Financing and Structuring Power Projects in Nigeria
Financing and Structuring Power Projects in Nigeria
Projects In Nigeria
Key financial and commercial factors in developing bankable power projects
Patrick Mgbenwelu,
Director & Head, Project & Structured Finance
FBN Capital Limited
1
Outline
4 St t i Issues
Structuring I 32
6. Closing Remarks 51
8. Q&A 52
9. Appendices 54
2 2
Challenges
g & Financing
g Issues
3
Financing Issues – Key Features of Power Financing
COMMENTS
Debt term varies from project to project and also on the plant type and
location:
Long
g Tenor – Power: 8 - 30 year debt term
Bridge funding available where required – but avoid if possible unless
take-out is 100% certain
4
Financing Issues – Funding Sources
Local Banks
International Banks
Regional Banks and DFI’s
DEBT ECAs
Capital Markets
Islamic Finance
P
Pension
i funds
f d
Government
Foreign and Local Partners
Local Private Sector
EQUITY Local Stock Market
Pension funds
Recent entries since 2001 = Infrastructure Funds, Sovereign Wealth Funds,
Private Equity…
5
Financing Issues – Potential Sources of Term Debt Finance
IPP
DFI’s MLA’s World Bank Group Commercial Sources DCM and Others
6
Credit Enhancement - World Bank “Partial Risk Guarantee”
The PRG is a tool used by the World Bank to catalyse private debt finance in support of
host governments' developmental objectives
The PRG has been used successfully in a number of developing markets such as:
– Phili i
Philippines (L t )
(Leyte)
– Pakistan (Uch Power / Hub Power)
– Morocco (Jorf Lasfar)
– Nigeria – (Power Holding Company of Nigeria)
– Bangladesh (Haripur Power Project)
– Vietnam (Phy My 2 Phase 2 Power Project)
– Uganda (Bujagali Hydro Power Project)
– Kenya (Kenya Power and Lighting Company Ltd., and Nairobi Toll Road (under negotiation))
– Mozambique – Sasol Natural Gas Pipeline project
The PRG has rarely if ever been called on. This can be attributed to:
– The World Bank’s influence and intervention, prior to an actual default and potential claim
under the PRG, to help resolve the issues that have arisen
– The importance of the PRG to the governments of developing countries:
7
Credit Enhancement – PRG in the Context of the Power Sector
Typically, the IDA will provide coverage to commercial lenders for loan default by the borrower
(often an SPV) resulting from a government’s failure to meet its payment obligations under:
– Concessions or Investment Agreements
– Power Purchase Agreements
– Gas Sales Agreements
– Water Supply Agreements, etc.
Obligations covered include both periodic payments and termination amounts. Allows for the
extension of debt maturities, reduction in spreads, and increased debt capacity;
Commercial risks such as completion and operational risks and natural force majeure risks are
typically not covered by the PRG. These should be mitigated through the normal contractual
arrangements
Guarantee support is documented in a Guarantee Agreement, which outlines the scope of risk
coverage and defines the trigger mechanisms of the Guarantee;
Charges fees of approximately 75 bps per annum on outstanding principal amounts of the
guaranteed loan (comprised of Guarantee Fees,
Fees Stand
Stand-by
by fees,
fees Initiation Fees and Processing
Fees);
In parallel, WB has an Indemnity Agreement with the host government, under which the
government has counter-guaranteed WB for any payments made under the Guarantee
Agreement;
8
Power Financing Typical Challenges
9
Due Diligence
g Issues
10
Due Diligence Issues
Grand total costs might be understated – though not deliberately but due to
absence of independent verification;
Costs might escalate – not as a result of any external inflationary pressure, but
CONSTRUCTION COSTS due to in-experienced
in experienced construction managers and poor project execution;
Variations and change orders;
Poor planning construction activities against other critical path items / key
dependencies;
EPC contractor might not have the requisite skills for project of such type and or
EPC CONTRACTOR magnitude which could lead to construction delay;
EPC contractor might not have the financial muscle to adhere to its terms of the
contract;
O&M contractor might not have extensive power plant experience which could
lead to escalating O&M costs over and above those budgeted in the financial
model;
O & M CONTRACTOR
O&M contractor might not have the financial muscle to adhere to its terms of the
O&M contract – i.e. compensating the borrower for any shortfalls in agreed
POWER PLANT performance;
11
Due Diligence Issues
