Real-Time Vertical Track Deflection Measurement System: Digitalcommons@University of Nebraska - Lincoln
Real-Time Vertical Track Deflection Measurement System: Digitalcommons@University of Nebraska - Lincoln
11-2008
Lu, Sheng, "Real-Time Vertical Track Deflection Measurement System" (2008). Mechanical (and Materials) Engineering -- Dissertations,
Theses, and Student Research. 2.
http://digitalcommons.unl.edu/mechengdiss/2
This Article is brought to you for free and open access by the Mechanical & Materials Engineering, Department of at DigitalCommons@University of
Nebraska - Lincoln. It has been accepted for inclusion in Mechanical (and Materials) Engineering -- Dissertations, Theses, and Student Research by an
authorized administrator of DigitalCommons@University of Nebraska - Lincoln.
REAL-TIME VERTICAL TRACK DEFLECTION
MEASUREMENT SYSTEM
by
Sheng Lu
A DISSERTATION
Major: Engineering
(Mechanical Engineering)
Lincoln, Nebraska
December, 2008
REAL-TIME VERTICAL TRACK DEFLECTION MEASUREMENT SYSTEM
Track quality is a major factor in railroad safety, and one accepted indicator of
track quality is the vertical track deflection. Measuring track deflection from a moving
deflection from a moving railcar in real-time is described in detail. The system consists
of a loaded hopper with a camera/laser sensor system to detect the vertical deflection of
the rail relative to the wheel/rail contact point. Modeling and simulation of the system
is also presented along with the mathematical models which can be used to estimate track
modulus.
The measurement system has been used to conduct revenue service tests over
three thousand miles of track. A special validation test was also performed. The
results from these tests have shown that the system’s measurement is repeatable and
accurate; the system has notable ability to indicate track support problems.
I
ACKNOWLEDGEMENT
I would like to thank Dr. Shane Farritor, who has been a wonderful advisor and
mentor. Without his guidance, none of these will be possible. Thanks to Dr. Richard
Arnold who has also been a great teacher. I would also like to thank my colleagues Curt
Greisen, Haoliang Duan and Cory Hogan for the help and supports during the research.
Their supports and love have been the major motivation and inspiration of my life.
UPRR and BNSF for operational support and track access for testing.
II
Table of Contents
ACKNOWLEDGEMENTS…………………………………………...….……………… I
TABLE OF CONTENTS………………………………………………………………....II
LIST OF FIGURES………………………………………………………………...….....V
1 INTRODUCTION ...................................................................................1
2 BACKGROUND ......................................................................................5
2.1 Problem Definition ................................................................................................... 5
2.2 Beam on Elastic Foundation Model ......................................................................... 7
2.3 Nonlinear Cubic Model ............................................................................................ 9
2.4 Methods for Determining Track Modulus ............................................................. 15
2.4.1 Beam On Elastic Foundation (BOEF) Method ................................................ 16
2.4.2 Deflection Basin Method ................................................................................. 17
2.4.3 Heavy-Light Load Method............................................................................... 18
2.4.4 Track Modulus at Characteristic Load ............................................................. 20
2.5 Factors Influencing Track Modulus ....................................................................... 22
3 SYSTEM MODELING AND SIMULATION ....................................24
3.1 Measurement Principle and Methodology ............................................................. 24
3.2 The Relation between Yrel and Modulus (Winkler Model) .................................. 28
3.3 Effects of Track Geometry ..................................................................................... 33
3.4 Eliminating the Effects of Track Geometry Variation ........................................... 38
3.4.1 10-ft ECO (End-Chord Offset) Calculation from Rail Profile ......................... 38
3.4.2 Subtracting -ECO from Yrel ............................................................................ 39
3.5 Stress and Strain on the Rail .................................................................................. 41
3.6 Different Loads ...................................................................................................... 45
4 MEASUREMENT SYSTEM ................................................................47
4.1 Instrumentation ...................................................................................................... 47
4.1.1 Sensor System .................................................................................................. 48
4.1.2 GPS and Encoder ............................................................................................. 54
III
V
LIST OF FIGURES
1 INTRODUCTION
The economic constraints of both passenger and freight railroad traffic are
moving the railroad industry to higher-speed vehicles and higher axle loads. The heavy
axle loads and high speeds of modern freight trains produce high track stresses leading to
quicker deterioration of track condition. As a result, the need for track maintenance
increases. Fast and reliable methods are needed to identify and prioritize track in need
costs.
parameters. Some of the factors that influence track quality are track modulus, internal
rail defects, profile, cross-level, gage, and gage restraint. Monitoring these parameters
can improve safe train operation by identifying track locations that produce poor vehicle
Automated methods of inspection are available for most of the parameters that
are included in track geometry (Li et al, 2002). An example of an automated vehicle is
the Federal Railroad Administration’s (FRA) high-speed track geometry vehicle, referred
to as the T-18. The T-18 is capable of measuring rail head profile, gage restraint, and
ultrasonic and inductive test vehicle capable of 60 mph produced by Sperry (Wanek,
2004).
2
However, at the present time, there is no vehicle available to measure one of the
most important parameters – track modulus at normal track speeds in real-time. Track
modulus is defined as the coefficient of proportionality between the rail deflection and the
vertical contact pressure between the rail base and track foundation (Cai et al, 1994). In
other words, track modulus is the supporting force per unit length of rail per unit rail
deflection (Selig and Li, 1994). Track modulus is a single parameter that represents the
effects of all of the track components under the rail (Cai et al, 1994). These components
and maintenance requirements. Both low track modulus and large variations in track
modulus are undesirable. Low track modulus has been shown to cause differential
settlement that subsequently increases maintenance needs (Read et al, 1994; Ebersohn et
al, 1993). Large variations in track modulus, such as those often found near bridges and
crossings, have been shown to increase dynamic loading (Zarembski and Palese, 2003;
Davis et al, 2003). Increased dynamic loading reduces the life of the track components,
resulting in shorter maintenance cycles (Davis et al; 2003). It has been shown that
reducing variations in track modulus at grade (i.e. road) crossings leads to better track
performance and less track maintenance (Zarembski and Palese, 2003). It has also been
suggested that track with a high and consistent modulus will allow for higher train speeds
and therefore increase both performance and revenue (Heelis et al, 1999). Ride quality,
Previous localized field testing has shown that it is possible to measure areas of
low track modulus, variable track modulus, void deflection, variable total deflection, and
3
inconsistent rail deflection (Sussmann et al., 2001; Ebersohn and Selig, 1994). In the
past, such systems have been used to identify sections of track with poor performance.
These measurements have been useful. However, they are expensive and have only
been made over short distances (in the range of tens of meters). The ability to make
these measurements continuously over large sections of track is desirable (Ebersohn and
developed by the military and used in highway research (Carr, 1999). The systems use
a long rigid truss that rides on two unloaded wheels. This truss creates a straight line, or
cord, that is used as a reference for the measurement. A third wheel is then used to
apply a load at the midpoint of the cord (or truss) and the relative displacement between
the loaded wheel and the unloaded truss is measured. The truss must be long enough so
that the two endpoints are not affected by the load at the center of the truss. This
method requires two measurements, one with a light load, made with a similar truss, and
one with a heavy load, to distinguish between changes in geometry and changes in
the loaded wheel with respect to the unloaded wheel. Using this measurement, track
One vehicle, called the Track Loading Vehicle (TLV), uses this approach
(Thompson and Li, 2002). This vehicle is capable of measuring track modulus at speeds
up to 16.1 km/hr (10 mph). The TLV uses two cars, each with a center load bogie
capable of applying loads from 4.45 kN to 267 kN (1 to 60 kips). A light load (13.3 kN
or 3 kips) is applied by the first vehicle while a heavier load is applied by the second
4
vehicle. A laser-based system on each vehicle measures the deflections of the rail
caused by the center load bogies. The test procedure involves two passes over a section
of track – first applying a 44.5 kN (10 kip) load and then a 178 kN (40 kip) load
Although the TLV is operational, it does have limitations. First, tests are often
performed at speeds below 16.1 km/hr (10 mph) so it is difficult to test long sections of
track (hundreds of miles). Second, significant expense in both equipment and personnel
is required for operation. For these reasons the TLV has not yet been widely
implemented.
This thesis presents a method to measure vertical track deflection from a moving
railcar. These deflection measurements can then be used to estimate track modulus. The
system uses a non-contact vision sensor system to make displacement measurements with
respect to the wheel/rail contact point. The system is inexpensive and does not require
2 BACKGROUND
Figure 2-1 shows a free-body diagram of the rail under a one-wheel load. The rail
is considered as a continuously supported beam where x represents the distance along the
beam and w(x) represents the vertical beam deflection. The approximation that the rail
is continuously supported improves as the cross-tie spacing decreases and as the rail
bending stiffness increases. The applied load, P, is assumed to be a point load and
0+
creates a vertical load on the rail, q(x), where P = ∫ − q( x)dx . The supporting structure
0
supports the bottom of the rail with a reaction distributed force, p(x). In real track, the
supporting structure consists of tie plates, fasteners, cross-ties, ballast, etc. In this model
The difference in the vertical distributed force applied to the beam (q(x) - p(x))
d 4w
EI 4 + p( x) = q( x) Equation 2-1
dx
where:
conditions of the beam as well as the loading conditions. A free body diagram that shows
sections of the beam is shown in Figure 2-2. The figure shows that the concentrated
7
applied load P must be supported by the foundation reaction distributed force p(x) on
∞ P
∫0
p( x)dx =
2 Equation 2-2
In addition, symmetry and the stiffness of the beam demand that the slope of the
dw
=0 Equation 2-3
dx x=0
The above differential equation and boundary conditions can now be set up and
assumes the distributed supporting force of the track foundation is linearly proportional to
8
the vertical rail deflection (i.e. p(x)=uw(x) ). Here, the coefficient u is defined as track
d 4 w( x)
EI + uw( x) = q( x) Equation 2-4
dx 4
This model has been shown to be an effective method for determining track
modulus (Raymond, 1985; Meyer, 2002) and derivations can be found in (Kerr, 1976;
Boresi and Schmidt, 2003). The vertical deflection of the rail, w, as a function of
longitudinal distance along the rail x (referenced from the position of the applied load) is
given by:
Pβ − β x
w( x) = − e [cos( β x ) + sin( β x )] Equation 2-5
2u
where: 1
⎛ u ⎞4
β =⎜ ⎟ Equation 2-6
⎜ 4 EI ⎟
⎝ ⎠
When multiple loads are applied, the rail deflections caused by each of the loads
are superposed (assuming small vertical deflections) (Boresi and Schmidt, 2003).
A plot of the rail deflection given by the Winkler model over the length of a
four-axle coal hopper is shown in Figure 2-3. The deflection is shown relative to the
wheel/rail contact point for five different reasonable values of track modulus (6.89, 13.8,
20.7, 27.6, and 34.5 MPa corresponding to 1000, 2000, 3000, 4000, and 5000 psi
9
respectively). This example assumes 115 lb rail with an elastic modulus of 206.8 GPa
(30,000,000 psi) and an area moment of inertia of 2704 cm4 (64.97 in4).
Figure 2-3: Relative Rail Displacement for Different Loads under a Railcar
The limitations of the Winkler model are clear given the widely accepted
non-linearity of track structure. However, this model is often used because it does
provide a clear closed-form solution to the relationship between load and deflection in
track structure.
Railroad Track (1918) clearly showed that the vertical rail deflections were not linearly
10
Zarembski and Choros (1980) also clearly documented this nonlinear response.
