0% found this document useful (0 votes)
114 views

Boiler 1 Boiler 2 ESP Switchyard: DAILY QC-Mech Report Dated: Sr. Steel Structure Erected Welded Joints UT Remarks

This daily mechanical report provides status updates on steel structures erected at a site, including two boilers, an electrostatic precipitator, and a switchyard. It also details the number of welded joints on those structures, non-destructive testing methods used, and any repairs needed. Welder qualifications and rejections are noted at the end.

Uploaded by

Umair Awan
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
114 views

Boiler 1 Boiler 2 ESP Switchyard: DAILY QC-Mech Report Dated: Sr. Steel Structure Erected Welded Joints UT Remarks

This daily mechanical report provides status updates on steel structures erected at a site, including two boilers, an electrostatic precipitator, and a switchyard. It also details the number of welded joints on those structures, non-destructive testing methods used, and any repairs needed. Welder qualifications and rejections are noted at the end.

Uploaded by

Umair Awan
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

DAILY QC- Mech Report Dated:

Sr. Steel Structure Erected Welded Joints UT Remarks

Boiler 1
Boiler 2
ESP
Switchyard

Boiler No. of Joint Welded RT Repair


Boiler 1
Boiler 2

Demin Water Storage No. of Joint Welded RT Repair

WQT Conducted
Welder Qualified
Welder Rejected