Demolition Works Foundation CPM

The document outlines the schedule for a construction project over several pages. It lists 27 separate tasks required to complete the project, including demolition, foundation work, installation of floors, walls, mechanical and electrical systems. It provides the start and finish dates for each task over the 14 month duration of the project, with most tasks 1-4 months in length. The document also includes sections for critical path tasks, milestones, and summaries.

Uploaded by

Ian Talaue
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
54 views

Demolition Works Foundation CPM

The document outlines the schedule for a construction project over several pages. It lists 27 separate tasks required to complete the project, including demolition, foundation work, installation of floors, walls, mechanical and electrical systems. It provides the start and finish dates for each task over the 14 month duration of the project, with most tasks 1-4 months in length. The document also includes sections for critical path tasks, milestones, and summaries.

Uploaded by

Ian Talaue
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

cpm Demolition Works Foundation

Start: Thu 01/02/18ID: 0 Start: Thu 01/02/18 ID: 1 Start: Thu 01/03/18 ID: 3
Finish: Wed 27/02/19
Dur: 14 mons Finish: Wed 28/02/18Dur: 1 mon Finish: Wed 23/05/18Dur: 3 mons
Comp: 0% Res: Res:

Toilet Fixtures
Start: Thu 01/03/18 ID: 21
Finish: Wed 25/04/18Dur: 2 mons
Res:

Electrical Roughing-ins
Start: Thu 01/03/18 ID: 23
Finish: Wed 20/06/18Dur: 4 mons
Res:

Layout And Excavation Ground Floor Columns


Start: Thu 01/02/18 ID: 2 Start: Thu 01/03/18 ID: 4
Finish: Wed 28/02/18Dur: 1 mon Finish: Wed 28/03/18Dur: 1 mon
Res: Res:

Page 1
Interior Wall Finishes
Start: Thu 01/03/18 ID: 15
Finish: Wed 20/06/18Dur: 4 mons
Res:

Page 2
Mechanical Works
Start: Thu 01/03/18 ID: 26
Finish: Wed 10/10/18Dur: 8 mons
Res:

Page 3
Second Floor Beams and Slab Fourth Floor Beams and Slab
Start: Thu 24/05/18 ID: 5 Start: Thu 21/06/18 ID: 9
Finish: Wed 20/06/18Dur: 1 mon Finish: Wed 18/07/18Dur: 1 mon
Res: Res:

Fourth Floor Columns


Start: Thu 21/06/18 ID: 10
Finish: Wed 18/07/18Dur: 1 mon
Res:

Second Floor Columns Waterproofing Interior Painting


Start: Thu 29/03/18 ID: 6 Start: Thu 26/04/18 ID: 13 Start: Thu 24/05/18 ID: 19
Finish: Wed 25/04/18Dur: 1 mon Finish: Wed 23/05/18Dur: 1 mon Finish: Wed 15/08/18Dur: 3 mons
Res: Res: Res:

Page 4
Third Floor Beams and Slab Plumbing Roughing-ins
Start: Thu 29/03/18 ID: 7 Start: Thu 26/04/18 ID: 20
Finish: Wed 25/04/18Dur: 1 mon Finish: Wed 18/07/18Dur: 3 mons
Res: Res:

Third Floor Columns Exterior Painting Ceiling Finishing


Start: Thu 29/03/18 ID: 8 Start: Thu 26/04/18 ID: 12 Start: Thu 19/07/18 ID: 14
Finish: Wed 25/04/18Dur: 1 mon Finish: Wed 18/07/18Dur: 3 mons Finish: Wed 15/08/18Dur: 1 mon
Res: Res: Res:

CHB Walls & Plastering


Start: Thu 29/03/18 ID: 11
Finish: Wed 18/07/18Dur: 4 mons
Res:

Floor Finishes
Start: Thu 19/07/18 ID: 16
Finish: Wed 10/10/18Dur: 3 mons
Res:

Page 5
Page 6
Page 7
Pumps and Tanks Service Entrace/Feeder Line
Start: Thu 16/08/18 ID: 22 Start: Thu 08/11/18 ID: 24
Finish: Wed 07/11/18Dur: 3 mons Finish: Wed 05/12/18Dur: 1 mon
Res: Res:

Site Development
Start: Thu 08/11/18 ID: 27
Finish: Wed 27/02/19Dur: 4 mons
Res:

Doors and Windows


Start: Thu 11/10/18 ID: 17
Finish: Wed 30/01/19Dur: 4 mons
Res:

Carpentry Works
Start: Thu 11/10/18 ID: 18
Finish: Wed 27/02/19Dur: 5 mons
Res:

Page 8
Lighting Fixtures, Panel Board, Devices
Start: Thu 11/10/18 ID: 25
Finish: Wed 05/12/18Dur: 2 mons
Res:

Page 9
Critical Critical Summary Critical Marked Project Summary

Noncritical Summary Marked Highlighted Critical


Project: cpm
Date: Thu 11/10/18 Critical Milestone Critical Inserted Critical External Highlighted Noncritical

Milestone Inserted External

Page 10