Figure 2-4 shows the experimental results of the track responses under various
applied loads. Rail deflection was measured at given locations using linear variable
differential transformers (LVDTs) as a short, slow moving train of known weight passed.
The axles of the train carried 150,600 N (33850 lbf), 60,230 N (13540 lbf), and 30650 N
(6890 lbf). The LVDTs were mounted to steel rods (about 1m (3ft)) driven into the
subgrade to provide a stable reference. The LVDTs then measured the vertical motion of
the flange relative to the steel rod. The results from four LVDTs are shown in Figure
2-4. Here the LVDTs were placed at 1m (3ft) increments along the track (x=1m, 2m,
3m, 4m).
These measurements, along with many others dating back to the Talbot Report
(ASCE-AREA Special Committee, 1918) clearly indicate that the vertical rail deflections
are not linearly proportional to the wheel loads. It is also important to note that the
“degree” of non-linearity can change dramatically over very short distances along the
track. Note the deflection of the track under the 30650 N (6890 lbf) load increased
about 60% over a distance of one meter. This non-linearity and variability greatly
complicates determining and modeling track structure. Several methods have been
developed for calculating modulus with each method assuming a different definition of
Here, a new model is proposed that represents the relationship between vertical
rail deflection and the distributed rail support force as a cubic polynomial. To define
this relationship the experimental results of (Zarembski and Choros, 1980) are plotted in
Figure 2-5 along with a cubic polynomial curve fit. The polynomial fits the
Using a cubic polynomial has several advantages. First, it clearly captures the
behavior of real track in that it provides for low stiffness at low loads and higher stiffness
at higher loads. Also, negative displacement of the track (track lift) does not result in
significant downward forces being applied to the rail. Unlike the previous models, the
cubic polynomial closely represents the fact that if the track rises slightly, the ballast does
Figure 2-5: Experimental Data (Zarembski and Choros, 1980) and Curve Fitting
Here, the supporting distributed load p(x) has a cubic relationship between p(x)
and w(x):
p ( x) = u1 w( x) + u 3 w 3 ( x) Equation 2-7
Note that symmetry about the applied load requires the second order term to
vanish. Substitution into the BOEF model gives the following differential equation:
d 4w
EI 4 + u1 w + u 3 w 3 = q Equation 2-8
dx
method can be found in McVey (2006). However, a numerical solution for this
⎡ w( x) ⎤
⎢ ⎥
∂ w′( x) ⎥
w′ = ⎢ = func( w, x) Equation 2-9
∂x ⎢ w′′( x) ⎥
⎢ ⎥
⎣ w′′′( x)⎦
⎡ w( x) ⎤ ⎡ w′( x) ⎤
⎢ ⎥ ⎢ w′′( x) ⎥
∂ ⎢ w′( x ) ⎥ ⎢ ⎥
=⎢ w′′′( x ) ⎥ Equation 2-10
∂x ⎢ w′′( x) ⎥ ⎢
⎢ ⎥ − 1 u w( x) + u w 3 ( x) ⎥
( )
⎣ w′′
′ ( x ) ⎦ ⎢⎣ EI 1 3 ⎥
⎦
As the name implies, the fourth order BVP described above requires the values of
w( x) | x =∞ = 0
w( x) | x = −∞ = 0
w′( x) | x =0 = 0 Equation 2-11
w( x) | x =0 = wo
Now, since the BVP can have more than one correct solution, an initial “guess”
for the last boundary condition is needed in order for the solution to converge to an
expected solution. In this case, the initial guess is provided by the Winkler model
Pβ ⎛ u ⎞4
w(0) = wo = − where : β = ⎜ 3 ⎟ Equation 2-12
2u 3 ⎜ 4 EI ⎟
⎝ ⎠
The mechanics of this problem also require that the solution be found subject to
∫ (u w + u w )dx = 2
∞
3 P
0
1 3 Equation 2-13
The unique solution that satisfies each of these constraints will give the rail
deflection. Many numerical techniques can be used to solve this well-posed BVP. In
this work the “bvp4c” function in Matlab (Kierzenka J. and Shampine L. F., 2001) was
used.
While the cubic model closely represents the deflection test data over the entire
range of wheel loads, the accuracy of the linear analysis depends on the magnitude of the
test load.
Since the cubic spring is initially softer than the one in the Winkler model, the rail
must deflect more before the base can pick up the full load. This means that the
distributed load will be spread over a wider span than for the linear model as shown in
Figure 2-6. Meanwhile, the deflection at the contact point for the cubic model is slightly
larger than the one for the Winkler model when the applied load is relatively large.
Although the cubic model represent the real track response more accurately, it is
not easy to apply. In other words, for a given load and known maximum deflection, it is
not possible to depict the actual track response. However, modulus can be simply
calculated from the applied load and maximum deflection using Winkler model.
15
Therefore, the application of cubic model is limited and the Winkler model is widely
Many methods and models have been developed and used to determine track
modulus. The methods include the Beam on Elastic Foundation method, Deflection
Basin method. In these methods, a static load must be applied to the rail, and rail
deflection measurements must be made before and after the load is applied. Focused on
characteristic load.
16
location is to simply measure the vertical deflection at the point of an applied known
load, P. This produces the measurement of the track stiffness, k, which is the ratio
between applied load and maximum deflection under the wheel, but this measurement
can be related to track modulus, u, using the BOEF model and assuming that the
relationship between rail supporting load p(x) and deflection w(x) is linear and elastic (i.e.
p(x)=uw(x) as in Selig and Li, 1994; Cai et al, 1994). These assumptions lead to the
1 4
1 ⎛ 1 ⎞3 ⎛ P ⎞ 3
u = ⎜ ⎟ ⎜⎜ ⎟⎟ Equation 2-14
4 ⎝ E1 ⎠ ⎝ w0 ⎠
This method only requires a single measurement and it has also been suggested to
be the best method for field measurement of track modulus (Zarembski and Choros,
1980). However, as shown in Figure 2-4, it is clear that this linear approximation has
large error for real track. Using a single applied load and a single measurement of
deflection does not capture the changes in the load-deflection curve present in real track.
17
The Deflection Basin Method uses the vertical equilibrium of the loaded rail and
approach, rail deflection caused by point loads is measured at several (ideally infinite)
locations along the rail and the entire deflected “area” calculated. The deflection basin
Using the concept of vertical equilibrium, the applied load can be shown to be
proportional to the integral of the rail deflection or the deflection basin area (Selig and Li,
1994; Cai et al, 1994). For a single applied load, the equation is:
Equation 2-15
This method requires several deflection measurements over the section of track
that supports the load(s), which makes it very time consuming (Selig and Li, 1994).
When using this method, the non-linearity caused by slack in the rail should be removed
by using a light load for the base measurements and a heavy load as deflected
measurements. This method is not recommended because it is more time consuming and
Many have represented the load/defection curve as piece-wise linear with a low
stiffness at low loads and a much higher stiffness at higher loads (Kerr and Shenton,
1986). This is seen in real track as slack in the rail and can be caused by many things
such as the ties not contacting the ballast. As the rail is loaded, a low stiffness is
experienced until the tie contacts the ballast, resulting in a higher stiffness. This leads to
a measurement of track stiffness using two loads as shown in Figure 2-8, that are ideally
both in the high stiffness range (e.g. slack is removed) (Ebersohn and Selig, 1994; Read
The Equation 2-16 demonstrated how to calculate track stiffness by using the two
different loads (seating load and full load). This calculated track stiffness can then be
P2 − P1
k= Equation 2-16
w2 − w1
two loads to track modulus. The clear difficulty with this measurement is that the real
load/deflection relationship is not piecewise linear and the resulting stiffness varies with
20
the selection of the two loads, P1 and P2. It is also clear that any two choices of loads
supporting distributed force relative to the variation in deflection near the characteristic
load for a given track (Lu et al., 2008). This characteristic load might be defined as the
nominal axle load for a given freight line (e.g. 160kN or 286,000/8=36kips). This can
∂p
u* = Equation 2-17
∂w
P*
To evaluate the derivative at the characteristic load, the load must again be
transformed to a distributed load. This can be done with the linear assumptions as
described previously (the Winkler model). This definition of track modulus has been
Finally, in the nonlinear cubic model described previously, the track modulus at
u* =
∂p
=
(
∂ u1 w + u 3 w 3 ) = u1 + 3u 3 w 2
∂w ∂w P* Equation 2-18
P* P*
Figure 2-9. In this figure, the load-deflection curve is plotted from the experimental
It is clear that for single data points at higher loads the Winkler model will always
underestimate the actual track modulus (Figure 2-9). The Winkler model will also poorly
represent changes in deflection with respect to changes in load at these higher values.
22
several components that all contribute to track modulus, including the rail, subgrade,
ballast, subballast, ties, and fasteners. The rail directly supports the train wheels and is
supported on a tie pad and held in place with fasteners to ties. The crossties rest on a
layer of rock ballast and subballast used to provide drainage. The soil below the
The subgrade resilient modulus and subgrade thickness have the strongest
influence on track modulus. These parameters depend upon the physical state of the soil,
the stress state of the soil, and the soil type (Li and Selig, 1994; Selig and Li, 1994).
Track modulus increases with increasing subgrade resilient modulus, and decreases with
increasing subgrade layer thickness (Selig and Li, 1994). Ballast layer thickness and
23
fastener stiffness are the next most important factors (Selig and Li, 1994; Li and Selig,
1998). Increasing the thickness of the ballast layer and/or increasing fastener stiffness
will increase track modulus (Stewart, 1985; Selig and Li, 1994). This effect is caused
by the load being spread over a larger area. The system presented in this dissertation
measures the net effective track modulus that includes all of these factors.
24
Based on Winkler model, the relation between system’s measurement and track modulus
will be analyzed so that modulus can be estimated from the system’s measurement.
Simulations will show that track geometry variations will affect system’s measurement.
beam rigidly mounted on the side frame of the hopper car extends a few feet away from
the wheels. A sensor head which includes a laser/camera system is attached to the end
of the beam. The sensor system has two line lasers and a camera as shown in Figure
3-2. The line lasers intersect the rail surface at an acute angle to create curves across the
surface of the rail. Using line lasers allows the system to compensate for lateral
movement of the rail relative to the camera and for changes in rail profile. The camera
captures images showing two curved laser lines on the rail surface and the distance
between the lines d is obtained by an image processing program. This distance d is then
converted to the distance between the beam and the rail surface under the camera h. A
Figure 3-1 illustrates that the fixed distance between the wheel/rail contact point
and the sensor, H, relates the relative rail displacement, Yrel, to the measured height of
the sensor above the rail surface, h. Here ycamera is the deflection of the rail at the
location underneath the camera/lasers and ywheel is the deflection of the rail at the
wheel/rail contact point. The deflections are negative in value because the positive axis
is defined upwards.
The sensor system measures the distance between the camera image plane and the
rail surface, h. Then, the displacement of the rail surface with respect to the wheel/rail
contact plane, Yrel (Figure 3-1) can be found. The displacement, Yrel, can then be
related to the absolute rail deflection of the wheel/rail contact point (with respect to the
unloaded rail), ywheel (Figure 3-1) by using the Winkler model or the Cubic model.
The mathematical model relates the measured distance between the laser lines to
the track modulus. The rail deflection measured by the sensor is dependent on the four
wheel loads. The sensor will measure the relative rail displacement between the rail and
wheel/rail contact point. This measurement can be made if it is assumed that the
instrument beam, truck, and wheels are rigid. With this assumption, the distance
between the sensor system and wheel/rail contact point can be assumed constant (H is
constant). This is a reasonable assumption as the instrument beam, side frame, and
wheels are all massive, nearly rigid elements and these elements do not include the
suspension of the railcar. Rotation of the side frame could cause this distance (H) to
change, but this rotation has been experimentally shown to be insignificant (Norman,
2004).
