Be It Enacted by The Senate and Hose of Representatives of The Philippines in Congress Assembled
Be It Enacted by The Senate and Hose of Representatives of The Philippines in Congress Assembled
9184 January 10, 2003 (a) Approved Budget for the Contract (ABC) - refers to the
budget for the contract duly approved by the Head of the
Procuring Entity, as provided for in the General
AN ACT PROVIDING FOR THE MODERNIZATION,
Appropriations Act and/or continuing appropriations, in the
STANDARIZATION AND REGULATION OF THE PROCUREMENT
National Government Agencies; the Corporate Budget for
ACTIVITIES OF THE GOVERNMENT AND FOR OTHER PURPOSES
the contract approved by the governing Boards, pursuant to
E.O.No.518, series of 1979, in the case of Government
Be it enacted by the Senate and Hose of Representatives of the Financial Institutions and State Universities and Colleges;
Philippines in Congress assembled: and the Budget for the contract approved by the respective
Sanggunian, in the case of Local Government Units.
ARTICLE 1
GENERAL PROVISIONS (b) BAC - refers to the Bids and Awards Committee
established in accordance with Article V of this Act.
Section 1. Short Title.- This act shall be known as the " Government
Procurement reform Act." (c) Bidding Documents - refer to documents issued by the
Procuring Entity as the basis for Bids, furnishing all
information necessary for a prospective bidder to prepare a
Section 2. Declaration of Policy.- It is the declared policy of the State
bid for the Goods, Infrastructure Projects, and Consulting
to promote the ideals of good governance in all its branches, Services to be provided.
departments, agencies, subdivisions, and instrumentalities, including
government-owned and/or -controlled corporations and local
government units. (d) Bid - refers to signed offer or proposal submitted by a
supplier, manufacturer, distributor, contractor or consultant in
response to the Bidding Documents.
Section 3. Governing Principles on Government Procurement.
Section 22. Pre-bid Conference. - At least one pre-bid conference A bidder may, through a letter, withdraw his bid or express his intention
shall be conducted for each procurement, unless otherwise provided in not to participate in the bidding before the deadline for the receipt of
the IRR. Subject to the approval of the BAC, a pre-bid conference may bids. In such case, he shall no longer be allowed to submit another Bid
also be conducted upon the written request of any prospective bidder. or the same contract either directly or indirectly.
The Pre-bid conference(s) shall be held within a reasonable period Section 27. Bid Security. - All Bids shall be accompanied by a Bid
before the deadline for receipt of the bids to allow prospective bidders security, which shall serve as guarantee that, after receipt of the Notice
to adequately prepare their bids, which shall be specified in the IRR. of Award, the winning bidders shall enter into contract with the
Procuring Entity within the stipulated time and furnish the required
performance security. The specific amounts and allowable forms of the
ARTICLE VIII
Bid security shall be prescribed in the IRR.
RECEIPT AND OPENING OF BIDS
Section 28. Bid Validity. - Bids and Bid securities shall be valid for
Section 23. Eligibility Requirements for the Procurement of Goods and
such reasonable period of time indicated in the Bidding Documents.
Infrastructure Projects.- The BAC or, under special circumstances
The duration for each undertaking shall take into account the time
specified in IRR, its duly designated organic office shall determine the
involved in the process of Bid evaluation and award of contract.
eligibility of prospective bidders for the procurement of Goods and
Infrastructure Projects, based on the bidders' compliance with the
eligibility requirements within the period set forth in the Invitation to Bid. Section 29. Bid Opening. - the BAC shall publicly open all bids at the
The eligibility requirements shall provide for fair and equal access to all time, date, and place specified in the bidding documents. The minutes
prospective bidders. The documents submitted in satisfaction of the of the bid opening shall be made available to the public upon written
eligibility requirements shall be made under oath by the prospective request and payment of a specified fee.
bidder or by his duly authorized representative certifying to the
correctness of the statements made and the completeness and
ARTICLE IX
authenticity of the documents submitted.
BID EVALUATION
The Procuring Entity shall issue the Notice to Proceed to the winning
In all cases, the contract shall be awarded only to the bidder with the
bidder not later than seven (7) calendar days from the date of approval
Lowest Calculated Responsive Bid or Highest Rated Responsive Bid.
of the contract by the appropriate authority. All notices called for by the
terms of the contract shall be effective only at the time of receipt
Section 35. Failure of Bidding. - there shall be a failure of bidding if: thereof by the contractor.
a. No bids are received; Section 38. Period of Action on Procurement Activities. - The
procurement process from the opening of bids up to the award of
contract shall not exceed three (3) months, or a sho0rter period to be
b. No bid qualifies as the Lowest Calculated Responsive Bid;
determined by the procuring entity concerned. Without prejudice to the
or,
provisions of the preceding section, the different procurement activities
shall be completed within reasonable periods to be specified in the
c. Whenever the bidder with the highest rated/lowest IRR.
calculated responsive bid refuses, without justifiable cause to
accept the award of contract, as the case may be.
