Daily Report BG. ANAND 5 (14 Januari 2019)

The daily report provides details of work completed on the BG. ANAND 5 ship including continuing to renew the manhole ring and finishing attaching a new sideboard drain hole, with photos documenting the work. Obstacles included rainy weather, and the next work plan involves docking the ship and beginning bottom plate sand blasting.

Uploaded by

Bang Niel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
268 views5 pages

Daily Report BG. ANAND 5 (14 Januari 2019)

The daily report provides details of work completed on the BG. ANAND 5 ship including continuing to renew the manhole ring and finishing attaching a new sideboard drain hole, with photos documenting the work. Obstacles included rainy weather, and the next work plan involves docking the ship and beginning bottom plate sand blasting.

Uploaded by

Bang Niel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

DAILY REPORT

CLIENT INFORMATION REPORT INFORMATION


Name: PT. PATRiA Maritime Lines Report Number : 01 Pages Number : 05
th
Report Date : January 14 2019

th
Work Date : January 14 2019
Attn: Mr. Najamuddin Target Finished Date : January 13th 2019
Arrival meeting : January th 2019
On keel : January th 2019
E-Mail: [email protected]
Inspected Items

PROJECT NAME PROJECT NUMBER


BG. ANAND 5
CLASSIFICATION BUREAU BKI
Shipyard PT. PATRiA Maritime Industry Technicians :
1. Daniel
Desa Sei Jingah Besar Kecamatan Tabunganen, 2. Ahmad Farohi
Location
Barito Koala Kalimantan Selatan 3. Ari Biworo
4. Richard E S
Project Leader Daniel Fr Sinaga
Mobile 085232079818

EXECUTIVE SUMMARY

1.0. ACTUAL PROGRESS

1. Continue renewing manhole ring


2. Finish attach new sideboard drain hole

2.0. ACTIVITIES DURING WORK

2.1. Continue renewing manhole ring


Fig.1.1. Dismantling old manhole ring and bolt

Fig.1.2. New manhole ring fabrication

Fig.1.3. New manhole ring fabrication


Fig.1.4. New well attached manhole ring

2.2. Finish attach new sideboard drain hole

Fig.2.1. New well attached sideboard drainhole


Fig.2.2. New well attached aft single bollard

Obstacles

 Today, the weather is quiet Rainy

Tools

 1 unit wheel loader

 4 units cutting torch

 8 units welding machine


Manpower

 5 men starboard (4 welder and fitter)

 4 men portside (3 welder and fitter)

3.0. Next Work Plan

- Docking (Hauling) process

- Start bottom plate sand blast