Interest rates may increase substantially over and above what was assumed in the
financial model – this will jeopardize the borrower’s ability to meet its debt service
INTEREST RATES and other obligations;
Therefore need to stress tests “pinch points” and how these can be covered via
some hedging arrangement or sponsor support / top-up;
This is a major risk factor for power plants projects that have costs and revenues
that are not matched in the same currency - exchange rates may increase
substantially over and above what was assumed in the financial model – this will
jeopardize the borrower’s ability to meet its debt service and other obligations;
EXCHANGE RATES
Structuring phase must include an exchange rate stress test to assess the
impact of a deteriorating exchange rate and structure protections into the
overall financing plan to protect the power plant and also debt service;
The risk that the Right of Way (“RoW”) may not be available in its entirerity,
leading to completion delay;
P
Promoters
t mustt ensure the
th RoW
R W has
h been
b f ll obtained
fully bt i d and
d secured
d and
d that
th t this
thi
RIGHT OF WAY is documented;
Power plants not always ring In certain projects, although a “sign-off” meeting may be held with the State and or
fenced… local government(s), it is now generally very common to also have “sign-off”
meetings with the various stakeholders chiefs through who’s land the RoW runs;
The cost impact of this risk can be quite sizeable, bringing projects to a complete
halt and furthermore if not suitably managed can remain unresolved for months;
12
Due Diligence Issues
Risk that either (i) power demand projections are below base case due to optimistic assumptions
or (iii) assumptions are correct but competition reduces expected demand;
Because independent assessments are never 100% correct (but necessary) the base case must
include substantial allowance for reduced power demand risk to ensure debt service is
OFFTAKER / protected;
DEMAND RISK In certain power projects, the host government / sponsor will provide demand guarantees so as
to ensure the project remains attractive to debt and or equity providers;
Independent demand and or market consultants are generally retained to provide advice in
these matters;
Less of a risk where PPA is based on a minimum demand threshold and “take or pay”
13
Due Diligence Issues
14
Due Diligence Issues
Feedstock source;
Dual or single fired;
FEEDSTOCK SUPPLY
Feedstock availability,
y, p
price,, escalation;;
Who carries risk for non-supply and compensation regime;
Tariff will be set out in the PPA – this must be captured in the financial model;
Question is what risks are there for possible changes (i.e. reductions) in tariffs;
TARIFF / PRICES A historical view of tariffs will need to be “married” against the plant’s future tariff
regime to determine its likely acceptability once the plant is up and running – of
course this will not hold if an agreed PPA is already in place;
Power plants require uninterrupted utility supply so due diligence will need to
ensure robust contracts are in place for the supply of utilities which will be critical
UTILITY SUPPLY f its
for i operations
i
Certain projects enter into various individual utility supply agreements;
15
Due Diligence Issues
16
Due Diligence Issues
Plant needs to comply with stringent requirements regarding noise and other
hazardous emissions;
ENVIRONMENTAL Construction and ongoing operations of the plant must ensure it does not cause
environmental
i t l damage;
d
17
Due Diligence Issues – Coal to Power
18
Due Diligence Issues – Gas to Power
Production
Supply Pipeline Power Plant MW Evacuated
Well
19
Due Diligence & Financiers’ View – Fuel Supply Risk
Available Fuels
The key determining factor. Influences plant technology, output, efficiency, capital and operating costs, water / sorbent
consumption, by-product disposal, asset life, emissions among others. Essentially, the generation investment hinges on
the types
yp of fuel that are available at the p
potential g
generation location
Typically, substantially cheaper to transport power than fuel. Conventional wisdom for coal is to build plant adjacent
to fuel source, given complexities/costs of long distance road / rail transport (e.g. cost, social impact, servitude risks).
Th
There i more flexibility
is fl ibilit for
f gas transportation
t t ti (
(especially)
i ll ) and
d oilil / diesel-fired
di l fi d generation
ti given
i l
lower t
transportation
t ti
costs.
I
I. Coal will lead to higher SO2 and CO2 emissions than comparators.
comparators (e.g.