If no action on the contract is taken by the head of the procuring entity
or by his duly authorized representative, or by the concerned board, in
Under any of the above instances, the contract shall be re-advertised the case of government-owned and/or -controlled corporations, within
and re-bid. The BAC shall observe the same process and set the new the periods specified in the preceding paragraph, the contract
periods according to the same rules followed during the first bidding. concerned shall be deemed approved.
After the second failed bidding, however, the BAC may resort to
negotiated procurement as provided for in Section 53 of this Act.
Section 39. Performing Security. - Prior to the signing of the contract,
the winning bidder shall, as a measure of guarantee for the faithful
Section 36. Single Calculate/Rated and Responsive Bid Submission. - performance of an compliance with his obligations under the contract
A single calculated/rated and responsive bid shall be considered for prepared in accordance with the Bidding Documents, be required to
award if it falls under of the following circumstances: post a performance security in such form and amount as specified in
the Bidding Documents.
a. If after advertisement, only one prospective bidder submits
a Letter of Intent and/or applies for eligibility check, and Section 40. Failure to Enter into Contract and Post Performance
meets the eligibility requirements or criteria, after which it Security. - If, for justifiable causes, the bidder with the Lowest
submits a bide, which is found to be responsive to the Calculated Responsive Bid or Highest Rated Responsive Bid fails,
bidding requirements; refuses or is otherwise unable to enter into contract with the Procuring
Entity, or if the bidder fails to post the required performance security
within the period stipulated in the Bidding Documents, the BAC shall
b. If after the advertisement, more than one prospective disqualify the said bidder and shall undertake post-qualification for the
bidder applies for eligibility check, but only one bidder meets next-ranked Lowest Calculated Bid or Highest Rated Bid. This
the eligibility requirements or criteria, after which in submits a
procedure shall be repeated until an award is made. However, if no
bid which is found to be responsive to the bidding award is possible, the contract shall be subjected to a new bidding.
requirements; or
c. For any justifiable and reasonable ground where the Section 48. Alternative Methods. - Subject to the prior approval of the
award of the contract will not redound to the benefit of the Head of the Procuring Entity or his duly authorized representative, and
government as defined in the IRR. whenever justified by the conditions provided in this Act, the Procuring
Entity may, in order to promote economy and efficiency, resort to any
of the following alternative methods of Procurement:
Section 42. Contract Implementation and Termination. - The rules and
guidelines for the implementation and termination of contracts awarded
pursuant to the provisions of this Act shall be prescribed in the IRR. a. Limited Source Bidding, otherwise known as Selective
The rules and guidelines shall include standard general and special Bidding - a method of Procurement that involves direct
conditions for contracts. invitation to bid by the Procuring Entity from a set of pre-
selected suppliers or consultants with known experience and
proven capability relative to the requirements of a particular
ARTICLE XII
contract;
DOMESTIC AND FOREIGN PROCUREMENT
c. Except in special circumstances defined in the IRR the Section 54. Terms and Conditions for the use of Alternative Methods. -
repeat order shall be availed of only within six (6) months The specific terms and conditions, including the limitations and
from the date of the Notice to Proceed arising from the restrictions, for the application of each of the alternative methods
original contract; and, mentioned in this Article shall be specified in the IRR.
d. The repeat order shall not exceed twenty-five percent ARTICLE XVII
(25%) of the quantity of each item of the original contract. PROTEST MECHANISM
Section 52. Shopping. - shopping may be resorted to under any of the Section 55. Protests on Decisions of the BAC.- Decisions of the BAC
following instances: in all stages of procurement may be protested to the head of the
procuring entity and shall be in writing. Decisions of the BAC may be
protested by filing a verified position paper and paying a non-
a. When there is an unforeseen contingency requiring refundable protest fee. The amount of the protest fee and the periods
immediate purchase: Provided, however, That the amount during which the protests may be filed and resolved shall be specified
shall not exceed Fifty thousand pesos (P50,000); or in the IRR.
b. Procurement of ordinary or regular office supplies and Section 56. Resolution of Protests. - The protest shall be resolved
equipment not available in the Procurement Service strictly on the basis of records of the BAC. Up to a certain amount to be
involving an amount not exceeding Two hundred fifty specified in the IRR, the decisions of the Head of the Procuring Entity
thousand pesos (P250,000): Provided, however, That the
shall be final.
Procurement does not result in Splitting of Contracts:
Provided, further, That at least three (3) price quotations
from bona fide suppliers shall be obtained. Section 57. Non-interruption of the Bidding Process.- In no case shall
any protest taken from any decision treated in this Article stay or delay
the bidding process. Protests must first be resolved before any award
The above amounts shall be subject to a period review by the GPPB. is made.
