ContractFormsDevAgencies TonyMarshall
ContractFormsDevAgencies TonyMarshall
• What is ENAA?
• The various ENAA forms:
– 1986: Process Plant Form (EPC)
– 1992: Process Plant Form (EPC), 2nd Edition
(Appendix 4, sample Work Procedures, and Appendix 5, version
without process licence, added)
– 1996: Power Plant Form (EPC)
– 2007: Engineering, Procurement & Supply Form (EPS)
– 2010: Process Plant Form (EPC), 3rd Edition
– 2012: Power Plant Form (EPC), 2nd Edition
– 2013: Engineering, Procurement & Supply , 2nd edition
www.hoganlovells.com 3
Background (2)
www.hoganlovells.com 4
Background (3) – User’s Guide (ADB version)
www.hoganlovells.com 6
The ENAA Process Plant Form – the broad
scheme (2):
www.hoganlovells.com 7
The ENAA Process Plant Form – the broad
scheme (3):
• Limitations on liability:
www.hoganlovells.com 8
Key features of the Process Plant Form (1):
• Ease of use
– clear language
– grouping into convenient parts
– key elements all included in the Agreement
– sample Appendices (forms of letter, etc) and Procedures
– full Guide Notes
• Process-related provisions
– Contractor's scope includes provision of process licence
(GC15.1)
– Contractor responsible for satisfactory working of process,
but NO fitness for purpose obligation (GC28; GC3.6)
www.hoganlovells.com 9
Key features of the Process Plant Form (2):
www.hoganlovells.com 10
Key features of the Process Plant Form (3):
• Dispute resolution
– Mutual consultation (GC6.11)
– Arbitration (Article 13; GC6.1.2-5)
– Expert determination as an option (GC6.2)
www.hoganlovells.com 11
The African context: a mix of legal systems (1)
Tunisia
Morocc
o Algeria
Libya Egypt
Mauritania
Mali Eritrea
Senegal Niger Sudan
Chad
The Gambia Djibouti
Cote B.
Guinea Ethiopia
Faso Nigeria South Ethiopia
Bissau Guinea C.A.R.
d'Ivoir Sudan
Sierra Liberia e Somalia
Leon Ghana Togo Beni Keny
Cameroo
e n Ug a
Equatorial Guinea n
Democratic Rw
Gabon Republic of Bu
Tanzania
Republic of the Congo the Congo
Seychelles
Malawi
Angola Comoros
Zambia
Swaziland
South
Common law jurisdictions Africa Lesotho Mauritius
www.hoganlovells.com 12
The African context: a mix of legal systems (2)
www.hoganlovells.com 13
The Francophone countries: the OHADA
Organisation pour l'Harmonisation en Afrique du Droit des Affaires
www.hoganlovells.com 14
The OHADA Unifying Acts
• The Unifying Acts are directly applicable in the 17 member
countries
• The 9 areas of unified law are:
1. General commercial law
2. Corporate law
3. Securities
4. Enforcement and execution proceedings
5. Insolvency proceedings
6. Harmonisation of business accountancy
7. Contracts for the transportation of goods by road
8. Co-operatives law
9. Arbitration law
www.hoganlovells.com 15
The OHADA institutions
• OHADA institutions
1. Council of Ministers, comprised of Finance and Justice Ministers of the State Parties
2. Common Court of Justice and Arbitration (Ivory Coast)
3. Permanent Secretary Office (Cameroon)
4. Regional High Judiciary School (Benin)
www.hoganlovells.com 16
PALOP - towards a Portuguese OHADA?
Morocc
o Algeria
Libya Egypt
Mauritania
Mali Eritrea
Senegal Niger Sudan
Chad
The Gambia Djibouti
Cote B.
Guinea Ethiopia
Faso Nigeria South Ethiopia
Bissau Guinea C.A.R.
