Short Circuit Study

The document describes a two-stage project to analyze short circuits in power systems. Stage 1 involves completing a short circuit study for a 5-bus test system, calculating fault currents, voltages, and branch currents for two types of faults. Stage 2 involves developing software to perform the same calculations for the IEEE 14-bus test system. The deliverables are reports detailing the work, results in polar form, and descriptions of the software and mathematical models used.

Uploaded by

muqtar4u
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
489 views4 pages

Short Circuit Study

The document describes a two-stage project to analyze short circuits in power systems. Stage 1 involves completing a short circuit study for a 5-bus test system, calculating fault currents, voltages, and branch currents for two types of faults. Stage 2 involves developing software to perform the same calculations for the IEEE 14-bus test system. The deliverables are reports detailing the work, results in polar form, and descriptions of the software and mathematical models used.

Uploaded by

muqtar4u
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

ELEN Project #1

666 Project Title: Short Circuit Study


Spring 2004

Description: Stage I
Complete a short-circuit study for 5 bus test system described in the Appendix I. The system Z
matrices are given. Consider two types of faults:
• Single-phase-ground (A phase), fault resistance Rf = 0.10 p.u.
• Three-phase-ground fault, fault resistance Rf = 0 p.u.
Assuming that the fault occurs at each non-source system bus (one at a time), calculate:
• Fault current (all phases)
• All bus voltages (all phases)
• All branch currents (all phases)
Stage II
Develop a computer software for completing a short-circuit study for IEEE-14 bus system described
in the Appendix II. The system data are attached. Either Z-bus or Y-bus method can be used.
Consider two types of faults:
• Single-phase-ground (A phase), fault resistance Rf=0 p.u.
• Three-phase-ground fault, fault resistance Rf=0 p.u.
Assuming that the fault occurs at each non-source system bus (one at a time), calculate:
• Fault current (all phases)
• All bus voltages (all phases)
• All branch currents (all phases)

Deliverables: Stage I - Report consisting of two parts:


• Explanation of the work completed
• The results as described above (see note below as well)
Stage II - Report consisting of three parts:
• Mathematical model used for the short-circuit study
• Developed software descriptions, flowcharts, code listing, source code
• The results as described above (see note below as well)

***Note: Express all results in polar form. The results in rectangular form will not be acceptable.

Programming
Consideration: - Matlab 5.3., MathWorks should be used for programming.
- Procedural style of programming should be used (do not write spaghetti code).

Literature: Paul M. Anderson, “Analysis of Faulted Power Systems”


Matlab 5.3 Reference Manual, MathWorks

Plagiarism: First page in the report should contain signed and dated statement that confirms that all the work in the
report is completed solely by the respective individual.

Total Points: 30 pts.

Extra Credit: 5 pts. for completing the stage two of the project using both Z-bus and Y-bus method.
Note that the method of building Z-bus or Y-bus matrices is important. Inversion of Y-bus matrix
obtained by Y-bus method should yield the same Z-bus matrix as obtained by Z-bus method.

Due Dates: March 1, 2004, 5 p.m. – for stage I report


March 24, 2004, 5 p.m. – for stage II report

Assigned: February 2, 2004


ELEN 666
Computer Program for Short-Circuit Studies
Appendix I
INPUT DATA FOR 5-BUS TEST SYSTEM

1 2 3

3 4

4 5 5
1 2

Parameters of the system are given in the following table:


Impedance Connecting Self Impedance Zero Sequence Mutual
Number Nodes Positive Negative Zero Mutual Impedance Element
1 4-1 0.25 0.25 0.03 … …
2 5-3 0.20 0.20 0.02 … …
3 1-2 0.08 0.08 0.14 … …
4 2-3 0.06 0.06 0.10 0.05 5
5 2-3 0.06 0.06 0.12 0.05 4
6 1-3 0.13 0.13 0.17 … …

