Test Methods For Driven Piles
Test Methods For Driven Piles
Piles
on April 6, 2017
Click to share on Facebook (Opens in new window)
Click to share on LinkedIn (Opens in new window)
Click to share on Twitter (Opens in new window)
More
More in Engineering:
The hydraulic jack and the load cell should both feature a spherical head and be
calibrated by a qualified individual. The jack and cells should also be read, compared,
and continually monitored throughout testing in order to ensure a load increment is
being maintained at a constant value.
Jacking against reaction piles is the most economical method, with the load in these
piles limited to 25 to 50 percent of the test pile’s load. Reaction piles must be located a
minimum of five feet from the tested pile, with provisions made to detect any upward
movement. For modest loads, wood reaction piles cabled together, with a test beam
running below the cables, should be considered.
Jacking against a dead load platform represents another preferred method, so long as
an adequate amount of dead load is available. To avoid tipping, contractors must allow
for at least 15 percent of additional dead load over the required load.
Applying a dead load directly to a pile was at one time a commonly used method. This
option is still applicable in situations where the total load is moderate, with the load
applied once and then removed.
Methods aside, these procedures should be followed when applying a load to test piles:
Static: Known for providing accurate measurements, this test processes how a deep
foundation reacts to an applied load. This method can provide significant project cost
savings and is frequently utilized in the design of major structures where a host of
differently sized piles are installed.
Types of conventional static load tests include axial compressive, axial tensile, and
lateral loading.
While static load tests allow for a more rational foundation design and use a lower
factor of safety, the costs associated with conducting them can be a hindrance.
Additionally, if conducted during the design phase of a project, delays can result.
Axial Compressive: Known as a quick and simple method, this test is recommended
on highway projects, and requires that a test load of 300 percent of the design load be
applied in 10 to 15 percent increments. After a load is added, it is maintained constantly
for nearly three minutes prior to the next increment.
Typically, the test takes three to five hours, but it can be performed in several hours
under certain circumstances. Because of its quickness, the test may not provide
necessary time for soils or clays to consolidate, which can result in the settlement of
these soils being underestimated.
Constant Rate of Penetration: In this test, the load applied causes the pile head to
settle at a predetermined, constant rate – typically 0.01” to 0.1” per minute.
Like an axial compressive test, this procedure can be conducted in less than one
working day. Note that ordinary pumps used for standard load tests are difficult to utilize
when conducting this type of procedure.
Tension: This load test provides data on piles that function in tension or tension and
compression. Following installation, a. In cohesive soils, the waiting period should be a
minimum of 14 days.
This procedure allows for a direct comparison of tension and compression on the same
underground profile;
Tensile: Utilized for pile groups that are subjected to , this load test determines uplift
capacities of piles by loading the pile in tension. Determining pile uplift has in
importance as engineers and contractors place a larger focus on seismic design.
Tensile loads are typically applied by centering a hydraulic jack on top of a test beam.
The jack moves against a reaction frame that’s connected to the pile, with the test beam
supported by piles or cribbing. A quick loading tensile test requires that a load be
applied in increments of 10 to 15 percent, with a time interval of more than two minutes.
Lateral: Commonly conducted on projects where seismic and vessel impacts exist, this
applies a lateral load via a hydraulic jack, which acts against a reaction system. A
hydraulic jack acting between two piles can also apply a lateral load.
The typical loading procedure requires the total test load be 200 percent of the
proposed lateral design. Differing load increments are applied with the magnitude of the
increment decreasing. Upon completion, the pile is unloaded in four load decrements
equal to 25 percent of the maximum load. Each decrement occurs an hour apart from
the others.
Low Strain: Used to determine pile length or the integrity of piles with high impedance,
low-strain methods can test many piles in one day. Of note, this procedure is not used
for steel H-piles or non-concrete pipe piles.
Primarily, two low-strain methods are utilized: pulse echo pile testing and the transient
response method.
The pulse echo method applies a low-strain impact, via a handheld hammer, to the
head of a pile and monitors the resulting response. A temporarily attached
accelerometer records the response as the low-strain stress wave moves down the pile
length.
The transient response method measures both the pile head response and the impact
force. Like the pulse echo method, a handheld hammer can produce the necessary
frequency.