Installation Chapter 3
Installation Chapter 3
INSTALLATION DESIGN
3.1. Terms and definitions
3.2. Load estimation
3.3. General design procedure
3.4. Branch circuit design guidelines Residential Non-residential:
Schools, Office spaces, Industrial spaces
3.5. Load tabulation
3.6. Feeder capacity
3.7. Service Equipment and Switch Board Design
3.8. Cable size determination Design procedure and Calculation of
Voltage Drop
1
3.1. Terms and definitions
Ampacity: current carrying capacity of electric conductors expressed in amperes.
Branch circuit: the circuit conductor between the final over current device
Demand factor: the ratio of the maximum demand of a system (part of a system, to
the total connected load of a system or the part of the system under consideration).
electric circuit or equipment and the earth, or to some conducting body that serves
Outlet: a point on the wiring system at w/c current is taken to the utilization
equipment 2
Cont.
Feeder: all circuit conductors between the service equipment, or the generator
switchboard of an isolated plant, and the final branch circuit over current device.
Lighting outlet: an outlet intended for direct connection of a lamp holder, a light
Receptacle: a contact device installed at the outlet for the connection of a single
attachment plug.
Service: the conductor and equipment for delivering energy from electric supply
Switch board: a large panel, frame or assembly of panels on which are mounted,
on the face or back or both, switches, over current and other protective devices,
branch circuitry,
feeders, and
• Reliability:
misuse of equipment or
ventilation,
power factor correction,
expandability,
use of switches for
centrality,
control, etc.
limitation of access,
• Economic cost:
noise,
initial cost and operating
space adequacy.
cost
7
3.2. Load estimation
• When initiating the wiring design of a building, it is important to be
able to estimate the total building load in order to plan such spaces as
transformer rooms and closet.
• Such estimation can be made from the knowledge of the loads the
building uses.
8
Cont.
• The electrical loads in any facility can be categorized as:
a. Lighting
f. Kitchen equipment's
g. Special equipment
9
3.3. General design procedure
The steps involved in the electrical wiring design of any facility are
outlined below.
1. Determine:
11
Cont.
• Electrical Loads include
Lighting
Heating, ventilating, and air conditioning(HVAC)
sanitary equipment: house water pump, air compressors, and vacuum
pumps etc.
Vertical transportation equipment: elevators, moving stairs, and
dumbwaiters.
Kitchen equipment(stove, oven, mitad, refrigerator)
Miscellaneous power, which includes convenience outlets and small
motors.
Electrical drives(motors)
12
Household loads…
13
Cont.
4. With the local electric utility, decide upon
5. Determine the location and estimate the size of all required electric
• Switchboard rooms,
9. Prepare the panel schedule (table). This table shows the load
distribution over the three phases(R, S, T) and the type of load which
is connected on each circuit. At this step, include the separate circuitry
for emergency equipment and for spare circuit.
15
Cont.
10. From the panel schedule (table) compute panel loads, and
make connection rearrangement so that you will be able
to do an optimum power balance over the three phases R,
S and T.
17
3.4.1.Guidelines for Residential Installation
a. The NEC requires for residences sufficient circuitry to supply a load of
3w/sq.ft. in the building, excluding unfinished spaces such as porches,
garages, and basements.
• Furthermore, all kitchen outlets must be fed from at least two of these
circuits (which may also feed other appliance outlets). And avoid placing
all the lighting in a building on a single circuit.
18
Cont.
c. The NEC requires that at least one 20-amp circuit supply to be set for
laundry outlets. This requirement satisfies good practice. If electric
clothes dryer is anticipated an individual branch circuit should be supplied
to serve this load, via a heavy-duty receptacle.
d. Do not combine receptacles and switches into a single outlet except where
convenience of use dictates high mounting of receptacles.
e. Circuit the lighting and receptacles so that each room has parts of at least
two circuits. This includes basements and garages.
f. Supply at least one receptacle in the bathroom and one outside the house
19
Cont.
h. In bedrooms supply two duplex outlets at each side of the bed location
to accommodate electric blanket, clocks, radios, lamps, and other such
appliances.
i. Since receptacles are counted as part of general lighting and no
additional load is included for them, no limit is placed on the number
of receptacle outlets that may be wired to a circuit. But for good
practice they should be limited to 6 on a 15-amp circuit and 8 on a 20-
amp circuit.
j. Kitchens should have a duplex appliance outlet every 36 in. of counter
space, but no less than two in addition to the normal wall outlets.