The system sequence matrices are also given (all impedances are in p.u.):
j 0.1274 j 0.1061 j 0.0981
Z 1 = j 0.1061 j 0.1345 j 0.1151 Positive-Sequence matrix
j 0.0981 j 0.1151 j 0.1215

j 0.1274 j 0.1061 j 0.0981


Z 2 = j 0.1061 j 0.1345 j 0.1151 Negative-Sequence matrix
j 0.0981 j 0.1151 j 0.1215

j 0.1157 j 0.0546 j 0.0200


Z 0 = j 0.0546 j 0.0831 j 0.0200 Zero-Sequence matrix
j 0.0200 j 0.0200 j 0.0200

Notes:
Assume that pre-fault voltage is flat, Vf = 1. All given impedances are in p.u.
Buses 4 and 5 are source buses and they have been eliminated from the system matrices.
ELEN 666
Computer Program for Short-Circuit Studies
Appendix II
INPUT DATA FOR THE IEEE 14-BUS TEST SYSTEM

• System line-to-line voltage is 230 kV


• Pre-fault voltage profile is assumed to be flat
• Sources are attached at buses 1 and 2, each at 230 kV (line-to-line, Y solidly grounded)
• Assume impedance for the sources to be zero
• Assume negative sequence same as positive sequence
• Assume system frequency 60 Hz
• Assume three-phase and single-line-to-ground faults at each bus (except 1 and 2) and give the
resulting phase currents into fault and in each line in polar form. Give phase voltages in polar form
at each bus
NUMBER OF NODES: 14
NUMBER OF BRANCHES: 19 non-zero impedance branches
2 generator branches with zero impedance (not listed)
INPUT DATA:

Self Impedance Mutual Impedance


Line Connected Mutual
Number Nodes Positive sequence Zero sequence Zero sequence Element
R [ohm] L [mH] R [ohm] L [mH] R [ohm] L [mH]
1 1-2 2.42 77.95 10.9 205.3 - - -
2 1-5 3.388 109.13 15.26 287.42 - - -
3 2-3 0.612 122.4 55.35 405 49.05 207 2-4
4 2-4 0.612 122.4 55.35 405 49.05 207 2-3
5 2-5 7.26 233.85 32.7 615.9 - - -
6 3-4 1.452 46.77 6.54 123.18 - - -
7 4-5 5.68 187.08 26.16 492.72 - - -
8 5-6 9.68 311.8 43.6 821.2 - - -
9 6 - 11 4.84 155.9 21.8 410.6 - - -
10 6 - 12 2.178 70.155 9.81 184.77 - - -
11 6 - 13 2.662 85.745 11.99 225.83 - - -
12 4-7 4.84 155.9 21.8 410.6 - - -
13 4-9 5.808 187.08 26.16 492.72 - - -
14 7-8 1.452 46.77 6.54 123.18 - - -
15 9 - 10 3.63 116.925 16.35 307.95 - - -
16 10 - 11 1.936 62.36 8.72 164.24 - - -
17 9 - 14 2.904 93.54 13.08 246.36 - - -
18 12 - 13 3.872 124.72 17.44 328.48 - - -
19 13 - 14 1.936 62.36 8.72 164.24 - - -

Table 1. Connected nodes, branch current orientation and line parameters


ELEN 666
Computer Program for Short-Circuit Studies

IEEE 14 bus system

BUS BUS

12 18 13
LINE 19
LINE
BUS

10 14
LINE 11
LINE

BUS BUS

BUS
9 11 10
LINE
6 17
LINE
16
LINE

15
LINE BUS
8
LINE
9
BUS
5
BUS BUS
13 7 8
LINE
7
2
LINE
LINE 12
LINE
BUS
1 5 14
LINE BUS LINE

4 4
LINE
6
1 LINE
LINE
3
LINE
BUS BUS
2 3

n Node (Bus) number

b Branch (Line) number

Figure 1. Power system for fault simulations

NOTE: Results, computer code, flow charts and related equations


Each student to certify that work is his/her own