(e g natural gas)
III. Equator Principles imposes a high financing hurdle and entails the need for a robust ESIA process
IV. Certain fuels (e.g. coal) produce huge by-products (ash) which may impact on ground water quality
20
Due Diligence & Financiers’ View – Fuel Supply Risk
Contractual Structure
I. Is the fuel supplier just a supplier or are they tied into the deal/ company? Co-shareholder?
II
II. Long-term contracting usually better than short-term but not without risks (e.g.
(e g cost indexation due to inputs
outside of utility’s control)
III. Where does the risk allocation lie? Held with the Generator or by the Fuel Supplier?
Price
II. Are base and variable fuel prices passed through to tariffs and a cost recovery enabled?
III. What is the mode of contracting (e.g. fixed price, cost-plus or otherwise)?
21
Due Diligence & Financiers’ View – Water Supply Risk
Underlying Hydrology
I. The key determining factor. The projected water balance influences the underlying risk profile, the selected
plant technology, concerns as to consumption, impacts on flora, fauna and nature (e.g. wetlands). Can the
water be extracted and
and, if so
so, at what cost (economic and environmental)?
II. Can the asset produce for the designated asset life? Is there the water balance to ensure this (with a suitable
reserve margin)?
Underlying Technology
I. Wet cooling requires constant supplies of water, for coal-fired and solar technologies. Dry cooling (currently
required in South Africa for new build coal-fired plants), requires less water (albeit significant compared to
many other water uses), although increases generation costs and commonly reduce efficiency.
II. Relatively low concerns regarding hydrological impact of oil or gas-fired technology
22
Due Diligence & Financiers’ View – Water Supply Risk
I. Does the utility (or a third party) have to build new water transmission infrastructure (e.g. dams, pipelines) to
supply the plant? and / or pay for it? How is this assessed within the initial investment decision?
II. Who takes the risk of non-supply of water during the plant life? Utility or Consumers?
III. Who takes the responsibility for securing of permits (e.g. water usage risks) and servitudes?
Contractual Structure
I. Is the water supplier just a supplier or are they tied into the deal/ company?
II. Water suppliers are typically a State owned entity so often a greater alignment with the incumbent utility than
regarding fuel suppliers
IV. Are private parties asked to take construction risks on State owned water suppliers? This is unlikely to be a
bankable risk
23
Due Diligence Issues – Environmental Implications
Potential negative impact on the surrounding environment will require an Environmental & Social Impact Assessment Plan which
is in compliance with the World Bank’s Equator Principles (which all major financiers are signatories of).
Kyoto Protocol
Future Carbon
Taxes?
Compliance with
Compliance with World Bank
World Bank Equator
q Equator
Principles CO2 / SO2 Principles
Emissions
Water
Consumption
Resettlement
of population
Thorough due
diligence in selection
and
d application
li ti Coall fi
C fired
d plants
l t generate
t hi
higher
h CO2
CO2, SO2 and
d
process use more water than gas-fired plants.
24
Due Diligence Issues – Gas or Coal Fired Plants
The critical first choice is to determine the Project Site and Fuel / Technology. All project issues flow from this
choice.
Therefore, the main issues pertaining to the development of power plants are as follows:
Frame Capacity (MW) by reference to what is ultimately financeable as a single transaction within the target
timeframe
Develop the Project commercial concept based on the above parameters, and including issues such as
interconnections, associated infrastructure and transmission
Develop Project Agreements, focusing upon (1) PPA and (2) Fuel Supply Agreements as the key priority
Identify equipment suppliers and contractors, partly based upon their ability to fund the project. A project is
not a project unless it can secure funding
25
Key
y Documents / Agreements
g
26
Key Document – The Power Purchase Agreement (PPA)
The PPA grants the concession and sets the tariff. It is the primary document all should focus on. To some extent
all the others are secondary.
