DPR Design Report Hamirpur Rath - R4
DPR Design Report Hamirpur Rath - R4
May 2018
India
Consulting engineers pvt. ltd.
Uttar Pradesh Core Road Network Development Program
DETAILED PROJECT REPORT
Volume-II: Design Report
Hamirpur – Rath Road (SH-42)
Document Authentication
Name Designation
Reviewed by Sudhendra Kumar Karanam Sr. General Manager (Roads & Highways)
Rajeev Kumar Gupta Deputy Team Leader
History of Revisions
Version Date Description of Change(s)
Page i| Rev: R4
Uttar Pradesh Core Road Network Development Program
DETAILED PROJECT REPORT
Volume-II: Design Report
Hamirpur – Rath Road (SH-42)
TABLE OF CONTENTS
6.6 Evaluation of Design Traffic (MSA) for Pavement Design ........................................................ 6-5
6.7 Design of Pavement Structure as per IRC: 37-2012 ................................................................ 6-6
6.8 Design of Rigid Pavement Structure as per IRC: 58-2015 ....................................................... 6-8
6.9 Design of Strengthening Overlay for Existing Carriageway ...................................................... 6-8
6.10 Proposed Maintenance/Repair Strategy before Placing Overlay ............................................. 6-11
6.11 Preparation of Surface and Profile Correction Course (PCC) .................................................. 6-13
6.12 Pavement Composition for Truck Lay byes ........................................................................... 6-14
LIST OF TABLES
Page v| Rev: R4
Uttar Pradesh Core Road Network Development Program
DETAILED PROJECT REPORT
Volume-II: Design Report
Hamirpur – Rath Road (SH-42)
LIST OF FIGURES
APPENDICES
ABBREVIATIONS
OD Origin – Destination
OFC Optical Fiber Cable
PAP Project Affected Person
PIA Project Influence Area
PMIS Project Management Information Systems
PWD Public Works Department
QAP Quality Assurance Plan
R&R Rehabilitation and Resettlement
RAP Resettlement Action Plan
RCC Reinforced Cement Concrete
RFP Request for Proposal
RHS Right Hand Side
ROB Road Over Bridge
ROW Right of Way
RUB Road Under Bridge
SH State Highway
SMA Stone Mastic Asphalt
SPT Standard Penetration Test
TAC Transport Association of Canada
TOR Terms of Reference
TYP Typical
UPCRNDP Uttar Pradesh Core Road Network Development Program
VDF Vehicle Damage Factor
VOC Vehicle Operating Costs
VUP Vehicular Underpass
Page x| Rev: R4
Uttar Pradesh Core Road Network Development Program
DETAILED PROJECT REPORT
Volume-II: Design Report
Hamirpur – Rath Road (SH-42)
1 INTRODUCTION
1.1 Introduction
The improvement proposal primarily covers widening and strengthening of existing road, CD
structure improvement and strengthening, user facilities etc. . The design of the project road
components includes following design components:
The design comprises geometric design i.e. the horizontal alignment and the vertical profile, and
the design of appurtenances and structures, traffic control devices, roadside furniture and other
project facilities. The geometric design consists of the below mentioned features. The design
standard/ practices proposed to be adopted for structure design are given in Chapter 8 and 9.
design of horizontal alignment, vertical alignment, intersections and other features for
upgrading the existing lanes to required 2-lane with paved shoulder configuration by
widening including realignment where required;
minimizing shifting/acquisition avoiding obstructions or constraints like trees, utilities and
structures as far as possible without affecting safety;
the geometric design is based on available right of way (ROW) and shall conform to the
standards, set out as minimum, as far as possible; safety mitigation measures to be
provided wherever desirable design standards cannot be achieved
wherever the existing road geometrics are deficient, due importance to improvement of
these sections to meet the standards subject to land constraints;
the uniformity of design standards is maintained throughout the length of the Project
road, to the extent practical with due consideration to safety;
Correction of any deficiencies in the vertical profile in respect of grades layout and sight
distance to meet the minimum requirements;
Design of road side appurtenances and project facilities in accordance with relevant
codes of IRC or other international standards;
The design of cross drainage works in accordance with the relevant IRC Codes and
considers the location of the cross drainage (CD) works, bridges and other structures. In
case of major bridges (above 60 m), the design alignment shall give precedence to the
bridge location.
Site Specific: The project roads pass through plain and rolling terrain having villages and towns
along the road. Considering the physical condition and cost effectiveness, the improvement
proposals are conceived and developed under following standards:
The highway design is based on the IRC Codes and publications shown in Table 1.1 and is in
conformity with requirements set forth in MORT&H Specifications for Road and Bridge Works.
Design codes proposed to be adopted are detailed below. A recently published Standard IRC:SP -
73 “Two Laning of State highways on BOT Basis” covering all requirements of 2-lane road, also
based on current practices would be largely adopted for detailed design of roads.
S.
Description Design Code
No
IRC:80 – Type design for pick up bus stops on Rural Highways
7. Ancillary Works
IRC: SP: 12 – Guidelines on provision of parking areas.
IRC:SP:42 – Guidelines on Road Drainage
8. Drainage
IRC:SP:50 – Guidelines on urban drainage
IRC:103 – Guidelines for pedestrian facilities
9. Safety Measures IRC:SP:44 – Highway Safety Code
IRC:SP:55 – Guidelines for safety in construction zones
The following codes and publications (latest editions) have been used for the design of bridge
components including approaches:
Where IRC Codes are silent, relevant BIS codes have been followed. In case even the BIS codes
are silent, sound engineering practice have been adopted.
The design standards are primarily based on IRC publications, MORTH Specifications and relevant
international standards and industry best practice. Where the design standards are silent, the
consultant has based the design on their past experience and sound engineering practices. e.g.:
geometrics embankment, pavement, structures, drainage, drawings, traffic safety and materials.
Terrain Classification
Site Specific: The project road from Hamirpur - Rath passes through predominately in plain
terrain.
Design Speed
The allowed speeds are dependent on both terrain and horizontal curvature. While the project
roads are in plain and rolling terrain, the roads have many horizontal curves not meeting the
design speed. In view of this, the design speeds that could be achieved shall be reviewed based
on the current geometry and efforts will be towards making the road safe and conforming to
design standards within the constraints.
The design speed of 100 and 80 Kph as ruling and minimum as per IRC: SP:73 has been adopted
for road falling in plain terrain.
Site Specific: There are 22 villages with numerous schools and colleges along the road with lots
of activities. Traffic calming is also proposed in 9 built-up areas. The reduced design speed of 40
kmph in urban areas has been imposed to enhance safety of users (both motorized, non-
motorised and other vulnerable users as pedestrians). As per Road Safety Audit
recommendations, the max speed limit posted is 65 kmph instead of 80Kmph, as, either frequent
calming down for safety will result in low average speed or the drivers will have a tendency to
ignore the signage and measures.
Horizontal, vertical and other design parameters are detailed in subsequent sections and
summary is given in Table 1.3 as follows.
2.1 Introduction
The project area was studied from satellite imaginaries and topographical maps (from Survey of
India) to understand the terrain, environmental and social features including water bodies, forest
areas, built-up areas etc. Reinforced with the information from maps, site visits were made to
study and understand various site constraints, land uses, environmental sensitive features,
developmental activities and presence of utilities. These were followed by detailed inventory and
surveys of various road and structure features including carrying out of utility survey.
The following IRC codes and standards have been referred to for finalizing the design of cross
sectional elements.
The above elements together constitute complete road cross section. Adoption of various
elements in an appropriate manner, in accordance with IRC guidelines for safe movement of
traffic is a major design requirement. These are detailed in the following sections.
The IRC 73 lays down formation width guidelines for 2 lane carriageway configuration for State
Highways in plain & rolling terrain as 7.0m.
Shoulders
The normal shoulder width as per IRC: SP 73 shall be 2.5m on either side in roads passing
through plain and rolling terrain, out of this 1.5m will be paved shoulder.
Camber
Footpath
Site Specific
The project road is proposed to be widened from existing single/intermediate/ 2-lane to standard
2-lane carriageway with paved shoulder. Since the road is important and considering the safety
and future capacity issues, it is proposed to have formation width as 12m; as also based on
discussion with PWD. The formation width components shall comprise of as under:
On horizontal curves, the carriageway width is increased to account for the extra
widening requirements for curvature
Paved shoulder and/ or earthen shoulder width will be reduced at the location of key land
constraints
Paved shoulder and/ or earthen shoulder width will be reduced to have smooth transition
to match with minor or major bridges width (existing and to be retained bridges having
less than 10.0m width)
In built-up areas, the earthen shoulder will be replaced by footpath
In built-up areas, having ROW (property line to property line) width more than 13m,
tactile paving is proposed till end of footpath
At built-up sections and other locations where traffic calming measures are considered,
central hatching in for virtually segregating directional traffic may be provided where
enough space is available
The ROW details have been collected from the local agencies and from revenue maps. The
widening/improvement work is within the existing right of way avoiding land acquisition.
Based on above features, operational requirements and to meet design standards stated in the
Two Lanes Manual for the State Highways; typical cross-sections for widening and new
construction of road have been developed. The main features of cross-sections are given in
Table 2.2 below. Typical road cross-sections are shown in Figure 2.1 and also provided in
Drawings Volume.
The cross section schedule for the project road is given in Table 2.3.
3 WIDENING PROPOSALS
Concentric widening i.e. widening will take place on both sides of existing carriageway
Eccentric widening i.e. widening will take place on one side (left - LHS/right - RHS) of
the existing carriageway
In one side widening, existing carriageway have to be widened either on the left or right side
of the existing carriageway. The existing carriageway may be partially used/ fully fully/or may not
be used.
The existing carriageway has to be strengthened by overlay or may require reconstruction based
on the pavement investigations and alignment options. The existing cross-drainage structures
would be either extended or reconstructed. The longitudinal drains would be provided on both
sides. Footpath cum covered drains would be provided on outside of carriageway in urban/ built-
up sections. Utility duct would be accommodated with footpath.
The widening options will largely depend on the constraints and land use (mainly open country
v/s built-up). Both sides widening is the preferred option in areas of constraints on both sides of
road. One side widening may be preferred option in rural areas. In some curve/geometry
improvement areas and near bridges that need to be widened concentric/eccentric widening will
be considered based on the site conditions. In such cases, key criteria will be that existing ROW is
utilized to the maximum possible extent.
In location of geometric improvements, re-alignment is the option and may entail land
acquisition. Where land acquisition is not possible and therefore geometric improvement,
additional measures to mitigate the adverse effects on safety, have been considered. Bypasses
may be required in areas of some settlements that pose serious constraints for widening to 2 lane
standard. In this particular road, no re-alignment and bypasses are envisaged due to land
constraint.
The locations with eccentric widening are shown in Table 3.1 below.
The details of major and minor settlements and improvement proposals in built-up sections of
existing road are given in Table 3.2 and Table 3.3 below.
4 ALIGNMENT DESIGN
4.1 Introduction
The existing road is a single/ intermediate- lane/ 2-lane and has relatively good geometry. The
road has been proposed to be improved for design speed of 100/80 kmph.
The following IRC codes and standards have been referred to for finalizing the alignment.
The various alignment (horizontal and vertical) elements of any road comprise of:
Radius of curve
Super-elevation
Transition length
Extra widening
Vertical Curve length
Gradient
The above elements together are integral part of geometry of road. Adoption of various elements
in an appropriate manner, in accordance with IRC codes for safe movement of traffic is a major
design requirement and is detailed in the following sections.
4.2.1 General
As per the requirements of IRC: 73, the following guidelines were followed during the design:
The geometric design shall also be undertaken so as to minimize impact on trees, utilities,
properties, religious places and avoid extending beyond the existing right of way (ROW).
Site Specific
The Project road is a State Highway. ROW details in the form of boundary stones are not found
at site, therefore ROW details based on Sajra map and observed property lines are considered for
the design of alignment.
The horizontal alignment has been designed in such a way that additional land requirement
/acquisition is minimum (to nil) and the impact of widening is less on existing built up areas and
existing environmental and social features. The existing carriageway, structures/bridges etc. are
utilized to the extent possible unless proved otherwise.
In general, horizontal curves consist of a circular curve portion flanked by a spiral transition on
both ends. These shall correspond to the ruling minimum and absolute minimum design speeds
and the maximum permissible values of super-elevation as per IRC: 73:1980 guidelines.
For the roads in plain/ rolling terrain, for the design speed of 100 kmph, the radius of more than
360 m and for the design speed of 80 km/h, the radius of more than 230 m shall be provided in
design for the horizontal curves and is as per IRC:SP:73/IRC:73. Wherever possible and
permissible, higher radii will be adopted.
The minimum radii of horizontal curves for different terrain conditions considering a maximum
super-elevation of 5% is shown in Table 4.2.
Super Elevation
Super elevation is required for all the horizontal curves with radius less than 1800 m in order to
counteract the effect of centrifugal force. As per IRC: 38-1988, super-elevation to fully counteract
the centrifugal force for 75% of the design speed neglecting the lateral friction developed will be
adopted in design.
The maximum super elevation allowed as 7%, however maximum adopted is 5% on the project
road.
At sharp horizontal curves, it is necessary to widen the carriageway to provide for extra width
occupied by vehicle’s wheel path on curves and ensure safe passage of vehicle.
Widening is effected by increasing the width at an approximately uniform rate along the transition
curve. Extra width is continued over the full length of the circular curve.
Transition Curves - Transition curves are necessary for a vehicle to have smooth entry from a
straight section into a circular curve. The transition curves also improve aesthetic appearance of
the road besides permitting gradual application of the super-elevation and extra widening of
carriageway as may be needed at the horizontal curves.
The horizontal curves with radius of curvature < 1800 m for 100 Kph and <1100 m for 80 Kph,
transition curves are provided on both ends of circular curve.
Based on above methodology, the horizontal alignment has been designed using MX Road
software. The horizontal alignment details with intersection points along with radius are listed in
Table 4.3 below.
Extra widening at curves is proposed depending upon the radii that are less than 300m.
Due to constraints in ROW, large scale easing of sub-standard curves is not feasible. Wherever,
improvement of curves for design speed considerations is not possible, speed limitation has been
applied along with necessary safety measures.
4.3.1 General
The vertical alignment is proposed to provide for a smooth longitudinal profile consistent with
design speed, layout of the terrain and land-use . Too frequent grade changes cause kinks and
visual discontinuities in the profile. Considering this, a gap of 150m has been adopted between
two grades, mainly on sections with re-construction of pavement.
The existing road profile has been followed as far as possible, where the project road
improvement is limited to widening and strengthening of the existing road. In case where the
existing pavement has disintegrated and in sections which are prone to submergence,
reconstruction of the pavement has been proposed and the design road level have been fixed
taking into consideration the HFL.
Decks of small cross-drainage structures will conform to the profile of the new road section in
case of new construction / reconstruction. Where existing structures are retained, the profile of
the road has been suitably adjusted to avoid loading the existing deck with
overburden/surcharge.
Site Specific
Details of submergence have been collected local enquiry and discussions with PWD. These are
included in the Table 4.4 below.
The vertical profile has been suitably raised in these sections as per IRC:SP:73.
The vertical alignment details are provided in the Table 4.5 below.
Gradients - Grades have been selected carefully keeping in view the design speed, terrain
conditions and nature of traffic on the road.
The ruling and absolute maximum longitudinal gradients are recommended by IRC:SP:73 as
3.3% and 6.7% respectively for plain terrain. Similarly, for rolling terrain ruling & absolute
maximum gradients are 5.0% & 7.0% respectively. Profile design of existing carriageway has
been done keeping in view to minimize profile corrective course (PCC) quantity.
Minimum Gradient for Drainage – As per IRC 73, on un-kerbed pavements on embankment,
near level grades may be acceptable when the pavement has sufficient camber to drain the storm
water laterally. However, in cut sections, or roads at ground level, or where the pavement is
provided with kerbs, it is necessary to provide some gradient for efficient drainage.
Recommended minimum gradient for this purpose is 0.5% if side drains are lined and 1.0%, if
these are unlined.
Further, a minimum longitudinal gradient of 0.3% would be ideally adopted from drainage point
of view in re-construction sections.
Vertical Curves - These are introduced for smooth transition at grade changes. There are two
types:
Length of these curves is controlled by sight distance requirement, but curves with greater length
are aesthetically better and improves safety. Minimum lengths of vertical curves as per IRC: 73-
1980 and adopted are shown in Table 4.6 below.
Due to changes in grade in the vertical alignment of the road, vertical curves at the intersection
of the different grades will be provided in the design so as to smoothen the vertical profile
resulting in easing off of the changes in the gradients for the fast moving vehicles. Both summit
curves and valley curves will be introduced as per IRC guidelines.
Length of summit curves is governed by the choice of sight distance. Length of the valley curves
should be such that for night travel, the head light beam distance is equal to the stopping sight
distance. The lengths of the valley curves are worked out as per the guidelines and formula given
in the IRC: 73.
As per IRC recommendations, the minimum sight distance (Stopping sight distance) is 180 m for
100 Kph and 120m for 80 Kph.
The vertical profile of the existing road is having the grades which are within permissible limits as
per the terrain requirements. The profile will be smoothened by providing smooth vertical curves.
The profile of new and existing carriageway alignment has been designed with reference to the
existing profile. The proposed alignment has been designed with smooth gradients. The profile of
the existing road has many undulations, which have also been smoothened.
The details of vertical profiles are given in the drawing, enclosed in the Drawings Volume. The
given profile shows the proposed levels along the proposed center line along with the details
super elevation, extra widening and all existing features.
The existing road has been used to maximum extent possible. The maximum proposed road
gradient is 2.5% to provide a smooth longitudinal. The height of embankment has also been
raised considering the hydrological data and HFL criteria. The road is designed for intermediate
sight distance.
5 JUNCTIONS/ INTERSECTIONS
5.1 General
Intersections are important element of road and at grade intersections are very common. The
design scope covers improvement of existing at grade junctions and intersections. The main
objective of the intersection design is to minimize the severity of potential conflicts between cars,
buses, trucks, cycles and pedestrians, while facilitating the convenience, ease and comfort of
people traversing the intersections.
Intersection design should be fitted closely to the operating characteristics of users. Basic
elements that have been considered in intersection design are:
• Human Factors: driving habits of road users, reaction time of various road users
• Traffic Considerations
• Physical Elements: median and island provisions, land availability, traffic control devices,
drainage features etc.
• Economic Factors: cost of improvements.
Primary considerations are safety, smooth and efficient flow of traffic. Intersections are designed
having regard to flow, speed, composition, distribution and future growth of traffic. Design has to
be specific for each site with due regard to physical conditions of the site, the amount and cost of
land. Cost of construction and the effect of proposal on the neighborhood. Allowances for space
are needed to accommodate traffic signs, lighting columns where applicable, drainage, public
utilities etc.