20
Cont.
k. A disconnecting means, readily accessible, must be provided
for electric ranges, cook tops, and ovens.
21
3.4.2. Guidelines for Non-residential Installations
Schools
22
Cont.
ii. Light switching should provide:
iii. Provide appropriate outlets for all special equipment in labs, shops,
24
Office Space
i. In small office spaces (less than 400 sq .ft) provide either one outlet for every
40 sq .ft, or one outlet for every 10 linear ft of wall space, whichever is greater.
In larger office spaces, provide one outlet every 100 to 125 sq ft beyond the
initial 400 sq ft (10 outlets). These should comprise wall outlets spaced as
above plus floor outlets sufficient to make up the required total. In view of the
increasingly heavy loads of office machines, these receptacles should be
circuited at no more than 6 to a 20-amp branch circuit, and less if the equipment
to be fed so dictates.
ii. Corridors should have a 20-amp, 220-v outlet every 50 ft, to supply cleaning
and waxing machines.
iii. As with all non-residential buildings, convenience receptacles are figured at
180 w each.
25
Cont.
• Stores: In stores, good practice requires at least one
convenience outlet receptacle for every 300 sq ft in addition to
outlets required for loads such as lamps, show windows, and
demonstration appliances.
26
Considerations and general rules affecting service equipment
27
Cont.
• Socket outlets must be mounted at a height above the floor or
work surface so as to minimize the risk of mechanical damage.
• The Building Regulations requires switches and socket outlets
in dwellings to be installed so that all persons, including those
whose reach is limited, can easily reach them.
• The recommendation is that they should be installed in
habitable rooms at a height of between 450 and 1200 mm
from the finished floor level.
28
Cont.
29
Location of electrical points in house wiring
1) Energy meter: The energy meter should be installed at a place which is easy
accessible to the consumer as well as to the meter reader . The height of the
meter should be 1.75 meter above floor. The meter should be installed in a
covered verandah such that the rain showers at an angle don’t damage the meter.
Its location should be in front verandah so that privacy of the owner is not
disturbed as the meter reader will be visiting for meter reading every month. The
other suitable place where there is no verandah is outside the wall, providing
protective covering.
2) Main switch: Its purpose is to isolate the supply to the building . It is normally
installed very close to the energy meter and should be readily accessible to the
consumer. The fuses are also provided inside main switch to interrupt the supply
due to short circuit current that may occur.
30
Cont.
3) Distribution board: The supply is given to main switch and then to main
distribution board for the purpose of distribution of electricity to various portions
of the house through sub circuits . Every sub circuit is protected by its individual
fuse or circuit breaker such that if one fuse or circuit breaker makes the circuit
off, the entire room is not plunged into darkness and the other circuit shall
maintain the supply to other parts.
4) socket outlet : 3 pin , 5A , socket outlets are used for general purpose , 15 A
socket outlets are used for higher loads ( such as electric mitad , stove , water
heater etc.) . The location of socket outlets should be such that its utility is most
convenient. If socket outlets in residential buildings are close to floor , the
children may get shock , for offices buildings , socket outlets are generally
installed close to floor . In bath rooms , 15 A socket outlets should be provided
2meter above floor. 31
Cont.
5) Lighting points : The lights should be so placed that these are most convenient
in their utility and control. For instance , when person has to go up stair, instead
of moving into darkness, he/she can switch on the light from starting point and
switch off at the end . The number of lighting pints are determined from the
size of room or hall .The main requirements that lighting points installed should
provide uniform illumination and minimum glare.
