ETI Program
ETI Program
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Ma
1 ETI Kick-off Workshop Mon 01/04/19 Mon 01/04/19 01/04
2 Submission Of ETI Report Tue 02/04/19 Tue 30/04/19
3 Key construction risks and risk management strategies Tue 02/04/19 Tue 30/04/19 Key construction risks and risk management strategies
4 Constructability review of Design Tue 02/04/19 Tue 30/04/19 Constructability review of Design
5 Key construction risks and risk management strategies Tue 02/04/19 Tue 30/04/19 Key construction risks and risk management strategies
6 Areas of design and construction uncertainty Tue 02/04/19 Tue 30/04/19 Areas of design and construction uncertainty
7 Construction methodology, program & construction Tue 02/04/19 Tue 30/04/19 Construction methodology, program & construction sequencing
sequencing
8 Site management from drawdown to commissioning Tue 02/04/19 Tue 30/04/19 Site management from drawdown to commissioning
9 Construction facilities layout Tue 02/04/19 Tue 30/04/19 Construction facilities layout
10 Design measures to improve management of construction Tue 02/04/19 Tue 30/04/19 Design measures to improve management of construction interface, dam operations, dam safety, project
interface, dam operations, dam safety, project risk and
safety
11 Key team - any changes from RPP submission Tue 02/04/19 Tue 30/04/19 Key team - any changes from RPP submission
12 Errors, omissions, ambuguities or discrepancies identified Tue 02/04/19 Tue 30/04/19 Errors, omissions, ambuguities or discrepancies identified by the ETI Participant in the design
by the ETI Participant in the design
13 Value management and risk reduction opportunities in Tue 02/04/19 Tue 30/04/19 Value management and risk reduction opportunities in design or construction
design or construction
14 Consideration of an appropriate allocation of risks between Tue 02/04/19 Tue 30/04/19 Consideration of an appropriate allocation of risks between the principal and contractor
the principal and contractor
15 Alternative proposals - design, construction sequencing, Tue 02/04/19 Tue 30/04/19 Alternative proposals - design, construction sequencing, risk manegement etc.
risk manegement etc.
16 Technical Session 1 Wed 01/05/19 Wed 01/05/19 01/05
17 Commercial Arrangements & Risk Allocation Workshop Mon 03/06/19 Mon 03/06/19
18 Marked ups of the construction contract and basis for Thu 18/04/19 Fri 17/05/19 Marked ups of the construction contract and basis for suggested departures
suggested departures
19 Proposed strategies for mitigating and managing Thu 18/04/19 Fri 17/05/19 Proposed strategies for mitigating and managing construction risks allocated to the contractor
construction risks allocated to the contractor
20 Draft management plans Thu 18/04/19 Fri 17/05/19 Draft management plans
21 Pre-tender review Workshop Mon 03/06/19 Mon 03/06/19 03/06
22 Issue Tender Request Wed 10/07/19 Wed 10/07/19 10/07
23 Tender Submission Thu 11/07/19 Thu 01/08/19 Tender Submission
24 Contract Award Mon 04/11/19 Mon 04/11/19 04/11
Project: ETI Phase Level 1 Task Milestone Project Summary Inactive Milestone Manual Task
Date: Thu 31/01/19 Split Summary Inactive Task Inactive Summary Manual Summary
Page 1