Intersections are to be designed for peak hour volumes. Estimation of future traffic and its
distribution during peak hours is done on the basis of estimated traffic and by accounting form
factors like new development of land, socio-economic changes etc.
The radii of intersections curves depend on the turning characteristics of design vehicles their
numbers and the speed at which vehicles enter or exit the intersection area. In urban area
additional conditions like restriction of right of way widths, abutting developments, pedestrian
crossings, parked vehicles and high cost of land govern minimum radii at intersections. However,
to ensure traffic operation on arterial streets as per IRC SP:41, the common turning radii of 4.5 to
7.3 for passenger cars and 9m to 15 m for trucks and buses are recommended. And also in urban
area if curve radii is increased, the pedestrian crossing distance increases. Since this has
pedestrian safety implications, this should be kept in view while deciding on the turning radius to
be provided.
In hilly and rolling terrain, site condition governs the alignment, grade of the intersection. The
following are the basic principles to be given due attention during the design.
the intersecting roads shall meet at or nearly at right angle. However, angles above 60 o
do not warrant realignment;
intersection on sharp curves should be avoided because the superelevation and widening
of pavement complicates the design;
The gradient of intersecting highways should be as flat as practicable up to section that
are used for storage space; and
Grades in excess of 3 percent should, therefore, be avoided on intersections while those
in excess of 6 per cent should not be allowed.
Junctions/ Intersections should be avoided inside the horizontal curves; primarily sharp as
they obstruct the sightlines/ forward visibility
The specific intersection design depends on physical conditions of the site, such as topography,
available ROW, land use, development along the intersecting roads, expected volume of through
and turning traffic.
It is desirable to provide kerbs at the intersections in urban and sub-urban area. Kerbs are to be
of mountable type except for pedestrian refuge where these shall be non-mountable. In
intersection design the possible use of traffic control devices and other road furniture is
considered. The common types of traffic control devices are: road markings; road signs;
reflectors/ delineators and railings
The majority of the existing road junctions are formed with village and minor roads except and
there are a few junctions formed with BT road that necessitate careful design considerations. No
new intersections or junctions are envisaged. The major and minor intersections are as below:
Road junctions with village/ minor roads, typical standard designs as per MORTH are proposed
with appropriate modifications, considering the ROW constraint and additional safety measures.
Specific designs will also be produced, as necessary.
The vertical profile/ grade line of cross-roads would meet the project road without undue steep
gradients with a flat section adjoining mainline; with due consideration given to land and local
constraints.
6 PAVEMENT DESIGN
6.1 Introduction
Pavement design aims at determining the total thickness of the pavement structure as well as the
thickness of the individual structural components for carrying the estimated traffic loading under
the prevailing environmental conditions. Many design methods, from purely empirical to rigorous
analytical ones are available and these are practiced in different parts of the world. The design
methods adopted in other countries may not be applicable to Indian climatic conditions. In India,
the generally adopted method of design of flexible pavement is based on IRC: 37. Accordingly
IRC: 37-2012 “Tentative Guidelines for the Design of Flexible Pavements”, have been adopted.
The overlay design has been carried out based on the procedure outlined in IRC: 81-1997.
The AASHTO and IRC methods of pavement design have been reviewed before recommending
the pavement composition. However, in the perspective of such review, it is important to note
that no method in practice can be considered better than the other as each method has its own
inherent limitations, owing to the characteristics of materials used in construction and their
complex interaction, climatic and traffic conditions. The other methods of TAC and NAASRA may
not be applicable for the current project road pavement design due to limitations on fatigue
failure criteria and nature of materials considered in the design criteria does not suit the project
requirements and hence the same were not considered for pavement design.
This method of approach is based on empirical expressions obtained from the AASHO road tests.
This approach considers the ‘Present Serviceability Index’ (or PSI, the performance variable),
‘reliability’ (probability that the pavement system will perform its intended function over the
design life and under the conditions encountered during the operation period), resilient modulus
of sub-grade besides the constituent materials, drainage and climatic conditions.
This method gives the total required pavement composition in terms of the parameter ‘Structural
Number’ (SN, which is represented by the sum of the product of the layer coefficient, the
thickness expressed in inches and the drainage coefficient of each layer of pavement) and a
procedure to arrive at the individual pavement layer thicknesses in relation to the strength
characteristics of the pavement layers, defined as layer coefficients. An acceptable ‘serviceability’
is considered as a main design criterion in this method. The end of design life is considered in the
form of a terminal PSI, which usually corresponds to a minimum acceptable riding quality.
6.2.2 IRC: 37 – 2012, Tentative Guidelines for the Design of Flexible Pavements
The pavement designs given in this guide are based on the results of pavement research work
done in India and experience gained over the years on the performance of the designs given
therein. Flexible pavement has been modelled as a three-layer structure with stresses and strains
at critical locations computed using the linear elastic model FPAVE developed under the Ministry
of Road Transport & Highways Research Scheme, R – 56 and further updated it with IITPAVE
recently .
The pavement designs are given for sub-grade CBR values ranging from 2% to 15% for different
pavement type options like Cement Treated base and Sub base, use of RAP in asphalt layer with
foamed bitumen or emulsion. The pavement compositions given in the design catalogue are
relevant to Indian conditions, materials and specifications. Where changes to layer thickness and
specification are considered desirable from practical considerations, the guidelines recommend
modifications using an analytical approach. Hence, the design has been carried out based on the
procedure given in IRC: 37-2012.
The design shall be based on various design parameters as evaluated from various field and
laboratory investigations, design procedures with the objective to ascertain optimal pavement
structure meeting the structural requirements for the traffic and complying with the provisions of
the relevant codes and guidelines. The structural requirements are:
(i) The total thickness of the pavement and the thickness of individual layers should be
designed in such a way that they are not subjected to stresses or strains exceeding those
admissible in view of the material characteristics and performance factors,
(ii) The pavement layers should be able to with stand repeated applications of wheel loads of
different magnitudes under the actual conditions of sub grade, climate, drainage, and
other environmental factors during the design life without causing
a. excessive permanent deformation in the form of rutting and undulations;
b. cracking of bituminous layers; and
c. other structural and functional deficiencies such as potholes
(iii) Ensure structural and functional performance under varied conditions and factors
affecting the performance of the road i.e. soil type , traffic, environment, etc
Pavement design guidelines given in IRC:37-2012 adopts are based on the Analytical method
which is believed to have been developed based on performance of existing designs and using
analytical approach (to limit the vertical compressive strain at the top of sub grade and horizontal
tensile strain at bottom of bituminous layer adopting linear elastic model). Flow chart showing the
various steps involved in the design process is given in Figure 6.1 below.
Pavement Design
as per IRC
Finalization of Pavement
Thicknesses
Finalization of materials as
per MoRTH Specifications
Design life is the time from original construction to a terminal condition for a pavement structure.
Structural design is carried to withstand the pavement for a traffic loading encountered over the
design life. IRC: 37-2012 suggests design life of 15 years for the flexible pavements and
accordingly, design period of 15 years has been considered for the design of pavement.
A detailed traffic surveys and analysis for the project roads have been conducted in the year
2014, hereinafter called, “Base Year”. Detailed traffic projections over the design life and growth
rates obtained for different types of vehicles are discussed in traffic chapter. For the purpose of
pavement design, commercial vehicles of gross vehicle weight more than 3 ton have been
considered. Such vehicles consisted of buses, LCVs, 2 axle trucks, 3 axle trucks and multi axle
trucks.
From total projected base year AADT and estimated traffic growth rates, vehicle category-wise
traffic volume projections have been made for various design periods. Table 6.1 gives the total
projected base year (2014) traffic volumes in terms of AADT for each of the identified traffic
homogeneous section and has been used for the estimation of design traffic in terms of MSA for
pavement design.
The total projected traffic is the sum of generated traffic, induced and diverted traffic. The total
projected traffic on to the project road has been presented in Table 5.37 of Chapter 5.
Project specific comprehensive axle load surveys were conducted for each the project road to
estimate the loading behaviour of commercial vehicles plying on the project road. The detailed
analysis and raw data of axle loads collected from site from axle load surveys is provided in
Chapter-3, Surveys & Investigations of this report. The summary of VDFs is given in Table 6.2
below.
Adopted
Average
Rath-
Type of Commercial
Rath
VDF
VDF
Vehicles
The maximum VDF’s have been adopted in estimating the design traffic in MSA. These VDF
factors have been used for estimating MSA.
The strength of sub-grade in terms of California Bearing Ratio (CBR) is required for the design of
new flexible pavement as per IRC: 37-2012. Consultants have explored the potential sources of
suitable borrow areas with minimal leads from the project road by enquiring from local
inhabitants. The details of borrow materials investigation and testing have been briefly covered in
the surveys and Investigations chapter. As per MoRT&H clause 305, the borrow earth material
shall satisfy the following engineering properties for use in the sub grade and embankment.
From laboratory test results of soil samples collected from few borrow areas along the project
alignment it was found that the available soil type is well graded with CBR values varying from
6.9 to 12.1 % and they also satisfy the above basic index properties. The soils in sufficient
quantity are available in the close vicinity of the project area. The CBR of 8% has been
considered as design CBR for subgrade construction as 9 out of 16 borrow soil areas are having ≥
8% CBR and FSI ≤ 20. However during construction the contractor can identify more borrow
areas in the close vicinity of the project for getting suitable material for subgrade and earthwork
construction. The borrow areas having CBR < 8% can be used in earthwork/embankment
construction.
Base year traffic (vehicle category-wise & in terms of AADT), traffic growth rates, design life (in
terms of number of years) and vehicle damage factors are required to estimate the design traffic
in terms of equivalent standard axles. The following data have been considered to arrive at the
design traffic (MSA).
With the base year traffic in terms of CVPD, annual growth rate of each of commercial vehicle
over the design period, design traffic in terms of MSA over the design life can be estimated using
the following formula.
Design of new flexible pavement applies to the widened portions of existing carriageway lanes
including paved shoulders. Paved shoulders are proposed to be constructed to the same standard
as the main carriageway and thus forming an integral part of the paved carriageway. The design
also applies to reconstruction stretches where the existing crust is much less than the required
design thicknesses and the existing BT layers are cracked; potholed, patched and are in poor
condition. In such cases, the existing bituminous surfacing (BT layers) are completely removed
and then the pavement is built up with WMM and bituminous layers.
Test pits were excavated along the existing road to understand the existing pavement
composition and layer thicknesses. The observed details are given in Table 6.4 below:
BT Non BT Total
Max 140 570 650
Min 0 210 260
Avg 67 383 450
With the design traffic loading in MSA and the sub grade strength in terms of CBR, the pavement
composition has been worked out by IRC catalogue design procedure to account for the design
period of 15 years. 500mm thick sub grade will be placed on embankment top layer. This layer
will also be constructed with selected borrow area soils with 8% CBR, and over which the
pavement crust will be built. The pavement structure has been worked out for all the
homogeneous sections of the project road and is given in Table 6.5 below.
Table 6.5: Proposed Pavement Composition and Thickness for New and
Reconstruction of Pavement
Traffic Chainage (km) New Construction/ Widening Reconstruction by Removing
Homogenous Traffic
From To Length CBR (mm) the BT Layers (mm)
Sections
(THS) (km) (km) (km) (msa) BC DBM WMM GSB Total BC DBM WMM GSB Total
2+065 18+500 16.435 108 8 Rigid Pavement Nil
THS-1 18+500 19+000 0.500 108 8 Rigid Pavement Reconstruction of Subgrade
19+000 36+000 17.000 108 8 50 145 250 200 645 50 145 250 0 445
36+000 42+000 6.000 30 8 40 100 250 200 590 Overlay
42+000 44+000 2.000 30 8 40 100 250 200 590 40 100 250 0 390
THS-2 44+000 52+300 8.300 30 8 40 100 250 200 590 Overlay
52+300 65+500 13.200 30 8 40 100 250 200 590 40 100 250 0 390
65+500 74+850 9.350 30 8 40 100 250 200 590 Overlay
Total 72.785
Drainage Layer – Considering the requirements of drainage, as per the provisions of IRC: SP:
42, the GSB layer for full thickness shall be extended over entire formation width i.e. till the
embankment slope on both sides of the pavement carriageway.
A part of road section from Design Ch. 2+065 to Ch. 18+000 (L=16.935 km) is used by trucks
carrying wet sand mined from nearby Betwa River. The water drips down from the trucks on the
pavement surface all along the road way and has damaged the pavement in the form of
stripping, cracking, potholes including base course failure. Rigid pavement is proposed in this
length of 16.935km as dripping of water on concrete surface will not result in “stripping”.
In order to provide a stable construction platform and non-erodible support for PQC, a DLC sub-
base, 150mm thick, is included as part of the pavement structure. Similarly, a layer of relatively
open graded GSB Gr-6 (as per IRC:58-2015 Table VI-I), 150mm thick above the sub grade has
been considered for drainage of water to prevent excessive softening of sub grade and prevent
erosion of the sub grade under adverse moisture condition.
A separation membrane of 125 micron polyethylene is considered to be placed between PQC and
DLC to reduce inter-layer friction.
The rigid pavement structure has been worked out (Appendix – 6.1) for this section of the
project road and summary is given in Table 6.6 below.
The dimensions of dowel bars & tie bars are given below:
The design of overlay for the existing pavement of project roads has been done taking into
account the strength of the existing pavement based on BBD testing. The BBD testing has been
carried out on all project roads and deflections were measured for the identified homogeneous
sections of similar performance based on the pavement condition. The summary of data analysis
for overlay design is presented in below table.
The BBD values vary from 1.64mm to 1.2mm with average value of 1.4mm for the entire project
length.
Design of overlay is based on IRC: 81, “Guidelines for strengthening of flexible pavement using
Benkelman Beam deflection Technique”, which provides design curves relating to characteristic
deflection (Dc) to the cumulative number of standard axles to be carried over the design life.
These curves (fig 9 of IRC: 81) give the thickness of BM overlay to be placed over an existing
road against the cumulative number of standard axles and characteristic deflection.
The thickness obtained from design curves is the overlay thickness in terms of Bituminous
Macadam. This thickness is converted into BC and DBM by taking a conversion equivalency 0.70
AC/DBM for 1 part of BM as per the guidelin1es of IRC: 81
As per IRC: SP: 73, the minimum design life of 10 years or operation period has to be adopted.
The design life adopted for the new designs is 15 years; accordingly the design life of 15 years
has been adopted for overlay sections to match with new pavement design.
The long term satisfactory performance of pavements is influenced by the pavement ingredient
materials and their properties. In bituminous pavements besides stone aggregates, the
bituminous binder is the key ingredient which makes its selection an important task. It is the
costliest component of the bituminous mix. In India, the bitumen grading was practised until
1992 on the basis of penetration test, which is conducted at a temperature of 25°C, and 60/70
penetration grade bitumen, was widely used. The most common problem in the performance of
bituminous mix with this binder was rutting during hot summer. The bitumen becomes soft in the
60 to 70°C temperature range (typical road surface temperature on a hot summer day) and starts
to push and shove under loaded truck tyres leading to rutting and corrugations in the wheel
tracks of the roadway. To minimise this problem, the BIS switched over from Penetration based
grading system (IS: 73-1992) to Viscosity based grading system (IS: 73-2006). This standard has
been further revised and the current standard is IS: 73-2013 (Paving Bitumen-Specifications).
The MORTH Specifications for Road and Bridge Works 5th revision allows use of both viscosity
grade bitumen and modified bitumen. It is proposed to use modified bitumen complying with the
IRC: SP: 53 and IS: 15462 for BC. For DBM layer VG30 bitumen is proposed for the present
project.
The project area lies in the region where the 7 days average maximum air temperature is in the
range from 38°C to 45°C and the lowest daily mean air temperature is more than -10oC. Hence
modified bitumen satisfying the properties given in column (5) of Table 2 of IRC: SP: 53 – 2010
which correspond to the ‘Highest Mean Air Temperature Above 35 0C and ‘Lowest Mean Air
Temperature Above (-) 10 0C is recommended for BC layer i.e. the top wearing course layer,
except the softening point. The softening point requirement is required to be increased from
60 0C to 65 0C [S.N. (ii) of Table 2 of IRC: SP: 53 – 2010] as the maximum temperature in the
project area exceeds 40 0C in summers.
The modified bitumen requires the use of appropriate industrial process and plant with high shear
mill, and testing facilities to achieve stable and homogeneous mix. Transportation tanks and
storage tanks need to be insulated and equipped with effective heating system and circulation/
agitating device to maintain the specified temperature, homogeneity and viscosity of bitumen
during transit and storage. The contractor will be required to fulfil all the requirements as
specified in the IRC: SP: 53 – 2010 “Guidelines on use of Modified Bitumen in Road Construction
for manufacture, transportation, storage, design of mixes, construction operations, quality
assurance plan at site etc.
To increase fatigue life of pavement, higher bitumen content of 0.55% than the optimum has
been considered with 3% air voids in DBM mix. Hence minimum bitumen content proposed for
DBM is as under:
Before implementing the overlay, the existing surface irregularities shall be corrected and brought
to proper profile by filling the cracks, pot holes, ruts and undulations. Based on the pavement
condition survey, major distresses noticed are potholes, cracking, patching, raveling at few
locations,. These defects would require rectification before placing an asphalt overlay. The
suggested remedial measures are given below in Table 6.9.
Suggested Treatment
Description
Description of Treatment Materials to be Use Execution Steps
a) Mark out the area with chalk
(draw a rectangle around
defect)
b) Excavation of area: Remove all
material of road surface from
the marked out area and apply
tack coat.
c) Increase depth of hole until
firm dry material is found.
Trim the walls of the hole to
be vertical. Remove all
moisture
d) Trim bottom of hole so that it
is flat horizontal and free of
Pothole Related to Bituminous
Pothole patching loose material and compacte)
patching Concrete
Fill hole with selected well
graded material.
f) Place material in the hole and
compact in one or more
layers. The last layer to have
greater thickness (1/5th extra)
to allow for settlement after
compaction
g) For compaction, use vibratory
roller, plate compactor or
rammer depending on size of
excavation
h) Reseal with thin surfacing to
prevent penetration of water
a) Air blow and clean.
b) Sweep the area (surface must
be dry and clean)
c) Prepare bitumen slurry by
Sealing with bituminous Related to Bituminous mixing 6 litres of bitumen
Ravelling
slurry Concrete emulsion with20 litres of
coarse sand (< 5mm)
d) Spread the slurry and
squeegee in thin layer (5 mm
thick) over marked Area
a) Air blow and clean.
b) Sweep the area (surface must
be dry and clean)
c) Prepare bitumen slurry by
Rectified
Bituminous emulsion mixing 6 litres of bitumen
Shoved Local Sealing
& coarse sand emulsion with20 litres of
portion
coarse sand (< 5mm)
d) Spread the slurry and
squeegee in thin layer (5 mm
thick) over marked area.
