2016 - SVL Connection at Terminations
2016 - SVL Connection at Terminations
1, JANUARY/FEBRUARY 2016
Fig. 5. (a) Variation of Z3 and Z4 with the GIS duct medium height hGIS . (b) Voltage distribution in uBT and uT C without considering the grounding leads.
Fig. 6. Variation of Zconnex with the grounding lead medium height h for
two different outer radiuses.
Fig. 7. Voltage distribution in uBT and uT C considering the grounding leads.
B. Grounding of the GIS Enclosure and the Cable Sheath
TABLE I
The evaluated voltage distribution in the previous section M EASURED OVERVOLTAGES D UE TO S WITCHING O PERATIONS
does not consider the effect of the grounding leads from the
cable sheath or the GIS enclosure. In transient analysis, these
grounding connections behave as transmission lines with a
propagation speed that is the same as the speed of light (c0 =
300 m/μs). For grounding connections with circular cross-
sectional conductors, normally used for connecting the cable
sheath to the Earth, the characteristic impedance according to ing leads is more unbalanced than that obtained by considering
[4] and [5] is defined with the following equation: only the tubular geometry of the cable sheath and the GIS duct
√ as shown in Fig. 7. For a value of 50 Ω for the characteristic
2 2h
Zconnex = 60 · ln (13) impedance of the grounding connection of the GIS enclosure
rext and a value of 360 Ω for the characteristic impedance of the
where grounding connection of the cable sheath, it can be seen that
the voltage distribution is unbalanced (80% for the cable sheath
rext outer radius of the grounding lead; and 20% for the GIS enclosure). In practice, the distribution
h height of the middle axis above the Earth floor. is even more unbalanced because the GIS, with its grounding
connections, typically has a lower characteristic impedance to
As an example, Fig. 6 shows the variation of Zconnex with the the Earth than the HV cable sheath.
medium height h for a circular cross-sectional grounding lead
and two different outer radiuses rext = 12.5 and 25 mm. It can
C. Measured Overvoltages Due to Switching Operations
be seen that, for a height of around 1 m, the impedance Zconnex
is between 300 and 360 Ω, which represents an inductance per In order to know the real voltage distribution in the cable
unit length between L ≈ 1.1 μH/m and L ≈ 1.2 μH/m. sheaths and the GIS enclosures, online measurements of the
In the case of the GIS, the grounding connections of the transient overvoltages uBT , uT C , and uBC were performed due
enclosure are made at different points using wide plates, and to closing operations in the gas-insulated switchgear from four
therefore, the equivalent characteristic impedance of these con- different 220-kV GIS substations. The voltages obtained are
nections is low. shown in Table I. GIS #1 and #2 did not have an installed bypass
The voltage distribution uBC between the cable sheath uBT SVL. In contrast, substation #3 did have nonlinear resistors with
and the GIS enclosure uT C considering the effect of the ground- 6 kV of rated voltage Ur , connecting the GIS enclosure with
566 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 52, NO. 1, JANUARY/FEBRUARY 2016
Fig. 8. Wave measures from uBT , uT C , and uBC during the closing operations in substations #1, #2, #3, and #4.
where where di/dt is the current variation in time after the actuation
Z c = c0 · L
characteristic impedance of each connection of the bypass SVL.
lead; When the bypass SVL actuates, the maximum length of each
c0 speed of the light propagation through air; SVL connection lead which limits the overvoltage up to the
L inductance per unit length of each connection admissible value of isolation level (BILBC ) with a protection
lead; margin M P is given by the following equation:
n number of parallel disposed nonlinear n BILBC
resistors. longmax = di · − Ures . (23)
L · dt 1 + MP
Deriving (15), it results in the following wave slope s: Equating (20) and (23), results in
L di di
s=c· · (16) BILBC
n dt Ures ≤ · 1− dt
di
(24)
1 + MP dt
and considering
long where the experimental values of di /dt and di /dt were
τ= (17)
c0 obtained experimentally from the measurements described in
Section IV-C, resulting in
(14) becomes the following:
BILBC 1 BILBC
L di Ures ≤ · 1− ≈ 0.95 · . (25)
s=c· · . (18) (1 + M P ) 21 (1 + M P )
n dt
As long as (18) corresponds to an overvoltage of the high- From the measurements in substation #3, it was obtained
frequency regime, the equivalent lightning impulse voltage that di /dt ≈ 1.7 · 109 A/s, and from the measurements in
1.2/50 is calculated by reducing the overvoltage uBC by a factor substations #1 and #2, cases without bypass SVL, the minimum
which depends on the frequency “k(f )” and considering the value of di /dt was chosen (0.36 · 1011 ) because it is the most
short time of this overvoltage. Assuming that k(f ) ≈ 0.5, it restrictive value to determine the Ures of (24).
results in The SVL residual voltage must be selected to protect the
insulation not only between the cable sheath and the GIS
L di
uBCequ = k(f ) · uBC = 0.5 · 2 · long · · . (19) enclosure (BILBC ) but also between these grounding parts
n dt and the nearby substation Earth structures (BILBT y BILT C ).
