0% found this document useful (0 votes)
68 views8 pages

HT TP: //qpa Pe R.W But .Ac .In: 2013 Production & Operation Management

The document is a test paper containing multiple choice and short answer questions related to production and operation management. It includes 12 multiple choice questions testing concepts like economic order quantity, assembly line balancing, control charts, inventory carrying costs, Six Sigma, and critical path. It also includes 6 short answer or numerical questions requiring calculation of things like site selection factors, control chart parameters, optimal job sequencing, and material requirement planning.

Uploaded by

Rushi Roy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
68 views8 pages

HT TP: //qpa Pe R.W But .Ac .In: 2013 Production & Operation Management

The document is a test paper containing multiple choice and short answer questions related to production and operation management. It includes 12 multiple choice questions testing concepts like economic order quantity, assembly line balancing, control charts, inventory carrying costs, Six Sigma, and critical path. It also includes 6 short answer or numerical questions requiring calculation of things like site selection factors, control chart parameters, optimal job sequencing, and material requirement planning.

Uploaded by

Rushi Roy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Name : …………………………………………….

………………
htt
Roll No. : …………………………………………...……………..
Invigilator’s Signature : ………………………………………..

CS/MBA/SEM-2(FT)/MB-204/2013
p:/
2013
PRODUCTION & OPERATION MANAGEMENT
/q
Time Allotted : 3 Hours Full Marks : 70

The figures in the margin indicate full marks.


pap

Candidates are required to give their answers in their own words


as far as practicable.

GROUP – A
( Multiple Choice Type Questions )
er.

1. Choose the correct alternatives for any ten of the following :


10 × 1 = 10
i) Procurement cost ................... with the increase in
wb

inventory level.
a) decreases
b) increases
c) does not change
ut .

d) may increase or decrease.


ii) The economic order quantity for an item has been found
out to be 300. If 12000 items are required per annum
a c.

and the ordering cost is Rs. 20 per order, then the


annual procurement cost is
a) Rs. 1,200 b) Rs. 800
c) Rs. 1,800 d) Rs. 20.
in

25001 (MBA) [ Turn over


CS/MBA/SEM-2(FT)/MB-204/2013

iii) The main objective of assembly line balancing is


a) to reduce the work element time
htt
b) to combine all the work elements into one work
station
c) to reduce the total number of operations
p:/
d) to reduce the balance delay of the line.
iv) After inspection of 10 carpets, each of length 2 metres,
the following number of defects is found on each
carpet : 35, 32, 42, 56, 41, 26, 40, 33, 51, 39.
/q
The control chart suitable will be
a) R-chart
b) p-chart
pap
c) c-chart
d) a combination of R-chart and p-chart.
v) Batch Production is adopted when
a) volume is very large and variety is less
b) volume is small and variety is large
er.

c) both volume and variety are medium


d) all of these.
vi) Which of the following is not a component of inventory
wb

carrying cost ?
a) Capital cost b) Insurance cost
c) Obsolescence cost d) Transportation cost.
vii) In a situation of rising prices, the LIFO method of stock
ut .

valuation will have which of the following impacts ?


a) Inflated Profit b) Suppressed Profit
c) Unchanged Profit d) none of these.
a c.

viii) A Six Sigma process ensures not more than ..................


defects per million opportunities.
a) 2700 b) 4·3
c) 3·4 d) 99·73.
in

25001 (MBA) 2
CS/MBA/SEM-2(FT)/MB-204/2013

ix) Which one of the following statements best fits with


htt
'Kaizen' ?

a) Kaizen is a system of production management for


streamlining certain repetitive operations
p:/
b) Kaizen is a system of continuous improvement in
quality, technology, processes, company culture,
productivity, safety and leadership
/q
c) Kaizen is a tool for work study

d) none of these.
pap

x) Fishbone diagrams

a) show that the causes of a certain event are charts


which identify potential causes for particular
er.

quality problems

b) show cause and effect relationship with respect to


manufacturing activities only
wb

c) show the difference between actual and planned


performance flow chart

d) none of these.
ut .

xi) Examples of variable Control Chart are

a) X-bar, R-Chart & P-Chart


a c.

b) R-Chart, MA-Chart & C-Chart

c) P-Chart, C-Chart & U-Chart

d) X-Bar Chart, R-Chart & MA-Chart.


in

25001 (MBA) 3 [ Turn over


CS/MBA/SEM-2(FT)/MB-204/2013

xii) A critical path has


htt
a) zero float
b) longest activity duration
c) both (a) and (b)
p:/
d) none of these.
GROUP – B
( Short Answer Type Questions )
/q
Answer any three of the following. 3 × 5 = 15
2. What factors need to be considered for the selection of a site
pap
for a plant ?
3. State the objectives of Work Study.
4. Ten woolen carpets were studied critically for total number of
defects in their texture. The details of the number of defects
er.

in each carpet are given below :


Carpet
1 2 3 4 5 6 7 8 9 10
No.
No. of
wb

5 7 3 2 6 4 5 3 2 3
defects
Calculate the following for constructing a control chart for
number of defects :
(a) Central line, (b) Upper Control Limit (UCL), (c) Lower
ut .