For this purpose, the GPPB shall be authorized to increase or
decrease the said amount in order to reflect changes in economic
conditions and for other justifiable reasons. Section 58. Report to Regular Courts; Certiorari.- Court action may be
resorted to only after the protests contemplated in this Article shall
have been completed. Cases that are filed in violation of the process
Section 53. Negotiated Procurement. - Negotiated Procurement shall
specified in this Article shall be dismissed for lack of jurisdiction. The
be allowed only in the following instances: regional trial court shall have jurisdiction over final decision of the head
of the procuring entity. Court actions shall be governed by Rule 65 of
a. In case of two (2) failed bidding as provided in Section 35 the 1997 Rules of Civil Procedure.
hereof;
This provision is without prejudice to any law conferring on the
b. In case of imminent danger to life or property during a Supreme court the sole jurisdiction to issue temporary restraining
state of calamity, or when time is of the essence arising from orders and injunctions relating to Infrastructure Projects of
natural or man-made calamities or other causes where Government.
immediate action is necessary to prevent damage to or loss
of life or property, or to restore vital public services, ARTICLE XVIII
infrastructure facilities and other public utilities; SETTLEMENT OF DISPUTES
c. Take-over of contracts, which have been rescinded or Section 59. Arbitration. - Any and all disputes arising from the
terminated for causes provided for in the contract and
implementation of a contract covered by this Act shall be submitted to
existing laws, where immediate action is necessary to arbitration in the Philippines according to the provisions of Republic Act
prevent damage to or loss of life or property, or to restore No. 876, otherwise known as the "Arbitration Law": Provided, however,
vital public services, infrastructure facilities and other public
That, disputes that are within the competence of the Construction
utilities; Industry Arbitration Commission to resolve shall be referred thereto.
The process of arbitration shall be incorporated as a provision in the
d. Where the subject contract is adjacent or contiguous to an contract that will be executed pursuant to the provisions of this Act:
on-going infrastructure project, as defined in the IRR: Provided, That by mutual agreement, the parties may agree in writing
Provided, however, That the original contract is the result of to resort to alternative modes of dispute resolution.
Section 60. Appeals. - The arbitral award and any decision rendered in Procurement operations manual for all offices and agencies of
accordance with the foregoing Section shall be appealable by way of a government; and (d) conduct an annual review of the effectiveness of
petition for review to the Court of Appeals. The petition shall raise pure this Act and recommend any amendments thereto, as may be
questions of law and shall be governed by the Rule of Court. necessary.
ARTICLE XIX The GPPB shall convene within fifteen (15) days from the effectivity of
CONTRACT PRICES AND WARRANTIES this Act formulate the IRR and for other related purposes. The GPPB
shall be supported by a technical support office.
Section 61. Contract Prices. - For the given scope of work in the
contract as awarded, all bid prices shall be considered as fixed prices, In addition to the powers granted under this Act, the GPPB shall
and therefore not subject to price escalation during contract absorb all the powers, function and responsibilities of the Procurement
implementation, except under extraordinary circumstances and upon Policy Board created under Executive Order No. 359, series of 1989.
prior approval of the GPPB. All affected functions of the Infrastructure Committee of the National
Economic and Development Authority Board are hereby transferred to
the GPPB.
For purposes of this Section, "extraordinary circumstances" shall refer
to events that may be determined by the National Economic and
Development Authority in accordance with the Civil Code of the Section 64. Membership. - The GPPB shall be composed of the
Philippines, and upon the recommendation of the procuring entity Secretary of the Department of Budget and Management, as
concerned. Chairman, the Director-General of the National Economic and
Development Authority, as Alternate Chairman, with the following as
Members; the Secretaries of the Departments of Public Works and
Section 62. Warranty. - (a) For the procurement of Goods, in order to
Highways, Finance, Trade and Industry, Health, National Defense,
assure that manufacturing defects shall be corrected by the supplier,
Education, Interior and Local Government, Science and Technology,
manufacturer, or distributor, as the case maybe, for a specific time
Transportation and Communications, and Energy, or their duly
after performance of the contract, a warranty shall be required from the
authorized representatives and a representative from the private sector
contract awardee for such period of time as may be provided in the
to be appointed by the President upon the recommendation of the
IRR, the obligation for which shall be covered by either retention
GPPB. The GPPB may invite a representative from the Commission on
money in the amount equivalent to a percentage of every progress
Audit to serve as a resource person.
payment, or a special bank guarantee equivalent to a percentage of
the total contract price, to be provided in the IRR. The said amounts
shall only be released after the lapse of the warranty period, provided ARTICLE XXI
that the Goods supplied are free from defects and all the conditions PENAL CLAUSE
imposed under the contract have been fully met.
