Cost Model: Crashing of Network
Cost Model: Crashing of Network
In some projects, it is desirable to cut down the total project time, even
if it leads to increase in cost. It is generally desired where cost
considerations are unimportant or less important than completing the
project in absolute minimum time e.g., defence works in emergency.
For studying the project time and cost analysis, we shall fast discuss
about project costs and time-cost relationship.
Project Costs:
There are two types of costs associated with a project:
(i) Direct costs:
It represents the expenditure which can be allocated to different
activities in a project, like manpower, material etc.
This shows that the network technique is an analytical tool for better
planning, scheduling, monitoring and decision-making.
Cost Slope:
In actual practice, we assume the time-cost curve to be linear between
crash point A and Normal point B. The curve has shown in Fig. 29.5
shows that, there is a change in cost for change in time. The term ‘cost-
slope’ is defined as the “increase in the cost of the activity per
unit decrease in the time”.
Mathematically, we can say,
Crashing Procedure:
The cost slope concept helps in finding lowest cost solution by
sequential compressing the activities having lowest cost slope, i.e.,
having lowest incremental cost, on critical path.
(ii) The activity having the lowest ratio is reduced to the next lower
time value.
(iii) The critical path for the network is again calculated using the new
time for the crashed activity.
(iv) Repeat step (ii) and (iii) until the critical path is equal to optimum
project duration or equal to prescribed project duration.
Example 1:
For a network shown in Fig. 29.6, Normal time, Crash time, Normal
cost and Crash costs are given in the table. Contract the network by
crashing it to optimum value and calculate the optimum project cost.
Indirect cost is given as Rs. 100 per day.
Solution:
By drawing the network with normal duration, we see (from following
figure) that critical path is 1-2-3-4-5.
Normal cost and crash cost can now be calculated by adding values of
all the activities, given in the table.
This network shows that, after crashing activities 2-3 by 2 days and 4-
5 by 1 day, the critical path is same, i.e. 1-2-3-4-5 and have 15 days
duration.
Now in second stage, the least cost slope in remaining activities is for
activity 3-4 on the critical path.
By crashing this activity, we see that two paths become
critical path, 1-2-3-4-5 and 1-2-4-5 as shown in Fig. 29.9
below:
Now we see that after crashing activities 2-3, 4-5 and 3-4, there is no
other activity on both the critical paths which have cost slopes less
than indirect cost. This shows that this is the optimum network and
hence optimum project duration is 14 days.
And indirect cost for 14 days @ Rs. 100 per day = Rs. 1400
Whereas total cost with all normal activities was (i.e. without crashing)
= Rs. 5900.