d'Ivoir Sudan
Sierra Liberia e Somalia
Leon Ghana Togo Beni Keny
Cameroo
e n Ug a
Equatorial Guinea n Rw
Democratic
Gabon Republic of Bu
Tanzania
Republic of the Congo the Congo
Seychelles
Malawi
Angola Comoros
Zambia
Swaziland
South
OHADA Treaty only Africa Lesotho Mauritius
www.hoganlovells.com 18
Enforceability of arbitral awards in Africa (2)
www.hoganlovells.com 19
Enforceability of arbitral awards in Africa (3)
www.hoganlovells.com 20
Enforceability of arbitral awards in Africa (4)
• FIDIC Pink:
– “The Contractor shall design (to the extent specified in the
Contract), execute and complete the Works in accordance
with the Contract and with the Engineer’s instructions, and
shall remedy any defects in the Works” (GC 4.1.1)
– If the Contract specifies that the Contractor shall design
any part of the Permanent Works, then unless otherwise
stated in the Particular Conditions … the Contractor’s
Documents for this part shall be in accordance with the
Specification and Drawings and … this part … shall, when
the Works are completed, be fit for such purposes for
which the part is intended as are specified in the Contract
(GC 4.1.6)
www.hoganlovells.com 22
Distinctions between the Forms - Design (2)
• FIDIC Pink:
– “After the Performance Certificate has been issued, each
Party shall remain liable for the fulfilment of any obligation
which remains unperformed at that time. For the purposes
of determining the nature and extent of unperformed
obligations, the Contract shall be deemed to remain in
force” (GC 11.10.1)
• ENAA (ADB version):
– “Except as provided in GC 5.2 and 5.4, the Contractor
shall be under no liability … in respect of defects … that
appear after Completion … except where ... the result of
… gross negligence … of the Contractor” (GC 5.2.9)
www.hoganlovells.com 24
Distinctions between the Forms – Defects (2)
www.hoganlovells.com 25
Distinctions between the Forms - Payment
www.hoganlovells.com 26
Distinctions between the Forms - Programming
• FIDIC Pink
– “Unless the Engineer, within 21 days after receiving a
programme, gives notice to the Contractor stating the
extent to which it does not comply with the Contract, the
Contractor shall proceed in accordance with the
programme, subject to his other obligations under the
Contract” (GC 8.2)
• ENAA (ADB version)
– Programme/Schedule to be submitted, and revised “when
appropriate”, but not binding – only the Times for
Completion are binding
www.hoganlovells.com 27
Distinctions between the Forms - Completion
• FIDIC Pink
– Completion is achieved when the Works are ready for
handing over and all Tests on Completion have been
done; risk transferred on Taking Over (GC8.2 and 17.2.1)
– Liquidated damages payable if late (GC 8.7)
• ENAA (ADB version)
– “Completion” is achieved, and risk transferred, once
Facilities “completed operationally and put in a tight and
clean condition … excluding minor items” and
Precommissioning complete (GC 4.8 and 6.2.1)
– Liquidated damages payable if late (GC 5.1.2)
– Commissioning and Operational Acceptance follow
www.hoganlovells.com 28
Bibliography: Articles on the ENAA Model Forms
in the International Construction Law Review (1)
• Sasaki, T., E.N.A.A. model form of contract, (1987]) 4 ICLR 93-105
• Gould, Nicholas, Some comments on the policies and drafting of the
E.N.A.A. model form international contract for process plant construction,
(1988) 5 CLR 205-231
• Westring, Gosta, Turnkey heavy plant contracts from the owner's point of
view, (1990) 7 ICLR 234-249
• Furuya, Kunihiko, ENAA revised model form of contract (1992 edition),
(1993) 10 ICLR 5-15
• Jaynes, Gordon L.,Turnkey contracts: Japan's model forms, (1993) 10
ICLR 251-287
• Gould, Nicholas, Comments on the ENAA Model Form international
contract for process plant construction (revised 1992), (1994) 11 ICLR
498-525
• Wiwen-Nilsson, Tore, A brief review of the 1992 edition of the ENAA
Model Form - international contract for process plant construction
(turnkey lump sum basis), (1994) 11 ICLR 526-548
www.hoganlovells.com 29
Bibliography: Articles on the ENAA Model Forms
in the International Construction Law Review (2)
• Wakame, N., An overview of major issues on ENAA Model Form
International Contract for Process Plant Construction, 1992 edition - a
drafter's view, (1995) 12 ICLR 98-122
• Niwa, Kazuhiko, Force majeure in Japan - law and practice, (1995) 12
ICLR 179-181
• Hoshi, Hiromi, New ENAA model form of contract, (1996) 13 ICLR 482-
487
• Hoshi, Hiromi, ENAA model form of contract for power plant construction,
(1997) 14 ICLR 61-70
• Wiwen-Nilsson, Tore, The 1996 edition of the ENAA Model Form -
international contract for power plant construction - a brief review (1997)
14 ICLR 273-288
• Marshall, A R (Tony), Process Plant Construction: the ENAA Model
Form of Contract (2010 Edition) – Comments and Comparisons (2011)
28 ICLR 138-171
www.hoganlovells.com 30
www.hoganlovells.com
"Hogan Lovells" or the "firm" refers to the international legal practice comprising Hogan Lovells International LLP, Hogan Lovells US LLP, Hogan Lovells Worldwide Group (a Swiss Verein), and their affiliated businesses,
each of which is a separate legal entity. Hogan Lovells International LLP is a limited liability partnership registered in England and Wales with registered number OC323639. Registered office and principal place of
business: Atlantic House, Holborn Viaduct, London EC1A 2FG. Hogan Lovells US LLP is a limited liability partnership registered in the District of Columbia.
The word "partner" is used to refer to a member of Hogan Lovells International LLP or a partner of Hogan Lovells US LLP, or an employee or consultant with equivalent standing and qualifications, and to a partner, member,
employee or consultant in any of their affiliated businesses who has equivalent standing. Rankings and quotes from legal directories and other sources may refer to the former firms of Hogan & Hartson LLP and Lovells
LLP. Where case studies are included, results achieved do not guarantee similar outcomes for other clients. New York State Notice: Attorney Advertising.
* Associated offices