27
The sensor reading, which is the measured distance between the lasers, is
geometrically related to the height of the sensor above the rail. The sensor in effect
measures its height above the rail by measuring the distance between the lasers. As the
sensor moves closer or farther from the rail surface, the distance between the lasers
d = l1 + l 2 Equation 3-3
28
where L1 and L2 are the horizontal displacement of the lasers from the camera, θ1
and θ2 are the angles between the lasers and the horizontal, l1 and l2 are the horizontal
distance between the center of the camera and laser/rail intersection, h is the vertical
distance between the camera/lasers and the surface of the rail, and d is the distance
between the lasers on the rail surface. Solving these equations results in:
h h
d= + − (L1 + L 2 )
tan θ 1 tan θ 2 Equation 3-4
Combining Equation 3-1 to Equation 3-4, a sensor reading can be calculated for a
Combining this information with the track model (e.g. Winkler model) the sensor
reading d can be related to the track modulus u. On softer track the rail will rise relative
to the wheel/rail contact point and the laser lines as observed by the camera will move
closer together. Conversely, the distance between the lasers will be large for stiffer
track.
Figure 3-4 shows the rail deflection from multiple loaded axles.
29
In Figure 3-4, assuming the loads of wheel one (the left one) and wheel two (the
right one) are the same (P), w1 is the deflection of the rail attributed to wheel one and w2
is the deflection of the rail attributed to wheel two. The total rail deflection is the
where: 1
⎛ u (c ) ⎞ 4
β1 = ⎜ ⎟
⎝ 4 EI ⎠
Pβ 2
and w2 (x ) = −
− β ⋅ x − c −b
e 2 [cos(β 2 x − c − b ) + sin(β 2 x − c − b )] Equation 3-6
2u (c + b)
⎛ u (c + b ) ⎞ 4
where: β2 = ⎜ ⎟
⎝ 4 EI ⎠
The total deflection of the rail is the superposition of the two expressions:
wtotal ( x ) = w1 ( x ) + w2 ( x )
Then the total deflection at the wheel-rail contact point of wheel one is:
Pβ1 Pβ 2
wtotal ( x ) x=c = w1 (c) + w2 (c) = − − e −β 2 ⋅b [cos(β 2b ) + sin (β 2b )]
2u (c) 2u (c + b) Equation 3-7
and the deflection of the rail under the sensor head which is four feet away from
wcamera ( x ) x=c−a = w1 (c − a) + w2 (c − a)
Pβ1 − β 2 ⋅a
=− e [cos(β 2 a ) + sin (β 2 a )] − Pβ 2 e −β2 ⋅( a+b) [cos(β 2 (a + b)) + sin(β 2 (a + b) )]
2u (c) 2u (c + b)
Equation 3-8
Then,
31
⎛ u ⎞4 Equation 3-9
β1 = β 2 = β = ⎜ ⎟
⎝ 4 EI ⎠
Therefore,
The result of Equation 3-10 is shown in Figure 3-5 where modulus is plotted as a
function of Yrel using a look-up table. In this model, 132 RE rail was chosen (I=87.9
in4); E is set to be 30,000,000 psi; the load on each wheel is 32500 lb; and the distance
between the two axles is six feet. The typical values of modulus for various main-line
track conditions (Kerr, 2003) are listed in Table 3-1 along with the corresponding Yrel
value.
32
Figure 3-5: Re
elation betw
ween Yrel and
a Moduluss (Winkler model)
m
Wo
ood-tie trackk, after tampping 1000 0.2
The relation
r betw
ween the raail deflections at the wheel-rail
w coontact pointt and
reelative deflection (Yrel) is shown inn Figure 3-6. This non-liinear relation is based on
o the
W
Winkler mod
del and supeerposition. For
F relativelyy small deflections (0~00.2 inch), Yrel
Y is
abbout 60% off the total deflection (defflection at thhe wheel-Raiil contact pooint).
33
Figure 3-6: Relation between the Total Deflection and Yrel (Winkler model)
The measurement of relative deflection (Yrel) uses the wheel/rail contact line as a
reference as shown in Figure 3-1. The measurement assumes the unloaded rail is
perfectly straight. However, if the rail has a significant pre-existing geometry variation
over a length comparable to the four feet between the measurement point and wheel/rail
contact point, the system’s measurement will be affected. Large vertical “dips” that
The relationship between modulus and geometry is complex. In real track, areas
of geometry variations often correlate with areas of modulus variations and vice versa.
34
A case study was chosen to investigate this relationship. Figure 3-7 shows a section of
track where there is a significant geometry variation and a significant modulus variation.
Measurements at the site indicated that the unloaded rail drops by 0.5” over a length of
about 200”. A geometry variation of this shape is significant and easily visible. The
light colored ballast seen at this site also suggests tie “pumping” and low track stiffness.
Figure 3-7: An Example Site with Both Significant Unloaded Geometry and Low
Track Stiffness
Relative rail deflection (Yrel) from the measurement system at this site is 1.1”.
Simulations, based on the Winkler model, have been conducted to quantify the effects of
track has both geometry and modulus variations. The unloaded track geometry is
described in the top subplot in Figure 3-8. It has a maximum “dip” of 0.5” in depth and
In the simulation it was assumed that the modulus over this section of track varies
as a cubic curve with a minimum at the center of the geometry variation, (the middle
subplot in Figure 3-8). The bottom subplot in Figure 3-8 shows the Yrel measurement
for this site. Here, the “total” measurement replicates the value of 1.1” as it did in the
real measurement when the measurement system passed over the location shown in
Figure 3-7. To create this value it was found that the modulus for this location had to
drop from 3000 psi (assumed as a reasonable value for “normal” track) to 800 psi in
addition to the unloaded geometry profile. This measurement is then broken into two
“elements” – a modulus element and a geometry element. The geometry element is the
measurement that would be made if the same unloaded geometry (top subplot) existed on
a perfectly rigid track. The modulus element in the remaining portion is the total
It can be seen that in this case the contribution of geometry (the geometry element)
is about equal to the contribution of modulus (the modulus element). However, both are
Now, the simulation can be used to study the relative contribution of geometry
and modulus as the length of the geometry variation (L) and the depth of the geometry (d)
Figure 3-9: Effects of Unloaded Geometry of Various Length (L) and Depth (d)
It can be seen in Figure 3-9 that there is a complex relationship between modulus
and geometry and that the effects vary depending on the length (L) and depth (d) of the
geometry variation. The three-dimensional plot on the left shows the relative size of the
geometry element and the modulus element. It can be seen that there is a curve where
The two graphs on the right show two cross sections of these surfaces. The top
right graph shows the effects of variations in the length of the geometry defect (L) at a
constant depth (d=0.5”). The bottom right graph shows the effects of variations in the
Again, the conclusions that can be drawn from these simulations are that (1) only
large vertical geometry defects occurring over a short distance significantly contribute to
the Yrel measurement, and (2) both geometry and modulus problems are generally
As seen in the simulation and analysis in the previous section, track geometry can
greatly affect the output of the system in terms of measuring rail deflection. In order to
eliminate the effects of track geometry variation and get the real rail deflection results,
rail profile data from track geometry measurement vehicles was introduced into the
system.
alignment of the track, smoothness and the cross-level of the two rails, etc. The space
curve channel of the geometry car uses multiple high-precision accelerometers onboard
As shown in Figure 3-10, P(x) is the rail profile from the space curve channel of
the track geometry data. The longitudinal position of the track is defined as x (units of
39
foot). ECO(x) is the 10-ft end-chord offset when the leading wheel’s longitudinal
position is x. (ECO is positive if the string is above the rail.) Here, the 6 ft and 4 ft were
chosen because they are the distance between the two wheel axles and the distance from
P( x − 6) − P( x) 6
= Equation 3-11
P( x) − [ P( x + 4) + ECO( x)] 4
Therefore,
2
ECO ( x ) = ⋅ [ P ( x ) − P ( x − 6)] + P ( x ) − P ( x + 4) Equation 3-12
3
In Figure 3-11, P(x) is the vertical position of the inboard wheel-rail contact point
when the inboard wheel’s longitudinal position is x. P(x-6) is the vertical position of the
inboard wheel-rail contact point when the inboard wheel’s longitudinal position is x-6.
If it is assumed the two wheels always have the same space curve, then P(x-6) is the
vertical position of the trailing wheel-rail contact point when the inboard wheel’s
longitudinal position is x. P4(x) is the rail’s vertical position four feet ahead of the
Moving
De
P ( x − 6) − P ( x) 6
=
P ( x) − A( x) 4
So, 1
A( x ) = ⋅ [5 P ( x ) − 2 P ( x − 6)] Equation 3-13
3
Therefore, 1
P 4( x ) = A( x ) + Yrel ( x ) = ⋅ [5 P ( x ) − 2 P ( x − 6)] + Yrel ( x ) Equation 3-14
3
The vertical position of the rail at location x+4 may be determined when the
inboard axle is at location x. The vertical rail position at the same location may be
determined again when the inboard axle is actually at location x+4. Then, the difference
“Deflection” = P4(x)-P(x+4)
1
= ⋅ [5 P ( x ) − 2 P ( x − 6)] + Yrel ( x ) − P ( x + 4)
3
2
= ⋅ [ P ( x ) − P ( x − 6)] + P ( x ) − P ( x + 4) + Yrel ( x )
3 Equation 3-15
= ECO ( x ) + Yrel ( x )
It should be noted that the so-called “Deflection” calculated above is not the
maximum deflection of the rail attributed to the loads. Rather, it is a relative deflection
of the rail from partially loaded (when the axle is four feet away) to fully loaded (when
Therefore, Yrel can be accounted for by two parts. One part is ECO, attributed to
the track geometry variations, and the other part is the deflection related to track modulus
variations.
One potential output from the measurement system is that rail stress and strain
can be estimated from system’s measurement. Here, some primary studies are
M ( x) z
σ x ( x, z ) = Equation 3-17
I
σ x ( x, z ) M ( x) z
ε x ( x, z ) = = Equation 3-18
E E
EI
For tw
wo axles, suuperposition was applied to obtain the rail respponse from each
raail; 32500 lb
b load on eaach axle) annd by combiining Equatiion 3-10, Eqquation 3-166 and
E
Equation 3-18. This analyysis is basedd on the Winnkler model with the asssumption thaat the
Fig
gure 3-12: Relation be
etween Rail Bending Moment
M and
d Yrel
43
plotted in Fig
gure 3-13 andd Figure 3-14 respectiveely.
Allowable
A Beending Stresss (AREA Manual
M (19966))
Figure 3-1
13: Relation
n between Rail
R Bendin
ng Stress (R
RE132, botttom) and Yrel
Y
44
σ σN
67y 8 67 8
70,000 − 20,000
σ= = 25,000lb / in 2
1{
.2 × 1{
.25 × 1{.15
1 × 1{
.15
La
ateral _ Rail _ Bendiing Track _ Condiition Rail _ Wear & Corrosion Unbaalanced _ elevation
The denominator
d consists of four
f reductioon coefficiennts. Note thaat the inclusion of
cooefficient sim
mplifies the analysis byy allowing thhe use of thee moment off inertia of a new
thhe analysis.
