Pekerjaan Assy Unit
Pekerjaan Assy Unit
CYCLE TIME/Pcs
ITEM PEKERJAAN MANPOWER JUMLAH MANPOWER (MINUTE)
HANDLE 4X4
PEMASANGAN KABEL HANDLE 4X4 DAUD 1 62
SETTING KABEL HANDLE + PEMASANGAN PLUNGER DAUD 1 117
PEMASANGAN COVER HANDLE RONI 1 6
TOTAL Pcs/DAY (PROSES 1 + PROSES 2 + PROSES 3)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1 + PROSES 2 + PROSES 3) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1 + PROSES 2 + PROSES 3)
TOTAL Pcs/MONTH (PROSES 1 + PROSES 2 + PROSES 3)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
SPEEDOMETER + POWER SUPPLY
SPEEDOMETER + POWER SUPPLY HERU 1 67
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
PEMASANGAN SIDE FENDER
PEMASANGAN SIDE FENDER RONI 1 25
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
PEMASANGAN SELANG + TANGKI SOLAR
PEMASANGAN SELANG + TANGKI SOLAR HERU 1 31
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
PENGISIAN OLI MESIN,TRANSFER,TRANSMISI,DAN D
PENGISIAN OLI RONI 1 28
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
PENGISIAN GREASE
PENGISIAN GREASE ADE 1 15
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
SETTING SUDUT BELOK STEER
SETTING SUDUT BELOK STEER ASEP + DAUD 2 14
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
PERAPIHAN ELECTRIC UNIT
FINISHING ELCETRIC UNIT,SELANG DAN CLAMP HERU 1 132
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
PEMASANGAN PLAT BOOT
PEMASANGAN PLAT BOOT ASEP 1 24
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
PEMASANGAN SELANG REM + PIPA REM BELA
PEMASANGAN SELANG + PIPA REM BELAKANG ASEP 1 18
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
KEBERSIHAN CABIN
KEBERSIHAN CABIN DAUD 1 33
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
SETTING KAMPAS REM
SETTING KAMPAS REM ADJIE 1 30
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
PENGOCOKAN MINYAK REM
PENGOCOKAN MINYAK REM RONI + ADJIE 2 76
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
STICKER
PEMASANGAN STICKER ASEP 1 20
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
SELANG REM DEPAN
PEMASANGAN SELANG REM BAGIAN DEPAN ADJIE 1 30
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
SPOORING RODA
PROSES SPOORING RODA ADJIE + DAUD 2 25
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS)
TOTAL Pcs/DAY (PROSES 1) (JUMAT)
TOTAL Pcs/WEEK (PROSES 1)
TOTAL Pcs/MONTH (PROSES 1)
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE)
TOTAL TIME/DAY (JUMAT) (MINUTE)
TOTAL TIME/WEEK (MINUTE)
TOTAL TIME/MONTH (MINUTE)
CYCLE TIME/Pcs TOTAL CYCLE Pcs/DAY (440 Pcs/DAY (420 Pcs/WEEK Pcs/MONTH NOTE
(MINUTE) TIME (MINUTE) MINUTE) MINUTE)
HANDLE 4X4
62 7.1 6.8 35.2 140.6
117 185 3.8 3.6 18.6 74.5
6 73.3 70.0 363.3 1453.3
2.38
2.27
11.78
47.14
440
420
2180
8720
OMETER + POWER SUPPLY
67 67 6.6 6.3 32.5 130.1
6.57
6.27
32.54
130.15
440
420
2180
8720
ASANGAN SIDE FENDER
25 25 17.6 16.8 87.2 348.8
17.60
16.80
87.20
348.80
440
420
2180
8720
GAN SELANG + TANGKI SOLAR
31 31 14.2 13.5 70.3 281.3
14.19
13.55
70.32
281.29
440
420
2180
8720
TRANSFER,TRANSMISI,DAN DIFFERENTIAL