6) Fans: The rooms of an average size should have only one fan but the larger
rooms serving as drawing and dinning room two fans may be used. The ceiling
fans should be installed at an average height of 2.75meters above floor . The
connection of ceiling fans should be given through ceiling roses installed close to
fan hooks . The ceiling fans shouldn’t be installed in kitchen, bathrooms ,
toilets and small stores . The exhaust fan should be installed in big cook housed
about half meters below ceiling , it should be installed in kitchen. 32
Cont.
7) Switch boards : The switch boards should be convenient to operate and
adequately located . The switch board (box) must be provided inside a room close
to the entry door so that there is no difficulty in switching on the light during night
time . The height of switch board should be about 1.2 meters above floor.
8) Earth wire installation : Earthing means , the direct connection of all the metal
non current carrying parts of electrical equipment such as metallic frame work ,
electric motor body , main switch , distribution board , earth terminal of socket
outlet , metallic covering of cable and conduit pipes etc . The earth plate is buried in
the ground which have a good electrical connection to the surrounding earth . This
is all done to avoid electrics shock
• The supply authority provides earthing to its meter. Beyond the meter , earthing is
the responsibility of the owner of the house . The owner should make arrangement
of his own earthing system with an adequate electrode. 33
3.5. Load Tabulation
• While circuiting the loads, a panel schedule is drawn up which lists:
The circuit numbers
Load description (the type of the load)
Wattage (actually in volt-amperes)
The current ratings
Number of poles of the circuit-protective device feeding each circuit.
Electrical Load panel KVA =
No. Description (serves) A(mm2) Rated (A) Load (kw) Phases (for 3∅)
R S T
1 lighting 1 1.5 10 2.2
2 lighting 2
3
34
4
Cont.
• Spare circuits are included to the extent that the designer
considers them necessary and consonant with economy, but
normally no less than 20% of the number of active circuits.
35
In calculating panel loads, the following rules apply:
i. Each specific appliance, device, lighting fixture, or other load is taken at its
nameplate rating, except certain kitchen and laundry appliances for which
the NEC allows a demand factor. (See NEC Article 220.)
ii. Each convenience outlet, in other than residential spaces, is counted as1.5
amp (180 W).
iii. Loads for special areas and devices such as show window lighting, heavy-
duty lamp holders, and multi outlet assemblies are taken at the figures
given in NEC Article 220.
iv. Spare circuits are figured at approximately the same load as the
average active circuits.
36
Cont.
• Note:
1. In calculating total panel load, no demand factors may be applied
except specifically stated in the NEC. This is because feeders are
calculated for maximum load to be carried, i.e. 100% demand
factor is used.
40
Riser Diagrams
• A power riser diagram is a type of diagram that illustrates the proper installation
of service level electrical components.
• Used to design electrical power distribution system for buildings
• Depict an interconnection among the main components that comprise a power
distribution system which include:
Utility transformer,
metering,
service entrance,
sub-panels(distribution boards),
large motors,
HVAC equipment,
emergency generator system,
elevator equipment etc. 41
Cont.
• The service entrance cable runs from the local utility company to
the meter socket
42
Cont.
• LP-lighting subpanels,
• RP-receptacle panel board
•EP-Emergency panel board
43
3.7. Service Equipment and Switch Board Design
The service equipment portion of the board comprises the metering and
the main switches feeding risers, motor control center (MCC), roof
machine room, and elevators.
The switches of the largest extent possible the motor loads (elevators, air-
conditioning equipment, basement power, etc.) should be separated from
the lighting switches, to minimizes lighting fluctuations resulting from
motor starting and yields simpler maintenance. Also, the size of the main
switch is reduced. 44
Cont.
Other considerations and general rules affecting service equipment are
listed below.
a) A building may be supplied at one point by either a single set or
parallel sets of service conductors.
b) Service drops may generally be not less than No. 8 AWG and service
entrance conductors or underground service conductors not less than
No. 6 AWG.
c) All equipment used for service including cable, switches, meters, and
so on, shall be approved for that purpose.
d) It is recommended that a minimum of 100-amp, 3-wire, 220/380 v
service be provided for all individual residences.