The maximum admissible overvoltage for the first transient, In this sense, to protect the insulation between the cable sheath
considering a protection margin “M P ,” is defined by the insu- or the GIS enclosure and the Earth, (11) and (12) become the
lation level (BILBC /(1 + M P )) between points B and C and following when taking (22) into account:
is associated with the maximum length of each SVL connection
lead, given by the following equation: uBT = rBT · (Ures + ucon ) = rBT · uBC (26)
uT C = rT C · (Ures + ucon ) = rT C · uBC . (27)
n · BILBC /(1 + M P )
longmax = (20)
L · didt Following the same procedure of the insulation between
points B and C for the insulation between points B and T
where (BILBT ) and for insulation between points C and T (BILT C )
BILBC insulation level between the cable sheath and the results in
GIS enclosure;
1 BILBT BILBC
L inductance per unit length of each connection Ures ≤ · − (28)
lead; (1 + M P ) rBT 21
1 BILT C BILBC
MP acceptable protection margin; Ures ≤ · − . (29)
di /dt before the actuation of the bypass SVL; (1 + M P ) rT C 21
n≥3 number of parallel disposed bypass SVL. For the protection margin M P , equal for all of the insula-
tions, of 15% (according to [7] and [8]) and considering that the
most unfavorable voltage distribution which may appear is
B. Insulation Level 100% (rBT = 1.0) in the cable sheath and 50% (rT C = 0.5)
For the subsequent instants at which the SVLs are limiting in the GIS enclosure, the selection of the bypass SVL is condi-
the voltage between its terminals, the overvoltage between tioned by the most restrictive of the three following inequations:
points B and C uBC is composed of two summands: the SVL
BILBC
residual voltage Ures and an additional voltage ucon due to the Ures ≤
effect of the connection 1, 2
BILBT BILBC 1
Ures ≤ · 1− ·
uBC = Ures + ucon (21) 1, 15 BILBT 21
1 di BILT C BILBC 1
ucon = · long · L · (22) Ures ≤ · 2− · . (30)
n dt 1, 15 BILT C 21
568 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 52, NO. 1, JANUARY/FEBRUARY 2016
R EFERENCES
[1] IEEE Guide for Cable Connections for Gas-Insulated Substations, IEEE
Std 1300-2011, Jan. 2012.
[2] Earthing of GIS—An Application Guide, Electra No. 151, CIGRE Work-
ing Group 23.10, Dec. 1993, p. 3151.
[3] F. Noack, P. Zahlmann, R. Broche, and J. Schwarz, “Fast transients in
the earthing systems of GIS,” in Proc. CIGRE Session, Paris, France,
Aug. 1988, p. 33-06.
[4] E. P. Dick, N. Fujimoto, G. L. Ford, and S. Harvey, “Transient ground
potential rise in gas-insulated substations—Problem identification and
mitigation,” IEEE Trans. Power App. Syst., vol. PAS-101, no. 10,
pp. 3610–3619, Oct. 1982.
[5] N. Fujimoto, E. P. Dick, S. A. Boggs, and G. L. Ford, “Transient
ground potential rise in gas-insulated substations—Experimental studies,”
IEEE Trans. Power App. Syst., vol. PAS-101, no. 10, pp. 3603–3609,
Oct. 1982.
[6] C. A. Jordan, “Lightning computations for transmission lines with over-
head ground wires—Part II,” General Electric Rev., vol. 37, no. 4,
pp. 180–186, 1934.
[7] Surge Arresters—Part 5: Selection and Application Recommendations,
Fig. 10. Single-point bonding connection in the immediate cable section with IEC 60099-5:2013, May 2013.
a sheath voltage limiter installed in the GIS side. [8] Insulation Co-Ordination—Part 2: Application Guide, IEC 60071-2:
1996, Dec. 1996.
[9] G. L. Ford and L. A. Geddes, “Transient ground potential rise in gas-
insulated substations—Assessment of shock hazard,” IEEE Trans. Power
C. Cable Sheath Bonding App. Syst., vol. PAS-101, no. 10, pp. 23–24, Oct. 1982.
[10] R. J. Harrington and M. M. El-Faham, “Proposed methods to reduce
In Fig. 10, the case of a single-point bonding connection transient sheath voltage rise in gas insulated substations,” IEEE Trans.
in the immediate cable section with a sheath voltage limiter Power App. Syst., vol. PAS-104, no. 5, pp. 1198–1206, May 1985.
installed in the GIS side is shown. In this case, the sheath
temporary overvoltages that appear between the cable sheath
and the Earth when a phase-to-ground fault occurs in the power Abderrahim Khamlichi received the B.Sc. degree
grid are seen by both limiters: the sheath voltage limiter which in electrical engineering from the Technical Uni-
protects the cable sheath and the bypass SVL located between versity of Madrid (UPM), Madrid, Spain, in 1999,
where he is currently working toward the M.Sc.
the cable sheath and the GIS enclosure. Therefore, the bypass degree in the area of electrical power transmission.