Performance criteria
Pl t specifications
Plant ifi ti and
d performance
f standards
t d d
Revenue write down provisions for Plant under / non-performance
Delays LDs for late commissioning
Thi d party
Third t responsibilities
ibiliti
Fuel, Water and power transmission interconnections
Supply of gas / coal / fuel
Permits and Licences
Force majeure
Natural / Political Force Majeure (e.g. Change in Law)
Implications for mitigation of risks
27
Key Document – The Power Purchase Agreement (PPA)
Termination
Key Decisions:
Whether fuel supply obligations (for gas-fired plant) should be contained in a Separate Fuel Supply Agreement or
also included in the PPA
If the former, need to identify the counterparty and structure the FSA so it is aligned with the PPA. This may be
difficult if a private company is the fuel supplier (e.g. an IOC)
If the latter, or if the fuel supplier is State owned, potential for the IPP to be “Tolled”, which is a globally proven IPP
risk structure. This may assist bankability, especially if the Ministry of Finance guarantees PPA payments
This
Thi iissue will
ill nott arise
i ffor coal-fired
l fi d plants
l t ((given
i th
they will
ill be
b mine
i mouth)
th)
28
Other Key Project Agreements
Excluding the Fuel Supply Agreement, the other documents would largely be the responsibility of the power
plant developers to draft and execute.
29
Other Key Project Agreements (Nigeria)
The following have emerged as some of the key documents which will need to be in place for power sector
financings in Nigeria.
O&M Agreement;
Pre-Completion
p Liabilities Transfer Agreement.
g
30
Non-documentation Commercial Issues
Other risks
Fuel Adequacy and Security of Fuel Supply
Volatility of Price Fuel Supply
Technical Specification Risk Agreement
31
Structuring
g Issues &
Considerations
32
Structuring Issues & Considerations
70.00
60.00
50.00
40.00
30.00
20 00
20.00
10.00
0.00
1 2 3 4 5 6 7 8 9 10
Equity Debt
33
Structuring Issues & Considerations
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1 2 3 4 5 6 7 8 9 10
Equity Debt
34
Structuring Issues & Considerations
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1 2 3 4 5 6 7 8 9 10
Equity Debt
35
Structuring Issues & Considerations
Financing structure should mitigate (i) exposure to each cash flow line item and (ii) pass other contractual risks as
distant as possible from the lenders.
Liquidated Damages;
Gearing;
Cash Waterfall;
36
Structuring Issues & Considerations
Early generation revenues – are these 100% certain and caught in the debt sizing computations?
ICA 1 ICA 2
Debt Repayments
PAYMENTS IN THE FOLLOWING ORDER OF PRIORITY
1) Operating Costs
2) Debt Service Reserve Account top up, if required
3) Dividend Reserve Account top ups, if required
4) Major Maintenance Reserve Account top up, if required
5) Any other costs
LENDING BANKS
Constant minimum cash balance of US$10 million
37
The Power Project
j Financial Model
(snapshot only)
38
Financial Modeling – Key Issues for Power Financing
Power project financial models must be as comprehensive as possible to capture all the revenue and cost items, ideally on
a line-line or input-by-input basis;
Sufficient time must be spent developing the model so as to adequately assess the project’s debt capacity and sensitivity
to a range of events;
The starting point is essentially gathering data from the feasibility study (i.e. if one
has already been prepared);
In a number of cases,
cases the project sponsors may already have an in-house in house model
DATA GATHERING
developed which will be made available to their lead arranger or financial adviser;
Other key sources of data will include the results / outputs from the various
independent consultant reports;
Review overall outputs to identify “pinch points” and areas that will require detailed
financial structuring;
Are ratios above acceptable levels;
Is desired initial equity sufficient;
STRUCTURING 1a
Is debt tenor likely to be acceptable to potential lenders;
Feed in escalation of inflation rates;
Undertake initial stress test to determine sensitivity of model to a range of likely
scenarios;
39
Financial Modeling – Key Issues for Power Financing
Validate / update all information in the financial model with final outputs from the following:
EPC contract;
Lenders Independent Technical consultant’s report;
Lenders Independent Market consultant’s report;
DATA VALIDATION
Lenders Independent Insurance consultant’s report;
O&M contract;
Updated rates for LIBOR / NIBOR as appropriate;
Assess impact of all the above on overall project economics;
40
Financial Modeling – Key Issues for Power Financing
41
Financial Modelling - key issues for power financing
Engage jointly with client / sponsors and lenders to achieve the following changes:
Increase in debt tenor;
