Silver TM Study
Silver TM Study
Time management is the process of managing the time spent on each activity in the project, in
an effective and efficient manner, such that the overall schedule/milestones of the project are
met as planned.
Time Management includes the processes, tools & techniques required to manage the timely
completion of the project.
Time Management
Time is one of the project’s most limited resources as once time has been expended, there is no
recovery.
Time management is key aspect of managing a project. As such, it is considered to be a core
knowledge area, and is closely knit to scope and cost areas.
The main purpose is to build processes for the project that assist the manager and team to
complete the project in timely manner.
Customer Expectation
Define Activities Estimate Activity Resources Estimate Activity Durations Develop Schedules
Control Schedule “Change Requests Leading to Change management processes”.
Define activities
While defining activities, we need to ensure that Activities are small enough to Estimate, Schedule,
Monitor and Manage.
Sequence Activities
The result of sequencing the activities is a Network Diagram
The next process involves taking the activities and milestones and starting to sequence them
into how the work will be performed
Arrange the Activities logically to show the interdependencies with Leads (Overlaps) & Lags
(mandatory wait time), when applicable.
The method of sequencing activities is called as “Precedence diagramming method”
Types of relationships:
Sequence Activities –Finish to start (FS) - E.g. ‘the water must be boiled before I can add my
coffee’.
Sequence Activities –Finish to finish (FF) - E.g. ‘I must finish frying the chicken before cooking
the sauce is finished’.
Sequence Activities –Start to start (SS) - E.g. ‘I need to start creating the specification document
before I can start editing it’
Sequence Activities –Start to finish (SF) - This relationship is not used often.
Define the sessions Create Workbook Template Add descriptive narrative Add binder, Index
and Format Delegate Workbook
Convert Slides to jpg Insert jpg schematics Add descriptive narrative Add binder, Index and
Format Delegate Workbook
Developing schedule
Project Schedule is calendar based and inclusive of resource constraints, lead lags, execution preferences
and reserves.
Analyses activity sequences, durations, resource requirements, and schedule constraints to
create the Project Schedule. Determines the project activities’ scheduled start and finish dates.
Determines the milestones’ scheduled start and finish dates
After creation of the schedule, the Schedule Network analysis is done using any or all of the
following techniques
i. Critical Path method
ii. Schedule Compression
iii. What-if scenario analysis
iv. Resource levelling
ES EF
LS LF
Total Float – Is the amount of time an activity can be delayed without delaying the project end date.
Free Float – This is the amount of time an activity can be delayed without delaying the early start of its
successor/s.
Project Float – Amount of time a project can be delayed without delaying the externally imposed project
completion date.
Fast Tracking - In this technique the activities which are originally planned in sequence are done in
parallel to complete more activities in same time. For this the activities on critical path are chooses as
Critical path has the overall impact on project schedule.
Fast Tracking generally increases risk and may create rework efforts.
Crashing - Crashing is the technique in which cost and schedule trade-offs are analysed. How to
compress the schedule most by having minimal impact on cost and maintaining the scope. For example,
purchasing a software utility for competing any phase of project in less time.
Crashing generally has the risk of increasing the cost.
Of the above two options, the Project Manager has to evaluate the option which has minimal negative
impact for schedule compression.
What-If Scenario Analysis - This analysis is used to evaluate the different scenarios in the network
diagram analysis. Activity assumptions may change and hence the estimate of activity can change, which
may have positive or negative impact on project schedule.
Look for option to a situation that can happen at a later stage and may have impact on project schedule.
Resource Levelling
It’s applied to schedule which has resource /critical resource availability constraints through the
life cycle of the project.
Project may have shared resource or the availability of resources is not uniform.
Done because mathematical analysis produces a preliminary early-start schedule that requires
more than the allocated resources during certain time periods e.g., Rule of thumb –“allocate
scarce resources to critical path activities first.”
Often results in a project duration that is longer than the preliminary schedule. (Also called
“resource based method”).
You may refer the following guidelines/ checklist while writing the plan. These guidelines are based on
the observations made in writing & tracking and best practices suggested by experts.
1. Ensure that all the team members have submitted the duly filled in Timesheets.
2. It is better to track the activities in a combination view comprising Resource Usage View (Top
Pane) & Task Usage View (Bottom Pane).
3. It is advisable to update the plan by updating the resource actual work information for the listed
tasks.
4. To start with an actual tracking, check for the leaves / unavailability of the resources. If the
resource is on unplanned leave or was not available on work, then modify the resource calendar
appropriately.
5. Next, check the status of the task – whether it is completed.
6. If the task is completed, mark % work complete as 100%, remaining work / remaining duration
as 0.
7. If the task is not completed then enter the actual work information for task and the remaining
duration for that task.
8. Check for work done by the resource on a task(s) not falling in the prescribed timeframe.
9. Check for the task(s) not listed in the project plan.
10. Check for the tasks that are not thoroughly planned in the project plan.
11. Some tasks, especially the tasks that are allocated to all of the resources (most of the resources)
simultaneously; are easy to update from the task usage
12. Over and above these guidelines, always keep an eye on the baselined information.
13. Make it a mandatory activity to make a note of any changes, assumptions, comment on
feedback, etc