45
Therefore, when Yrel is larger than 0.6”, the stress at the bottom of the rail will
exceed the allowable bending stress. However, it should be noted that Figure 3-13 is
based on the Winkler model and simple superposition which are not very suitable for
combined with geometry effects, and the complexity of the track (joints, switches,
bridges, etc.) will also contribute to large values of Yrel. All these complex factors
were not considered in the analysis in Figure 3-13, so it will be difficult to evaluate
stresses on the rail just based on Yrel measurements, especially when large deflections
occur.
From Equation 2-5, it can be observed that rail deflections are linearly
proportional to the applied loads given a constant track modulus. Based on the Winkler
model and superposition, the relations between Yrel and modulus under various loads are
illustrated in Figure 3-5. The values of load shown here are the loads on each axle.
Two axles as in Figure 3-4 were taken into consideration in this model. This figure
shows that given a certain modulus, the Yrel measurements increase linearly as the loads
considered when designing the measurement system. Clearly, heavier weights will
4 MEASUREMENT SYSTEM
described in detail. These components include sensors, GPS and encoder, power supply
and management system, remote supervision, data downloading system, and a database
for testing results. The methods and procedures of image processing and calibration
will be illustrated. The potential errors in the measurements will also be analyzed.
4.1 Instrumentation
car is filled with sand such that the total weight of the car and sand is about 260,000 lb.
As shown in Figure 4-1, the system includes two rigid beams attached to the side frames
(structural members that connect the axles of a truck) of the hopper car, two sensor heads
holding cameras and lasers at the ends of the rigid beams, a solar panel array, a GPS
(Global Positioning System) antenna on the top of the car and an enclosed box containing
two computers, a data acquisition (DAQ) boards and a GPS receiver for on-board image
The sensor head is attached to highly rigid steel beams that are fastened to the
side frames as shown in Figure 4-2. The beams are bolted to the side frames without
Side Frame
Rigid Beam
These beams suspend the sensor heads out in front of the wheel/rail contact point
and over the top of the rail. Investigations into rigidity have shown that the beams are
sufficiently rigid to be considered stationary relative to the side frames (Norman, 2004).
Therefore, the measurement will not be affected by the bending or movement of the
Rigid Beam
Sensor Head
A sensor head holds a digital vision system and two line lasers as shown in Figure
3-2. The camera and line lasers are rigidly attached to an enclosed sensor assembly
which is mounted at the end of the rigid beam on the side frame. These lasers are
projected at an acute angle (~40˚). They cross and create curves (because of the curved
The assembly of the sensor head is shown in Figure 4-4. The two laser holders are
adjustable to ensure that the lasers project at an appropriate angle. The height of the
camera is also adjustable. This ensures that well-proportioned images will be captured.
51
Caamera Positiion
L
Laser
Lasser
Ambient light, sppecifically suunlight, ruinns the image of the laserr lines acrosss the
raail and makes it imposssible for thee image proccessing proggram to disttinguish the laser
liight aluminu
um frame bolted
b to thee bottom off the rigid beam. Rubbber landscaaping
m
material is attached
a alonng the bottoom edge to add furtherr shading. This material is
fllexible, mak
king it resistaant to rocks and debris, but is also continuously
c y solid, makiing it
reesistant to wind
w effects.. As shownn in Figure 4-5, even inn very sunnny conditionss, the
shhroud provid
des adequatee shading forr the lasers and
a camera image.
52
Shrouds
beams interseecting the toop of the raill. Images arre captured and
a processeed in real tim
me to
Figure 4-6:
4 Typical Test Image
e
53
This measurement is geometrically related to the height of the sensor above the
rail (h in Figure 3-1). As the sensor moves closer or farther from the rail surface the
distance between the laser lines changes. Using a calibration technique which will be
described in detail in later sections, Yrel can be calculated from the distances between the
laser lines in the images. As the system’s output, Yrel is the relative displacement
between the rail surface under the camera and the wheel/rail contact line. Yrel can then
be mathematically related to track stiffness and modulus (Lu et al, 2007; McVey, 2005;
Norman, 2004).
on board. These computers are installed in an enclosed box as shown in Figure 4-7. A
GPS receiver and two DAQ boards are also installed in this box. All of the cables and
wiring for the equipments are run through flexible conduits. This sealed box protects
The measurement system includes a GPS receiver. The latitude and longitude
are reported in real time and recorded in the output data. The GPS data are used to get
The GPS receiver used in the system is a NovAtel OEM4 model which is capable
of absolute single-point positioning accuracies of 1.8 meters circular error probable (CEP)
accuracy is really only an estimation, and may vary widely depending on numerous GPS
system biases, environmental conditions, as well as the GPS receiver design and
engineering quality.
55
Numerous factors will influence the single-point position accuracies of any GPS
receiving system. As the following list will show, a receiver’s performance can vary
widely when under the influences of these combined system and environmental biases:
propagation delays.
3. Ephemeris Errors. Some degree of error always exists between the broadcast
ephemeris’ predicted satellite position and the actual orbit position of the
satellites.
4. Satellite Clock Errors. Some degree of error also exists between the actual
satellite clock time and the clock time predicted by the broadcast data.
In general, all these factors combined may cause an error of up to 60 feet. GPS
errors may cause problems when data from multiple tests are compared in trending
analysis, because data from different tests may be out of alignment. As a result, data
In order to obtain more accurate and reliable GPS readings, a more sophisticated
differential GPS system was proposed to upgrade the current GPS system. Some
Due to the GPS error, there may be some stretches in the data in terms of
mileposts. An encoder has been introduced into the system to eliminate this stretching
Two rugged computers are used to process images in real time and save the data.
In order to reduce power consumption when the testing vehicle is not moving, the whole
measurement system enters a “sleeping” mode in which the lasers and cameras are turned
off and the PCs remain in standby mode. The total power consumption is about 50
watts when the system is in full-on testing mode and 10 watts in sleeping mode.
automated testing possible. As shown in Figure 4-8, four solar panels installed on the
top of the testing vehicle provide the power source for the measurement system. The
solar panels are rated at 400 watts maximum. A battery pool consisting of eight
deep-cycle marine batteries is used as energy storage and as a buffer to provide stable and
consistent power to the system during both day and night. The eight batteries have a
total capacity of 400 Amp-hours which can supply 4 days of continuous testing or 16
days of “sleep” mode without inputs from the solar panels. The batteries are enclosed in
the black box as shown in Figure 4-8 along with a solar panel voltage regulator which
manages the battery recharge process and prevents the batteries from being overcharged.
Inside of the battery box, two watt meters were also installed to provide information
about the measurement system’s energy usage and energy input from the solar panels.
57
The power supply system has proved to be sufficient and reliable during
automated tests in March and April of 2008. In these tests, the batteries were returned
The voltage across the batteries, the current input from the solar panels and the
ambient temperature are monitored by the computer in the white box shown in Figure
4-8. This information can be recorded and sent back to a server on the internet through
monitored.
The data which were logged and uploaded in real time from the computer on
board to a remote server through the internet during the test in April of 2008 are
58
displayed in Figure
F 4-9. As shownn by the currrent and volttage traces in
i this figuree, the
batteries weree charged duuring the dayytime. Thee output of thhe solar paneels was meassured
ass high as 15
50 watts. T highest output
The o from the solar paanels usuallyy occurred in
i the
m
morning to co
ompensate for
f the powerr consumption during thhe nights. While
W in sleeeping
m
mode, the battteries can be
b fully chargged before noon
n and thee voltage of the batteriess will
4.1.5 Testin
ng Results Database
D
The teesting vehiccle has been tested on thhousands off miles of trrack. As a result,
thhe database and to deveelop plots. A screenshot from thiss website is shown in Figure
F
In the typical image captured during the test shown in Figure 4-6, the laser lines
are easily identifiable on the top of the rail. The image processing program scans
through all the pixels on each horizontal line of the image and finds the peaks of the pixel
intensities which represent the locations of the laser lines. Subsequently, the laser lines
can be reproduced as shown in Figure 4-12. After scanning through the image and
obtaining the valid points on each laser line, some points may be considered as valid but
out of the curve due to reflections on the rail surface or other noise captured in the images
as shown in Figure 4-13. These outliers are filtered out and cubic curves are applied to
The current image processing method for the measurement system has some
limitations when the system works under certain extreme conditions and the images
captured are not ideal. The image in Figure 4-6 is a typical one captured by the system.
In this image, the laser curves only appeared on the top of the rail and they are clear and
easy to identify. However, images like the one in Figure 4-14 are not ideal to process.
In this image, the lasers lines projected on the bottom of the rail and tie were captured by
the camera and bright reflections appear on top of the rail. These effects may cause the
In ord
der to avoidd false alertts caused by incorrect image proccessing, a neural
n
network is in
ntroduced innto the systeem to verifyy the imagee processingg. Based onn the
prrocessing. The prograam scans thrrough all thhe pixels onn each horizzontal line inn the
im
mage and fiinds the peaaks of the intensity whhich represennts the locaation of the laser
cuurves on thee top of the rail. Howeever, if theree is no obvioous peak onn some horizzontal
sccanning thro
ough all of the
t horizonttal lines, onnly the validd points com
mpose the cuurves.
T
Therefore, the number off valid pointts on each laaser curve inndicates how
w well the cuurves
w interpreted.
were
63
Another factor consists of determining the number of outliers. There may be some
points valid but out of the curve. The program will filter out these outliers. Better
The standard deviation of the fitting curve is a third consideration in the image
processing. After filtering out all the outliers, the program will fit remaining valid
points to a cubic curve and calculate the standard deviation of the fitting. Smaller
The position of the center lines between the two lasers presents yet another issue
for image processing, because in general the two laser curves should be symmetric along
Finally, the change in rail position from the last two images also plays an
important role in the image processing. When the system passes by turnouts, there will
be changes in rail and occasionally multiple parallel rails are captured in the image.
When the lasers are projected onto multiple rails, it is important to pick the correct rail.
Therefore, the position of the rail in the images should not drift dramatically.
The above five parameters were used as inputs to construct a neural network as
shown in Figure 4-15. Two units are used in the hidden layer. About 50 images were
processed and the five parameters resulting from those images were saved as training
samples. Each of these images were then reviewed and assigned to an output based on
whether the program processed the image correctly. The network was then trained
The trained neural network was then implemented into the image processing
program. Each image is verified based on the output from the network. A threshold of
0.6 was used to decide if the image was processed correctly. Figure 4-16 shows the
results output from the program without using neural networks. A number of outliers
The results from the program with the neural network are shown in Figure 4-17.
After each image was processed, the neural network was used to verify if the processing
was successful. If the output from the neural network indicated the image was
processed incorrectly, the result from current processing is discarded and the reading
from the last image is saved. As shown in Figure 4-17, all of the outliers were
eliminated which shows that the neural network works well to identify the incorrect
image processing.
As shown in Figure 3-1, Yrel is the relative displacement between the rail surface
under the sensor and the wheel/rail contact line. Yrel is the measurement system’s
output.
The system processes images in real-time and obtains the number of pixels
between the two laser lines in the images. This number of pixels is the system’s direct
66
measurement. In order to convert this number of pixels into the value of Yrel in inches,
The purpose of the calibration procedure is to obtain the relation between the
system’s direct measurement (n, the number of pixels between the laser lines in images)
Figure 4-18 shows how to convert the number of pixels into the actual distance in
inches. An image of a ruler on top of the rail was captured. The six inch ruler
corresponds to 208 pixels in the captured image. Therefore, one inch in the image
corresponds to 208/6=34.67 pixels (i.e. if the number of pixels between the two lines is n,
Now the problem consisted of finding the relation between d and Yrel.