Ideal repayment profiles which the project can accommodate;
Agreement to inject standby debt to accommodate likely completion delay;
Finalize any impact of debt pricing and fees;
Timing for funding of reserve accounts and quantum they will be satisfied with – the
STRUCTURING 2
LTA will also be involved in agreeing
g gqquantum for the maintenance accounts;;
Ensure the financial model is constantly being updated and re-run to ensure the desired
ratios are being achieved / moving towards what will be accepted as all the above changes
and negotiations are taking place;
It is your responsibility as the financial modeler to raise any alarms / red flags if
it is clear that the direction of negotiations / changes will not achieve the desired
resultl / ratios
i / financing
fi i structure;
42
Financial Modeling – Key Issues for Power Financing
You only have a Base Case once all the issues discussed on the preceding pages have been
THE BASE CASE
made and your ratios are at or above the minimum thresholds;
Documentation is important and therefore the changes made over time should be logged in
the audit trail worksheet;
The actual key assumptions and use of the model should be set out in a “User Manual / Data
MODEL DOCUMENTATION Book of Assumptions
Assumptions”;;
Both of the above will be a useful reference for all parties – potential lenders, the client, the
lenders independent consultants who will be expected to provide sign-off of their individual
sections of the model and also the model audit consultant;
The model audit is undertaken to provide all parties (particularly the lending banks) with the
assurance that:
All algorithms used in the model are correct;
The tax and accounting assumptions are correct and have been computed correctly;
MODEL AUDIT Th model
The d l produces
d the
h desired
d i d results
l after
f allll the
h various
i sensitivity
i i i changes
h h
have
been undertaken;
The model auditor will be expected to give a 1 / 2 page report on the model;
Finally, the audited Base Case should be saved as the VERY FINAL version which will be the
reference version for any changes to be made post financial close;
43
Financial Modelling - key issues for power financing
44
Financial Modeling – Key Issues for Power Financing
E
Energy P
Paymentt Energy Dispatched x Feedgas
46
Financial Modeling – Key Issues for Power Financing
1,000.0
800.0
600.0
400.0
200 0
200.0
0.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
(200.0)
(400.0)
(600.0)
Negative Cash Revenues All Bank Debt Drawn Project Loan Drawn Equity subscribed
47
Financial Modelling - key issues for power financing
2,500.0
2,000.0
1,500.0
1,000.0
500 0
500.0
0.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
(500.0)
(1,000.0)
Negative Cash Revenues All Bank Debt Drawn Project Loan Drawn Equity subscribed
48
Modelling – monthly / quarterly build up
Advantages:
Captures timing differences in cash flows (overdraft / working capital requirement?);
Tracks seasonality where revenues in model are driven by cyclical demand / volume;
C t
Captures tturbine
bi / plant
l td downtime
ti
Timing of capital expenditure and funding requirement; Monthly or Quarterly key inputs
/ assumptions are best…...
Drawbacks:
Spreadsheet end up larger in size;
49
Modelling – key banking ratios
3 - LLCR NPV of future cash flow to service debt over loan life
Principal and interest outstanding for the period
3 - PLCR NPV of future cash flow to service debt over project life
Principal and interest outstanding for the period
Above represent only a select few ratios looked at for assessing project economics but financing term sheet will include others such as balance sheet
ratios…..
50
SUMMARY & CLOSING REMARKS
51
Summary and Closing Remarks
Value chain must be contractually linked – obligations must be replicated in the model, project
agreements and financing documents;
The financial model is fundamental, start early – do not rely on the sponsors projections;
Documentation
52
Q&A
53
Appendices
54
About The Presenter
55
About the presenter
Patrick joined FBN Capital in December 2011 having spent 3 years heading the project financing department at Stanbic IBTC
Bank. He joins FBN Capital with over 20 years banking experience of which 17 years has been dedicated primarily towards
financial advisory, structuring, debt arranging / lending and closing of big‐ticket project finance transactions in the UK,
Portugal, Saudi Arabia, Qatar, Oman, U.A.E. and other GCC countries. He has worked on project financings in excess of US$67
billion since 1996. As head of FBN Capital’s project and structured finance division, he is responsible for leading the deal team
involved in originating,
originating structuring,
structuring executing and closing of all the firm
firm’ss project and structured finance business.