Section 65. Offenses and Penalties. - (a) Without prejudice to the
b. For the procurement of infrastructure projects, the provisions of Republic Act No. 3019, otherwise known as the "Anti-
contractor shall assume full responsibility for the contract Graft and Corrupt Practice Act" and other penal laws, public officers
work from the time project construction commenced up to a who commit any of the following acts shall suffer the penalty of
reasonable period as defined in the IRR taking into imprisonment of not less than six (6) years and one (1) day, but not
consideration the scale and coverage of the project from its more than fifteen (15) years:
final acceptance by the government and shall be held
responsible for any damage or construction or works except
1. Open any sealed Bid including but not limited to
those occasioned by force majeure. The contractor shall be
Bids that may have been submitted through the
fully responsible for the safety, protection, security, and
electronic system and any and all documents
convenience of his personnel, third parties, and the public
required to be sealed or divulging their contents,
large, as well as the works, equipment, installation and the
prior to the appointed time for the public opening
like to be affected by his construction work and shall be
of Bids or other documents.
required to put up a warranty security in the form of cash,
bank guarantee, letter of credit, Government Service
Insurance System bond, or callable surety bond. 2. Delaying, without justifiable cause, the
screening for eligibility, opening of bids, evaluation
and post evaluation of bids, and awarding of
The contractor shall undertake the repair works, at his own expense, of
contracts beyond the prescribed periods of Bids or
any defect or damage to the infrastructure projects on account of the
other documents.
use of materials of inferior quality within ninety (90) days from the time
the Head of the Procuring Entity has issued an order to undertake
repair. In case of failure or refusal to comply with this mandate, the 3. Unduly influencing or exerting undue pressure
governments shall undertake such repair works and shall be entitle to on any member of the BAC or any officer or
full reimbursement of expenses incurred therein upon demand. employee of the procuring entity to take a
particular bidder.
Any contractor who fails to comply with the preceding paragraphs shall
suffer perpetual disqualification from participating in any public bidding 4. Splitting of contracts which exceed procedural
and his property or properties shall be subject to attachment or purchase limits and competitive bidding.
garnishment proceedings to recover the costs. All payables of
government in his favor shall be offset to recover the costs.
5. When the head of the agency abuses the
exercise of his power to reject any and all bids as
ARTICLE XX mentioned under Section 41 of this Act with
THE GOVERNMENT PROCUREMENT POLICY BOARD manifest preference to any bidder who is closely
related to him in accordance with Section 47 of
this Act.
Section 63. Organization and Functions. - A Government Procurement
Policy Board (GPPB) is hereby established to: (a.) protect national
interest in all matters affecting public Procurement, having due regard When any of the foregoing acts is done in collusion with
to the country's regional and international obligations; (b.) formulate private individuals, the private individuals shall likewise be
and amend, whenever necessary, the IRR and the corresponding liable for the offense.
standard forms for Procurement; (c) ensure that Procuring Entities
regularly conduct Procurement training programs and prepare a
In addition, the public officer involved shall also suffer the not limited to, performance security, preparatory to
penalty of temporary disqualification from public office, while the final award of the contract.
the private individual shall be permanently disqualified from
transacting business with the government.
(d) When the bidder is a juridical entity, criminal liability and
the accessory penalties shall be imposed on its directors,
(b) Private individuals who commit any of the following acts, officers or employees who actually commit any of the
including any public officer, who conspires with them, shall foregoing acts.
suffer the penalty of imprisonment of not less than six (6)
years and one (1) day but not more than fifteen (15) years:
Section 66. Jurisdiction. - Jurisdiction over the offenses defined under
this Article shall belong to the appropriate courts, according to laws
1. When two or more bidders agree and submit existing at the time of the commission of the offenses.
different Bids as if they were bona fide, when they
knew that one or more of them was so much
ARTICLE XXII
higher than the other that it could not be honestly
CIVIL LIABILITY
accepted and that the contract will surely be
awarded to the pre-arranged lowest Bid.
Section 67. Civil Liability in Case of Conviction. - Without prejudice to
administrative sanctions that may be imposed in proper cases, a
2. When a bidder maliciously submits different
conviction under this Act or Republic Act No. 3019 shall carry with it
Bids through two or more persons, corporations,
civil liability, which may either consist of restitution for the damage
partnerships or any other business entity in which
done or the forfeiture in favor of the government of any unwarranted
he has interest of create the appearance of
benefit derived from the act or acts in question or both, at the discretion
competition that does not in fact exist so as to be
of the courts.
adjudged as the winning bidder.
The members of the BAC and the BAC Secretariat shall also be
entitled to medical assistance for injuries incurred in the performance
of their functions.
ARTICLE XXV
FINAL PROVISIONS