SVL rated voltage Ur should be equal or higher than the sheath He is currently the responsible of the High
limiter rated voltage Ursheath in order to ensure the bypass SVL Voltage Calibration Laboratory, High Voltage Tech-
nological Center (LCOE-F2I2), and an Electrical
integrity in case of phase-to-ground fault, as well as to satisfy Engineer with the R&D&I Department. He is also
the restrictions of (30) an Educator with the Department of Electrical Engi-
neering, ETSIDI-UPM.
Ur ≥ Ursheath . (31)
If the condition required by (31) does not allow satisfying Gonzalo Donoso received the B.Sc. degree in elec-
the restrictions of (30), it must be necessary to increase the trical and mechanical engineering from the Uni-
insulation level (BILBC , BILBT , or BILT C ) in order to versity of Extremadura (UEx), Spain, in 2007, the
M.Eng. degree in design, construction, and mainte-
satisfy simultaneously (30) and (31). nance of high-voltage electrical infrastructure from
the Comillas Pontifical University (ICAI), Madrid,
Spain, in 2012, and the M.Eng. degree in industrial
VI. C ONCLUSION economics and markets from Carlos III University of
Madrid (UC3M), Madrid.
In order to mitigate TEVs in installed 220-kV GISs, the He is currently a Project Engineer with the Line
shortest possible grounding leads from the cable sheath and Maintenance Department, Red Eléctrica de España
(REE), the Spanish TSO, Madrid, where he is managing the maintenance of
the GIS enclosure to the Earth should be installed, and the cables for rated voltages up to 400 kV.
capacity coupling between these grounding parts and the Earth
floor should be increased. Furthermore, the use of properly
selected bypass SVLs joining the GIS enclosure with the cable Fernando Garnacho received the B.Sc. degree in
sheath is the most effective solution to mitigate TEV when industrial engineering and the Ph.D. degree from
both parts are connected to the station ground through different the Technical University of Madrid (UPM), Madrid,
Spain, in 1981 and 1986, respectively.
grounding leads, but their selection should satisfy the insulation Since 1981, he has been with the High Voltage
coordination criteria. Additionally, if a sheath voltage limiter Technological Center (LCOE-F2I2), Madrid, where
exists in the cable single-point bonding, coordination between he is currently the Director. He is also a Profes-
sor with the Department of Electrical Engineering,
its characteristics and the bypass SVL ones should be achieved ETSIDI-UPM.
in order to ensure the bypass SVL integrity in case of phase- Dr. Garnacho has been a full member of many CI-
to-ground fault. Finally, it should be emphasized that these GRE Working Groups such as D1.35, D1.36, D1.37,
and D1.60 since 1990. Since 2004, he has been the Chairman of Technical Com-
guidelines do not ensure complete security against possible haz- mittee 42, “High Voltage Testing Techniques,” of the Spanish Standardization
ardous disruptive discharges, but they certainly help to prevent. Institute AENOR.
KHAMLICHI et al.: IMPROVED CABLE CONNECTION TO MITIGATE TEVs IN 220-kV GISs 569
Gregorio Denche received the B.Sc. degree in in- Fernando Álvarez received the B.Sc. degree in
dustrial engineering from the Technical University electrical engineering from the Technical University
of Madrid (UPM), Madrid, Spain, in 2002, where he of Madrid (UPM), Madrid, Spain, in 1999 and the
is currently working toward the Ph.D. degree in the B.Sc. degree in industrial engineering from Carlos III
area of electrical power transmission. University of Madrid (UC3M), Madrid, in 2008. He
Since 2006, he has been an Associate Profes- is currently working toward the Ph.D. degree in the
sor with the Department of Electrical Engineering, High Voltage Tests Laboratory (LAT-UPM).
ETSIDI-UPM. Since 2003, he has also been with Since 2004, he has been an Associate Profes-
Red Eléctrica de España (REE), the Spanish TSO, sor with the Department of Electrical Engineering,
Madrid, where he is a Senior Engineer with the ETSIDI-UPM. He has participated in several re-
Engineering Lines Department. His research inter- search projects related to HV electrical insulation
ests include grounding grid analysis and overvoltage in metallic screens of diagnosis. His research is focused on high-voltage insulating materials and
underground cables. partial discharge measurement.