Plastic
movement of
a) Remove the shoved area
pavement
Replacement of shoved Related to Bituminous (minimum 30mm below
materials
materials Concrete adjoining level).
resulting in
b) Fill with thin surfacing BC mix
localized
bulging
The existing granular or black-topped surface for laying bituminous course shall be prepared as
per Section 501.8 of the MORT&H specifications.
A profile corrective course for correction of any deficiency in profile/ camber or super elevation of
the existing carriageway shall be provided as per Section 501.8.3.4 of the MORT&H specifications.
Profile Correction Course (PCC) criteria for reconstruction sections are given in following tables:
After the PCC, granular/ bituminous layers as estimated above shall be provided.
Interlocking concrete block pavement option is proposed for truck lay bye locations. The choice of
concrete block pavement option has been based on following technical advantages:
Technical Advantages
Paving blocks are manufactured from high strength, low absorption concrete in controlled
conditions, ensuring high quality control. High/low temperatures, moisture, petrochemicals do not
damage them. They offer high frictional resistance. They come to construction site as a finished
product, and require no curing, allowing traffic immediately after installation.
Paving blocks can be easily removed in order to correct pavement distress, or to allow utility
repair etc. Paving blocks have a good record of long-term performance under heavy loads in
industrial, airport and port applications also.
Short/ long duration parking of trucks is envisaged at the truck lay-bye areas. Hence these areas
will experience POL droppings from the truck engines and water spills [from trucks carrying wet
sand from Betwa River] for which concrete blocks will be more durable compared to bituminous
surface.
Uneven and differential deformation of subgrade/ underlying soils is more easily handled by
interlocking paving blocks as they can withstand greater deformation than conventional
pavements while remaining in service.
IRC: SP: 63 – 2004, “Guidelines for the use of interlocking concrete block Pavement”
In order to provide a stable construction platform and firm support for CC blocks, a granular
aggregate base course (WMM), 250mm thick, is included as part of the pavement structure. To
provide a cushion between block pavements and base a layer of sand bedding is provided.
Similarly, a layer of open graded GSB, 250mm thick above the sub grade has been considered for
drainage of water to prevent excessive softening of sub grade and prevent erosion of the sub
grade under adverse moisture condition.
The laboratory and field test results for the subgrade soils are presented in Table 6.14 and
Table 6.15.
Bottom-up Cracking Fatigue Analysis for Day-time (6 hour) traffic and Positive Temperature Differential
Top-Down Cracking Fatigue Analysis for Night-time (6 hour) traffic and Negative Temperature Differential
Expected Flex Stress Allowable Fatigue Expected Stress Allowable Fatigue Expected Flex Stress Allowable Fatigue
Flex Stress
Repetitions Stress Ratio Repetitions Damage Repetitions Ratio Repetitions Damage Repetitions Stress Ratio Repetitions Damage
MPa
(ni) MPa (SR) (Ni) (ni/Ni) (ni) (SR) (Ni) (ni/Ni) (ni) MPa (SR) (Ni) (ni/Ni)
- 2.629 0.531 220,107 0.000 - 2.655 0.536 185,959 0.000 - 2.586 0.522 297,674 0.000
19,576 2.578 0.521 317,308 0.062 - 2.604 0.526 262,928 0.000 - 2.535 0.512 445,603 0.000
- 2.526 0.510 479,042 0.000 24,745 2.552 0.516 387,356 0.064 - 2.483 0.502 706,107 0.000
- 2.474 0.500 767,557 0.000 24,745 2.500 0.505 601,248 0.041 - 2.431 0.491 1,206,828 0.000
- 2.423 0.489 1,331,811 0.000 222,706 2.448 0.495 999,396 0.223 - 2.379 0.481 2,292,103 0.000
- 2.371 0.479 2,585,152 0.000 49,490 2.397 0.484 1,824,608 0.027 - 2.328 0.470 5,095,677 0.000
58,727 2.319 0.468 5,946,638 0.010 24,745 2.345 0.474 3,818,406 0.006 - 2.276 0.460 14,703,637 0.000
19,576 2.267 0.458 18,240,912 0.001 - 2.293 0.463 9,928,681 0.000 - 2.224 0.449 infinite 0.000
19,576 2.216 0.448 infinite 0.000 24,745 2.241 0.453 38,536,570 0.001 - 2.172 0.439 infinite 0.000
39,152 2.164 0.437 infinite 0.000 24,745 2.190 0.442 infinite 0.000 - 2.121 0.428 infinite 0.000
19,576 2.112 0.427 infinite 0.000 - 2.138 0.432 infinite 0.000 - 2.069 0.418 infinite 0.000
19,576 2.060 0.416 infinite 0.000 - 2.086 0.421 infinite 0.000 3,450 2.017 0.408 infinite 0.000
- 2.009 0.406 infinite 0.000 123,726 2.035 0.411 infinite 0.000 - 1.966 0.397 infinite 0.000
- 1.957 0.395 infinite 0.000 - 1.983 0.401 infinite 0.000 - 1.914 0.387 infinite 0.000
- 1.905 0.385 infinite 0.000 98,980 1.931 0.390 infinite 0.000 - 1.862 0.376 infinite 0.000
- 1.853 0.374 infinite 0.000 24,745 1.879 0.380 infinite 0.000 - 1.810 0.366 infinite 0.000
- 1.802 0.364 infinite 0.000 24,745 1.828 0.369 infinite 0.000 - 1.759 0.355 infinite 0.000
548,121 1.750 0.354 infinite 0.000 272,196 1.776 0.359 infinite 0.000 44,854 1.707 0.345 infinite 0.000
665,576 Fat Dam from Sing. Axles = 0.073 593,883 Fat Dam from Tand Axles = 0.362 48,304 Fat Dam from Tridem Axles = 0.000
Total Top-Down Fatigue Damage = 0.073 + 0.362 + 0.000 = 0.435
DESIGN IS SAFE SINCE SUM OF CFD FOR BUC AND TDC< OR EQ.1
101 . 6 bd f
Fb = 26.709 Mpack
95 . 25
Assumed spacing between dowel bars 180 mm
First dowel bar is placed at a distance 150 mm from pavement edge
Dowel bars up to a distance of 1.0 x radius of relative stiffness (l), from the point of load application are effective in load transfer
Number of dowel bars participating in load transfer when the wheel load is just over the dowel bar close to the edge of the slab = 4 Nos.
Assuming that the load transferred by the first dowel is Pt and that load on dowel bar at a distance of 1 from the first dowel is zero
The total load transferred by dowel bar system………… 2.421 Pt
Hence, the dowel bar spacing and diameter assumed are safe
Design Parameters:
Area of deformed Steel bar required per meter width of joint to resist the frictional b f W 182.7 sq.mm/m
A s
S
force at slab bottom, As st
Increase length by 100 mm for loss of bond due to painting and another 50 mm for tolerance in placement………. 487.8 + 100 + 50 = 637.80 Say length (mm) 640
DESIGN CONCLUSIONS:
I) Provide pavement thickness of 300mm Pavement Quality Concrete ( PQC ) having 28-days Flexural and Compressive Strengths 4.5 MPa and 40 MPa respectively over 150 mm Dry Lean
Concrete Subbase with a minimum 7-Day Compressive Strength of 7 MPa with 38 mm diameter Dowel bars of length 500 mm at a spacing of 180 mm and deformed Tiebars of 12 mm
diameter, 640 mm length at a spacing of 600 mm (c/c).
II) Provide a drainage layer (GSB) of 150 mm thickness with a drainage coefficient of min. 350 m per day.
7 GEOTECHNICAL INVESTIGATIONS
7.1 Introduction
To carry out the geotechnical investigation at proposed bridges (widening/new), EGIS appointed
M/s. CE Testing Company Pvt. Ltd. This report contains the following information;
For the given road, we have carried out soil exploration at 4 bridge locations in order to:
obtain soil samples, both representative and undisturbed (wherever necessary) for
classification tests and other laboratory tests for determining its engineering properties &
studying various foundation options;
obtain soundings of penetration resistance by Standard Penetration test in the soils;
The summary of field data and laboratory test results is presented in Appendix-7.2.
The investigation was planned to obtain the subsurface stratification in the proposed project site
and collect soil samples for laboratory testing to determine the engineering properties such as
shear strength, along with basic engineering classification of the subsurface stratum to arrive at
the foundation design parameters.
The boreholes of 150 mm diameter were progressed using rotary rig to the specified depth.
Where caving of the borehole occurred, casing was used to keep the borehole stable. The work
was performed in general accordance with IS: 1892-1979.
Standard Penetration Tests (SPT) were conducted as per IS specifications. SPT split spoon
sampler of standard dimensions is driven into the soil from the borehole bottom using 63.5 kg
Hammer falling from 75 cm height. The SPT weight is mechanically lifted to the specified height
and allowed to fall freely on the anvil with the use of cat-head winch with one to one and half
turn of the drum. Blow counts for the penetration of every 15 cm are recorded and the N is
reported as the blow counts for 30 cm penetration of the sampler leaving the first 15 cm
penetration as seating drive.
When the number of blows exceeded 50 to penetrate the first or second 15 cms length of the
sampler, the SPT N is regarded as more than 100. The test is terminated in such case and a
record of penetration of the sampler under 50 blows or more is made. SPT refusal is recorded
when there is no penetration of the sampler at any stage and also when a rebound of the
sounding system is recorded.SPT ‘N’ values are correlated with relative density of non-cohesive
stratum and with consistency of cohesive stratum.
Disturbed soil collected in the SPT sampler was preserved in polythene covers and transported to
the laboratory. One more polythene cover was provided to prevent the loss of moisture during
the transit period.
Undisturbed samples were collected using 100mm diameter and 450mm long MS tubes provided
with sampler head with ball check arrangement. Undisturbed soil samples were collected in soft
to stiff clayey soils. Collection of undisturbed samples in refusal strata is practically not possible.
The subsoil is characterized by a stiff to very stiff, silty clay / clayey silt layer followed by a hard,
silty clay / clayey silt layer is encountered and that continued up to the terminating depth of both
the boreholes. The layer wise descriptions are presented below.
Stratum – I :
The soil in this layer is characterized by a stiff to very stiff, brownish grey / grayish brown to
reddish brown, silty clay / clayey silt layer. Kankars & Sand mixture have been observed in this
layer. The average “N” value of this layer is 17.
Stratum – II :
The soil in this layer is characterized by hard, grayish brown to reddish brown, silty clay / clayey
silt with fine sand & mica. The average “N” value of this layer is 47.
The subsoil is characterized by a top soil followed by a stiff, clayey silt layer. Underlying the
above, a very stiff to hard, silty clay / clayey silt layer is encountered and that continued up to
the terminating depth of the borehole. The layer wise descriptions are presented below.
Stratum – I :
The soil in this layer is characterized by a stiff, greyish brown, clayey silt layer. Light grey patches
& mica have been observed in this layer. The “N” value of this layer is 10.
Stratum – II :
The soil in this layer is characterized by a hard, greyish brown, silty clay / clayey silt layer. Light
grey spots have been observed in this layer. The average “N” value of this layer is 44.
The subsoil is characterized by a stiff to very stiff, silty clay / clayey silt layer followed by a
medium dense, silty sand layer is observed. Underlying the above, a hard, silty clay / clayey silt
layer is encountered and that continued up to the terminating depth of the borehole.
Stratum – I :
The soil in this layer is characterized by a stiff to very stiff, grayish brown, clayey silt / silty clay
layer. Light grey patches & Sand mixture have been observed in this layer. The average “N” value
of this layer is 14.
Stratum – II :
The soil in this layer is characterized by a medium dense, grayish brown, silty sand. Clay binder
have been observed in this layer. The corrected “N” value of this layer is 18.
Stratum – III :
The soil in this layer is characterized by a hard, grayish brown, silty clay / clayey silt layer. Sand
mixture have been observed in this layer. The “N” value of this layer is 40.
The subsoil is characterized by a stiff to very stiff, silty clay / clayey silt layer. A medium dense,
silty sand layer follows the above. After that, a very dense, silty sand layer is encountered and
that continued up to the terminating depth of the borehole.
Stratum – I:
The soil in this layer is characterized by a stiff to very stiff, brownish grey to greyish brown, silty
clay / clayey silt with sand mixture. Gravels have been observed in this layer. The average “N”
value of this layer is 20.
Stratum – II:
The soil in this layer is characterized by medium dense, brownish grey, silty sand. Mica and clay
binder have been observed in this layer. The average corrected “N” value of this layer is 15.
Stratum – III:
The soil in this layer is characterized by very dense, brownish grey, silty sand. Mica and clay
binder have been observed in this layer also. The average corrected “N” value of this layer is 46.
7.5.2 Groundwater
The following table summarizes the measured groundwater depths in the completed boreholes:
There are no Sub-soils that consist of loose fine sand / silty sand under shallow ground water
table. Hence site may be classified as “Liquefaction unlikely” in earthquake event.
Shallow foundations bearing on the natural / untreated soils are a feasible foundation option.
Bearing capacity analysis was carried out based on the shear parameters (c- ), as interpreted
from field and laboratory tests to determine the safe net bearing capacity (shear criterion).
qnet safe = safe net bearing capacity of soil, based on the shear failure criterion.
c = cohesion intercept
= angle of internal friction
= total unit weight of soil
p = overburden pressure
B = width of foundation
Rw = water table correction factor
F = Factor of safety, taken as equal to 2.5 in accordance with
IS:1904
Appropriate values have been substituted into the bearing capacity equation given above to
compute the safe net bearing capacity. The values have been checked to determine the
settlement of the foundation under the safe bearing pressure. The allowable bearing pressure
has been taken as the lower of the two values computed from the bearing capacity shear failure
criterion as well as that computed from the tolerable settlement criterion.
In predominantly granular soils, settlement analysis has been performed based on the SPT values
in accordance with Clause 9.1.4 of IS 8009 (Part 1) - 1976 Fig.9.
Where applicable (typically where substantial incremental stresses are anticipated in cohesive
strata below groundwater table), settlement analysis has been performed based on classical
theory; as the sum of elastic settlement and consolidation settlements. The elastic settlement is
calculated in accordance with Clause 9.2.3 of IS 8009 Part 1-1976. The consolidation settlement
is computed in accordance with Clause 9.2.2 of IS 8009 (Part 1)-1976.
The soils at the project site are predominantly clayey soils. As per IRC 78-2014, clause 703.2.2.2,
the silt factors at various borehole locations are calculated based on the Appendix-1 guidelines
and are presented below:-
Cohesion Calculate
Chainage BH
Layer Depth (M) (Kg/sq d Silt
(Km) No.
cm) Factor
I (Stiff to Very stiff, silty clay) 0.00-9.50 0.41 3.28
A1
II (Hard, silty clay) 9.50-15.0 1.10 4.09
25.900
I (Stiff to Very stiff, silty clay) 0.00-9.00 0.85 3.84
A2
II (Hard, silty clay) 9.50- 15.0 1.31 4.28
Top Soil 0.00-1.30 -- --
47+900 A1 I (Stiff , clayey silt) 1.30-3.55 1.52 3.90
II (Very Stiff to hard , silty clay / clayey silt) 3.55-15.00 1.09 4.08
69+950 A1 I (Stiff to Very stiff, silty clay/clayey Silt) 0.00-15.00 0.79 3.77
I (Stiff to Very stiff, silty clay / clayey silt) 0.00-10.30 1.12 3.60
II (Medium dense to dense, clayey silty sand / silty 10.30-
72+550 -- 0.951
sand) 14.50
14.50-
III (Very dense, silty sand) -- 0.909
15.00
The silt factor is considered as maximum 2.4 for the purpose of scour calculations. The scour
depth calculations were done by our hydrologist and the scour data has been provided as below:
Based on the subsurface conditions, the various foundation options for different structures are
summarized below:
Chemical tests were performed on few soil and water samples for determining the pH value,
Sulphate, Chloride etc. The results are given below:
a) Bridge at Km 25+900
Sulphate as
BH No. Depth (M) pH value Chloride as (mg/litre)
(mg/litre)
A1 2.75 7.32 60 21.3375
A2 2.50 7.28 60 25.6049
It is seen that the values are on a safe side and so no precaution will be required for foundation
concrete. Either Ordinary Portland Cement or Portland slag Cement or Portland
Pozzolana cement can be used for concreting.
b) Bridge At Km 47+900
It is seen that the values are on a safe side and so no precaution will be required for foundation
concrete. Either Ordinary Portland Cement or Portland slag Cement or Portland
Pozzolana cement can be used for concreting.
c) Bridge At Km 69+950
Sulphate as
BH No. Depth (M) pH value Chloride as (mg/litre)
(mg/litre)
A1 4.80 7.77 60 25.6049
It is seen that the values are on a safe side and so no precaution will be required for foundation
concrete. Either Ordinary Portland Cement or Portland slag Cement or Portland
Pozzolana cement can be used for concreting.
d) Bridge at Km 72+550
Sulphate as
BH No. Depth (M) pH value Chloride as (mg/litre)
(mg/litre)
A1 6.90 7.67 180 105.2649
It is seen that the values are on a safe side and so no precaution will be required for foundation
concrete. Either Ordinary Portland Cement or Portland slag Cement or Portland
Pozzolana cement can be used for concreting.
6.30M
CH. =25.900KM
( LOCATION / VILLAGE
=> CHHARI )
M
6.80
2.10M
BH-A1
( Road Level ) ELECTRICAL POLE
10.30M
LEGEND:-
BORE HOLE
HAMIRPUR
Page 1 of 4
Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, UP.
RATH
A2
P3
P2
P1
M
70
3.
BH-A1
( Below Road Level-2.30m )
A1
3.10M
LEGEND:-
BORE HOLE --
HAMIRPUR
Page 2 of 4
RATH
A2
P2
0M
4.3
3.00M
P1
BH-A1
( Below Road Level= 3.30m )
A1
LEGEND:-
HAMIRPUR
BORE HOLE --
Page 3 of 4
RATH
A2
3.30M
BH-A1
6 0M
3.
P2
P1
A1
HAMIRPUR LEGEND:-
BORE HOLE ---
Page 4 of 4
APPENDIX – 7.2
Unconfined Compressive
Dry Density in gms/cm 3
Symbolic representation
below
Depth of Sample below
% Silt 0.06-0.002mm
% Clay<0.002mm
reference
Specific Gravity
Percent RQD
reference level
at Laboratory
Content (%)
Void Ratio
Resistance in Deg.
Remarks
Angle of Shearing
SO 4 (%)
Depth in Metre
Cl (%)
pH
Cohesion C
Visual Description of Soil
(kg/cm )
2
Value
From
To
Unconfined Compressive
Dry Density in gms/cm 3
Symbolic representation
below
Depth of Sample below
% Silt 0.06-0.002mm
% Clay<0.002mm
reference
Specific Gravity
Percent RQD
reference level
at Laboratory
Content (%)
Void Ratio
Resistance in Deg.
Remarks
Angle of Shearing
SO 4 (%)
Depth in Metre
Cl (%)
pH
Cohesion C
Visual Description of Soil
(kg/cm )
2
Value
From
To
116.702 8.00 8.45 8.00 SPT-05 8.00 20 Very stiff, greyish brown to reddish
brown, clayey silt. Obs. Sand mixture.
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
0.002
0.075
0.425
4.75
Grain size (mm)
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
2
4.75
0.002
0.075
0.425
Grain Size(mm)
Project:- Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, Bridge at
UP. 25+900km
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
0.002
0.075
0.425
4.75
Grain size (mm)
Project:- Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, Bridge at
UP. 25+900km
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
0.002
0.075
0.425
4.75
Grain size (mm)
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
2
4.75
0.002
0.075
0.425
Grain Size(mm)
Project:- Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, Bridge at
UP. 25+900km
Project : Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, UP.
e-logp Curve
0.700
0.690 BORE HOLE : A1
UDS NO : 01
0.680
DEPTH (M) : 3.00
0.670 e0 : 0.692
0.660
0.650
0.640
0.630
0.620
0.610
0.600
0.590
0.580
VOID RATIO
0.570
0.560
0.550
0.540
0.530
0.520
0.510
0.500
0.490
0.480
0.470
0.460
0.450
0.440
0.430
0.420
0.10 1.00 10.00
PRESSURE RANGE KG / SQCM
Project : Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, UP.
e-logp Curve
0.540
BORE HOLE : A1
0.530 UDS NO : 03
DEPTH (M) : 10.00
0.520
e0 : 0.541
0.510
0.500
0.490
0.480
0.470
0.460
VOID RATIO
0.450
0.440
0.430
0.420
0.410
0.400
0.390
0.380
0.370
0.360
0.350
0.10 1.00 10.00
PRESSURE RANGE KG / SQCM
Project : Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, UP.
e-logp Curve
0.540
BORE HOLE : A2
0.530 UDS NO : 02
0.520 DEPTH (M) : 6.00
e0 : 0.542
0.510
0.500
0.490
0.480
0.470
0.460
VOID RATIO
0.450
0.440
0.430
0.420
0.410
0.400
0.390
0.380
0.370
0.360
0.350
0.340
0.10 1.00 10.00
PRESSURE RANGE KG / SQCM
Project : Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, UP.
e-logp Curve
0.590
BORE HOLE : A2
0.580 UDS NO : 03
0.570 DEPTH (M) : 9.00
0.560 e0 : 0.585
0.550
0.540
0.530
0.520
0.510
0.500
VOID RATIO
0.490
0.480
0.470
0.460
0.450
0.440
0.430
0.420
0.410
0.400
0.390
0.380
0.370
0.360
0.10 1.00 10.00
PRESSURE RANGE KG / SQCM
BRIDGE AT 47+900KM
FIELD & LAB TEST RESULTS
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, UP. Commencement Date : 18/10/2014 Level of Ground : 136.600 M Job No : 3367-32
Bore Hole No. : A1 Location : Ch.KM.47.900 Completion Date : 21/10/2014 Standing Water Level : 8.70 m Sheet No :
Depth in Mete
Unconfined Compressive
Dry Density in gms/cm 3
Symbolic representation
below
Depth of Sample below
% Silt 0.06-0.002mm
% Clay<0.002mm
reference
Specific Gravity
Percent RQD
reference level
at Laboratory
Content (%)
Void Ratio
Resistance in Deg.
Remarks
Angle of Shearing
SO 4 (%)
Depth in Metre
Cl (%)
pH
Cohesion C
Visual Description of Soil
(kg/cm )
2
Value
From
To
Top Soil
135.600 1.00 1.00 DS-02 silty clay with decompsed roots &
boulder.
135.100 1.50 1.95 1.50 SPT-01 1.50 10 11 77 12 2.73 37 21
1.30m
134.100 2.50 2.50 DS-03
Stiff, greyish brown, clayey silt. Obs.
CI
133.600 3.00 3.40 3.00 *UDS-01 mica & light grey spots.
133.050 3.55 3.95 3.55 UDS-02 3.55m UU 14 78 8 1.85 2.74 16 34 18 15 1.52 8
130.100 6.50 6.63 6.50 *UDS-03 Hard, greyish brown, silty clay with
gravels. Obs. light grey spots.
129.800 6.80 7.25 6.80 SPT-04 6.80 68 43 19
124.600 12.00 12.00 DS-09 Very stiff to hard, greyish brown, silty
clay / clayey silt. Obs. light grey spots.
124.100 12.50 12.95 12.50 UDS-05 UU 10 83 7 1.57 2.73 25 33 19 0.91 0
Undisturbed (UDS) Penetrometer (SPT) Disturbed (DS) Water Sample (WS) R = Refusal
* means sample could not be recovered Note: Chemical Test results for Water Samples for Chloride & Sulphate is given as mg/Litr &
for soil samples SO4 content is expressed as SO3.
B.D.L=Below Detection Limit
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
0.002
0.075
0.425
4.75
Grain size (mm)
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
2
4.75
0.002
0.075
0.425
Grain Size(mm)
Project:- Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, Bridge at
UP. 47+900km
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
0.002
0.075
0.425
4.75
Grain size (mm)
Project:- Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, Bridge at
UP. 47+900km
Project : Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, UP
e-logp Curve
0.520
BORE HOLE : A1
UDS NO : 04
0.510 DEPTH (M) : 9.50
e0 : 0.518
0.500
0.490
0.480
0.470
VOID RATIO
0.460
0.450
0.440
0.430
0.420
0.410
0.400
0.10 1.00 10.00
PRESSURE RANGE KG / SQCM
BRIDGE AT 69+950KM
FIELD & LAB TEST RESULTS
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, UP. Commencement Date : 10/10/2014 Level of Ground : 149.000 M Job No : 3367-02
Bore Hole No. : A1 Location : Ch.KM. 69.950 Completion Date : 10/10/2014 Standing Water Level : 4.80 m Sheet No :
Depth in Mete
Unconfined Compressive
Dry Density in gms/cm 3
Symbolic representation
below
Depth of Sample below
% Silt 0.06-0.002mm
% Clay<0.002mm
reference
Specific Gravity
Percent RQD
reference level
at Laboratory
Content (%)
Void Ratio
Resistance in Deg.
Remarks
Angle of Shearing
SO 4 (%)
Depth in Metre
Cl (%)
pH
Cohesion C
Visual Description of Soil
(kg/cm )
2
Value
From
To
Undisturbed (UDS) Penetrometer (SPT) Disturbed (DS) Water Sample (WS) R = Refusal
Note: Chemical Test results for Water Samples for Chloride & Sulphate is given as mg/Litr &
# means(Silt + clay) % for soil samples SO4 content is expressed as SO3.
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
0.002
0.075
0.425
4.75
Grain size (mm)
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
2
4.75
0.002
0.075
0.425
Grain Size(mm)
Project:- Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, Bridge at
UP. 69+950km
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
0.002
0.075
0.425
4.75
Grain size (mm)
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
2
4.75
0.002
0.075
0.425
Grain Size(mm)
Project:- Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, Bridge at
UP. 69+950km
Project : Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, UP.
e-logp Curve
0.490
BORE HOLE : A1
UDS NO : 01
0.480 DEPTH (M) : 3.00
e0 : 0.484
0.470
0.460
0.450
0.440
VOID RATIO
0.430
0.420
0.410
0.400
0.390
0.380
0.370
0.10 1.00 10.00
PRESSURE RANGE KG / SQCM
Project : Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, UP.
e-logp Curve
0.650
BORE HOLE : A1
0.640 UDS NO : 02
DEPTH (M) : 6.00
0.630 e0 : 0.645
0.620
0.610
0.600
0.590
VOID RATIO
0.580
0.570
0.560
0.550
0.540
0.530
0.520
0.510
0.500
0.490
0.10 1.00 10.00
PRESSURE RANGE KG / SQCM
BRIDGE AT 69+950KM
FIELD & LAB TEST RESULTS
SUMMARY OF FIELD AND LABORATORY TEST RESULTS
Project : Geotech. Inv. for Prop. Structure from Hamirpur to Rath section on SH-42, UP. Commencement Date : 11/10/2014 Level of Ground : 149.955 M Job No : 3367-03
Bore Hole No. : A1 Location : Ch.KM.72.550 Completion Date : 12/10/2014 Standing Water Level : 6.90 m Sheet No :
Depth in Mete
Unconfined Compressive
Dry Density in gms/cm 3
Symbolic representation
below
Depth of Sample below
% Silt 0.06-0.002mm
% Clay<0.002mm
reference
Specific Gravity
Percent RQD
reference level
at Laboratory
Content (%)
Void Ratio
Resistance in Deg.
Remarks
Angle of Shearing
SO 4 (%)
Depth in Metre
Cl (%)
pH
Cohesion C
Visual Description of Soil
(kg/cm )
2
Value
From
To
149.955 143.055
0.00m
149.455 0.50 0.50 DS-01
148.955 1.00 1.00 DS-02
148.455 1.50 1.95 1.50 UDS-01 UU 19 55 22 4 1.66 2.74 0.403 10 1.12 7 7.84 0.0156 0.050
Stiff to very stiff, brownish grey, silty
148.005 1.95 2.40 1.95 SPT-01 1.95 12 clay / clayey silt with sand mixture.
Obs. gravels.
147.255 2.70 2.70 DS-03
146.955 3.00 3.45 3.00 SPT-02 3.00 19
145.955 4.00 4.00 DS-04
4.00m
145.455 4.50 4.95 4.50 SPT-03 4.50 16 20 71 9 2.73 36 18 17
CL
137.955 12.00 12.45 12.00 SPT-08 12.00 13 Medium dense, brownish grey, silty
sand. Obs. mica & clay binder.
136.955 13.00 13.00 DS-10
136.455 13.50 13.95 13.50 SPT-09 13.50 28 87 13#
135.455 14.50 14.50 DS-11
14.50m
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
0.002
0.075
0.425
4.75
Grain size (mm)
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
2
4.75
0.002
0.075
0.425
Grain Size(mm)
Project:- Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, Bridge at
UP. 72+550km
Sheet No.:
C. E. Testing Company Pvt. Ltd.
GRAIN SIZE DISTRIBUTION CURVES
Hydrometer Sieve
100
80
Percentage finer
60
40
20
0
0.001 0.01 0.1 1 10 100
0.002
0.075
0.425
4.75
Grain size (mm)
Project:- Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, Bridge at
UP. 72+550km
Project : Geotech. Inv. for Prop. Structure from Hamirpur-Rath section on SH-42, UP.
e-logp Curve
0.410
BORE HOLE : A1
UDS NO : 01
0.400 DEPTH (M) : 1.50
e0 : 0.403
0.390
0.380
0.370
VOID RATIO
0.360
0.350
0.340
0.330
0.320
0.310
0.10 1.00 10.00
PRESSURE RANGE KG / SQCM
APPENDIX – 7.3
Safe Net
Depth,m
Page 1 of 12
SETTLEMENT ANALYSIS FOR SHALLOW FOUNDATIONS
Cc2 (p>=pc)
Density T/m
Elasticity, T/m
Cc1 (p<pc)
Depth , m
Modulus of
SoilType*
Initial Void
(pc), T/m2
C,G or H
Layer
Ratio
Soil Classification
No.
From To
* For "Soil Type", Enter : C (Cohesive soil), G (Granular soil) or H (Hard soils/Rock - no consolidation)
2
E (Weighted Average),T/m2 : 1163 T/m
Elastic Settlement = 44.3 mm
Page 2 of 12
SETTLEMENT ANALYSIS FOR SHALLOW FOUNDATIONS
CONSOLIDATION SETTLEMENT
As per Terzaghi's theory of one dimensional consolidation :
cc H
Sc = {log(p+∆p)/p} λoed df dr
1+e0
= mv ∆p H λoed df dr e0 = Initial void ratio
where: cc = compression index cc1 = cc for stress range < pre-
p = overburden pressure consolidation pressure
∆p = incremental pressure computed using stress cc2 = cc for stress range >= pre-
distribution theory (Boussenesq or
consolidation pressure
Westergaard)
mv = coeff. of volume change, to be selected
λoed = oedometer correction factor
depending on the pressure in layer
2
Applied Bearing Pressure : 16.0 T/m
Foundation Depth, (D) : 4.3 m Stress Distribution Theory : Enter B for
W
Foundation Width (B) : 5.0 m Boussenesq or W for Westergaard :
Foundation Length L : 8.0 m
Oedometer Correction Factor, λ : 0.70
2
Overburden Pressure @ Fndn Lvl : 4.30 T/m
dp)/p] /(1+e0)
AT CENTRE OF LAYER
Thickness, m
Cc H log[(p+
below GL.
Soil
Layer
(Z) Below
LAYER ∆p
Depth,m
Depth, m
p Influence Cc
Fndn.
1 3.0 C 1.50 5.80 5.800 2.67 1.67 0.698 11.17 0.0220 0.0200
1 1.5 C 3.75 8.05 8.050 1.07 0.67 0.387 6.20 0.0220 0.0053
2 3.0 C 6.00 10.30 10.000 0.67 0.42 0.226 3.62 0.0180 0.0046
2 3.0 C 9.00 13.30 12.400 0.44 0.28 0.125 1.99 0.0180 0.0022
2 1.0 C 11.00 15.30 14.000 0.36 0.23 0.089 1.43 0.0180 0.0005
Page 3 of 12
BEARING CAPACITY ANALYSIS FOR
SHALLOW FOUNDATIONS
Analysis as per IS 6403-1981
Safe Net
Depth,m
Page 4 of 12
SETTLEMENT ANALYSIS FOR SHALLOW FOUNDATIONS
Cc2 (p>=pc)
Density T/m
Elasticity, T/m
Cc1 (p<pc)
Depth , m
Modulus of
SoilType*
Initial Void
(pc), T/m2
C,G or H
Ratio
Layer
Soil Classification
No.
From To
* For "Soil Type", Enter : C (Cohesive soil), G (Granular soil) or H (Hard soils/Rock - no consolidation)
2
E (Weighted Average),T/m2 : 1544 T/m
Elastic Settlement = 38.9 mm
Page 5 of 12
SETTLEMENT ANALYSIS FOR SHALLOW FOUNDATIONS
dp)/p] /(1+e0)
AT CENTRE OF LAYER
Thickness, m
Cc H log[(p+
below GL.
Layer
(Z) Below
Soil ∆p
Depth,m
Depth, m
LAYER p Influence Cc
Fndn.
2 3.0 C 1.50 5.10 5.100 2.67 1.67 0.698 12.57 0.0120 0.0123
2 2.0 C 4.00 7.60 7.600 1.00 0.63 0.364 6.55 0.0120 0.0041
3 3.0 C 6.50 10.10 10.040 0.62 0.38 0.203 3.66 0.0120 0.0031
3 3.0 C 9.50 13.10 12.920 0.42 0.26 0.114 2.06 0.0120 0.0015
Page 6 of 12
BEARING CAPACITY ANALYSIS FOR
SHALLOW FOUNDATIONS
Analysis as per IS 6403-1981
Safe Net
Depth,m
Page 7 of 12
SETTLEMENT ANALYSIS FOR SHALLOW FOUNDATIONS
Cc2 (p>=pc)
Density T/m
Elasticity, T/m
Cc1 (p<pc)
Depth , m
Modulus of
SoilType*
Initial Void
(pc), T/m2
C,G or H
Layer
Ratio
Soil Classification
No.
From To
* For "Soil Type", Enter : C (Cohesive soil), G (Granular soil) or H (Hard soils/Rock - no consolidation)
2
E (Weighted Average),T/m2 : 1010 T/m
Elastic Settlement = 58.2 mm
Page 8 of 12
SETTLEMENT ANALYSIS FOR SHALLOW FOUNDATIONS
dp)/p] /(1+e0)
AT CENTRE OF LAYER
Thickness, m
Cc H log[(p+
below GL.
Soil
Layer
(Z) Below
LAYER ∆p
Depth,m
Depth, m
p Influence Cc
Fndn.
1 1.5 C 0.75 3.75 3.750 5.33 3.33 0.843 14.33 0.0180 0.0125
2 3.0 C 3.00 6.00 6.000 1.33 0.83 0.471 8.00 0.0160 0.0107
2 3.0 C 6.00 9.00 9.000 0.67 0.42 0.226 3.85 0.0160 0.0045
2 3.0 C 9.00 12.00 12.000 0.44 0.28 0.125 2.12 0.0160 0.0021
2 1.0 C 11.00 14.00 14.000 0.36 0.23 0.089 1.52 0.0160 0.0004
3 3.0 C 13.00 16.00 16.000 0.31 0.19 0.067 1.14 0.0160 0.0009
3 2.5 C 15.75 18.75 18.750 0.25 0.16 0.047 0.80 0.0160 0.0004
Page 9 of 12
BEARING CAPACITY ANALYSIS FOR
SHALLOW FOUNDATIONS
Analysis as per IS 6403-1981
Safe Net
Depth,m
Page 10 of 12
SETTLEMENT ANALYSIS FOR SHALLOW FOUNDATIONS
Cc2 (p>=pc)
Density T/m
Elasticity, T/m
Cc1 (p<pc)
Depth , m
Modulus of
SoilType*
Initial Void
(pc), T/m2
C,G or H
Layer
Ratio
Soil Classification
No.
From To
* For "Soil Type", Enter : C (Cohesive soil), G (Granular soil) or H (Hard soils/Rock - no consolidation)
2
E (Weighted Average),T/m2 : 1445 T/m
Elastic Settlement = 45.6 mm
Page 11 of 12
SETTLEMENT ANALYSIS FOR SHALLOW FOUNDATIONS
dp)/p] /(1+e0)
AT CENTRE OF LAYER
Thickness, m
Cc H log[(p+
below GL.
Soil
Layer
(Z) Below
LAYER ∆p
Depth,m
Depth, m
p Influence Cc
Fndn.
1 3.0 C 1.50 3.50 2.905 2.67 1.67 0.698 12.57 0.0100 0.0147
2 3.0 C 4.50 6.50 5.650 0.89 0.56 0.321 5.78 0.0100 0.0056
2 3.0 C 7.50 9.50 8.650 0.53 0.33 0.165 2.98 0.0100 0.0023
2 3.0 C 10.50 12.50 11.650 0.38 0.24 0.097 1.74 0.0100 0.0011
2 0.5 C 12.25 14.25 13.400 0.33 0.20 0.074 1.34 0.0100 0.0001
3 3.0 G 14.00 16.00 15.150 0.29 0.18 0.058 1.05
3 2.5 G 16.75 18.75 17.900 0.24 0.15 0.042 0.76
Page 12 of 12
Uttar Pradesh Core Road Network Development Program
DETAILED PROJECT REPORT
Volume-II: Design Report
Hamirpur – Rath Road (SH-42)
The design standards and loading considered for culverts, and bridges, are those laid down in the
latest IRC codes and/or IS codes. Where the said codes are silent other codes at national or
international level shall be followed in consultation with the client.
The Indian Road Congress (IRC) codes will be the basis of bridge designs, underpasses
and flyover/ROB’s. For items not covered by latter, provisions of Special Publications and
Specification for Roads and Bridges published by IRC shall be followed.
Since number of new bridges in the project roads is less and majority of existing
structures will be widened, it is proposed to design structures with working stress method
based on IRC: 112.
Grades of Concrete for superstructures will be as per MOST Specifications and IRC
Standards. The Minimum grade shall be M40 for PSC and M25 for RCC respectively.
For substructures and foundations, the concrete grade will not be lower than M25. For
PCC substructures minimum grade of M20 will be adopted.
The deck will have 2.5% bi-directional camber/cross fall and the wearing course will be of
uniform thickness of 40mm BC overlaid with 25mm thick Mastic asphalt on all bridge
decks.
In general it has been observed during the preliminary study that the open type
foundations for the existing bridges have not suffered any distress.
Pile / well foundations will be adopted for some of the r bridges wherever open
foundation is not feasible, depending on the properties of the foundation strata based on
sub-soil investigation reports.
Type of Structures
The structures are classified based on their functional use. The structures for the project road are
classified as given below:
i Drainage Structures
Major Bridges
Minor Bridges
Culverts
ii Viaducts
Overpasses
Road/Rail over Bridges
Underpasses
The Bridges having an overall length varying from 6 m to 60 m are termed as minor bridges and
those having an overall length more than 60 m are termed as major bridges.
The structures carrying the project road over land and spanning across the valleys are termed as
viaducts. The structures carrying the cross roads above the project road are termed as
overpasses and the structures carrying the cross roads below the project road are called
underpasses. Box type structures are generally proposed at important village road crossings.
Design Loading
The bridges have been designed to sustain safely the most critical combination of various loads,
forces and stresses that can co-exist as per the provisions of IRC: 6-2014. The allowable stresses
and the permissible increase in stresses for various load combinations have been adopted as per
the relevant IRC codes.
Structures carrying the proposed project road with carriageway width of 11.0 m are proposed to
be designed for 3 lanes of Class-A loading or one lane of 70-R wheeled/tracked loading plus 1
lane of Class – A loading, whichever produces the most severe effect.
Structures carrying the proposed project road with carriageway width of 7.5 m shall also be
designed for 3 lanes of Class-A loading or one lane of 70-R wheeled/tracked loading plus 1 lane
of Class – A loading, whichever produces the most severe effect.
The tractive and braking forces shall be considered as per the provisions of clause no. 211 of IRC:
6-2014.
The footpath live load shall be considered as per the provisions of clause no. 206 of the IRC: 6-
2014. The intensity of the footpath loading has been considered as 500 Kg/sqm as per clause no.
206 of IRC: 6-2014.
Wind Forces
The effect of wind as per clause no. 209 of IRC: 6-2014 shall be considered for the design of the
various components of the bridge.
Seismic Forces
Project roads pass through seismic zone II, III and IV. Seismic forces shall be calculated in
accordance with clause number 219 of IRC: 6-2014.
Buoyancy Effects
The following buoyancy effects shall be considered wherever applicable for the design of various
components of the bridge:
The deck levels of the structures carrying the project road have been adopted based on the
following parameters:
8.3 Hydrology
8.3.1 Scope
Hydrological analysis
Hydraulic Investigation
Methodology of hydraulic computation
Evaluation of Waterways of new structure/Check of hydraulic Adequacy of existing
structure
Results of hydraulic Assessment
These investigations are primarily intended for evaluating the adequacy of waterways of the
existing/proposed bridges for the design flood flow. The hydrological study has been done based
on the field investigations and survey data. This report describes the method of evaluation of
performance of existing bridges on the existing highways for widening proposals, and design
discharges, waterway required, scour depth and afflux etc for the new/existing bridges.
The project roads pass through areas of heavy to average rainfall intensity . Detail hydrological
investigations have been carried out to confirm the adequacy of existing structures and
requirement of additional culverts.
The hydraulic condition of each structure was assessed thoroughly by visual observations. These
observations were supplemented with local inquiries.
As per IRC: 5 – 1998 (Standard Specifications and Code of Practice for Road Bridges, Section – 1,
General Features of Design) the bridges are designed for a return period of not less than 50
years. A flood of this specified return period should pass easily through the structure, while an
extraordinary and rare flood may pass without doing excessive damage to the structure or the
road.
The 50-year, 24-hour rainfall for the zone under consideration varies from 240 mm. (Ref:
“Estimation of Design Flood Peak, Betwa sub-zone – 1 (c), published by CWC.
Topographic maps, obtained from Survey of India, on 1:50,000 scale, have been utilized for the
hydrological study of the corridor.
For the calculation of discharge of the stream by Area-Velocity method, topographical survey
including levelling surveys have been carried out across and along the watercourses to determine
the cross-section and the longitudinal section of stream. A number of cross-sections have been
taken at regular intervals on both upstream and downstream side of the structure, including one
at the proposed location of the structure in accordance with IRC specifications.
For bridges where the cross section is not defined, the cross-sections shall be extended up to the
HFL, in order to calculate the effective cross-section of flow.
The longitudinal section to determine the bed slope shall be taken at an approximate regular
interval following the channel course extending on both the upstream and the downstream sides
of the structure. Caution shall be exercised by following the curved flow line for longitudinal
gradient, rather than a straight line.
The peak discharge and the HFL shall be calculated by following methods
Empirical Method
Rational Method
Area Velocity Method
SUH Method
Empirical Method
Q = C M3/4
Where
The catchment area M is determined from toposheets, Coefficient of run-off C is determined from
IRC SP-13 depending upon the intensity of rainfall. This formula gives a simplified approach and
results are approximate. Comparison is made with alternative methods for important structures.
Q = CM2/3
Where
The catchment area M is determined from the toposheets, Coefficient of run-off C is determined
from IRC SP-13 depending upon the intensity of rainfall. This formula gives a simplified approach
and results are approximate. Comparison is made with alternative methods for important
structures.
Rational Method
Rational Formula:
Where:
Q = Maximum runoff in cumecs
A = Catchment area in hectares
Ic = Critical intensity of rainfall in cm/ hr.
Ic = (F/T)*(T+1) / (Tc+1)
F= Total Rainfall of T hours duration (24 hrs.) in cm corresponding to 50 yrs return period.
Ic values found from Inglis formula (as per IRC: SP-13) give extremely high intensity of rainfall
when 24 hrs rainfall is considered. Design rainfall intensity Ic is, therefore computed from
rainfall distribution given in CWC’s flood estimation reports for sub zone 1(c), corresponding to 50
years return period for bridges for storms of duration equal to time of concentration. Tc is found
for every catchment for the given stream from respective toposheets assuming a tortuisity factor
of 1.25 and also from Dickens’s and Time of Travel formulas as given above. Average of the two
values is taken for finding Tc and corresponding Ic. Total rainfall in 24 hrs is adjusted
corresponding to Tc for finding critical rainfall intensity Ic from the rainfall distribution curve
(Duration vs. conversion ratio) of CWC report.
Q = AxV
Where,
Q = Discharge (cumecs)
A = Area of the cross section (sq. m.)
V = Velocity in (m/sec)
R = Hydraulic mean depth (m); R = A / P
P = Wetted perimeter of the stream (m)
S = Bed slope of the stream
n = Rugosity Co-efficient.
This method is based on unit hydrograph principle, used when catchment area is greater than 10
sq miles. CWC has published Flood Estimation Reports for different zones for India.
Comprehensive hydraulic analysis of various CD structures shall be carried out based on detailed
topographical survey.
A detailed approach and equations of unit hydrograph has been given in the report “Estimation of
Design Flood Peak,Betwa sub-zone – 1 (c)”, published by CWC. In this method the design flood
discharge has been calculated as per guidelines given in the report.
Design discharge has been taken as the maximum of the peak flood discharge by different
methods provided it does not exceed the next highest discharge more than 50%. If it exceeds, it
is restricted to that limit (As per Article 6.2.1 of IRC: SP: 13-2004).
As the highest flood level should be ascertained by intelligent local observation, bridge inventory
supplemented by local enquiry, and marked on the cross-sections. The design engineer has to
determine the design HFL corresponding to adopted design flood for the bridges and cross
drainage structures under natural and constricted conditions. This elevation is very important in
the analysis for foundations, scour free board, formation levels etc.
Afflux Calculation
When the waterway area of the opening of a bridge is less than the unobstructed natural
waterway area of the stream, i.e. when bridge contracts the stream, afflux occurs. The afflux will
V2
h 0.01524 ( A / a)2 1
17 .88
be calculated using Molesworth formula as given below:
Where
h = afflux (meters)
V = average velocity of water in the river prior to construction (m/sec)
A = Unobstructed sectional area of the river at proposed site (sq.m)
a = Constricted area of the river at the bridge (sq.m)
Lacey’s equation is adopted for estimating normal scour depth as per IRC: 5
Where R is the Lacey’s regime scour depth, measured below HFL, q is the design discharge
intensity under bridge in cumecs per meter and f is silt factor given by the equation
f= 1.76 (d50)1/2
Where d50 is the mean sediment size in mm. Normal scour depth based on Lacey’s equation and
the actual observed depth (equal to the difference between HFL and LBL)/1.27 are compared as
per code. Higher of the two values is adopted for design. Silt factor ‘f’ is found from Lacey’s
equation corresponding to d50 size of bed materials. Maximum scour level for pier and abutment
are calculated using a factor of safety of 2 and 1.27 respectively as per IRC: Code-5. For
computing scour depth, design discharge is enhanced by 30% to provide for adequate margin of
safety as per provision of IRC: 78 - 2000.
When a new bridge is to be constructed, a designer has all the freedom to provide waterway as
required. As per IRC-5:1998 clause 104, waterway (W) should be equal to Lacey’s regime
waterway (P) given by the equation:
P =W= C (Q1/2)
Where,
C = a constant usually taken as 4.8 for regime channels but it may vary from 4.5 to 6.3
according to local conditions.
The code also stipulates that the waterway so found should also be compared with linear
waterway at HFL corresponding to design flood discharge and the minimum of the two should be
adopted as the clear waterway under the bridge.
The detailed hydrological calculations have been carried out for all new/reconstruction
Bridges. The summary of these calculations has presented in Appendix-8.1.
General - the following aspects shall be considered while planning for the new bridges and
structures:
Deck Width – it is proposed to provide ooverall deck width of 12.00 m consisting of 11.00 m
carriageway and 0.50 m wide concrete crash barriers on either side of carriageway for new minor
bridges.
Proposals - The proposals for minor bridges are based on the following considerations:
Total deck width of the new minor bridges shall be 12.0 m with crash barrier on both
sides.
The new bridges are proposed to be designed for 3 - lanes of traffic.
In order to reduce the number of expansion joints for improving the riding quality and for
providing unobstructed flow under the bridges, the small multiple spans are proposed to
be replaced with equivalent single spans wherever possible, matching with the existing
opening.
The new 3-lane bridges will be parallel to the existing ones.
Piers and abutments of the new bridge will be in line with those of old structure. In case
larger span lengths are adopted, the foundations shall be in line with that of old bridge
with alternate foundations being omitted.
For bridges with RCC solid slab superstructures, tar paper bearings will be proposed and
for bridges with PSC / RCC T-Beam and slab superstructures Pot cum PTFE / elastomeric
bearings will be proposed based on design requirements.
Strip seal expansion joints will be proposed for bridges with RCC T-beam and slab
superstructure. For bridges with RCC solid slab superstructure filler type expansion joints
are proposed.
Foundations for the proposed structures will be same as those of existing bridges.
Bed protection works will be provided for bridges with box cell structures.
Splayed wing walls shall be provided for new / widened side of minor bridges.
Figure 8.1: Typical Cross-sections for New Two Lane Minor Bridge
Existing Minor Bridges
Deck Width - The existing two lanes minor and major bridges in good condition having deck
width > 10 m are proposed to be retained with repairs and will not be widened under this
project. For structures having deck width less than 10 m, the improvement proposals will be as
under:
Existing slab bridges in good condition are proposed to be widened to 12.0 m deck width
by integrating existing and widened part. Symmetrical widening shall be proposed in
general.
b. Arch Bridges with open foundations:
Existing arch bridges in good condition are proposed to be widened to 12.0 m deck width
by adding a new structure along existing arch bridge [Asymmetrical widening] to get 12
m deck width.
Foundation details of arch bridges are not known except of few cases where well
foundations are visible.
iii. Decision for existing structures in good condition having carriageway width
marginally less than 7.5 m regarding retaining them with repairs / replaced with
new 2 Lane Bridge will be taken on case to case basis in consultation with Client.
e. Existing bridges having poor structural condition, hydraulic deficiency [Overtopping,
excessive scouring] or falling under realignment of road geometry are proposed to be
replaced by new 2-lane bridge having 12 m deck width.
Repair and Rehabilitation - The following measures are proposed for repair and rehabilitation
of existing bridges:
General
Most of the bridges have many common deficiencies/defects, which are proposed for repaired as
follows:
1) Railings / handrails are proposed be replaced with crash barriers to bring common bridge
furniture across the project road. Keying of concrete crash barrier with brick work walls
shall be done in addition to anchoring crash barrier reinforcement into brickwork by
drilling holes and grouting with cement mortar.
2) Drainage spouts provided in the railing kerb, ending at face of soffit of slab are proposed
be replaced with new drainage spouts having adequate length to prevent the water from
falling / splashing on the superstructure.
3) Damaged faces of RCC pier caps/abutment caps over brick masonry (BM) / coursed
rubble masonry (CRM) substructure shall be repaired by guniting after removing the
affected portions.
4) Damaged pointing in the BM / CRM to be removed and cleaned before applying fresh
pointing.
1) Edges of solid slab which show spalling of concrete over a smaller width or only small
patches of the underside of slab which are distressed, are proposed be repaired by
guniting. The reinforcement, which has corroded, shall be sand ballasted and additional
reinforcement, if required, shall be welded to the existing reinforcement before guniting.
2) RCC solid slabs, which show honeycombing, shall be strengthened by pressure grouting
with cement grout from the underside of the slab.
T-Beam and Slab Superstructure
Details of improvement proposals for bridges on Hamirpur-Rath section of SH-42 are as follows:
Table 8.3: Details of New Major Bridges, Rehabilitation/ Repair/ Widening Scheme for
Existing Major Bridges
Details of Existing Bridge Improvement Proposal
Design Carriage-
S. No Chainage (Km) Total Proposed Proposed Proposed
Type of way Deck Existing
Span Length Bridge Bridge Width
Superstructure Width Width Bridge
(m) Type Span (m) (m)
(m) (m)
PSC T beam with Retain with
1 59+731 8 x 30.0 240.0 7.5 8.5 - - -
slab repairs
Legend:
There is 1 major bridge and 9 minor bridges in this section. Description of existing bridges and their
improvement proposal is given below:
The existing brick arch minor bridge has 5 spans of 2.4 m clear span and total length 14.4 m
between outer edges of end spans. Type of foundations could not be ascertained in absence of
as built drawings. The existing bridge has 6.2 m deck width comprising of 5.4 m wide
carriageway and 0.4 m wide brick parapets on either side of the carriageway. It has brick
masonry straight return walls.
Wearing coat is damaged. There is vegetation growth on pier and parapet. Parapet is
damaged on both sides. One vent is blocked due to debris. Straight return walls are partially
damaged.
The bridge is in fair condition and can be widened to 12 m deck width by adding a new 5.8 m
wide box cell structure adjacent to existing bridge in present condition with repairs.
The 2 lane existing minor bridge across Irrigation Canal has 2 spans of 3.45 m [sk] clear span
and total length 7.7m [sk] between inner faces of dirt walls. It has 48.5 degree skew. It has
RCC solid slab superstructure supported on brick masonry piers and abutments resting on open
foundations. The existing bridge has 10.6 m deck width comprising of 5.5 m wide carriageway,
earthen shoulders and parapets. It has RCC parapets. It has brick masonry straight returns
and small wing walls along the flow direction. It has brick work bed protection works.
The water flow runs for full vertical depth of structure during FSL discharge flows at this
location. This bridge has been retained with repairs after discussion with client as canal is
manmade with regulated defined discharge and FSL. Because of regulated / controlled flow,
overtopping and obstruction due to debris is not anticipated.
There is vegetation growth in vent way and on pier. Parapet is damaged on both sides. There
are horizontal cracks in abutments walls. Wing walls are partially damaged. Approach slab
has not been provided. Wearing coat is damaged. Bed protection works are partially
damaged, drainage spouts have not been provided.
The existing minor bridge has 2 spans of clear span 5.5 m [sk] and total length 12.3 m [sk]
between inner faces of dirt walls. It has 69 degree skew. It has RCC solid slab superstructure
supported on brick masonry piers and abutments resting on open foundations. The existing
bridge has 10.6 m deck width comprising of 7.0 m wide carriageway, earthen shoulders and
parapets. It has RCC parapets. It has brick masonry straight returns. It has brick work bed
protection works.
There is vegetation growth in vent way, wing walls and on pier. Parapet is damaged on both
sides. There is minor damage in brick masonry in piers. Pointing of abutment and piers is
damaged. Approach slab has not been provided. Wearing coat is damaged. Cracks observed in
abutment wall. Drainage spouts have not been provided.
General View of Bridge Showing Vegetation growth in vent way and Pier
The existing minor bridge has 3 spans [1x4.6+1x4.6+1x4.8 (sk)] and total length 16.8 m [sk]
between inner faces of dirt walls. It has 33 degree skew. It has RCC solid slab superstructure
supported on CRM piers and abutments resting on open foundations. The existing bridge has
10.8 m deck width comprising of 7.0 m wide carriageway, earthen shoulders and brick
parapets. It has RCC parapets. It has CRM straight returns. It has brick work parapet and bed
protection works.
Parapet is damaged on both sides. There is minor damage in brick masonry in piers.
Approach slab has not been provided. Wearing coat is damaged. Drainage spouts have not
been provided. Deck slab is damaged near expansion gap at pier location, small areas of
honey combing in soffit of deck slab. Drainage holes are provided in parapet. Exposed
reinforcement is corroded. Scouring is noticed near abutment. CRM is damaged in pier
footing.
The existing brick arch minor bridge has 4 spans of 1.35 m clear span and total length 7.4 m
between outer edges of end spans. Type of foundations could not be ascertained in absence of
as built drawings. The existing bridge has 6.4 m deck width comprising of 5.4 m wide
carriageway and 0.5 m brick parapets on either side of the carriageway. It has brick masonry
straight return walls.
The vertical profile of the road has been raised at this location and existing bridge has been
proposed to be replaced with new 2 – Lane bridge. single cell box structure of 7.4 m span.
Bed protection works and splayed wing walls have been proposed for new bridge.
`
General View of Bridge Showing vent way with debris
The existing minor bridge has 2 spans [1X3.85 +1X1.85] and total length 6.6 m between inner
faces of dirt walls. It has RCC solid slab superstructure supported on CRM piers and abutments
resting on open foundations. The existing bridge has 10.0 m deck width comprising of 7.0 m
wide carriageway, earthen shoulders and parapets. It has RCC parapets. It has CRM Splayed
wing walls. It has CRM parapet.
There is vegetation growth in vent way. Cut waters of CRM piers are repaired and shall be
reconstructed with PCC. Approach slab has not been provided. Wearing coat is damaged.
Drainage spouts have not been provided. Deck slab is damaged near edges, there are small
areas of honey combing in soffit of deck slab. Drainage holes are provided in parapet.
The existing minor bridge across Irrigation Canal has 3 spans [1x3.825+1x3.85+1x3.825m] and
total length 13.80 m between inner faces of dirt walls. It has RCC solid slab superstructure
supported on CRM piers and abutments resting on open foundations. The existing bridge has
10.0 m deck width comprising of 7.0 m wide carriageway, earthen shoulders and parapets. It
has RCC parapets. It has CRM straight return walls and BM parapets.
Approach slab has not been provided. Wearing coat is damaged. Drainage spouts have not
been provided. Deck slab is damaged near edges, there is honey combing in soffit of deck slab
at some locations. Reinforcement is exposed at slab edges. Drainage holes are provided in
parapet. Parapet and straight return walls are damaged. CRM pier foundation top is damaged.
The existing major bridge across has 8 spans of 30m and total length 240 m between inner
faces of dirt walls. It has PSC T Beam and slab superstructure supported on RCC circular piers
and RCC spill through abutments. Piers are resting on well foundations, abutment foundations
are not visible. The existing bridge has 8.5 m deck width comprising of 7.5 m wide carriageway.
It has steel railing. It has RCC cantilever return walls. It has roller – rocker bearings and angle
& plate type expansion joints.
Approach slab is settled. Wearing coat is damaged near expansion joints. Drainage spouts
grating is missing. Down take pipes are small and not of proper shape. Steel railing partially
damaged. There is settlement of earth fill around abutments. Bottom of cantilever returns are
exposed. Expansion joints are not extending in the railing part. There is gap between top plate
of bearings and soffit of girder at Rath side abutment location
Grating missing in drainage pipe View showing insufficient length of Drainage Pipe
The existing brick arch minor bridge has 3 spans of 2.4 m clear span and total length 8.4 m
between outer edges of end spans. Type of foundations could not be ascertained in absence of
as built drawings. The existing bridge has 6.35 m deck width comprising of 5.35 m wide
carriageway and 0.5 m brick parapets on either side of the carriageway. It has brick masonry
splayed wing walls.
Wearing coat is damaged. There is vegetation growth on pier. Parapet is damaged on both
sides. Loosening of bricks in arch spandrel is noticed. Pointing of BM damaged in substructure
and arch.
The bridge is in fair condition and can be widened to 12 m deck width by adding a new 5.5 m
wide box cell structure adjacent to existing bridge in the present condition with repairs.
The existing brick arch minor bridge has 3 spans of 2.4 m clear span and total length 8.4 m
between outer edges of end spans. Type of foundations could not be ascertained in absence of
as built drawings. The existing bridge has 6.22 m deck width comprising of 5.22 m wide
carriageway and 0.5 m brick parapets on either side of the carriageway. It has brick masonry
splayed wing walls.
Wearing coat is damaged. There is vegetation growth on pier. Parapet is damaged partially
of LHS and no parapet on RHS.
The bridge is in fair condition and can be widened to 12 m deck width by adding a new 5.5 m
wide box cell structure adjacent to existing bridge in the present condition with repairs.
Damaged Parapet on LHS Damaged Wearing coat and missing parapet on RHS
Results of Hydrological
Uttar Pradesh Core Road Network Development Program Appendix - 8.1
1 25600 14.838 124.447 1.012 0.60 5x2.6 125.047 122.560 5x2.7 2.4 122.365 121.363
2 47900 4.044 137.759 0.813 0.60 2x3.6 138.359 136.759 1x6.4 2.4 136.551 135.882
3 69900 7.222 150.559 0.636 0.60 3x2.6 151.159 148.774 3x2.9 2.4 149.145 148.331
4 72550 10.705 151.832 1.837 0.60 3x3.6 152.432 149.720 3x3.3 2.4 149.756 148.563
Annexure 1
1 0 120.00 0 0 - -
2 5.00 125.00 5.00 5.00 5.00 25.00
3 7.00 130.00 2.00 10.00 15.00 30.00
55.00
Slope (S) = Li(Di-1+Di) = 1.12 m/km 0.00112
L2 = 0.11 %
The value of runoff coefficient (C) may be taken from the following Table
Average slope
Soil and
Mild Mdium Steep
land use
(0-4 %) (4-10%) (10 % +)
Rocky, heavy clay 0.6 0.75 0.85
Intense cultivation,
0.5 0.6 0.7
loamy/clay soils
Grass cover, medium soils 0.4 0.5 0.6
Dense vegetation, forest 0.05 0.15 0.25
Q = 52.222
0 122.5
20 122.44 Rugosity co-efficient 'n' = 0.05
40 122.51
Long Section
125
124.5
124
Arbit.R.L(m)
123.5
Br.C/L
123
122.5
122
121.5
121
0 10 20 30 40 50
L to R(m) Series1
L sec
124.0
R.L. (m)
123.0
122.0
-30 -25 -20 -15 -10 -5 0 5 10 15 20 25 30
Chainage (m)
LBL= 122.560
depth= 1.563
2/3 1/2
AR = K*n = Q*n/S
Q = 14.84 Cumecs
n = 0.05
S = 0.0011
2/3
AR = 22.17 22.59
water depth= 1.850
Chainage(m) HFL (m) HFL Distance h Avg h Diff in h Area Perimeter
1.850 124.410
-20 124.75 124.410 0.000 0 0.000 0.000 0.000 0.000 0.000
-10 124.65 124.410 0.000 10.000 0.000 0.000 0.000 0.000 0.000
0 122.56 124.410 0.000 10.000 1.850 0.925 1.850 9.250 10.170
10 123.72 124.410 0.000 10.000 0.690 1.270 1.160 12.700 10.067
20 124.64 124.410 124.410 0.000 10.000 0.000 0.345 0.690 3.450 10.024
30 124.64 124.410 1.000 10.000 0.000 0.000 0.000 0.000 0.000
Cross Sectional Area, A = 25.400 Sum 25.400 30.261
Wetted Perimeter, P = 30.261 m HFL = 124.410
Hydraulic Radius, R = 0.839 m When 22.59
AR2/3 = 22.59
125
HFL=124.410m
124
123
122
-30 -20 -10 0 10 20 30
The mean scour depth,Dsm below HFL is computed vide IRC 78 2000 clause 703.2.
dsm= 1.34[Db^2/Ksf]1/3
dsm= mean scour depth below HFL
Db= discharge in cumecs per m width
Ksf= Silt factor 2.40
Discharge,Q= 14.84 cumecs
Discharge for foundation= 19.29 cumecs
= 2xdsm
= 2.75 m
MSL for Pier = 121.36 m
= 1.27xdsm
= 1.74 m
MSL for Abutment = 122.37 m
1 Emperical Formula
Q = 121 Cumecs
3 Manning's Formula
Q = 9.89 Cumecs
4 UP Irrigation's Formula
Q = 52.22 Cumecs
Qd = 14.84 Cumecs
Annexure 2
1 0 135.00 0 0 - -
2 3.00 140.00 3.00 5.00 5.00 15.00
15.00
Slope (S) = Li(Di-1+Di) = 1.67 m/km
L2 = 0.17 %
The value of runoff coefficient (C) may be taken from the following Table
Average slope
Soil and
Mild Mdium Steep
land use
(0-4 %) (4-10%) (10 % +)
Rocky, heavy clay 0.6 0.75 0.85
Intense cultivation,
0.5 0.6 0.7
loamy/clay soils
Grass cover, medium soils 0.4 0.5 0.6
Dense vegetation, forest 0.05 0.15 0.25
Q = 6.296
0 136.504
7.85 136.442 Rugosity co-efficient 'n' = 0.05
12.121 136.616
16.362 136.664
20 136.395
30 136.006
40 136.729
50 136.771
60 136.9
70 136.471
80 136.885 Average bed slope along the stream = 0.0017
90 137.531 or, 1 V in H = 588.2353
100 137.459 (frm contour)
Long Section
140
139.5
139
Br.C/L
138.5
138
Arbit.R.L(m)
137.5
137
136.5
136
135.5
135
134.5
134
0 10 20 30 40 50 60 70 80 90 100
L to R(m) Series1
L sec
(m) (m) (m) (m) (m) (m) (m) (m) (m2) (m)
139.0
138.0
R.L. (m)
137.0
136.0
-7 -2 3
Chainage (m)
140
139
HFL=137.7590m
138
137
136
-7 -5 -3 -1 1 3 5
The mean scour depth,Dsm below HFL is computed vide IRC 78 2000 clause 703.2.
dsm= 1.34[Db^2/Ksf]1/3
dsm= mean scour depth below HFL
Db= discharge in cumecs per m width
Ksf= Silt factor 2.40
Discharge,Q= 4.04 cumecs
Discharge for foundation= 5.26 cumecs
= 2xdsm
= 1.83 m
MSL for Pier = 135.88 m
= 1.27xdsm
= 1.16 m
MSL for Abutment = 136.55 m
BRIDGE AT KM 47+900
1 Emperical Formula
Q = 25 Cumecs
3 Manning's Formula
Q = 2.70 Cumecs
4 UP Irrigation's Formula
Q = 6.30 Cumecs
Qd = 4.04 Cumecs
Annexure 3
1 0 145.00 0 0 - -
2 3.00 160.00 3.00 15.00 15.00 45.00
45.00
Slope (S) = Li(Di-1+Di) = 5.00 m/km
2
L = 0.50 %
The value of runoff coefficient (C) may be taken from the following Table
Average slope
Soil and
Mild Mdium Steep
land use
(0-4 %) (4-10%) (10 % +)
Rocky, heavy clay 0.6 0.75 0.85
Intense cultivation,
0.5 0.6 0.7
loamy/clay soils
Grass cover, medium soils 0.4 0.5 0.6
Dense vegetation, forest 0.05 0.15 0.25
C) UP Irrigation's formula
Design discharge Q shall be computed from the equation
Q = 7.222
0 148.417
10 148.676 Rugosity co-efficient 'n' = 0.05
20 148.94
30 149.007
40 148.83
50 148.515
60 148.764
70 148.848
80 148.872
90 148.906
100 148.876 Average bed slope along the stream = 0.0013
110 148.651 or, 1 V in H = 798.3193
120 148.736
130 148.525
140 148.904 C/L of brg. at ch.140
150 148.778
160 147.486
170 147.488
180 147.684
190 148.179
200 147.695
210 147.92
220 148.326
Long Section
150
149.5
Br.C/L
149
Arbit.R.L(m)
148.5
148
147.5
147
0 50 100 150 200
L to R(m) Series1
L sec
lsec
(m) (m) (m) (m) (m) (m) (m) (m) (m2) (m)
150.0
R.L. (m)
149.0
148.0
-10 -5 0 5 10 15
Chainage (m)
1 Emperical Formula
Q= 34 Cumecs
3 UP Irrigation's Formula
Q= 7.22 Cumecs
4 Manning's Formula
Q= 7.17 Cumecs
Qd = 7.22 Cumecs
Note:
The discharge is calculated by various methods as computed above and design discharge recommended based on provision of IRC: SP-13
and IRC 5-1998 is as :When the variation between the two values of the discharges computed by different methods is more than 50%, design
discharge has been taken as 1.5 times the lower of two values.So here design discharge computed is 1.5times of the lowest value i.e,
discharge from slope area method.But from this computed discharge ,clear waterway found will be increased i.e,existing span will be changed.
If the all discharge will be ignored and only lowest value i.e, discharge from slope area method will be taken into consideration,span will be
same as existing one.
Require bridge with a minimum span of 10m and minimum vent of 2.5m. Provide 1 x 10m.
The mean scour depth,Dsm below HFL is computed vide IRC 78 2000 clause 703.2.
dsm= 1.34[Db^2/Ksf]1/3
dsm= mean scour depth below HFL
Db= discharge in cumecs per m width
Ksf= Silt factor 2.40
Discharge,Q= 7.22 cumecs
Discharge for foundation= 9.39 cumecs
= 2xdsm
= 2.23 m
MSL for Pier = 148.33 m
= 1.27xdsm
= 1.41 m
MSL for Abutment = 149.14 m
AR2/3 =
1/2
K*n = Q*n/S
Q = 7.22 Cumecs
n = 0.05
S = 0.0013
2/3
AR = 10.20 15.26
water depth= 1.770
151
150 HFL=150.544m
149
148
-10 -5 0 5 10
Annexure 4
1 0 147.00 0 0 - -
2 9.00 165.00 9.00 18.00 18.00 162.00
162.00
Slope (S) = Li(Di-1+Di) = 2.00 m/km
L2 = 0.20 %
The value of runoff coefficient (C) may be taken from the following Table
Average slope
Soil and
Mild Mdium Steep
land use
(0-4 %) (4-10%) (10 % +)
Rocky, heavy clay 0.6 0.75 0.85
Intense cultivation,
0.5 0.6 0.7
loamy/clay soils
Grass cover, medium soils 0.4 0.5 0.6
Dense vegetation, forest 0.05 0.15 0.25
Q = 25.92576
0 150.489
20 150.898 Rugosity co-efficient 'n' = 0.05
40 150.839
60 151.673
80 151.596
100 150.678
120 151.01
140 150.753
160 151.482
180 151.374 C/L of brg. at ch.200
200 151.669 Average bed slope along the stream = 0.0035
220 151.716 or, 1 V in H = 287.4251
240 150.769
260 150.063
280 152.143
300 150.624
320 150.865
340 151.863
344 152.331
Long Section
155
154.5
154
153.5
153
Arbit.R.L(m)
152.5 Br.C/L
152
151.5
151
150.5
150
149.5
149
148.5
148
0 50 100 150 200 250 300 350 400
L to R(m) Series1
L sec
(m) (m) (m) (m) (m) (m) (m) (m) (m2) (m)
152.0
R.L. (m)
151.0
150.0
149.0
-8 -3 2 7 12
Chainage (m)
BRIDGE AT KM 72+550
1 Emperical Formula
Q= 51 Cumecs
3 UP Irrigation's Formula
Q= 25.93 Cumecs
4 Manning's Formula
Q= 11 Cumecs
Qd = 10.70 Cumecs
Note: The discharge is calculated by various methods as computed above and design discharge recommended based on provision of IRC: SP-13 and
IRC 5-1998 is as :When the variation between the two values of the discharges computed by different methods is more than 50%, design
discharge has been taken as 1.5 times the lower of two values.So here design discharge computed is 1.5times of the lowest value i.e, discharge
from slope area method.But from this computed discharge ,clear waterway found will be increased i.e,existing span will be changed.
If the all discharge will be ignored and only lowest value i.e, discharge from slope area method will be taken into consideration,span will be same
as existing one.
Require bridge with a minimum span of 10m and minimum vent of 3.0 m.
The mean scour depth,Dsm below HFL is computed vide IRC 78 2000 clause 703.2.
dsm= 1.34[Db^2/Ksf]1/3
dsm= mean scour depth below HFL
Db= discharge in cumecs per m width
Ksf= Silt factor 2.40
Discharge,Q= 16.06 cumecs
Discharge for foundation= 20.87 cumecs
= 2xdsm
= 3.27 m
MSL for Pier = 148.56 m
= 1.27xdsm
= 2.08 m
MSL for Abutment = 149.76 m
AR2/3 =
1/2
K*n = Q*n/S
Q = 10.70 Cumecs
n = 0.05
S = 0.0035
AR2/3 = 9.07 13.85
water depth= 2.030
Chainage(m) HFL (m) HFL Distance h Avg h Diff in h Area Perimeter
2.030 151.750
-11.839 153.605 151.750 0.000 0 0.000 0.000 0.000 0.000 0.000
-8.566 153.59 151.750 0.000 3.273 0.000 0.000 0.000 0.000 0.000
-8.325 152.805 151.750 0.000 0.241 0.000 0.000 0.000 0.000 0.000
-7.924 152.815 151.750 0.000 0.401 0.000 0.000 0.000 0.000 0.000
-6.911 152.018 151.750 151.750 0.000 1.013 0.000 0.000 0.000 0.000 0.000
-5.139 151.49 151.750 1.000 1.772 0.260 0.130 0.260 0.230 1.791
-4.915 151.548 151.750 2.000 0.224 0.202 0.231 0.058 0.052 0.231
-4.518 151.538 151.750 3.000 0.397 0.212 0.207 0.010 0.082 0.397
1.993 149.72 151.750 4.000 6.511 2.030 1.121 1.818 7.299 6.760
10.338 151.435 151.750 5.000 8.345 0.315 1.173 1.715 9.785 8.519
28.781 152.246 151.750 6.000 18.443 0.000 0.157 0.315 2.905 18.446
154
153
152
HFL=151.75mm
151
150
149
-15 -10 -5 0 5 10 15 20 25
As we know, Drainage of road is one of the many components of a road project. The objective of
road drainage is to remove the storm water as rapidly as possible so that traffic may move safely
and efficiently without any loss of time. Speedy disposal of the storm water runoff likely to be
accumulated due to construction of the road embankment is very important for the success of a
road project from technical and environmental points of view. Inadequate drainage invariably
results in reduction of life span of a road, increase in maintenance cost and drainage congestion
in the countryside leading to submergence of land and consequent loss of agricultural and other
properties.
Provision of culverts of adequate size and numbers in a road drainage scheme - whether the road
is a new one or an up-gradation of an existing one - is intimately related to the health and safety
of the road.
In a very flat terrain, most of the streams are shallow and the banks are spilled with flood water
moving in wide flood plains. In the absence of road, the spill flow moving over the land surface
constitutes a substantial amount of peak flood. When a road is built in such a terrain with wide
flood plains, the entire flood water has to move across the road through the bridge opening of
limited span, resulting in very high afflux and other problems. Usually, the spill water is found to
move along the toe of the road causing scouring and damage to road embankment. Provision of
relief culverts/bridges on either side of the bridges in such flood plains are very helpful in the
quick disposal of spill flood across the road which results in less afflux and ensures safety of the
road embankment
During the road side drainage hydrological survey, the following information has been collected to
propose new structures.
Type of terrain
Direction of cross slope of terrain
Adjacent land use
Size and type of existing drains and their hydraulic condition
Existing structures along the highway
The Project Road should have adequate cross drainage facility if large number of culverts and
natural drains/outfalls are present in our road. It should be based on that no overtopping of the
road has been observed on the project area. Also no significant scoring was observed in any of
the structures/roadside. Therefore, it is concluded that all the existing structures are hydraulically
sound and road has sufficient cross drainage structures.
• To balance the discharge from road catchment area and discharge passing through
new/existing cross drainage structures.
• Culverts are required to be provided under earth embankment for crossing of water
course like streams, Nallas across the embankment as road embankment cannot be
allowed to obstruct the natural water way.
• The culverts are also required to balance the flood water on both sides of earth
embankment to reduce flood level on one side of road thereby decreasing the water head
consequently reducing the flood menace.
Guidelines suggested in IRC: SP: 42, IRC: SP: 13-2004 and relevant IRC are followed for
proposed the no. of cross drainage structures.
In the plains, however, the available longitudinal slope along the proposed alignment is generally
very flat and roadside ditches are commonly aligned with available longitudinal slope for
economy. If the existing dips are long apart, the distance between an existing dip and an
adjacent ridge becomes too long entailing a bigger size of the ditch and acquisition of more land.
In such cases, intermediate culverts, also called balancing culverts, are proposed just to reduce
the length and size of the roadside ditches. In fact, most of the culverts in plains are balancing in
nature. However, all natural dips may not be used as suitable culvert locations. It depends on the
available longitudinal slope and consequently the required size of the roadside ditches that
govern the locations to be utilized as suitable culvert points. If the available longitudinal slope is
good enough to carry the roadside ditches for a longer distance with reasonable size, some
intermediate minor dips may be crossed over without having to provide a culvert structure.
Culverts can be of different shapes such as arch, slab and box. These can be constructed with
different material such as masonry (brick, stone etc) or reinforced cement concrete. Further the
size, invert level, layout etc. are decided by hydraulic considerations and site conditions. The
cushion depends on road profile at the culvert location.
Generally, for medium height of embankments, both of the options viz., box culverts with road
embankment supported on roof slab and slab culvert with roof slab directly supporting the wheel
loads, are feasible. One of the options is chosen on the basis of LTEC (Least Total Expected Cost)
method. For high embankments (for example near approach of bridges), however, box culverts
are preferred to slab culverts from both structural and economic considerations.
Proposal for cross drainage structures in this package are briefly outlined below:
Data may be collected from site investigation / study of toposheets / Satellite Imagery / local
enquiry and from records maintained by Government agencies like CWC, IMD, RDSO and
Irrigation / PWDs.
Broadly, the several data required for the design of cross drainage structures(culvert) are:
• Topographic maps showing contours, nature and slope of terrain, soil and cover
conditions, physical features in the vicinity of the proposed culverts etc.
• Existing stream and canal network in the project area crossing the road indicating
direction of flow and the drainage area contributing flow to the culverts.
• Stream data e.g. L-section and cross-sections of the stream upstream and downstream of
the point of crossing, gauge-discharge data, if available, HFL from flood marks and local
enquiry.
• Soil and sub-soil data for computation of run-off from the drainage basins.
• Hydro-meteorological data like amount, intensity, duration and frequency of rainfall.
• Proposed roadway alignment , L-section and cross-sections of the road near the cross-
drainage sites
• Fish passage requirement, if any.
• Debris and sediments to be passed through the culverts.
• Points of flow accumulation and areas of prolonged submergence, if any.
• Nearest human habitation / property, places of worship, places of strategic importance
etc.
In case the proposed alignment runs parallel to any existing major road, it is very helpful
to study the drainage particulars and performance of culverts on the existing road to
have an idea about the required numbers and size of culverts for the proposed road from
the drainage efficiency of the existing road.
• Information regarding likely damage to habitats, crops etc, due to ponding upstream of
culverts.
• Maximum permissible velocity at the outlets of culvert to determine nature of protective
works to be adopted.
For efficient functioning of road in rainy season and proposed size and location of structures,
several data are required to be collected at site and from other dependable sources. A brief
description of the various data collected for hydraulic computations are given below:
IRC: SP:42 (1994), however, recommends a return period of 25 years for important roads like
National and State highways (50 years for depressed sections) and 10 years for lower category
roads. Here we assume return period of 50 yr 1hr rainfall for our road stretch i.e, coming 77mm.
Rainfall for Jhansi Hamirpur zone is noted from CWC report Betwa subzone 1(c) i.e., 240 mm
(50yr 24hr rainfall) as shown below.
The time taken by the run-off from the farthest point on the periphery of the catchment (called
the critical point) to reach the site of the culvert is called the "concentration time". In considering
the intensity of precipitation it was said that the shorter the duration considered the higher the
intensity will be. Thus safety would seem to lie in designing for a high intensity corresponding to
a very small interval of time. But this interval should not be shorter than the concentration time
of the catchment under consideration, as otherwise the flow from distant parts of the catchment
will not be able to reach the outfall in time to make its contribution in raising the peak discharge.
Therefore, when examining a particular catchment, only the intensity corresponding to the
duration equal to the concentration period (t) of the catchment needs to be considered.
The concentration time Depends on (1) the distance from the critical point to the structure; and
(2) the average velocity of flow. The slope, the roughness of the drainage channel and the depth
of flow govern the later. Complicated formulae exist for deriving the time of concentration from
the characteristics of the Catchment. For our purpose, however, the following simple relationship
Where
t c = (0.87* L3 /H)^0.385
Mean runoff coefficient used for estimation of design discharge for the drains given in Appendix-
9.1. Runoff coefficients are taken according to the type of surface, namely paved, unpaved,
agricultural, and residential, forest and hilly areas etc. as per the recommendations made in IRC:
SP-42 and SP-13.
For plain regions, toposheets having 20m contour interval may not be at all useful in delineating
catchment or determination of fall of the channel. However, the artificial ridge lines like roads,
canals etc can be easily traceable on the toposheet/map and these ridges can be considered as
catchment boundary for a particular culvert. For plain regions, most of the culverts are designed
as balancing ones and do not span any distinct channel. As such, area of catchment applicable for
any particular point is governed by the countryside length discharging towards the culvert and
the distance between two consecutive cross ridges (natural or artificial) on either side of it. The
countryside length may be taken as the distance between the proposed alignment and existing
artificial ridges (roads, canals etc), if any, running parallel to it. The distance between the existing
cross ridges (running perpendicular to the proposed alignment) can be measured from
toposheets or the survey data of the road corridor. However, if the distance between two
consecutive cross ridges is so large that it entails unreasonable size of the roadside ditches, the
acceptable size of the roadside ditches shall limit the spacing of the culverts. In such cases, group
of culverts at available dips may be required between two cross ridges.
The peak run-off from the area in between the catchments of identifiable streams, will have to be
evacuated through the culvert openings to be proposed at natural dips between the two
consecutive Stream outfall points where bridges are recommended.
Catchment area for whole road alignment is observed roughly from Google earth(in absence of
Toposheets) is equal to the total length along the road multiplied by the distance from the center
lines of the road to upstream side of road up to a point 4km (determined at site by visual
observation).
Based on the above data, drainage discharge is found by using Rational method
Q = 0.028 PfIcA
Where Q= the design discharge in m3/sec, f is the spread factor, taken as 1.0 (for small
catchment), P is the mean run-off coefficient, Ic is the design rainfall intensity in cm/hr
corresponding to time of concentration (tc) in hour and A is the catchment area in hectares.
9.7 Conclusion
There are 28 no. of box culvert and Pipe culvert in existing road has been proposed here to
balance the discharge available on road site. Location of culverts is based on ground/road profile
as shown in Plan Profile of road. A detailed computation has been attached in Appendix-9.1 and
list of new culverts are given in Table 9.1 below:
Existing Hume pipe and arch culverts having diameter / span < 900 mm are proposed for
reconstruction in NP4 RCC Pipes in full formation width of 12 m including parapets, as per type
design requirements laid down in IRC:SP:13. These culverts have been proposed in such
stretches where required minimum cushion over the pipe is available. The bedding for pipe shall
be first class bedding, comprising of granular material for culverts with cushion above the pipe
not less than 0.6 m and not exceeding 4 m.
Culverts along with their improvement proposals (widened, reconstructed, and retained) are listed
in Table 9.3.
Improvement
Details of Existing Culvert
Proposal
S. Improvement Proposed
Design Superstructure Substructure Span
No code Culvert*
Chainage Arrangement Width
(Km) Type Material Type Material ** Type Span
Widen with
21 19+776 Pipe - - - 1 X 0.9 10.25 Pipe 1 X 0.9
Repairs
Widen with
22 20+621 Pipe - - - 1 X 0.9 10.3 Pipe 1 X 0.9
Repairs
Widen with
23 20+707 Pipe - - - 1 X 0.9 10.3 Pipe 1 X 0.9
Repairs
24 22+642 Slab RCC wall Brick 1 X 2.6 10.8 Reconstruction Box 1 X 2.6
Retain with
25 24+103 Slab RCC wall Brick 1 X 3.0 12.0 - -
Repairs
Widen with
26 25+067 Arch Brick wall Brick 2 X 1.8 6.4 Box 1 X4.2
Repairs
Widen with
27 26+901 Slab RCC wall Brick 1 X 3.0 10.2 Slab 1 X 3.0
Repairs
Widen with
28 27+511 Pipe - - 1 x 0.9 10.65 Pipe 1 x 0.9
Repairs
Widen with
29 28+071 Pipe - - 1 x 1.0 10.25 Pipe 1 x 1.0
Repairs
Widen with
30 30+911 Arch Brick wall Brick 2 X 1.8 6.25 Box 1 X4.2
Repairs
31 31+136 Slab RCC wall PCC 1 X 1.5 10.6 Reconstruction Box 1 X 1.5
32 33+323 Slab RCC wall Brick 1 X 1.5 13.25 Reconstruction Box 1 X 1.5
Retain with
33 34+166 Pipe - - 1 X 0.9 12.7 - 2 X 1.0
Repairs
Retain with
34 34+458 Slab RCC wall PCC 1 X 1.8 10.97 - -
Repairs
Widen with
35 34+924 Pipe - - 1 X 1.0 10.32 Pipe 1 X 1.0
Repairs
Retain with
36 35+466 Slab RCC wall Brick 1 X 2.5 11.3 - -
Repairs
Retain with
37 36+264 Pipe - - 1 X 1.0 12.5 - -
Repairs
38 36+907 Slab RCC wall PCC 1 X 2.7 11.0 Reconstruction Box 1x2.7
Retain with
39 37+986 Slab RCC wall Brick 1 X 1.25 13.05 - -
Repairs
Retain with
40 41+334 Slab RCC wall PCC 1 X 0.75 11.0 - -
Repairs
Retain with
41 41+627 Slab RCC wall PCC 2 X 0.75 11.0 - -
Repairs
42 42+210 Pipe - - 1 X 0.9 9.85 Reconstruction Pipe 1 X 1.2
43 43+644 Pipe - - 1 X 0.6 10.1 Reconstruction Pipe 1 X 1.2
Buried
44 43+901 10.8 Reconstruction Pipe 1 X 1.2
Improvement
Details of Existing Culvert
Proposal
S. Improvement Proposed
Design Superstructure Substructure Span
No code Culvert*
Chainage Arrangement Width
(Km) Type Material Type Material ** Type Span
Retain with
55 49+705 Pipe - - - 1 X 1.0 12.1 - -
Repairs
Retain with
56 50+491 Slab RCC wall Brick 1 X 1.0 11.05 - -
Repairs
Widen with
57 51+523 Pipe - - 1 X 0.9 9.9 Pipe 1 X 0.9
Repairs
58 51+768 Slab RCC wall CRM 1 X 1.8 10.0 Reconstruction Box 1x2.0
59 51+868 Stone Slab Stone slab wall Brick 1 X 1.2 9.0 Reconstruction Box 1 X 1.5
Widen with
60 54+136 Slab RCC wall Brick 1 X 1.7 9.7 Slab 1 X 1.7
Repairs
Retain with
61 54+551 Pipe - - - 1 X 1.0 12.3 - -
Repairs
62 54+927 Stone Slab Stone slab wall Brick 1 X 0.9 7.0 Reconstruction Box 1 X 1.5
63 55+721 Pipe - - - 1 X 0.3 11.1 Reconstruction Pipe 1 X 1.2
64 56+121 Pipe - - - 1 X 0.4 10.50 Reconstruction Pipe 1 X 1.2
65 56+335 Pipe - - - 1 X 0.6 9.93 Reconstruction Pipe 1 X 1.2
66 56+676 Pipe - - - 1 X 0.3 10.9 Reconstruction Pipe 1 X 1.2
67 58+171 Arch Brick wall Brick 1 X 1.5 6.7 Reconstruction Box 1 X 1.5
68 58+809 Arch Brick wall Brick 1 X 2.45 6.75 Reconstruction Box 1 X 2.5
69 59+051 Arch Brick wall Brick 1 X 1.15 6.74 Reconstruction Box 1 X 1.5
Widen with
70 59+351 Arch Brick wall Brick 1 X 2.4 6.65 Box 1 X 2.5
Repairs
71 62+751 Arch Brick wall Brick 1 X 0.87 8.55 Reconstruction Box 1 X 1.5
72 63+454 Arch Brick wall Brick 1 X 2.4 6.4 Reconstruction Box 1 X 2.5
Widen with
73 63+785 Slab RCC wall CRM 1 X 0.9 10.95 Slab 1 X 0.9
repairs
74 64+370 Arch Brick wall Brick 1 X 1.85 6.35 Reconstruction Box 1 X 2.0
75 64+930 Stone Slab Stone wall Brick 2 X 0.9 6.8 Reconstruction Box 1 X 2.0
76 65+605 Arch Brick wall Brick 1 X 3.05 6.25 Reconstruction Box 2 X 3.5
Widen with
77 65+740 Slab RCC wall Brick 1 X 1.2 6.9 Slab 1 X 1.2
repairs
78 66+650 Arch Brick wall Brick 1 X 0.75 8.45 Reconstruction Box 1 X 1.5
Widen with
79 67+130 Slab RCC wall CRM 1 X 1.5 10.9 Slab 1 X 1.5
repairs
80 67+160 Slab RCC wall Brick 1 X 0.9 6.74 Reconstruction Pipe 1 X 1.2
81 68+080 Pipe - - - 1 X 0.4 9.75 Reconstruction Pipe 1 X 1.2
Widen with
82 68+204 Pipe - - - 2 X 1.0 10.15 Pipe 2 X 1.0
Repairs
Widen with
83 68+290 Pipe - - - 1 X 1.0 10.23 Pipe 1 X 1.0
Repairs
Retain with
84 68+657 Slab RCC wall CRM 1 X 1.5 11.4 - -
Repairs
Widen with
85 69+106 Pipe - - 1 X 1.0 10.25 Pipe 1 X 1.0
Repairs
Widen with
86 71+216 Slab RCC wall CRM 2 X 2.4 10.05 Slab 2 x 2.4
repairs
Retain with
87 71+390 Slab RCC wall CRM 1 X 1.5 10.95 - -
Repairs
Widen with
88 72+286 Pipe - - 2 X 1.0 10.2 Pipe 2x1.0
Repairs
Q = A x lo x λ
where
2
Catchment Area, A = 304.000 Km = 30400 Hectares
(Road width*Length of Road)
One hour rainfall, Lo = 8.0 cm
(Taken from cwc report sub zone 1(c))
λ = 0.056 x f xP
tc + 1
where
fraction co-efficient f = 0.9 (Taken from Fig. 4.2,Page 14, IRC:SP:13-2004)
co-efficient of run-off P = 0.40 (Taken from table 4.1,Page 13, IRC:SP:13-2004)
3
= (0.87*L /H)0.385
Time of Concentration tc
where
Length, L = Distance from critical point to structure
= 5.00 Km
Height, H = Fall in level from critical point to structure
= 10.0 m
λ = 0.006
Area A 3.00
Perimeter P 7.00
R 0.43
Entry Loss Coefficient Ke 0.444 (Taken from Table 19.1, Page 76, IRC:SP:13-2004)
λ 2.41 λ = A / SQRT( 1+ Ke + Kf )
Q 5.85 Q = λ * SQRT(2*g*h)
Discharge Capacity of New Proposed Box(2X2) Culverts Discharge Capacity of New Proposed Pipe Culverts
Operating head (h) 0.3 Operating head (h) 0.3
Length of pipe 10.000 Length of pipe 10.000
Size of Box 2.0 Diameter of pipe 1.2
Depth 2.0
Area A 1.13
Area A 4.00 Perimeter P 3.77
Perimeter P 8.00 R 0.30
R 0.50
Friction Loss Coefficient Kf 0.17
Friction Loss Coefficient Kf 0.084 Entry Loss Coefficient Ke 0.1
Entry Loss Coefficient Ke 0.465 λ 1.01
λ 3.21
Q (per Pipe) 2.44
Q 7.80 No. of Pipes 1.00
No. of spans 1.00 Similar No of culverts 12
Similar No of culverts 11 Total Q 29.27
Total Q 85.78
Discharge contribution from 1no.Of Major Bridge 375 (10 to 20% of Qdesigned)
Discharge contribution from 16no. Of Arch culvert 20
Discharge contribution from 57 no. of slab culverts 281.05
Discharge contribution from 120no. of Pipe culverts 292.68
Discharge contribution from 8no.Of Minor Bridge 300.00
10 DRAINAGE DESIGN
10.1 Introduction
Drainage, both surface and subsurface, is essential for efficient and healthy functioning of a road.
Broadly, drainage has two aspects, namely
(i) Cross-drainage works to ensure free and smooth movement of surface run-off through
bridges and culverts, so that there is no overtopping of road
(ii) Road drainage, which ensures quick and safe disposal of water from road surface and
embankments through roadside drains to their respective outfalls.
During the roadside drainage survey, the following information has been collected to design the
drainage system.
Type of terrain
Direction of cross slope of terrain
Adjacent land use
Size and type of existing drains and their hydraulic condition
Requirement of drains.
The Project Road has adequate cross drainage facility as large number of culverts and bridges are
present. In some urban areas localized side drains are present which will be continue. The road
drainage in urban area is very few. In rural areas ditches are found at a few locations. A number
of streams, nalas cross the project road. It is reported that overtopping of the road / structures
has been observed on the project road at few location. Therefore, it is concluded that all the
existing structures excepting few are hydraulically sound and road has sufficient cross drainage.
Few new structures have been proposed in the detail study especially in overtopping area.
a) Localized side drains exist on few locations are found to be in good condition.
b) Unlined trapezoidal drains (Type 1) are provided only at rural area, as there are chances of
blockage of these drains during flood or high rainfall.
c) Generally RCC lined drains (Type 2 and type 3) are provided in urban and semi urban area.
d) Existing drains are proposed to be maintained wherever applicable with existing size and
invert level.
e) However at some stretches of existing road where drains are missing or in poor condition, the
drains are recommended or to be reconstructed.
f) Adequate numbers of culvert along with drains are provided to see the smooth runoff of
surface water.
In open areas, unlined drains are proposed near the ROW limits, sufficiently away from the toe of
the embankment. Through built up areas to drain off surface run off from the road and to
intercept sullage from road side properties, lined drains are proposed in the following stretches,
For efficient functioning and proper design of drains, several data are required to be collected at
site and from other dependable sources. A brief description of the various drainage data
collected for design of drains are given below:
The drains have been designed for a rainfall of 25 year return period and 1 hour rainfall per IRC:
SP-42 recommendation. 24 hour rainfall of 25 year return period taken from isopluvials map for
25 years return period as given in Flood Estimation report for sub zone 1©.
Time of concentration (tc) in hours and design rainfall intensity ( I c) in cm/hr, to be used in the
Rational formula . The following formula recommended by IRC-SP-42 is used.
Tc = Lc/Vc +B/Vb
Where F is the total rainfall in cm in T hrs. Lc and B are the respective length and breadth of
catchment contributing flow into the drain. V c and Vb are the mean velocity along and across the
drain respectively. First equation over estimates rainfall intensity, I c when T is taken as 24 hrs
and the F value is taken from isopluvials of 25-year return period. F and Ic are found from the
rainfall distribution curves given in CWC flood estimation report for subzone1(c), where 25-year
hourly rainfall distribution are given from measured actual rainfall with recording gauge. Time of
concentration is found as equal to inflow time into the drain plus flow time through the drain upto
the cross drainage structure i.e. the outfall of the drain. Design rainfall intensity (I c) is found
corresponding to time of concentration (tc).
Runoff coefficients are taken according to the type of surface, namely paved, unpaved,
agricultural, and residential, forest and hilly areas etc. as per the recommendations made in IRC:
SP-42 and SP-13.
Average distance between consecutive cross-drainage structures was determined from bridge and
culvert inventory. Catchment area for each drain is found as equal to the average distance
between consecutive cross drainage structures along the road multiplied by the distance between
the centre lines of the road up to a point 10 to 1000 m (determined in the site by visual
observation) away from the ROW across the road.
Based on the above data, drainage discharge is found by using Rational method
Q = 0.028 PfIcA
Where Q= the design discharge in m3/sec, f is the spread factor, taken as 1.0 (for small
catchment), P is the mean run-off coefficient, Ic is the design rainfall intensity in cm/hr
corresponding to time of concentration (tc) in hour and A is the catchment area in hectares.
Bed slope of the drain is found from longitudinal profile of ground under the drain. Ideally, top of
RCC drain should be kept at Shoulder Edge level to avoid excessive cutting and filling. Attempt
has been made to avoid high cutting or filling by changing bed slope of the drain as per the
existing ground/Road profile. Details of drains e.g. location, type, length, bed slope, invert level,
outfall points etc. are given in long profiles of drains as well as in the design abstract .
Based on the methodology described above the drains are designed for reconstructed and
proposed section of road. Adequacies of existing drains are also checked. Open drains are the
intercepting drains of surface runoff and are designated as side drains, catch water drains, or
gutters depending on their location and formation. Open side drains are proposed on either side
of the road embankment in order to intercept surface water runoff from the carriageway and
shoulders. The open drains are at ground level.
Type of road pavement and rainfall intensity is the main factors which influence the shape,
location and capacity of open drains. The drains should have sufficient capacity to carry natural
peak run off without water overflowing, the surface. Open drains are generally unlined and are
located near the ROW boundary, as far as possible and away from the toe of embankment.
The choice of cross section of open drains is generally limited to 3 types – triangular, trapezoidal
and rectangular. The triangular section has lesser flow capacity. Rectangular sections prove an
efficient profile. Side drains must be connected to some natural channel, drain or natural
watercourse as outfall. So trapezoidal section is suitable earthen drain.
Lined drains are proposed in built-up areas. These drains are lined with concrete (PCC M-20) and
are 150 mm thick with a bottom width of 1000 mm over a leveling course of 50 mm thick PCC M-
15. The minimum depth of the drain is 1000 mm including free board. The drain is proposed
rectangular in section. To provide access to the road side properties and side streets, the lined
drains are covered with pre cast M-20 RCC covers with perforations for ease of maintenance. A
minimum free board of 150 mm has been provided as recommended in IRC: SP- 42. The design
abstract includes the following information:
Based on design abstract and layout plans of the road, long profile of drains will be prepared
showing CD works, bed slope, flow direction, invert levels, size of drain (B o), type of drain etc.
Longitudinal profile of drain is given in Drawings Volume. Standard drainage drawings have been
prepared for different types of drains and other structures as shown in Drawings Volume.
3.560 3.680 0.120 104.219 105.244 -0.854 Lined Drain 0.700 0.5 adequate
10.340 10.550 0.210 118.115 116.768 0.641 Lined Drain 0.700 0.50 adequate
10.550 10.936 0.386 116.768 121.794 -1.302 Lined Drain 0.700 0.50 adequate
10.936 11.000 0.064 121.794 122.579 -1.227 Lined Drain 0.700 0.50 adequate
20.620 20.706 0.086 126.450 125.971 0.557 Lined Drain 0.700 0.50 adequate
20.706 20.830 0.124 125.971 125.615 0.287 Lined Drain 0.700 0.55 adequate
25.400 25.655 0.255 124.633 123.586 0.411 Lined Drain 0.700 0.50 adequate
25.655 26.000 0.345 123.586 124.464 -0.254 Lined Drain 0.700 0.50 adequate
26.000 26.220 0.220 124.464 124.554 -0.041 Lined Drain 0.700 0.50 adequate
26.220 26.500 0.280 124.554 124.966 -0.147 Lined Drain 0.700 0.50 adequate
33.900 34.165 0.265 130.724 130.454 0.102 Lined Drain 0.700 0.50 adequate
34.165 34.457 0.292 130.454 130.707 -0.087 Lined Drain 0.700 0.50 adequate
34.457 34.923 0.466 130.707 130.418 0.062 Lined Drain 0.700 0.65 adequate
34.923 35.000 0.077 130.418 130.870 -0.587 Lined Drain 0.700 0.50 adequate
41.627 41.850 0.223 134.772 134.911 -0.062 Lined Drain 0.700 0.50 adequate
Outfal in existing earthen
138.1 47.875 48.000 0.125 138.583 138.597 -0.011 Lined Drain 0.700 0.50 adequate
drain
48.000 48.185 0.185 138.597 138.412 0.100 Lined Drain 0.700 0.50 adequate
50.490 51.100 0.610 141.600 142.747 -0.188 Lined Drain 0.700 0.80 adequate
51.100 51.522 0.422 142.747 143.612 -0.205 Lined Drain 0.700 0.60 adequate
51.522 51.767 0.245 143.612 143.015 0.244 Lined Drain 0.700 0.50 adequate
51.767 51.867 0.100 143.015 142.663 0.352 Lined Drain 0.700 0.50 adequate
51.867 52.300 0.433 142.663 143.701 -0.240 Lined Drain 0.700 0.50 adequate
3.380 3.560 0.180 104.187 104.000 0.104 Lined Drain 0.700 0.5 adequate
Outfal to the culvert
103.988
3+560
3.560 3.680 0.120 104.000 104.528 -0.440 Lined Drain 0.700 0.5 adequate
Outfal in existing
107.9 5.460 5.660 0.200 108.400 108.732 -0.166 Lined Drain 0.700 0.50 adequate
earthen drain
Outfal in existing
113.500 9.950 10.340 0.390 113.940 118.393 -1.142 Lined Drain 0.700 0.50 adequate
earthen drain
10.340 10.550 0.210 118.393 116.949 0.688 Lined Drain 0.700 0.50 adequate
10.550 10.936 0.386 116.949 121.633 -1.213 Lined Drain 0.700 0.50 adequate
10.936 11.000 0.064 121.633 122.579 -1.478 Lined Drain 0.700 0.50 adequate
25.400 25.655 0.255 124.633 123.586 0.411 Lined Drain 0.700 0.50 adequate
Outfal to the culvert
MNBR
25+655
25.655 26.000 0.345 123.586 124.464 -0.254 Lined Drain 0.700 0.50 adequate
26.000 26.220 0.220 124.464 124.700 -0.107 Lined Drain 0.700 0.50 adequate
Outfal to the culvert
125.27
26+220
26.220 26.500 0.280 124.700 124.966 -0.095 Lined Drain 0.700 0.50 adequate
33.900 34.165 0.265 130.992 130.454 0.203 Lined Drain 0.700 0.50 adequate
Outfal to the culvert
130.012
34+165
34.165 34.457 0.292 130.454 130.707 -0.087 Lined Drain 0.700 0.50 adequate
Outfal to the culvert
34+457
34.457 34.923 0.466 130.707 130.418 0.062 Lined Drain 0.700 0.65 adequate
Outfal to the culvert
130.280
34+923
34.923 35.000 0.077 130.418 130.870 -0.587 Lined Drain 0.700 0.50 adequate
Outfal in existing
133.8 41.380 41.627 0.247 134.283 134.439 -0.063 Lined Drain 0.700 0.50 adequate
earthen drain
Outfal to the culvert
134.49
41+627
41.627 41.850 0.223 134.439 134.911 -0.212 Lined Drain 0.700 0.50 adequate
Outfal in existing
138.1 47.875 48.000 0.125 138.583 138.597 -0.011 Lined Drain 0.700 0.50 adequate
earthen drain
48.000 48.185 0.185 138.597 138.412 0.100 Lined Drain 0.700 0.50 adequate
51.100 51.522 0.422 142.747 143.235 -0.116 Lined Drain 0.700 0.60 adequate
Outfal to the culvert
142.5
51+522
51.522 51.767 0.245 143.235 143.015 0.090 Lined Drain 0.700 0.50 adequate
Outfal to the culvert
141.45
51+767
51.767 51.867 0.100 143.015 142.663 0.352 Lined Drain 0.700 0.50 adequate
Outfal to the culvert
142.12
51+867
51.867 52.300 0.433 142.663 143.931 -0.293 Lined Drain 0.700 0.50 adequate
= 612 m say
(25 years 24 hourly rainfall taken from CWC report for Betwa sub zone-1c)
TCS2A,2B
Varied Width = 3
Drain width = 1
Beyond ROW = 10
0.58 Ha
0.34 Cumecs
TCS4A,4B
Varied Width = 3
Drain width = 1
Beyond ROW = 10
0.61 Ha
0.38 Cumecs
TCS3
To enhance the safety of road users adequate provisions for roadway width, geometric elements
and junction improvements, have been proposed. In addition, due consideration has been given
to the provisions contained in IRC: SP 44-1994, “Highway Safety Code”. Various measures have
also been proposed to enhance traffic control.
Adequate road signs have been proposed for the project road in order to provide advance
information to guide, regulate / control traffic flow and ensure safe operations. Road signs will
either be ground mounted or displayed as overhead gantry signs. The signs will be of retro-
reflective sheeting of encapsulated type as per the MoRT&H specifications for Road and Bridge
Works, 2001. Detailed drawings will be prepared for major intersections showing position and
type of road sign. Road signs are to be installed at 2.0 m from the extreme edge of carriageway
to ensure a safe clear zone and bottom edge of the lowest sign is not less than 1.5 m above the
crown of the pavement. Ideally, In kerbed sections it is to be installed 60 cm away from the edge
of the kerb and bottom edge of the lowest sign is not be less than 2.0 m above the kerb.
Generally all signs are to be placed on the left side of the project road except at few locations
where duplicate signs are to be placed on right side as well as signs related to traffic calming
measures.
There are three categories of signs; Cautionary, mandatory and informatory signs. These would
be provided depending on the situation and function they perform in accordance with the IRC:
67-2001 guidelines for Road Signs. The sign boards would be in accordance with specification of
clause 801-3 of MORTH for high insensible sheeting. Overhead signs are proposed in accordance
with IRC: 67 -2001.
Road markings are provided to guide and assist the road users to negotiate conflict points and to
be positioned at precisely the right location to make his maneuvers in the safest and quickest way
so that the time vehicle’s/ user’s exposure to risk is minimized.
The markings serve as psychological barriers and signify the delineation of traffic paths and their
lateral clearance from traffic hazards for safe movement of traffic. Road markings are therefore
essential to ensure smooth and orderly flow of traffic and to promote road safety.
Pavement markings on the project road, location and type of marking lines, material and colour
have been proposed as per IRC: 35, “Code of Practice for Road Marking” with centre-line,
shyness and edge strip. The road markings would be carefully planned on carriageways,
intersections, bridge locations and built-up sections.
The pavement marking will be in thermo-plastic paint with glass beads as per the MORT&H
specification for Road and Bridge Works, 2001. Detailed instruction has been provided in the
drawings for major and minor intersections showing lane markings, pedestrian crossings,
directional arrows etc.
The det ails of kilometre and 5th Km stones would be in accordance with IRC: 8 guidelines. These
are to be made of precast M-20 grade reinforced cement concrete, and lettering / numbering as
per the respective IRC codes. Kilometre stones would be located on the left-hand side of the road
as one proceeds from the station from which the Kilometre count starts. Kilometre stones would
be fixed at right angles to the centre line of the carriageway.
The details of 200m stones and boundary stones would conform to IRC: 26 and IRC: 25. 200m
stones would be located on the same side of the road as the kilometer stones. The inscription on
the stones would be the numerals 2, 4, 6 and 8 marked in an ascending order in the direction of
increasing kilometer age away from the starting station. The numerals would be 80mm high. The
color of the numerals would be black on a white background.
Boundary stones at 100 m interval staggered on each side and kilometer stone have been
proposed as per the provision of IRC: 25-1967. In addition these would be fixed at all angular
points of the boundary. Where the boundary is on a curve or the land is of significant value and
likely to be encroached upon, the boundary stones, as required, would be installed at closer
intervals.
Roadway delineators are intended to mark the edges of the roadway so as to guide drivers on the
alignment ahead. Object markers are used to indicate hazards and obstructions within the
vehicle flow path, for example, traffic islands close to the intersections.
Delineators and object markers would be provided in accordance with the provisions of IRC: 79.
They are basically driving aids and would not be regarded as substitutes for warning signs, road
markings or barriers. They are not provided at locations where Chevron sign boards are provided
Delineators provide visual assistance to drivers about the alignment of road ahead, particularly at
right side. Three types of delineators have been proposed for the project roads as per the
provision contained in IRC: 79 ’Recommended Practice for Road Delineators’, namely:
Cluster of red reflectors arranged on triangular panel as object markers provided at the
heads of medians and directional islands. The object markers are to be setback by 50 cm
from the face of the kerb. Height of the post will be 50 cm. Size of equilateral triangular
panel will be 30 cm and there will be four red reflectors of 75 mm diameter. Triangular
panel and post will be painted white.
Guard posts are proposed on the location where embankment height is in between 2.0 and 3.0m.
The spacing of guard post would be 5.0m c/c in these areas. Typical Guard post consists of
precast (M20) post of size 200mm x 200mm and a height of 600mm above ground level. They
are encased in M15 cement concrete for a depth of 450mm below ground level. Guard posts are
painted with alternate black and white reflective paint of 150mm wide bands.
The road reflective pavement markers (RRPM) i.e. road studs are proposed to improve the
visibility in night time and wet weather conditions.
Metal W Beam Crash Barrier is proposed at high embankment sections with embankment height
more than or equal to 3.0m, and at major bridge approaches. Metal beam rail would be W-profile
corrugated sheet steel beams complying with the following mechanical properties.
The beam elements would have nominal width of 483mm. Post consists of formed channel of size
150 x 75 x 5, 785mm long and space consists of formed channel of size 150 x 75 x 5, 330 mm
long. All members of the system would be hot dipped galvanised to have a minimum counting of
550g/sqm, each face in compliance to relevant MORTH Specification (Cl. 810). The spacing of
posts would be 2.0m c/c. Crash barrier system absorbs impact of vehicle and laterally restrains a
vehicle from veering off. This would ensure minimum damage to the vehicle and passengers.
Besides that, metallic W beam crash barriers are proposed at safety hazard locations/sections like
ponds and sharp curves of radius less than 100m (that cannot be improved because of site
constraints)
RCC crash barriers are proposed on both sides of major bridges, minor bridges, culverts and
earth retained structures. The locations are given in tables below.
2+100 RHS
49+900 10 LHS
53+200 10 RHS
Total 20
For efficient functioning and operation of road, user facilities such as bus bays, bus shelters and
truck laybyes and traffic calming measures through built-up and activity areas are required to be
paid adequate attention.
The project road is passing through a number of villages/towns. The bus-bays and bus shelters
are proposed at these locations to provide user facilities and improve safety of other users
negotiating bus stop areas. Pedestrian crossing facility is also an integral part of bus stops to
warn vehicle users and provide guided path for pedestrian to cross the highwayProposed bus-
bays and bus shelters locations are given below in Table 12.1.
Truck laybyes primarily provide temporary resting place for the tired truck drivers along the
highway. These will be segregated from the usual travel way of traffic on the highway. These are
generally provided at areas/sections of freight activity and generally at 30km intervals.
On the project road, the initial 20km of road section is witnessing higher activity of sand carrying
trucks. Therefore, truck lay-byes are provided in this section and another is provided in the rest
of the section. The proposed locations for truck lay-bye are given below in Table 12.2.
- Reduce and control vehicle speeds to a level commensurate with the activities taking
place along the road
- Will encourage drivers to adopt a uniform speed without excessive acceleration and
declaration
- Influence driver behaviour towards non-motorised users
Traffic calming measures, when proposed on roads passing through urban areas/ environment,
whilst encouraging lower speed, will have reduced rate of accidents involving non-motorised
users.
As an initiative on this project, based on International practices, primarily the Gateway/ Entry
Points concept is used as the measure. This can be achieved by road markings, build outs,
coloured surfacing and/ or signs indicating that the driver is entering an area where road
conditions change, for example entering an urban area or a change of speed limit.