45
Cont.
e) No service switch smaller than 60 amp or circuit breaker frame smaller than 50
amp shall be used.
g) All building equipment shall be connected on the load side of the service
equipment except that service fuses, metering, fire alarm, and signal equipment
and equipment serving emergency systems may be connected ahead of the main
disconnect.
• In computing a size for the service equipment bus a total is taken of the various
feeder loads. Although application of a Diversity Factor to this total is
permissible, good practice dictates the use of a unity Diversity Factor in order to
provide a measure of spare capacity in the service equipment.
46
3.8. Cable size determination Design procedure and Calculation of
Voltage Drop
The correct choice of cable size for any installation is dependent upon
fundamental aspects of :
When current flows through a conductor, the resistance offered by the conductor
produces heat. The increase in heat is proportional to the cable resistance which in
turn depends upon the cross-sectional area of the cable.
Since overheating damages the insulation, the conductor size must be of adequate
size to prevent this from occurring.
47
Cont.
Plunging into calculations of cable size is of little value unless the type of
cable and its method of installation is known. This in turn will depend on
the installation’s environment.
At the same time, we would need to know whether the supply was single
or three phases, the type of earthing arrangements, and so on. Here then is
our starting point.
Having ascertained all the necessary details, we can decide on an
installation method, the type of cable, and how we will protect against
electric shock and over currents.
We would now be ready to begin the calculation part of the design
procedure.
48
Cont.
Basically there are eight stages in such a procedure. These are,
Determine the design current Ib .
Select the rating of the protection In .
Select the relevant rating factors from the standard tables
Divide In by the relevant correction factors(CFs) to give tabulated
cable current carrying capacity It
Choose a cable size to suit It .
Check the voltage drop.
Check for shock risk constraints.
Check for thermal constraints.
49
Design current (Ib)
It is the rating of the electrical apparatuses to be operated.
50
Nominal setting of protection
Having determined we must now select the nominal rating of the
protection in such that > . This value may be taken from IEE
regulations.
6, 10, 16, 20, 25, 32,35, 40,50, 63, 80, 100,110, 125,
150,160, 175, 200, 225, 250, 300, 350....
The EBCS-10 regulation lists all the cable sizes, current carrying capacity and
127, 129, 131, 133, 135, 137, 139, for both ac and dc circuits operating at
53
a. Ambient temperature Ca
Is a rating factor for surrounding temperature of the equipment to be used where
T is above c since, the cable rating in the IEE regulations are on an
ambient temperature of C, and hence it is only above this temperature that
an adverse correction is needed.
The cable ratings quoted in the EBCS-10 are based on an ambient temperature
of 30°C. And above this temperature an adverse correction is needed. (Available
on EBCS-10 page 112)
54
Cont.
55
b. Grouping Cg
Is a rating factor to be used where the cable is grouped /touched with other
cables. When cables are grouped together they impart heat to each other.
Therefore the more cables there are the more heat they will generate, thus
increasing the temperature of each cable. IEE regulation also gives factors for
such groupings of the same cable sizes.
EBCS-10 tables A.1, A.2 and A.3 of the standard give factors for such groups of
cables or circuits.
It should be noted that the figures given are for cables of the same size, and hence
no correction need be made for cables grouped at the outlet of a domestic
consumer unit, for example, where there is a mixture of different sizes.
There are many different types and sizes of fuse, all designed to perform
a certain function.
BS 3036 fuses have a high fusing factor and, as a result, when this type
of fuse is used a correction factor of 0.725 must always be applied.
Hence 0.725 is the correction factor to be used when semi-enclosed fuses
are used.
In≤0.725Iz or Iz≥In/0.725
(where Iz the current carrying capacity/rating of the
conductor).
The tabulated current-carrying capacity It is such that, It ≥Iz.
57
d. Thermal insulation Ci
Is a factor for use where a conductor is surrounded by the thermal
insulation and can be found from table.
The use of thermal insulation in buildings, in the forms of cavity wall
filling, roof space blanketing, and so on. is now standard.
Since the purpose of such materials is to limit the transfer of heat, they
will clearly affect the ability of a cable to dissipate the heat build up
within it when in contact with them.
