Contractor: Client:: Project Title

This document is an inspection and test plan (ITP) for internal painting works. It outlines the main activities to be inspected, including surface preparation, primer application, and paint application. It specifies the inspection points, acceptance criteria, responsible parties and required documentation for each activity. Key activities include verifying approvals of methods, materials, drawings and clearances before work begins and conducting visual inspections before and after surface preparation to ensure specifications are met. The ITP is intended to ensure quality control and compliance with specifications for the internal painting project.

Uploaded by

Prasanna Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
404 views2 pages

Contractor: Client:: Project Title

This document is an inspection and test plan (ITP) for internal painting works. It outlines the main activities to be inspected, including surface preparation, primer application, and paint application. It specifies the inspection points, acceptance criteria, responsible parties and required documentation for each activity. Key activities include verifying approvals of methods, materials, drawings and clearances before work begins and conducting visual inspections before and after surface preparation to ensure specifications are met. The ITP is intended to ensure quality control and compliance with specifications for the internal painting project.

Uploaded by

Prasanna Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Client: Contractor: ITP Reference Number:

Project Title: Inspection and Test Plan for: Rev: 0

CONTRACT NO:
INTERNAL PAINTING WORKS Date:
Location:
Legends: ITL= Independent Testing Laboratory, SUB-CON= Sub-Contractor, ITP= Inspection Points: H= Hold Point, W= Witness Point, R=
Inspection and Test Plan, CI= Comments Incorporated, IR-Inspection Request Review Point, S= Surveillance, A=Approval

Inspection Points
Item Inspection and Test Specification
Activity Description Frequency Acceptance Criteria CONTRACT OWNER/EN Verifying Document / Report
No. Activity Reference SUB-CON
OR
ITL
GINEER

1 Method Statement
Approval of Method Method Statement Comment
1.1 Verrify Approval Before work Approval from NG TES-H-107-01 -- H -- R
Statement sheets
1.2 Test Reports Not Applicable Not Applicable Not Applicable - -- -- -- -- Not Applicable
2 Approval of Material
2.1 Paint Verrify Approval Before work Approval from NG - -- H -- R Verify approved Submittal
Verify the source and
2.2 Supplier Before work Approval from NG - -- H -- R Verify approved Submittal
approval.
Material Submittal form/
2.3 Material Verrify Approval Before work Approval from NG -- H R
Comment sheet
2.4 Accessories Before work Approval from NG -- S -- R
3 Prior Activities
Drawings Submittal Form/
3.1 Approved Drawings Verify the Approval Approval from NG - -- H -- R
Comment sheet
3.2 Material Stacking Visual inspection Approval from NG 7.1 of TES-H-107-01 -- S -- W

Identification, location and Before work Every existing service has to be correctly
3.4
protection of existing services
Verify location
located and protected prior to block work
Not Applicable -- H -- R Not Applicable

Obtain clearance for NOC from all concern MEP


3.5 Clearance
Painting
All concern agency to give Clearance on IR .. -- H -- A
agencies

Page 1
Client: Contractor: ITP Reference Number:

Project Title: Inspection and Test Plan for: Rev: 0

CONTRACT NO:
INTERNAL PAINTING WORKS Date:
Location:
Legends: ITL= Independent Testing Laboratory, SUB-CON= Sub-Contractor, ITP= Inspection Points: H= Hold Point, W= Witness Point, R=
Inspection and Test Plan, CI= Comments Incorporated, IR-Inspection Request Review Point, S= Surveillance, A=Approval

Inspection Points
Item Inspection and Test Specification
Activity Description Frequency Acceptance Criteria CONTRACT OWNER/EN Verifying Document / Report
No. Activity Reference SUB-CON
OR
ITL
GINEER

4 Main Activities
Before & after As per Contract Specification for Civil 6.2.3 of TES-H-107-
4.1 Surface Preperation Visual Inspection -- S -- R By NG Consultant
Work Construction Works. 01
As per Contract Specification for Civil As Per Approved
4.2 Primer Applicaion Verify the Approval Before Work -- H -- A By NG Consultant
Construction Works. Drawing
Before & after As per Contract Specification for Civil
4.3 Filler Application Verify the Approval TES-H-107-01 -- H -- R By NG Consultant
Work Construction Works.
As per Contract Specification for Civil
4.4 Primer Applicaion Verify the Approval Before work TES-H-107-01 -- H -- A By NG Consultant
Construction Works.
Before & after As per Contract Specification for Civil
4.5 Mixing Paint Verify the Approval 7.2/TES-H-107-01 -- S -- H By NG Consultant
Work Construction Works.
Before & after As per Contract Specification for Civil
4.6 Emulsion Paint Visual Inspection TES-H-107-02 S S -- A By NG Consultant
Work Construction Works.
ITP SIGN OFF – POST COMPLETION OF WORKS

FOR FOR FOR NG CONSULTANT

SIGN: SIGN: SIGN:

NAME: NAME: NAME:

DATE: DATE: DATE: