Estimate

This document provides a cost breakdown for a construction project totaling PHP 1,206,074.26. It lists the costs of various materials and works including concrete masonry, hardware, formworks, roofing, tiling, and fencing. It then calculates the subtotal and adds costs for labor, engineering fees, supervision fees, and paper works to arrive at the grand total cost.

Uploaded by

GEr JrvillaruEl
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

Estimate

This document provides a cost breakdown for a construction project totaling PHP 1,206,074.26. It lists the costs of various materials and works including concrete masonry, hardware, formworks, roofing, tiling, and fencing. It then calculates the subtotal and adds costs for labor, engineering fees, supervision fees, and paper works to arrive at the grand total cost.

Uploaded by

GEr JrvillaruEl
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Summary:

I. Concrete Masonry Php 221,090.00


II. Hardware Php 208,415.00
III. Formworks/Scaffolding Php 86,063.00
IV. Roofing Php 140,000.00
V. Tiling Works Php 66,410
VI. Fencing Php 66,000

Subtotal: Php 822,978.00


Labor Cost: Php 329,191.20
1.05% Engineer's PF: Php 8,641.27
4%Supervision: Php 32,919.12
1.5% Paper Works: Php 12,344.67
GRAND TOTAL: Php 1,206,074.26