Daily Report of Engineering Supervision: 0024 Date
The daily engineering report summarizes construction progress for March 8, 2018. It notes sunny morning weather transitioning to rain in the afternoon with fine conditions at night. Planned versus actual construction progress percentages are provided along with notes on site conditions, supervision of work, material specifications and quality control, and any notifications to contractors.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
31 views
Daily Report of Engineering Supervision: 0024 Date
The daily engineering report summarizes construction progress for March 8, 2018. It notes sunny morning weather transitioning to rain in the afternoon with fine conditions at night. Planned versus actual construction progress percentages are provided along with notes on site conditions, supervision of work, material specifications and quality control, and any notifications to contractors.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2
DAILY REPORT OF ENGINEERING SUPERVISION
Serial No.: 0024
Today Weather: Morning: Sunny Afternoon: Rain Date: 08March-2018 Night: Fine Construction Commencement Completion Date Actual period days Date (planned) completion Date Original: Change Order No. Extension period days Contract Planned Construction Actual Construction Price After change: Progress (%) Progress (%) 1. Present Site Conditions(including major work items and Quantities):
2. Supervision on Construction Work (including checking point, construction inspection , etc.):
3. Specification and Quality of Material (including checking point, material and equipment control point, inspection and sampling, etc.):
4.Other items(including, notification to the Contractor):