.Yancy.Org
V isitor