67
If at one moment, Yrel=Yrel* and d=d* are known, and the ratio of ΔYrel and Δd,
ΔYrel
(R= ) is also known, then the relationship between ΔYrel and Δd may be
Δd
determined as follows:
ΔYrel=Yrel-Yrel*
Δd=d-d*
Figure 4-19 is the diagram of the sensor head and the rail.
The vertical distance from the laser heads to the top of the rail is 13”;
The distance between the two laser lines in the images (d) is 3.768” (131pixels);
ΔYrel 13
R= = = 0.40778
Δd 28 .112 + 3.768
68
1
Therefore, one pixel in the image represents ⋅ 0.40778 = 0.01176 inch of
34 .67
ΔYrel.
A special plate is made for this calibration procedure. The device consists of
seven steps as shown in Figure 4-20 and Figure 4-21. The lowest step is 1/4 inch high
while the other six steps are 1/8” high. When doing the calibration, this plate is placed
on top of the rail under the camera, and the two laser lines project onto the plate.
Figure 4-20:
4 Calibrration Plate on the Top
p of the Raiil
The image in Figure 4-22 is then processed. The distances between the laser
lines on each step of the plate were obtained and plotted in Figure 4-23 with respect to
the step’s height above the rail. As shown in Figure 4-23, a linear line fits the data
points very well (R2=0.9988). From the line fit, one pixel in the image represents
1
= 0.01178 inch of ΔYrel.
84.857
140
120
100
80
Pixes
60
40
y = -84.857x + 139.04
2
R = 0.9988
20
0
0 0.2 0.4 0.6 0.8 1 1.2
Distance above rail(inch)
This result verifies the calibration results very well. Based on the geometric
relation, one pixel in the images was calculated to represent 0.01176 inch of Yrel. The
This difference may be attributed to many factors including the limited resolution
of the captured images, the wide laser lines in the images, measurement error during the
calibrations, etc. Some of these factors will be discussed in detail in section 4.4.
71
After calculating the ratio of Δd and ΔYrel, all that is needed is to find a reference
point where both the relative deflection (Yrel) and the distance between the laser lines (d)
may be determined.
Assuming that a section of track is perfectly uniform and the modulus over the
section is constant, the deflection of the rail under the axles will be identical over the
entire section. If a train moves over this section at a very slow speed, the rail deflection
at one fixed point as a function of time can be mapped from the time domain into the
space domain so that the static rail profile under the axles can be obtained. The
dynamic load factor can be ignored since the train speed is slow.
Figure 4-24 demonstrates the setup for capturing the rail deflection with a video
camera. A sticker is placed on the side of the rail head as a marker while a video
camera away from the track captures this sticker in its view. Another marker is placed
The measurement vehicle is pulled at a constant speed and passes by the video
camera. Meanwhile, the video camera captures and saves the video for post-processing.
An image from the captured video is demonstrated in Figure 4-25. As the wheels of the
measurement vehicle move closer to the position of the marker, the deflection of the rail
increases and the marker in the camera image goes down. When the wheels move away
An image processing program was developed to process the video and determine
the vertical position of the top edge of the marker as shown in Figure 4-25. Assuming
the deflection of the rail is zero when the locomotive and measurement vehicle are far
away from the marker, the vertical position of the marker in the video can then be
converted into the actual deflection of the rail which is plotted in Figure 4-26. When the
sensor head passes by the marker, the two ends of the shielding shroud will block the
marker from the camera view which causes the image processing program to fail during
that time. Therefore, Yrel*, the vertical height difference between the rail surface under
the camera and the wheel/rail contact plane, is shown in Figure 4-26. From these
During the calibration procedure, the measurement camera in the sensor head also
captures the video of the laser lines on the top of the rail. This video is post-processed
to capture the image of the marker placed on the ballast as shown in Figure 4-27. From
this image, the distance between the two laser lines (d*) is obtained.
75
The Marker
Figure 4-27: Captured Image when Sensor Head Passes by the Marker
This calibration procedure assumes that the section of track (about 40 feet around
the sticker’s position) is uniform. However, track conditions may change from tie to tie.
Even though this procedure was done on a section of specially selected quality track,
there is no guarantee that modulus over the section is constant. Therefore, the accuracy
After obtaining the ratio of Δd and ΔYrel, Yrel* and d*, the distance between the
two laser lines in the images can be converted into the measurement results, Yrel, by
Yrel* and d*. Therefore, another procedure was developed to verify Yrel*, d* and the
A mechanical shop for railroad vehicles (shown in the satellite map in Figure 4-28)
is involved in this procedure. The track in this shop is assumed to be absolutely stiff such
that no rail deflection will be considered when trains move across this section of track.
This assumption is reasonable since the track in the shop is in good condition and the rail
The results of the Yrel data for this section of track are plotted in Figure 4-28.
As shown in the information section of this figure, the average of Yrel over this section
of track is 0.0018”. Since this value is very close to zero, it confirms the calibration
results very well. The variations of Yrel, which are relatively small (standard deviation
is less than 0.1”), are attributed to the pre-existing geometry variations of the track.
77
factors causing measurement errors include limited sampling rate, the wide laser lines in
The cameras in the current measurement system produce analog video signals in
NTSC standard which is 30 frames per second. As a result, individual data points are
spaced approximately every two feet when the measurement vehicle travels at 40 mph.
However, Yrel measurements may change considerably within two feet since certain
track modulus and geometry variations occur over extremely short distances. Therefore,
The highest peak within the 50 ft range is point B, which is 0.77”. If the test is
conducted at a speed of 40 mph, the system will record readings every two feet. As a
result, the peak at point B could be missed while only the data points at A and C would
be recorded. Hence, an error of 0.04” (the difference between point A and B) would
result. Since the errors based on limited sampling rate depend on how the actual data
varies over short distances they are difficult to quantify. Some locations such as joints
are much more sensitive to this sampling rate issue because the actual Yrel data can
change dramatically over a few ties. Based on examination of the data from past tests,
To address the problem caused by the limited sampling rate, high-speed cameras
are proposed to upgrade the system’s sampling rate to 120 frames per second.
Therefore, the data can be collected every six inches at a testing speed of 40 mph. This
measurement output is the number of pixels between the two laser lines in the images.
captured images.
79
The current frame grabbers are set to capture images in half frame mode which is
320x240 pixels. Based on the calibration results, for images of 320x240 pixels, one pixel
in each image represents 0.0118 inch of Yrel. Hence, the measurement system’s
However, the current cameras and frame grabbers can easily be upgraded to
capturing images of 640x480 pixels. In that case, the system’s resolution may be
peaks of pixel intensities. However, as shown in Figure 4-30, a laser line can be as wide
as three or four pixels in a captured image. Therefore, it is difficult for the image
processing program to precisely distinguish which pixel should represent the location of
the laser lines, especially when two adjacent pixels have the same intensity. Although the
curve fitting algorithm used in the image processing program greatly reduces the error
between the beam propagating axis (where the laser beam is pointing) and the mechanical
axis (where the laser housing is pointing). Due to the nature of the measurement
principle and the calibration procedure, the boresight accuracy has no effect on the
measurement result because the measurement is not related to the mechanical axis of the
inaccuracy.
However, pointing stability, a measure of how much the laser beam alignment
drifts over a period of time, will cause errors. The laser line generator’s pointing
stability is rated at <50 μrad. The geometry relation between the lasers and the rail is
shown in Figure 4-31, where H is the vertical height of the laser generator above the rail,
α is the angle between the laser beam and the vertical direction, Δα is the drifted angle
From the calibration, we know H=13.6, α=50°, and the maximum Δα is 50μrad.
Considering the worst case in which both laser beams are drifting towards the
camera at the same time or away from the camera at the same time, the maximum error
will be doubled. Therefore, the maximum error of Yrel that the laser beams drifting can
Since 2006, the measurement system has conducted revenue service tests in many
locations including the Burlington Northern Santa Fe (BNSF) Railway’s St. Joseph
subdivision in Kansas, and the Union Pacific Railroad (UPRR)’s South Morrill
Nebraska. Some short distance tests such as between Lincoln and Ashland, NE and
Recent tests focused on the 160 miles of heavy axle load freight line of the Union
Pacific Railroad on the South Morrill subdivision of the North Platte division. The tests
Main 2 (primarily loaded with approximately 250 MGT/year). Repeated tests were
conducted on this subdivision in October 2006, December 2006, February 2007, April
2007, January 2008, April 2008, and June 2008. Tests were done at speeds up to 60
mph in a work train consist. The automated testing ability of the system made these
tests easy to conduct and cost-efficient. These repeated tests were performed in
tremendous amounts of data for analysis. Figure 5-1 shows the measurement vehicle in
An example of data recorded over a distance of one mile is shown in Figure 5-2.
The plot shows the relative deflection of the rail, Yrel (as defined in Figure 3-1), as a
function of GPS coordinates given in degrees of longitude and latitude. The data are
trace changes in relative deflection to specific track events such as grade road crossings,
Figure 5-3 shows data sampled over one mile of track. The plot shows the
relative rail deflection between the measurement point and the wheel/rail contact point
(Yrel as defined in Figure 3-1). Also shown are the mean and standard deviation of the
data. The mean represents the average value over the past 0.1 miles of track and the
standard deviation corresponds to the mean over that same distance. This distance was
chosen arbitrarily as a characteristic length. The mean and standard deviation are
crossover between MP 0.6 and 0.9. A non-insulated joint bar (near 0.9) is located at the
right end of the crossover. The relative deflection at this point became very large (over
1”) indicating a very low track modulus. The joint bar failed and caused a derailment
85
only two weeks after the track modulus measurements were taken. This location
represented the second highest relative deflection measurement recorded over the nearly
350 miles of track tested for this portion of the test. This spike in relative displacement
obviously caused a jump in both the mean and standard deviation of the data. The other
end of the crossover (near MP 0.65) also displayed a rise in the standard deviation,
Figure 5-4. Yrel and therefore modulus were both very consistent over this section of
track. The consistent mean and relatively low standard deviation emphasize the track’s
quality.
86
The results of these tests suggest that information in these measurements may be
useful in indicating unsafe sections of track in need of repair. The contrast between the
two figures suggests a quantitative method to more rationally schedule and prioritize
track maintenance.
The multiple tests over the same section of track (South Morrill Subdivision of
UPRR) allow for comparison between tests. This comparison highlights the high
Measurements over the same section of track from tests in December of 2006,
February of 2007 and April of 2007 are shown in Figure 5-5. The measurements from
the three different tests show almost no difference over this section of track, which
indicates the system’s measurement is highly repeatable. The high repeatability of data
as shown in Figure 5-5 is observed over most sections of the 320 miles of track in this
subdivision.
The results from multiple tests in South Morrill subdivision also provided
abundant data for studies on system’s measurement under various conditions such as at
different testing speed, under different weather condition, and for different size of rail.