Control Limit (LCL).


5. What do you understand by 'Material Requirement
Planning' ? How is it used in planning for materials ?
a c.

6. M/s. Raj Engineering Works, Durgapur has been given a


contract by Indian Railways to make seven components.
Each of these components require processing on two
in

25001 (MBA) 4
CS/MBA/SEM-2(FT)/MB-204/2013

machines M 1 and M 2 in the order M 1 , M 2 . The time


htt
required by each of these jobs for processing on two
machines is given below. Find the optimal sequence for
processing the seven jobs and calculate the waiting time for
p:/
jobs.
Job M1 M2

A 9 2
/q
B 5 4
C 8 10
D 3 5
pap

E 4 6
F 1 11
G 7 6
er.

GROUP – C
( Long Answer Type Questions )
Answer any three of the following. 3 × 15 = 45
7. a) What are the various costs associated with inventory
wb

management ?
b) Explain why ordering costs decrease with increase in
inventory.
c) A factory uses annually 24,000 units of raw material,
ut .

which cost Rs. 1·25 per unit. Placing each order costs
Rs. 25 and carrying cost is 6% per year of the average
inventory.
a c.

i) Find the economic order quantity and the total


inventory cost including the cost of material and
no. of orders to be placed for the above per year/or
how frequently should the order be placed ?
in

25001 (MBA) 5 [ Turn over


CS/MBA/SEM-2(FT)/MB-204/2013

ii) The factory works for 320 days a year. If the


htt
procurement time is 10 days and the safety stock
is 450 units, find the reorder point, the minimum,
maximum and average inventory. 5+4+6
p:/
8. a) What is ERP ? What are the benefits of ERP ?

b) Jobs A through E in the aircraft repair facility must


each pass through the Sheet Metal centre and then
/q
through Paint centre. The processing time for each job
in each centre is shown below. Find the sequence that
minimizes completion time of the job. Calculate the
pap

cumulative flow time and idle time.

PROCESSING TIME IN DAYS

Wc-1 Wc-2
Jobs
(Sheet metal centre) (Paint centre)
er.

A 4 5

B 17 7
wb

C 14 12

D 9 2
ut .

E 11 6

6+9
9. a) Explain Range Chart and its application in Quality
a c.

Control function.

b) Briefly justify relevance of Economic Order Quantity


(EOQ) in management of inventory.
in

25001 (MBA) 6
CS/MBA/SEM-2(FT)/MB-204/2013

c) A spare part "I-10" is produced by a water pump


htt
manufacturer from a local firm and the average usage
rate in pump manufacturing activity is 500 numbers
per month. Ordering cost of "I-10" is Rs. 36 per order
and the cost of holding this inventory is Rs. 1·20 per
p:/
piece per year.

i) Determine the quantity that should be procured at


/q
a time to optimize the total cost.

ii) If the usage of I-10 increases to 40 numbers per


day and inventory carrying cost becomes
pap

Re. 0·02 per unit per day, what will be the revised
EOQ ? (Assume : 300 days in a year.)

iii) From the sum, show that ordering cost is equal to


inventory holding cost in case of EOQ.
er.

iv) If the company maintains a safety stock of


1000 units, calculate total cost (ordering cost and
inventory carrying cost) with respect to (i) above.
wb

3+3+(2+3+2+2)

10. a) What do you mean by PERT in Project Analysis ?

b) What are the three time estimates related to PERT ?


ut .

c) Write down the difference between PERT and CPM.

d) A firm is considering the launch of a new product in the


a c.

national market. This project consists of ten major


activities. The firm does not have adequate prior
experience of similar project. The project is riddled with
in

considerable uncertainty due to political and public

25001 (MBA) 7 [ Turn over


CS/MBA/SEM-2(FT)/MB-204/2013

interference. The precedence relationship and the three


htt
possible time estimates of each activity are given in the
table below :

Most
Optimistic Pessimistic
Predecessor Likely
p:/
Activity Duration Duration
Activity Duration
(weeks) (weeks)
(weeks)
A None 2 4 6
B None 2 3 10
/q
C B 4 7 10
D A 4 5 12
E B 2 7 12
pap
F C, D 3 4 5
G C, D 6 8 10
H E, F 6 7 14
I G, H 2 3 16
i) Draw the network of the above project.
ii) What is the expected project completion time ?
er.

iii) Identify the critical activity and critical path.


iv) Determine the float of each activity.
2+1+2+(3+2+1+4)
wb

11. Write short notes on any three of the following : 3×5


a) PDCA cycle
b) Johnson's Rule
ut .

c) Critical path
d) Vendor Rating
e) Value Analysis.
a c.

=============