28 28 15.7 15.0 77.9 311.4
15.71
15.00
77.86
311.43
440
420
2180
8720
PENGISIAN GREASE
15 15 29.3 28.0 145.3 581.3
29.33
28.00
145.33
581.33
440
420
2180
8720
NG SUDUT BELOK STEER
14 14 31.4 30.0 155.7 622.9
31.43
30.00
155.71
622.86
440
420
2180
8720
APIHAN ELECTRIC UNIT
132 132 3.3 3.2 16.5 66.1
3.33
3.18
16.52
66.06
440
420
2180
8720
MASANGAN PLAT BOOT
24 24 18.3 17.5 90.8 363.3
18.33
17.50
90.83
363.33
440
420
2180
8720
ELANG REM + PIPA REM BELAKANG
18 18 24.4 23.3 121.1 484.4
24.44
23.33
121.11
484.44
440
420
2180
8720
KEBERSIHAN CABIN
33 33 13.3 12.7 66.1 264.2
13.33
12.73
66.06
264.24
440
420
2180
8720
ETTING KAMPAS REM
30 30 14.7 14.0 72.7 290.7
14.67
14.00
72.67
290.67
440
420
2180
8720
GOCOKAN MINYAK REM
76 76 5.8 5.5 28.7 114.7
5.79
5.53
28.68
114.74
440
420
2180
8720
STICKER
20 20 22 21 109 436
22.0
21.0
109.0
436.0
440
420
2180
8720
SELANG REM DEPAN
30 30 14.7 14.0 72.7 290.7
14.7
14.0
72.7
290.7
440
420
2180
8720
SPOORING RODA
25 25 17.6 16.8 87.2 348.8
17.6
16.8
87.2
348.8
440
420
2180
8720
753
0.6
0.6
2.9
11.6
440
420
2180
8720
NOTE
STICKER
PEMASANGAN STICKER 4X4 & knob handle ASEP 1 20 20 22 21 109
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS) 22.0
TOTAL Pcs/DAY (PROSES 1) (JUMAT) 21.0
TOTAL Pcs/WEEK (PROSES 1) 109.0
TOTAL Pcs/MONTH (PROSES 1) 436.0
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE) 440
TOTAL TIME/DAY (JUMAT) (MINUTE) 420
TOTAL TIME/WEEK (MINUTE) 2180
TOTAL TIME/MONTH (MINUTE) 8720
SPOORING RODA
PROSES SPOORING RODA ADJIE + DAUD 2 25 25 17.6 16.8 87.2
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS) 17.6
TOTAL Pcs/DAY (PROSES 1) (JUMAT) 16.8
TOTAL Pcs/WEEK (PROSES 1) 87.2
TOTAL Pcs/MONTH (PROSES 1) 348.8
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE) 440
TOTAL TIME/DAY (JUMAT) (MINUTE) 420
TOTAL TIME/WEEK (MINUTE) 2180
TOTAL TIME/MONTH (MINUTE) 8720
KEBERSIHAN CABIN
KEBERSIHAN CABIN DAUD 1 33 33 13.3 12.7 66.1
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS) 13.33
TOTAL Pcs/DAY (PROSES 1) (JUMAT) 12.73
TOTAL Pcs/WEEK (PROSES 1) 66.06
TOTAL Pcs/MONTH (PROSES 1) 264.24
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE) 440
TOTAL TIME/DAY (JUMAT) (MINUTE) 420
TOTAL TIME/WEEK (MINUTE) 2180
TOTAL TIME/MONTH (MINUTE) 8720
PEMASANGAN SIDE FENDER
PEMASANGAN SIDE FENDER RONI 1 25 25 17.6 16.8 87.2
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS) 17.60
TOTAL Pcs/DAY (PROSES 1) (JUMAT) 16.80
TOTAL Pcs/WEEK (PROSES 1) 87.20
TOTAL Pcs/MONTH (PROSES 1) 348.80
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE) 440
TOTAL TIME/DAY (JUMAT) (MINUTE) 420
TOTAL TIME/WEEK (MINUTE) 2180
TOTAL TIME/MONTH (MINUTE) 8720
TOTAL CYCLE TIME (MINUTE) 290
TOTAL Pcs/DAY (PROSES 1)(SENIN-KAMIS) 1.52
TOTAL Pcs/DAY (PROSES 1) (JUMAT) 1.45
TOTAL Pcs/WEEK (PROSES 1) 7.52
TOTAL Pcs/MONTH (PROSES 1) 30.07
TOTAL TIME/DAY (SENIN-KAMIS) (MINUTE) 440
TOTAL TIME/DAY (JUMAT) (MINUTE) 420
TOTAL TIME/WEEK (MINUTE) 2180
TOTAL TIME/MONTH (MINUTE) 8720
109 436 5.0 100.0 320.0
67 219 electric
30
18
132 173 kocok rem
24
28
15
-14
30
76
20
25
33
25