88
The results of South Morrill subdivision suggest that the measurements are not
strongly related to the train speed. The average train speed for the 0.1 miles shown in
Repeated tests over the same section of the track at different speeds were
performed during a special validation test on the Yoder subdivision. Four different
speeds (20, 30, 40 and 50 mph) were tested. For most of the sections, the measurements
from the different speeds are highly repeatable, which indicates that the speed is not a
differences do exist between the different speeds. The section shown in Figure 5-7 is an
the four different speeds within this short section (21, 30, 40 and 48 mph) are 0.607”,
0.687”, 0.692” and 0.77” respectively. The Yrel measurements increased 0.163” when
89
the train speed increased from 21 mph to 48 mph. This can be explained by the
shown in Figure 5-5 and Figure 5-6, there were some variations in certain sections of
track. The most noticeable variation is the comparison between the December, 2006
test and the other tests. At multiple locations of the track, the relative deflection data
(Yrel) from the test in December, 2006 has an offset compared with the results from other
tests as shown in Figure 5-8. The test in December, 2006 was special because it was
conducted in extreme weather conditions with falling snow and an ambient temperature
around a high of 20° F. Figure 5-8 shows similarity in the shape of the measurements,
90
but a shift in the Test 2 measurement. The December 2006 test has a lower mean value
indicating the track is stiffer (smaller Yrel). This could indicate a change in track
modulus associated with frozen subgrade that may contain moisture. These results
suggest the system could be useful to quantify seasonal variations in track modulus
Interestingly, the offset of the measurements shown in Figure 5-8 only occurred at
some track sections. Figure 5-9 shows a section of track where only the measurements
on the left half of the figure has this offset while on the right half of the figure the results
from the three tests are very similar. This could indicate variations of subgrade moisture
One method used to inspect the change in Yrel data over long distances up to an
entire subdivision is to plot the average Yrel measurement over every 500 feet. The
data from three tests on the South Morrill subdivision are presented using this procedure
as shown in Figure 5-10. The sizes of the rail over the entire subdivision are also
displayed. A general correlation exists between the 500 feet Yrel averages and the rail
sizes. For example, the size of the rail between MP82 and MP104 is 141 lb per yard.
The data from all three tests display a noticeable decrease in Yrel over these 22 miles.
However, it is difficult to single out one factor’s effect since the track performance is
affected by many interconnected sources. Further theoretical studies and data analysis
are needed to examine how Yrel data varies as the rail size changes.
92
Figure 5-10: Average Yrel from Three Tests on Different Size Rail
A special validation test was conducted in October, 2008 on the UPRR’s Yoder
Subdivision between Cheyenne, WY, and Yoder, WY. The purpose of this validation
test was to confirm the measurements collected by the system. Three methods were
As described in section 3.1, Yrel is the distance from the rail surface under the
camera to the wheel/rail contact plane. Therefore, the method depicted in Figure 5-11 to
measure Yrel is very straightforward. Here, a string is pulled to pass the bottoms of the
two wheels. Then the distance from the top surface of the rail under the camera to the
As sh
hown in Figuure 5-12, a specially
s maade magneticc ruler is atttached to the rail
duuring the fieeld measureement to maake the readding process easier. Thee string is tiightly
frrom the top surface of thhe rail underr the cameraa to the stringg is read to compare
c witth the
The string
s measuurement wass performed at three loccations durinng the validdation
liisted in Tab
ble 5-1. Thhe field strinng measurem
ments and the
t Yrel meeasurements each
measurements from the testing vehicle, which suggests that the system’s Yrel
measurements are correct. However, this type of string measurement is not very
accurate. A significant practical limitation is ensuring that the string perfectly passes
the bottom of each of the two wheels – a rather difficult task. This limitation can easily
contribute a relatively large error in the measurement results. To provide more accurate
results, further methods are proposed and described in the following sections.
independently measure the vertical deflection of the rail. Such instruments are
commonly available with an indicated accuracy of less than one millimeter. In this
scenario, rulers used as targets are attached to the side of the railhead by strong magnets
Figure 5-14 demonstrates the measurement scenario. Thirteen rulers are placed
every three feet on the side of the rail so that the total measurement range is 36 feet.
This distance is usually enough to cover the entire deflection basin. First, the unloaded
profile of the rail is measured by using the total station and a glass Porro prism
commonly used in surveying. Next, the total station is used to measure the height of
each ruler on the side of the rail while the rail is unloaded. After the measurements are
recorded, the locomotive parks the measurement vehicle on this section of the track such
that the inboard axle is directly on top of the center ruler as shown in Figure 5-14. The
total station is then used to take the height measurement of each ruler a second time. The
difference between the two height measurements for the same ruler is the rail deflection
at that ruler’s location. Adding the deflection measurement to the unloaded rail profile,
the loaded rail profile can then be determined. Analyzing the resulting measurements
Survey measurements were conducted at two locations during the validation test.
Measurement results from one of these locations are presented in Figure 5-15. The
curve demonstrates the loaded profile of the rail with one wheel at position 0 and the
other at a position of 70 inches since the distance between the two axles is 70 inches.
The profile points at these two locations are connected with a line which is then extended
by -48 inches in the horizontal direction because the horizontal distance between sensor
head and inboard axle is 48 inches. As a result, the distance from the end of the line to the
rail at position -48 inches is the Yrel measurement at this location. As shown in the
The testing vehicle’s measurements are compared with the survey measurements
from each site as shown in Table 5-2. The two methods produced almost identical
results at both sites. This suggests that the testing vehicle’s measurements are accurate
and reliable.
caamcorder is used to obbserve the veertical displacement of the rail as shown in Figure
F
5-16. A wh
hite magnetiic strip is affixed
a to thhe rail to usse as a targget. The caamera
prrocess is mu
uch simpler than using LVDT’s
L as described
d in Section 2.3 and will proovide
coomplete infformation onn the passiing train. A section of sampledd deflection data
prrocessed fro
om a video of a coal train is presennted in Figuure 5-17. In
I this sectioon of
data, a seriess of coal hooppers causees the rail too deflect abbout one hallf inch and three
heavier locom
motives at thhe end of the train to defllect the rail over
o 0.9 inchhes.
Figure 5-16:
5 Wayside Camera
a Measurem
ments Setup
p
99
Coal hopppers
Three locom
motives
Figure 5-17:
5 Samp
ple Data of Absolute
A Deflection fro
om Waysid
de Camerass
Durin
ng the validdation test, this
t type off absolute deflection
d m
measurement
t was
coonducted at three locatioons where suurvey measuurements werre also perfoormed. Thee raw
data of deflecction over tiime from onne of the loccations is plootted in Figuure 5-18. Here,
H
thhe deflection
n caused by the locomootive, the tesst vehicle (U
UNLX002) and
a the geom
metry
he magnetic strip.
position of th The maximum absolute
a defl
flection was determined to be
differences arre less than 0.1” at eachh location, soo the two typpes of measuurements suupport
onne another.
Location #1
# 0.35 0.344 0.01
Location #2
# 1.14 1.1 0.04
Location #3
# 0.7 0.8 0.1
101
One focus of recent testing on the UP’s South Morrill subdivision is on using
trends in measurements made over time to better predict track performance and better
derailments.
Due to GPS misalignment, data from different tests may not exactly coincide with
each other in terms of milepost. Figure 5-19 shows the two sets of data from the same
Measurements from two tests over approximately 0.05 miles of track are shown in
Figure 5-19. The figure clearly shows that the measurements from both tests have
similar shape. However, the two sets of data have an obvious horizontal offset. The
offset represents errors in the milepost location associated largely with GPS error in
localizing the data. Despite errors in GPS measurement, the shape of the curve is
maintained because the relative GPS measurement (one data point with respect to the
next) is much more accurate than two independent absolute GPS measurements.
102
Offset
For the purpose of trending, it is desirable to remove the offsets so that relative
comparisons can be made over short sections of track. The relative comparisons would
evaluate one measurement relative to a previous measurement made at the same location
at an earlier time.
the degree of correlation between two sets of measurements. Consider two series x(i)
and y(i,), both of length N, where i=0,1,2...N-1. The cross correlation, R̂xy , at delay m
is defined as :
N −1
1
Rˆ xy (m) =
N
∑ x ( n) y ( n + m)
n =0
Equation 5-1
indicates a high correlation but where one series is the inverse of the other series.
The results of applying the cross correlation function to the two series in Figure
5-19 at numerous values of m (between -100 and 100) is shown in Figure 5-20. This
figure shows the cross correlation as a function of offsets. Clearly, the cross correlation
reached a maximum when the offset was 8 feet. The value of the cross correlation at this
offset is 0.8, indicating a high correlation between the data (this also suggests the
Based on the cross correlation plot, the second series in Figure 5-19 was shifted
by 8 feet and the new plot is shown as Figure 5-21. Now the two series of data line up
well, which is helpful and convenient for further data comparison and analysis.
104
Some trending results from the South Morrill subdivision are now presented.
Several tests were conducted over the same approximately 160 miles of this sub-division
at three-month intervals. Figure 5-22 shows the relative deflection measurement (Yrel)
over 0.1 miles of track from MP A.70 to A.80 (exact mileposts are removed). Here the
third axis (into the page) illustrates the time interval between the tests in months. Figure
5-22 clearly demonstrated the changes in this section of track as a function of time.
Specifically, two locations are singled out over time. It can be seen that MP A.76 is not
changing quickly over time while MP A.74 corresponds to a peak in the measurement
From the measurements shown in Figure 5-22, two sections at MP A.74 and A.76
are extracted as an example and shown as a function of time in Figure 5-23. Since three
tests were performed, three data points are shown in each of the plots for these milepost
locations. Given these data, a prediction can be made based on the trends. In this case
a line is fitted to the data and used as the prediction. A correlation can be produced to
indicate how well the line fits the three data points. Having only three points (three
tests) of course may not accurately predict the trend, and clearly the prediction has
uncertainty. More testing will improve the prediction. With more available tests it
may be desirable to use other curves (rather than linear extrapolation) to improve the
prediction.
106
again in Figure 5-24. Here an assumption is made that a given threshold of relative
1.2 inches is chosen and indicated by the red dashed line. Now, the linear prediction
can be used to estimate the time required to reach this threshold. In this case, five and a
half months from the last test is the window for maintenance. The accuracy of this
prediction is difficult to quantify, however, this is a tool that can be used to prioritize
maintenance based on actual track data. It is also possible to apply this technique to
other track measurements such as gauge, gauge restraint, cross-level, and other standard
measurements.
107
The above approach can now be applied over the entire section of track between
A.70 and A.80. This range is broken into 12 ft bin lengths and a curve fit is created for
each bin. The Yrel measurements are shown in Figure 5-25 for the three tests. A
subplot is created that represents the slope of the trending line (linear curve fit in Figure
∆
5-24). Here the slope, given by in units of inches per month, is approximated as
∆
the difference between the two tests. When both differences are equal it represents a
linear change over time. The figure shows that MP A.74 is changing approximately
linearly over time at a relatively fast rate while the other part of the track in this section
and the needed maintenance schedule can now be estimated (given some amount of
uncertainty).
108
Data used in this section come from tests performed on the BNSF’s Creston, St.
Joseph, and Ravenna subdivisions. Tests were performed over two bridge approaches
as shown in Figure 5-26 and Figure 5-27. The two soft approaches to the bridge
corresponding to high Yrel can be identified in the figures. Both bridges are concrete
ballast deck bridges. Trending from two tests on the bridge at MP B.6 is shown in
Figure 5-26. An examination of the two measurements of Yrel indicates little change in
the measurement. This is confirmed in the trending analysis where the rate of change
Trending for a second bridge near MP C.64 is shown in Figure 5-27. Here, three
tests were performed, and again an examination of each of the Yrel measurements
indicates little change in the measurement near the bridge. This is confirmed in the
trending analysis. However, a few significant observations may be made. First, the
difference between the June and February tests is consistently more substantial than the
difference between the August and February tests. It could be speculated that more
moisture was present in the track structure in June as compared to both February and
August. Second, a significant change can be seen near MP C.60. Here the June test
indicates both stiff and soft locations with large variations in Yrel as compared to the
other tests. This is also clearly indicated in the trending results. It is suggested that such
Based on the analysis in section 3.4.2, combining Yrel data and space curve data
from the track geometry vehicle can provide information regarding vertical track
displacement. In other words, using ECO data calculated from rail profile data, the
element in Yrel contributed by the track geometry variation can be eliminated. ECO
data is calculated by using the equations in section 3.4.1. Since Yrel data and ECO data
come from two different measurement systems which have two separate GPS systems, an
offset between the position readings from each GPS system is expected. As a result, an
alignment algorithm is required for implementing geometry data into Yrel measurements.
