0% found this document useful (0 votes)
191 views

Bill of Quantities: Project: Design of Flood Wall Along Morong River For Tradeoff 1 (Sheet Pile)

The document contains 3 bills of quantities comparing the costs for 3 different flood wall design options along the Morong River: 1) sheet pile, 2) concrete retaining wall, and 3) seawall. The costs include design, general requirements, and civil works. For the sheet pile option, the total civil works cost is estimated at 30.8 million. The concrete retaining wall option has a total civil works cost of 14.7 million, and the seawall option is estimated at 12.5 million.

Uploaded by

Ian Talaue
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
191 views

Bill of Quantities: Project: Design of Flood Wall Along Morong River For Tradeoff 1 (Sheet Pile)

The document contains 3 bills of quantities comparing the costs for 3 different flood wall design options along the Morong River: 1) sheet pile, 2) concrete retaining wall, and 3) seawall. The costs include design, general requirements, and civil works. For the sheet pile option, the total civil works cost is estimated at 30.8 million. The concrete retaining wall option has a total civil works cost of 14.7 million, and the seawall option is estimated at 12.5 million.

Uploaded by

Ian Talaue
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 19

Project: Design of Flood Wall along Morong River

For Tradeoff 1 (Sheet Pile)

BILL OF QUANTITIES

ITEM NO. DESCRIPTION QTY UNIT TOTAL UNIT COST TOTAL COST

I. DESIGN PHASE:
Preliminary Survey/Studies 1.00 lot 187,590.00 187,590.00
TOTAL FOR DESIGN PHASE 187,590.00

II. CONSTRUCTION PHASE


A. GENERAL REQUIREMENTS
1 Temporary Facilities 1.00 lot 533,910.00 533,910.00
2 Safety & Health Standard and Housekeeping 1.00 lot 899,100.01 899,100.01
TOTAL GENERAL REQUIREMENTS 1,433,010.00

B. CONSTRUCTION OF FLOOD WALL .


1 CIVIL WORKS
1.1 FORMWORKS AND EXCAVATION
Cover Walls 288.68 cu.m 3,515.40 1,014,833.20
Hauling & Disposal of debris 1.00 lot 1,065,036.00 1,065,036.00
1.2 INSTALLATION OF SHEET PILES
U- Type Sheet Piles 1067 pcs 27000 28,809,000
Total Civil Works 30,888,869.20
Project: Design of Flood Wall along Morong River
For Trade-offs 2 (Concrete Retaining Wall )

BILL OF QUANTITIES

ITEM NO. DESCRIPTION QTY UNIT TOTAL UNIT COST TOTAL COST

I. DESIGN PHASE:
Preliminary Survey/Studies 1.00 lot 187,590.00 187,590.00
TOTAL FOR DESIGN PHASE 187,590.00

II. CONSTRUCTION PHASE


A. GENERAL REQUIREMENTS
1 Temporary Facilities 1.00 lot 533,910.00 533,910.00
2 Safety & Health Standard and Housekeeping 1.00 lot 899,100.01 899,100.01
TOTAL GENERAL REQUIREMENTS 1,433,010.00

B. CONSTRUCTION OF FLOOD WALL .


1 CIVIL WORKS
1.1 FORMWORKS AND EXCAVATION
Cover Walls 288.68 cu.m 3,515.40 1,014,833.20
Hauling & Disposal of debris 1.00 lot 1,065,036.00 1,065,036.00
1.2 INSTALLATION OF CONCRETE RETAINING WALL
Concrete Retaining wall blocks 14000 pcs 800 13,140,000
Base Gravel 43.3579 m3 784.17 34000
Backfill Gravel 1981.933 m3 784.17 1,555,350
Special Cap blocks 2000 pcs 970 40000
Total Civil Works 14,769,350
Project: Design of Flood Wall along Morong River
For Trade-offs 3 (SeaWall )

BILL OF QUANTITIES

ITEM NO. DESCRIPTION QTY UNIT TOTAL UNIT COST TOTAL COST

I. DESIGN PHASE:
Preliminary Survey/Studies 1.00 lot 187,590.00 187,590.00
TOTAL FOR DESIGN PHASE 187,590.00

II. CONSTRUCTION PHASE


A. GENERAL REQUIREMENTS
1 Temporary Facilities 1.00 lot 533,910.00 533,910.00
2 Safety & Health Standard and Housekeeping 1.00 lot 899,100.01 899,100.01
TOTAL GENERAL REQUIREMENTS 1,433,010.00

B. CONSTRUCTION OF FLOOD WALL .


1 CIVIL WORKS
1.1 FORMWORKS AND EXCAVATION
Cover Walls 288.68 cu.m 3,515.40 1,014,833.20
Hauling & Disposal of debris 1.00 lot 1,065,036.00 1,065,036.00
1.2 INSTALLATION OF CONCRETE SEAWALL
Concrete (cement,sand, gravel) 12000 m3 1000 12000000
Rebars 10000 pcs 40 400000
Carriage Bolts 5000 pcs 250 125000
Total Civil Works 12,525,000

You might also like