business
Patrick’s project financing career commenced as a financial modeller at London Underground Limited’s (“LUL”) project finance
advisory group as an executive member of the deal‐team developing complex financial models, business cases, payment
mechanisms and financing options where he advised and negotiated on various projects being implemented by London
Transport utilizing the UK Government’s Private Finance Initiative (“PFI”) at that time. His career further developed at the
London branch of Bayerische Landesbank
Landesbank’ss ((“BLB”)
BLB ) structured finance group where he undertook various project finance (PFI
/ BOT / PPP) duties, and subsequently as Assistant Manager, Project & Trade Finance Department, GCC Group, at Arab
Petroleum Investments Corporation (“APICORP”) Saudi Arabia where he was actively involved in a varied number of power,
petrochemical, oil & gas and shipping transactions both in the execution, advisory, lending and syndication of facilities. He
was subsequently appointed Senior Corporate Banker and acting Head of project finance at The National Commercial Bank
(“NCB”), Saudi Arabia with prime responsibility for managing the banks project finance lending and advisory activities. At NCB
Patrick led the deal team advising the Kingdom of Saudi Arabia on the US$11 billion plus Saudi Railway expansion Projects.
Projects
Patrick has been involved in structuring and closing power project financing transactions in the UK and the Middle
East since 1996. He has worked on power transactions in excess of US$$3.8 billion (UK and Middle East
combined) and was involved in financing the first wave of independent power projects (“IPP”) launched in the
Middle East from 2001 through to 2006. Prior to returning to Nigeria in 2008 he was Managing Director and Head of
Project and Corporate Finance at Bahrain based Gulf One Investment Bank, Bank Bahrain.
Bahrain His notable achievement at
Gulf One was setting up the bank’s project and corporate finance division and leading the deal team responsible for
funding the King Abdulaziz International Airport (Hajj Terminal) – the first ever project financing for an airport in the
GCC on a 100% Islamic finance basis.
Patrick Mgbenwelu is a regular industry speaker and panelist and writes case studies / articles in various PPP / project finance
publications – i.e.
i e Infrastructure Journal,
Journal Project Finance Magazine and Project Finance International.
International He is an Associate of the
Chartered Institute of Bankers (“ACIB”) London, holds an M.Sc. Finance & Investment (London), and an MBA (London).
56
Case Study
y
57
Case Study 1: Shuaibah IWPP, Saudi Arabia
The first IWPP (Independent Water & Power Project) development in Saudi Arabia, Project Summary
which laid out the framework for other IWPP transactions in the Kingdom of Saudi
Arabia Project:
P j t Shuaibah
Sh ib h IWPP
Sector: Power & Water
– framework mirrors that in UAE, Qatar and Oman
Total cost: US$2.45 billion
PPP: Build, Own and Operate (“BOO”) Debt term: 20 years
20 year Power & Water Purchase Agreement (“PWPA”)
( PWPA )
36.5 months construction schedule
Desalinated Water production (880k cm per day, using 12 units of Multi Stage Flash
technology)
Power generation
P ti (900 MW 3 units,
it light
li ht crude
d oilil fi
fired
dbburners, b
back
k pressure
steam turbines)
100% of water and power capacity and output sold to Government-owned entity for
20 years
Main project parties are Saudi & Malaysian sponsors (60%) and Kingdom of Saudi
Arabia (40%)
Groundbreaking IWPP in Saudi Arabia laying down the framework for future IWPP projects in the country.
58
Case Study 1: Shuaibah IWPP, Saudi Arabia ― Finance Plan
H E R ME S 400
Is la m ic Tra n ch e 225
K E XIM 418
E q u ity 496
0 100 200 300 400 500 600 700 800 900 1000
(U S $ m )
$500
$450
$400
$
$350
$300
$250
$200
$150
$100
$50
$50
$0
Equity Bridge Loan Drawdwns
q y g Commercial Banks Drawdowns KEXIM Drawdowns Islamic Tranche Drawdowns HERMES Drawdowns
59
Case Study 1: Ownership Structure
50%
32% 8%
6% PIF
8%
32% ACW A Power Projects
12%
Khazanah
Malakoff
12% SEC
30% Tenega Nasional Berhad
60
Case Study 1: Bankability Issues
Saudi Aramco (National Oil Company) is supplier of light crude (tolling structure)
Fuel Supply
Plant site has reasonable fuel supply storage facilities
Risk
Incremental cost for back-up fuel passed to Government
61
Indicative Contractual Structure
IPP Company
C
Power Purchase
Agreement
62