Therefore, there may be a need to derate cables to account for heat
retention.
If a cable is totally surrounded by thermal insulation for more than 0.5
m, a factor of 0.5 must be applied to the tabulated clipped direct ratings.
58
Cont.
Length of Cable (mm) in Thermal Derating Factor(up to 10mm2)
Insulation
50 0.89
100 0.81
200 0.68
400 0.55
>=500 0.50
For cables shorter than 0.5m, derating factors shown in Table above
should be applied.
59
Application of correction factors
• Some or all of the onerous conditions just out lined may
affect a cable along its whole length or parts of it, but not
all may affect it at the same time. If all conditions are to
appear at the same time consider all correction factors,
otherwise take the worst.
• Having chosen the relevant correction factors, we now
apply them to the nominal rating of the protection as
divisors in order to calculate the current carrying
capacity of the cable.
60
Selection of cable size
Having established the current carrying capacity I of the cable
to be used, it now remains to choose a cable to suit that value.
The IEE regulation also list all the cable sizes, current carrying
capacity and voltage drops of varies types of cables.
The EBCS-10 requires that the voltage drop V should not be so excessive
that equipment does not function safely.
The voltage drop should not exceed 4% of the nominal voltage i.e. a drop
of no more than 3% of the nominal voltage for a lighting circuit and 5%
for a power circuit will satisfy the load requirements.
63
Cont.
For single-phase 230 V, the voltage drop for lighting should not exceed 3% of
230 V = 6.9 V and for power circuit should not exceed 5% of 230 V = 11.5V for
three-phase 400V, the voltage drop should not exceed 20 V.
The voltage drop(in volts) of a cable with length L meters carrying rated
current Ib, is:
= ∗ ∗
1000
× × ( )
Cable voltage drop ( )= (mv from IEE Regulation)
× × ( ) . × ×
= = =2.125V
As we have just seen, the maximum volt drop for a 220 V installation is 8.8V, so
we can determine the maximum length of the cable by transposing this formula:
× . ×
Max length = = =95m
× . ×
There are other constraints, however, that may not permit such a length.
65
Cont.
The mV value of standard size conductors is presented in EBCS-10
on page 93,95 97, 101,103,105,107 ,109,111 and113 ,119,, 120,
123, 124, 126, 128, 130, 132, 134, 136, 138 and 140 for copper and
aluminum conductors used in both ac and dc circuits operating at
different temperature.
66
Demand factor
In normal operating conditions the power consumption of a load is
sometimes less than that indicated as its nominal power rating.
The demand factor is the ratio of the maximum demand on a system to the
total connected load of the system. This factor is also called factor of
power utilization
The demand factor is based on the assumption that the whole of the
connected load will not be turned on at the same time. 67
Cont.
Demand factors are generally used for determining the capacity and cost
of the power equipment required for serving a given load.
Connected load
It is the Sum of all the loads connected to the electrical system, usually
expressed in watts(KW, or MW).
Maximum demand
69
Cont.
• As every single load or group of loads in a circuit are not operating simultaneously, and
normally working under partial load, the power demand factor is always less than 1.0.
2. Heating loads
71
Cont.
In the case of lighting for each type of installation, it will be
noticed that the more the total lighting load is likely to
switched on over definite periods, the smaller is the payment/
allowance made for diversity.
In a domestic installation, it is estimated that some two- thirds
(0.66) of the lighting load will be ON at any one time. In a
hotel, the figure is 75%(0.75), and in a shop, where almost all
the lights are ON for most of the time when the shop is open,
the figure is 90% (0.90).
72
Difference between demand and diversity factor
Most of the electrical engineers confuse between the demand and
diversity factors, to solve this confusion, don't forget that:
73
Cont.
Example:Consider that a feeder supplies five users with the following
load conditions:
• On Monday, user one reaches a maximum demand of 100 amps;
• on Tuesday, two reaches 95 amps;
• on Wednesday, three reaches 85 amps;
• on Thursday, four reaches 75 amps;
• on Friday, five reaches 65 amps.
• The feeder’s maximum demand is 250 amps.
