Schedule Margin Key in Produc
Schedule Margin Key in Produc
2) if I have key where floats before prodution is 5 days and same values in next floats and in house
production time as 1 day.
All above with MTO what is impact of above cases in scheduling.
While "Basic Scheduling" in MRP... Scheduling margin key is not considered. It takes the "In house
production" days for fixing up the start date. This is only exact to "days".
Lead Time scheduling is carried out on request from the scope of MRP. Target dates are calculated from
routing and Capacity requirement calculations are also done. The calculations are exact to the seconds
(time).
SCHEDULING MARGIN KEY takes effect only for Lead Time Scheduling. For this you have to configure for
"scheduling horizon" to limit the period for which lead time scheduling and capacity planning should be
carried out. scheduling horizon is the period in working days. If a planned order has its basic start date
within this period in future, lead time scheduling is carried out using the selected routing. The production
times are calculated from the float times of the scheduling margin key in the material master record and the
time from the individual operations. If the planned order has its basic start date further in the future than this
scheduling horizon, the basic dates are calculated from the in-house production times in the material
master and are transferred to the production times.
Could you explain what's function of opening period in Sched Margin key.
Opening period is like a "release window". The length of the opening period is the window of opportunity a
planner has to convert the planned order to a purchase req.
For example - Component A has a lead time of 14 days and opening period of 5 days. Requirement on 12-
22-03
Now the planner can convert the order starting Dec. 1st, instead of Dec. 8. It basically is a buffer in the lead
time to get things on order a little sooner than needed.
As your example,
Requirement on 12-22-03
http://www.sap-img.com/production/schedule-margin-key-in-production-scheduling.htm 5/9/2008
Schedule Margin Key in Production Scheduling Page 2 of 3
Opening Date - 12-01-03
Start Date - 12-08-03
Finish Date - 12-22-03
But I can convert plan order to production before 12-01-03 at random, so I wonder what is the
opening period real function? it looks useless to restrict when to convert plan order to production
order.
CO41 and MD15 are used for the conversion process. Here you enter the opening dates you wish to
convert. Of course the opening period will not stop you from converting planned orders - hopefully your
planner is not randomly converting orders or you have much bigger issues!!!!
The opening period is basically just to get the planned order to show up on the CO41 or MD15 lists in case
you wish to convert it sooner than the lead time suggests.
For example - Component A has a lead time of 14 days and opening period of 5 days. Requirement
on 12-22-03
Opening Date - 12-01-03 ???
Start Date - 12-08-03 (from requirement date - lead time ?)
Finish Date - 12-22-03 (from requirement date ?)
Why Openning date = 12/01/2003 how system calculate , Could you please explain to me..
I know that when we run MRP system will check if the opening date is out of open period system
will generate Plan order instead of PR .
The times in the sch. margin key are in workdays. That's how it gets the dates. The component I was
describing originally would have been a purchased part, where lead time is in calendar days.
The order start date and the order finish date form the framework within which a production order is to be
executed. Since malfunctions and disturbances in the production process can never be fully prevented, the
system uses particular floats in a production order. The system takes into account so-called "before and
after production floats" when scheduling an order.
The floats before and after production are defined for each material using a scheduling margin key. This
scheduling margin key is automatically transferred from the material master when an order is created.
However, you can change the times in the order.
http://www.sap-img.com/production/schedule-margin-key-in-production-scheduling.htm 5/9/2008
Schedule Margin Key in Production Scheduling Page 3 of 3
The system calculates the scheduled start of the order by adding the float before production to the order
start date. It calculates the scheduled finish of the order by subtracting the float after production from the
order finish date.
The system deducts the number of days defined in the release period from the scheduled start of the order
and thus determines the scheduled release date of the order. This date can be used for collective release.
Sch. Lines
What Is Mean By Schedule Lines
SAP PP Books
SAP Production Planning and Control Certification, Interview Questions and Configuration Reference
Books
Ads by Google Production Scheduling Planning Scheduling Manufacturing Schedule Project Planning
SAP PP Tips
SAP PP Tips and Production Planning/Control Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.sap-img.com
All the site contents are Copyright © www.sap-img.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies. The site www.sap-img.com is in no way affiliated with SAP
AG.
Every effort is made to ensure the content integrity. Information used on this site is at your own risk.
The content on this site may not be reproduced or redistributed without the express written permission of
www.sap-img.com or the content authors.
http://www.sap-img.com/production/schedule-margin-key-in-production-scheduling.htm 5/9/2008
This document was created with Win2PDF available at http://www.win2pdf.com.
The unregistered version of Win2PDF is for evaluation or non-commercial use only.
This page will not be added after purchasing Win2PDF.