The Yrel and ECO data were aligned by the same method used in the trending
analysis, which included calculating the cross correlation between the two sets of data
111
and shifting the distance where maximum cross correlation occurs. The procedure is
The geometry data are measured in increments of one foot, however Yrel data is
not. As a result, an interpolation is needed to transform Yrel data into one foot
increments so that the cross correlation function can be applied to the two sets of data.
This interpolation was done by the function “interp1” (one-dimensional data interpolation)
in MATLAB. The method “pchip” (piecewise cubic Hermite interpolation) was used.
After the Yrel data is interpolated into one foot increments, it is then divided into
sections of 300 ft. The length of 300 ft was chosen because it appeared to be able to
Then, the GPS latitude and longitude data for each 300-ft section are used to
extract the corresponding 300 ft of ECO data, as well as the 300 ft of ECO data before
and after the corresponding 300 ft. Altogether, 900 ft of ECO data will be available for
the next step of the procedure. For example, over the 300 feet (MP19.536 to MP19.478)
shown in Figure 5-28, the GPS latitude and longitude for the starting data point (A) is
given as 41.185069 -101.425016. The program searches through the ECO data and
finds the point where the GPS is the closest to point A which is 41.185073 -101.4250164
(point B). Then, the 600 ft after point B and 300 ft before point B are extracted for the
The next step is to calculate the cross correlation between the two series which
include the 300 ft after point A in the Yrel data and the 300 ft after point B in the original
ECO data. The program calls a subroutine to finish the calculation and return the cross
determined. For the example data shown in Figure 5-28, the offset value was 43 ft and
the maximum cross correlation was 0.9351 which indicates a very high correlation
between the two data series. After the offset value is determined, the ECO data is
simply shifted by this offset distance. For the section shown in Figure 5-28, the 300
data points from the original ECO data (from the 43rd point after point B to the 342nd
point after B) are cut off to match the 300 ft of Yrel data. This process is then repeated
for every 300 ft long section until all 158 miles of data are analyzed.
113
from Yrel.
The Yrel data presents a multitude of information about the track condition but
automate and simplify the interpretation of such rail deflection and track modulus
information. In this case, the exception criteria identify points of interest in the data.
The preliminary exception criteria are based on identifying distinct changes in the
condition of the track. Changes are identified relative to a mean and standard deviation
n
di
μ=∑ Equation 5-2
i =1 n
Where μ is the mean, di is a single data point, and n is the number of data points
over a characteristic length of track. Currently, 0.1 miles is used as the characteristic
length.
Given the mean as calculated in Equation 5-2, the standard deviation can be
determined by:
114
∑d i −μ
σ= i =1 Equation 5-3
(n − 1)
With these two definitions, several exception criteria may be generated. One
standard criterion is to create a deviation ratio by computing the ratio (σratio) of the
di − μ
σ ratio = Equation 5-4
σ
This is often used in industry as a quality control metric. For example, a given
parameter should never vary beyond “six sigma”. The difficulty with this metric in the
evaluation of the relative deflection is that it can lead to false exceptions. For example,
a smooth section of track such as the one in Figure 5-4, has a consistent mean and the
standard deviation is very small (around 0.05”). As a result, any medium sized change
(e.g. greater than 0.30”) will create an exception when in reality this medium sized
Δ = di − μ Equation 5-5
The above exception criteria may only capture a small percentage of the
information contained in the relative displacement data. However, past tests suggest
A test was conducted on August 9, 2006 from Bill, WY to North Platte, NE.
The test was performed on the Union Pacific Railroad’s Powder River and South Morrill
subdivisions. The line consisted of double track with approximately 250 MGT/year on
main track No. 2 and 50 MGT/year on main track No. 1. The test was conducted in a
special work train consist. Testing was done at speeds of up to 60 mph and the total test
Table 5-4 shows the results of this test. Values for both the difference criteria
exceptions, Δ, and the deviation ratio exceptions, σratio, are shown. The sites are ranked
in descending order of the Δ criterion over the entire 270 miles of the test (i.e. #1 having
the largest value of Δ=1.424”, #2 having the second highest value of Δ=0.989”, and so
on). Under this criterion, mile post A.47 was the “worst” section over the 270 miles of
the test. Note that the exact mile post numbers were changed to letters so as not to
Track
MP Δ σ µ σ ratio
Feature
1 A.47 Signal 1.424 0.062 0.112 22.85
2 B.89 Turnout 0.989 0.065 0.142 15.12
3 C.97 Signal 0.973 0.100 0.121 9.72
4 D.65 Unknown 0.970 0.112 0.078 8.64
5 E.51 Turnout 0.919 0.122 0.099 7.56
6 F.95 Turnout 0.916 0.133 0.11 6.91
7 G.97 Unknown 0.828 0.127 0.129 6.53
8 H.30 9' CBC 0.815 0.115 0.097 7.10
9 I.17 Unknown 0.800 0.085 0.119 9.42
10 J.58 Turnout 0.796 0.083 0.118 9.56
11 K.43 Crossing 0.773 0.054 0.119 14.23
12 L.44 Crossing 0.753 0.120 0.098 6.30
Several observations may be made from this exception list. First, there is not an
exact correlation between the difference criterion, Δ, and the deviation ratio criterion,
σratio. For example, site MP F.95 is the sixth highest when ranked by the difference
criterion, but has a relatively small deviation ratio. This is a result of a large standard
deviation surrounding the turnout (a rough turnout). Therefore, even though there is a
large data reading at this site, the deviation ratio is relatively low (as compared to site
Post processing of the data indicated a correlation with two of the top ten
deflection locations and the location of two derailments. These were within 30 days of
The exception list was generated based on the Δ criterion and was independent of
the knowledge of the derailments. The site with the second highest difference
exception, MP B.89, coincided with the location of a defective field weld which caused
an eight car derailment 14 days after the test. The site with the tenth highest exception
at MP J.58 coincided with the location of a broken joint bar derailment 30 days after the
test.
The site with the second highest Δ was mile post B.89. The raw data from that
location are shown in Figure 5-29 for one mile of track. The exception at MP B.89 is
clearly visible with a large peak in relative displacement. The standard deviation is also
larger around this turnout. This large relative displacement suggested a problem with
The site with the tenth highest Δ was at mile post J.58. The raw data from that
location are shown in Figure 5-30 for one mile of track. The exception at MP J.58 is
also visible with a large peak in Yrel measurements. The standard deviation is also
larger around this turnout with both ends of the turnout clearly visible. The track failed 30
days after the data was collected. The assumption is that the low modulus continued to
degrade, resulting in increasingly larger defections until failure of the non-insulated joint.
Following the procedure described in section 5.6, the data from the vertical track
deflection measurement system and track geometry car can be combined and the relative
effects of track geometry variations and are more directly related to the track supporting
investigations, and the subsequent visits suggest that this criterion is fairly useful in terms
Interaction (VTI)
currently in use by the Union Pacific Railroad. This system has been successfully
integrated into revenue service. The VTI system uses accelerometers mounted on
used on both locomotives and hopper cars and has been fully integrated into revenue
Results presented here are from a test conducted on a locomotive that passed over
the same section of track (the Powder River and South Morrill subdivisions) two days
after the vertical rail deflection measurements presented in section 5.7.2 and 5.7.3. The
relevant VTI results come from an accelerometer mounted to the axle of the locomotive
(below the suspension system). The acceleration data are used (with knowledge of the
locomotive’s mass and suspension characteristics) to estimate loads between the wheel
and rail.
120
fundamentally different. For example, a smooth section of track with a low modulus
section of high modulus track. However, this difference will be captured by the vertical
A test of the same section of track (270 miles of the Powder River and South
Morrill subdivisions) was conducted using the VTI system on August 11, 2006 – two
days after the VTD measurements were made. Some results of this test are shown in
Table 5-5 as a comparison between the two measurements. Selections of the ranked
results from VTI measurements are shown in the left four columns. The right two
columns show how the same measurements appear in the Δ criterion exceptions from
Table 5-4. Only the locations common to both tables are shown in Table 5-5.
121
The most important conclusion to reach from Table 5-5 is that the two
measurements are fundamentally different. The highest force estimated from the VTI
data (at MP X.5) does not appear in the top twelve Δ criterion exceptions of Table 5-4.
The top VTD exception (at MP A.47) appears at #123 in the VTI measurements. The
two derailment locations described above appear on both lists (highlighted in both
tables). The derailment that occurred 14 days after the vertical modulus measurements
(MP B.89) appears as #2 on the VTD list and #62 on the VTI list. Similarly, the
derailment that occurred 30 days after the test (MP J.58) was #10 on the VTD list and
#27 on the VTI list. However, an enormous impact load at MP X.5 is not indicated in
the top 12 of the VTD measurements. Clearly, these are different measurements.
122
The relation between Yrel and ECO has been explained in section 3.4.2.
Although high correlations exist between Yrel and ECO, they are fundamentally different
measurements. Results from revenue service tests further confirm the fundamental
differences.
A test was conducted in South Morrill subdivision in April, 2007. The VTD
system and UPRR’s track geometry car (EC5) collected data over the same 160 miles of
track on the same day. Exception lists were produced based on Yrel measurements and
Table 5-6 lists the top 20 locations in the VTD list along with their rankings in the
ECO list. Among the three highlighted sites, #4 and #17 in the list are the locations
where a derailment occurred one week before the testing day. The track was under
construction at these locations on the day of the test. The #1 item in the list is the
location where another derailment occurred two weeks before the test. Again, the track
It can be observed that nine of the top 20 sites in the VTD list did not show up on
the ECO list (ECO list includes 200 sites). Besides the derailment locations, only four
locations (#5, #9, #18 and #20 in VTD list) were identified by both top 20 lists. In
A list ranked by ECO data was also produced as shown in Table 5-7. In this
table, 18 of the top 20 locations in the ECO list were also in the VTD list (VTD list
includes 90 sites). However, most of these locations have lower rankings in the VTD
list. Except for the derailment locations and five unknowns, almost all of the top 20
The VTD measurement system conducted a test in a coal train consist at the South
Morrill subdivision in June, 2008. About a month earlier, UPRR’s EC5 geometry car
collected track geometry data on the same subdivision. The track geometry data
provided by UPRR was then integrated into the VTD’s Yrel measurements so that Yrel
and ECO measurements could be compared and relative deflection measurements could
be calculated.
Based on both the VTD’s Δ criterion and the calculated relative deflection
measurements, 15 sites were selected and field investigations were completed on July 1st,
2008. The track visits identified the reasons for large Yrel and deflection measurements
at all sites with varying levels of maintenance urgency. Among them, one site was
taken out of service immediately and two additional sites were called for maintenance to
be repaired. A variety of track problems were identified including poor joints, broken
ties, muddy ballast, and crushed rail head, etc. Some of the sites will be discussed in
detail in the following sections. The actual mileposts for these sites are concealed in the
discussions.
The data from the first site is plotted in Figure 5-31. The peak in the Yrel data on
the north rail measures 0.89” while the ECO measurement is 0.34”. As a result, the
The pictures of this location are displayed in Figure 5-32. The white-colored
ballast indicates that strong pumping has occurred. The track inspector estimated the
pumping to be up to three quarters of an inch. The rail profile dropped down half an
inch at the crushed spot. This site was investigated two weeks after the test. The track
inspector suggested that the weather was damp and a flash flood warning was issued
around the testing time, so that the deflection was expected to be large.
128
C
Crushed Rail Head
Figure 5-3
32: A Crush
hed Rail He
ead
exxhibited fou
uled ballast and broken ties. Dataa from one particular site are show
wn in
T
They represen
nt the two appproaches too the road croossing. Thhe approach at
a the east siide of
b much woorse than thee west side based on thhe Yrel data. The
thhe crossing appears to be
At least four ties were center cracked and some of them appeared to have
horizontal cracks at the bottom. The muddy ballast and the tie cavities indicated large
movements of the ties. Based on observation, the ties were estimated to have moved by
over 0.5”. This muddy area was located at an approach to a road crossing. The other
side of the road crossing was also muddy. This explains the two peaks in the Yrel data.
Again, the track was much wetter on the day of the test.
130
Approximately half of the sites in the VTD exception list are joints. The
measurement system demonstrated a notable ability to identify bad joints. Figure 5-35
shows the data at one particular joint. In this case, Yrel measured 1.21” at the joint with
Figure 5-36 shows the condition of the insulated joint. This supported joint is
rare in North America where suspended joints are dominant. The supporting tie in the
center was in a very poor condition. The tie was split and a large portion (left part in the
picture) was nearly separated from the rest of the tie. Applying pressure with a foot was
enough to deflect the tie. The bolts on the joint bars were loose and one of them would
actually rotate as a train passed. The track inspector commented that this joint was
probably among the worst 10% of all joints. A wayside camera measurement was taken
as a coal train passed the site. The video showed that the deflection at the joint was over
The peak in the Yrel data from this site reads 0.95” while the ECO is 0.41”. The
measurements of the MCO (mid-chord offset) were consistent with the geometry car
measurements. As shown in Figure 5-37 the curve of Yrel data from this site has a
special shape when compared to the data from other sites. Unlike the sharp peaks in
Figure 5-35, the peak here is broader and high deflections occurred over a relatively long
distance.
133
A picture of this site is displayed in Figure 5-38 in which a series of broken ties
are clearly visible. The ties barely constrained the south rail. The clips were either
missing or unattached to the rail due to the cracks in the ties. The broken parts of the
ties could easily be lifted by hand. Recent geometry car tests and VTI tests did not
identify an exception at this location. The track inspector explained that defects like
these were difficult for track inspectors to notice. The track director immediately
An important goal of the project is to obtain the track modulus information using
the system’s measurements. The relation between Yrel and track modulus based on the
Winkler model was discussed in Section 3.2. The track modulus determined by this
relation is an overall effective modulus. The method does not distinguish between
Using Equation 3-10 and Figure 3-5, the Yrel measurement can be converted into
track modulus. As mentioned earlier, Equation 3-10 is based on the analysis which
neglects track geometry variations. The discussions in Section 3.3 explained how using
using the calculated relative deflection (“Yrel+ECO”) as Yrel in Equation 3-10, the
The previous results may be implemented in further analysis of site four. The
Yrel and ECO data from the south rail of this site as shown in Figure 5-37 were
converted into track modulus. The calculated modulus over the same section of track
foundation is indicated since the modulus value drops from around 3,000 psi to a mere
200 psi.
136
6 CONCLUSION
estimate track modulus based on mathematical models describing the relation between
loads and track deformation. The system consists of a loaded hopper car outfitted with a
camera/laser sensor system to detect the vertical deflection of the rail relative to the
wheel/rail contact point. In order to eliminate the effect of track geometry variations,
All of the components of the measurement system have been described in detail.
The methods and procedures of image processing and calibration were illustrated. The
potential errors in the measurements were also analyzed, showing that the system can
The measurement system has conducted revenue service tests over three thousand
miles of track. A special validation test was also performed. Based on the results from
speed, testing seasons, rail size) on the testing results were also evaluated. Three
validation approaches have been developed, and results from the validation test confirm
138
that the system measures accurate outputs. Trends in the data from different tests were
examined to better monitor the changes in the track quality. Exception criteria were
proposed and used to identify and prioritize track locations in need of maintenance.
These criteria proved to be valid, although further improvements are still possible. The
data from different systems (VTD and VTI, VTD and ECO) were then compared, and the
results showed that the VTD system provides unique and valuable information that is not
available from the other systems. Furthermore, the VTD system has notable ability to
indicate track support problems. Last but not least, the process of using the system’s
8 REFERENCES
Arnold, R., Lu, S., Hogan, C., Farritor, S., Fateh, M., El-Sibaie, M., "Measurement of
Vertical Track Modulus From a Moving Railcar," Proceedings of the AREMA 2006
Annual Conference, Louisville, KY, September, 2006.
Cai, Z., Raymond, G. P., and Bathurst, R. J., 1994, “Estimate of Static Track Modulus
Using Elastic Foundation Models,” Transportation Research Record 1470, pp. 65-72.
Carr, Gary A, 1999, “Dynamic Response of Railroad Track Induced by High Speed
Trains and Vertical Stiffness Transitions With Proposed Method of Measurement”,
Master Thesis, Tufts University. September 1999.
Carr, Gary A. and Greif, Robert, 2000. “Vertical Dynamic Response of Railroad Track
Induced by High Speed Trains,” Proc. of the ASME/IEEE Rail Joint Conference, pp.
135-151.
Chang, C. S., Adegoke, C. W., and Selig, E. T., 1980, “GEOTRACK Model for Railroad
Track Performance,” Journal Of the Geotechnical Engineering Division, Proc. Of the
American Society of Civil Engineers, November 1980, Vol. 106, No. GT11, pp
1201-1218.
Hogan, C., Dick, M., Lu, S., Farritor, S., Arnold, R., GeMeiner, W., Clark, D., "Track
Stiffness Measurement with Implementation to Rail/Vehicle Dynamic Simulation,"
Proceedings of the AREMA 2008 Annual Conference, Salt Lake City, UT, September,
2008.
Hogan, C., Design of a System to Measure Vertical Railroad Track Deflection From a
Moving Railcar and Implementation to Dynamic Railcar Simulation, Master Thesis,
University of Nebraska-Lincoln, August, 2007.
141
Craig, J. J., 1989, Introduction to Robotics: Mechanics and Control, 2nd Edition,
Addison-Wesley Publishing Company, Inc., Reading, MA: pp 19-60 .
Davis, D. D., Otter, D., Li, D., and Singh, S., December 2003, “Bridge Approach
Performance in Revenue Service,” Railway Track & Structures, pp. 18-20.
Ebersohn, W., and Selig, E. T., 1994, “Track Modulus on a Heavy Haul Line,”
Transportation Research Record 1470, pp. 73-83.
Ebersohn, W., Trevizo, M. C., and Selig, E. T., 1993, “Effect of Low Track Modulus on
Track Performance,” International Heavy Haul Association, Proc. Of Fifth International
Heavy Haul Conference, pp. 379-388.
Federal Railroad Administration, March 2001, “T-16: FRA’s High Speed Research Car,”
Research Results, RR01-01.
Heelis, M. E., Collop, A. C., Chapman, D. N. and Krylov, V., 1999, “Predicting and
measuring vertical track displacements on soft subgrades,” Railway Engineering. 117
Kerr, Arnold D. “A Method for Determining The Track Modulus Using A Locomotive
Or Car On Multi-Axle Trucks,” Proceedings American Railway Engineering Association,
1983, Vol. 84, pp 269-286.
Kerr, Arnold D. “On the Stress Analysis of Rails and Ties,” Proceedings of American
Railway Engineering Association, 1976, Vol. 78, pp 19-43.
Kerr, A. D. and Shenton, H. W., “On The Reduced Area Method For Calculating The
Vertical Track Modulus,” American Railway Engineering Association Bulletin,
December 1985, Vol. 86, No. 703, pp 416-429.
Kierzenka J. and Shampine L. F., 2001, “A BVP Solver based on Residual Control and
the MATLAB PSE,” ACM TOMS, Vol. 27, No. 3, pp. 299-316.
Li, Dingqing, Hass, Kevin, and Meddah, Abe, June 2002, “Moving closer to
performance-based track geometry inspection,” Railway Track and Structures, pp. 15-17.
Li, Dingqing, and Selig, Ernest T., 1994, “Resilient Modulus for Fine-Grained Subgrade
Soils,” Journal of Geotechnical Engineering, Vol. 120, No. 6, pp 939-957.
Li, Dingqing, and Selig, Ernest T., 1998, “Method for Railroad Track Foundation Design
I: Development,” Journal of Geotechnical And Geoenvironmental Engineering, Vol. 68,
No. 7-8, pp 457-470.
142
Lu, S., Arnold, R., Farritor, S., "On The Relationship Between Load and Deflection in
Railroad Track Structure," Proceedings of the AREMA 2008 Annual Conference, Salt
Lake City, UT, September, 2008.
Lu, S., Farritor, S., Arnold, R., GeMeiner, W., Clark, D., Al-Nazer, L., Carr, G.,
El-Sibaie, M., "Measurement of Vertical Track Modulus - Field Testing, Repeatability,
and Effects of Track Geometry," Proceedings of the 2008 Joint Rail Conference,
Wilmington, DE, April 22-24, 2008.
Lu, S., Hogan, C., Minert, B., Arnold, R., Farritor, S., Seeger, W., Oliver, M., Lees, H.,
Thornton, D., Fateh, M., Carr, G., "Vertical Track Modulus Testing On BNSFs Heavy
Haul Coal Line," Proceedings of the AREMA 2007 Annual Conference, Chicago, IL,
September, 2007.
Lu, S., Hogan, C., Minert, B., Arnold, R., Farritor, S., GeMeiner, W., Clark, D.,
"Exception Criteria in Vertical Track Deflection and Modulus," Proceeding of 2007
ASME/IEEE Joint Rail Conference & Internal Combustion Engine Spring Technical
Conference, Pueblo, CO, March 13-16, 2007.
McVey, B., Norman, C., Wood, N., Farritor, S., Arnold, R., Fateh, M., El-Sibaie, M.,
"Track Modulus Measurement From A Moving Railcar," Proceedings of the AREMA
2005 Annual Conference, Chicago, IL, September, 2005
Norman, C., Measurement of Track Modulus From A Moving Railcar, Master Thesis,
University of Nebraska – Lincoln, May 2004.
Read, D., Chrismer, S., Ebersohn, W., and Selig, E., 1994, “Track Modulus
Measurements at the Pueblo Soft Subgrade Site,” Transportation Research Record 1470,
pp. 55-64.
Selig, E. T., and Li, D., 1994, “Track Modulus: Its meaning and Factors Influencing It,”
Transportation Research Record 1470, pp. 47-54.
Stewart, Henry E., 1985, “Measurement and Prediction of Vertical Track Modulus,”
Transportation Research Record 1022, pp. 65-71.
Sussmann, T. R., Ebersohn, W., and Selig, E. T., 2001, “Fundamental Nonlinear Track
Load-Deflection Behavior for Condition Evaluation,” Transportation Research Record
1742, pp. 61-67.
Thompson, R., and Li, D., 2002, “Automated Vertical Track Strength Testing Using
TTCI’s Track Loading Vehicle,” Technology Digest, February.
Wanek, Mischa, 2004, “Quality instruments for rail-flaw detection,” Railway Track and
Structures, February, pp. 19-22.
Zarembski, Allan M. and Choros, John. “On the measurement and calculation of vertical
track modulus,” Proceedings of American Railway Engineering Association, 1980, Vol.
81, pp. 156-173.
Zarembski, A. M., and Palese, J., August 2003, “Transitions eliminate impact at
crossings,” Railway Track & Structures, pp. 28-30.