Calculate the Diversity Factor for this feeder?
Solution:
The diversity factor can be determined as follows:
sum of total demands
Diversity factor =
maximum demand on feeder
(100+95+85+75+65)A 420
= = = 1.68
250 A 250 74
Final circuit fed from wiring to which diversity applies:
lighting
heating
floor-warming installation
13A fused socket outlets and appliance fed there from and
76
Electrical Installation design steps
1 Determine the types of electrical loads(residential, Industrial or commercial
electrical loads).
2 Make an electrical load estimation based on areas involved, building data, and
any other related data.
5 Select the appropriate type of lamps, lighting schemes and consider the factors
required for lighting schemes .
6 Use the luminous flux according to the type of selected lamp from recommended
data.
77
Cont.
8. Calculate the power consuming for each loading and their power demand by
taking in to account the diversity factor.
78
Distribution/Panel board schedule
While circuiting the loads, a panel schedule is drawn up which lists:
The circuit numbers
Load description (the type of the load)
Wattage (actually in Watt)
The current ratings
Number of poles of the circuit-protective device feeding each circuit and
the like.
79
Cont.
80
Installation drawings
Lighting layout diagram
82
Cont.
83
Socket outlet layout diagram
Signal load layout diagram
Worked examples
1. From EBCS-10. Table B.1, select cables of suitable current-
carrying capacity for the following loads and conditions (p.v.c.
cables into screwed conduit).
12/31/2018 88
Solution
1 (a)
Therefore In=32A
12/31/2018 89
Cont.
iii. Relevant correction factor for ambient temperature from EBCS-10
Table A.4 for 250C is 1.03.
Iz = 32/1.03 = 31.1 A
From table B.2 voltage drop for 4mm2 conductor size = 11mv/Am
12/31/2018 90
Cont.
As the actual voltage drop is less than the allowable maximum voltage
drop, selected size will be 4 mm2
If BS 3036 fuse is chosen for protection, this fuse type requires a
correction factor of 0.725.
In = 32 Amp
Therefore the load current will be :
Iz = In/CF CF- Correction Factors.
Ca = 1.03, Cf = 0.725
Required cable rating Iz = 32 Amp/1.03 * 0.725= 42.85 Amp.
From Table B.1, 10mm2 conductor carries 57 A. Take 10mm2 area
conductor.
12/31/2018 91
Cont.
Testing for Voltage drop = (mV/A.m) * Ib * l
Since the actual voltage drop is less than the allowable maximum
Observe the conductor size difference in using Circuit breaker and fuses.
12/31/2018 92
Solution 1(b)
Efficiency = Output/Input
→ In = 50 Amp
12/31/2018 93
Cont.
The current carrying capacity of the cable will be :
→ Iz = 50 A
→ Iz = 50 A / 0.725 = 68.966 A
Solution (a)
Design current Ib = P/V
Ib = 10000/230 = 43.48 A.
For Ib = 41.67 A. 50-Amp m.c.b. is adequate for protection
12/31/2018 96
Cont.
In = 50 A. And from Table A.4 correction factor for 350C = 0.94
From table A.1, Correction factor for cables group together is 0.75
Ca = 0.94, → Cg = 0.75
From Table B.3 (for multi core cable) 25mm2 cable carries 90A.
From Table B.3 (for multi core cable) 35 mm2 cable carries 111
Amp.
12/31/2018 98
Cont.
Testing for Voltage drop:
=(mV/Am)*41.67A*30m
=1.25*43.48*30=1.63<5.5V
12/31/2018 99
Problem
• An apartment having 6 individual rooms each 3.5mX2.5m (see figure
below) is to be installed with the following loads: Ventilator (500W),
Fridge (1kW), Stove (2kW), six 60W lamps, and five socket outlets.
ii. Calculate the sub-feeder cable size for one room if the average ambient
temperature of the local area is taken as 35oC and five groups of
circuits are running together in a conduit with it. The length of run is
15m and protection is by MCB.
iv. Choose the rating of the MCB and the branch circuits breakers.
12/31/2018 100
12/31/2018 101
102