Insp Load Securing Devices
Insp Load Securing Devices
19
Lifting Equipment, Lifting Tackle and REV: 0
Load Securing Devices DATE: 17. 02. 2001
1. OBJECTIVE:
This procedure covers lifting equipment, small lifting tackles and load securing devices used in MBDO operations. The
procedure will cover the periodic examination and testing of this equipment to ensure fitness for purpose.
2. REFERENCE:
3. PROCESS DESCRIPTION
Lifting Tackle Equipment, which is movable between areas such as chain blocks, slings, shackles,
chain/load binders etc.
Lifting Equipment Register: This is an electronic register where all MBDO lifting equipment, lifting tackle and
load securing devices are recorded.
Periodicity: All fixed equipment will be examined and load tested every 12 months.
All movable equipment will be visually examined every 6 months and load tested
every 12 months.
Each item of lifting equipment, tackle and load securing devices will have a valid test certificate held on file by RTS.
Section 6.19
Page 1 of 5
Prepared By Road Transport Supervisor Authorized By Operations Manager
Date: 17. 02. 2001 Date: 17. 02. 2001
/conversion/tmp/scratch/410256009.doc
INSPECTION of OP 6.19
Lifting Equipment, Lifting Tackle and REV: 0
Load Securing Devices DATE: 17. 02. 2001
5. TEST METHOD
5.1 The inspection of the equipment shall be carried out by a competent inspector approved by the AFPC.
5.2 A visual examination shal be carried out at a frequency set by the inspection strategy.
5.3 The examination will be carried out on oerhead crane in the rest position followed by an examination with the crane
in motion to determine that all systems are functioning correctly.
5.4 Safe Working Load (SWL) shall be clearly marked on all lifting equiment.
5.5 Proof load test shal be completed on all lifting equipment every 12 months. The test will be carried out following a
thorough examination.
5.5.1 The SWL not exceeding 20 tons the applied load will be 1.25 x SWL
5.5.2 The SWL of 20-50 tons, the applied load will be 5 tons + SWL
5.5.3 The SWL of 50 tons and above, the applied load will be 1.1 x SWL
5.6 Following the proof load test a thorough examination of the lifting equipment will be completed to ensure no
damage has been caused to the equipment by the test.
6. COLOUR CODING
6.1 Following the close visual examination, equipment, which has satisfied the test criteria, will be colour coded. The
colour code is pre defined for that test period.
6.2 Equipment, which has not satisfied the test criteria, will be sprayed RED. Where possible equipment will be
repaired, tested and returned to service such as Chain Blocks or Chains e.g. replaced the defective link with … link.
Equipment, which cannot be repaired, such as slings, will be removed from service and destroyed.
6.3 The exception to the above are fibre slings (both natural and synthetic). They should have an attached tag with the
current colour coding. The application of paint or any other marker is not recommended. If there is any doubt of
their integrity RTS should be contacted.
6.4 Only a competent inspector, approved by the MBDO, may apply the colour coding to the equipment.
Section 6.19
Page 2 of 5
Prepared By Road Transport Supervisor Authorized By Operations Manager
Date: 17. 02. 2001 Date: 17. 02. 2001
/conversion/tmp/scratch/410256009.doc
INSPECTION of OP 6.19
Lifting Equipment, Lifting Tackle and REV: 0
Load Securing Devices DATE: 17. 02. 2001
Section 6.19
Page 3 of 5
Prepared By Road Transport Supervisor Authorized By Operations Manager
Date: 17. 02. 2001 Date: 17. 02. 2001
/conversion/tmp/scratch/410256009.doc
INSPECTION of OP 6.19
Lifting Equipment, Lifting Tackle and REV: 0
Load Securing Devices DATE: 17. 02. 2001
8.4 Inspection of LOAD BINDER devices shall focus on the following defects:
Wear at pivot, swivel surfaces and at the hooks (see furthermore 8.6)
Defective welds
Spreading
Bent, twisted part of device
Cracks, nicks and gouges
Home made modification or repairs
8.7 Inspection of SYNTHETIC AND NATURAL FIBRE SLINGS shall focus on the following defects:
Mechanical damage
Burn marks
Chemical attack
Mildew or rotting
Brittleness
Spliced ends
Section 6.19
Page 4 of 5
Prepared By Road Transport Supervisor Authorized By Operations Manager
Date: 17. 02. 2001 Date: 17. 02. 2001
/conversion/tmp/scratch/410256009.doc
INSPECTION of OP 6.19
Lifting Equipment, Lifting Tackle and REV: 0
Load Securing Devices DATE: 17. 02. 2001
Section 6.19
Page 5 of 5
Prepared By Road Transport Supervisor Authorized By Operations Manager
Date: 17. 02. 2001 Date: 17. 02. 2001
/conversion/tmp/scratch/410256009.doc