0% found this document useful (0 votes)
301 views

6 - ASurvey - Leveling Part 2 - Other Leveling Methods - 1730672714 PDF

Double-rodding leveling involves taking two sets of independent backsight and foresight readings at each instrument setup to provide continuous checking of elevations as work progresses. It is useful for differential leveling over short periods where no benchmarks exist. Three-wire leveling takes readings from three horizontal hairs for greater precision. Profile leveling determines elevations along a fixed line at intervals to design horizontal structures. Reciprocal leveling employs two instrument setups to reduce errors when sights are long between points across obstacles like rivers. Trigonometric leveling uses vertical angles and distances to indirectly determine elevation differences over rugged terrain for efficient topographic surveys.

Uploaded by

Chichi Channel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
301 views

6 - ASurvey - Leveling Part 2 - Other Leveling Methods - 1730672714 PDF

Double-rodding leveling involves taking two sets of independent backsight and foresight readings at each instrument setup to provide continuous checking of elevations as work progresses. It is useful for differential leveling over short periods where no benchmarks exist. Three-wire leveling takes readings from three horizontal hairs for greater precision. Profile leveling determines elevations along a fixed line at intervals to design horizontal structures. Reciprocal leveling employs two instrument setups to reduce errors when sights are long between points across obstacles like rivers. Trigonometric leveling uses vertical angles and distances to indirectly determine elevation differences over rugged terrain for efficient topographic surveys.

Uploaded by

Chichi Channel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 35

Double-Rodded

Leveling
Double-Rodded Leveling

A method of determining the differences in


elevation between points by employing two level
routes simultaneously
 Two turning points are established such that at
each set up of the leveling instrument, two sets of
independent backsights and foresights are taken
Double-Rodded Leveling

 Advantage: provide a continuous check on the


process of determining ground elevations while the
work is in progress
 Useful when there is an urgent need to undertake
differential leveling in a short period of time where
no established benchmarks are available for
checking results.
Illustrative Problem

 Complete the following differential level notes for a double-


rodded line from BM1 to BM2. Show the customary
arithmetic check.
STA BS HI FS ELEV
BM1 1.86 205.60m
1.86
TP1 H 2.15 1.10
L 2.52 1.58
TP2 H 1.40 1.79
L 1.76 2.27
TP3 H 0.33 2.99
L 0.74 3.41
BM2 2.63
2.63
Illustrative Problem

 Arithmetic Check
 1st Method  2nd Method
• Mean Elev BM2 = • Mean Elev BM2 = BM1 + [(ΣBS-ΣFS)/2]

• DE1 = (ΣBS-ΣFS)/2

• DE2 = BM1 – Mean Elev BM2


Three-Wire
Leveling
Three-Wire Leveling

 More precise method


 Method of determining the differences in elevation
wherein three horizontal hairs are read and
recorded rather than from a single horizontal hair
 Any level equipped with three horizontal cross
hairs can be used for three-wire leveling
Three-Wire Leveling

s = a-b
m = (a+b+c)/3
HD = Ks + C
Elev = HI - m

a = upper stadia hair reading


b = lower stadia hair reading
c = horizontal cross hair reading
s = stadia intercept
- difference between the upper
and lower stadia hair reading
m = mean of the three-hair readings
HD = horizontal distance from the level to
the rod
K = stadia interval factor (100)
C = instrument constant (0)
Illustrative Problem
BACKSIGHT FORESIGHT
STA HAIR MEAN HI HAIR MEAN ELEV
S S
RDGS RDG RDGS RDG
1.15
BM1 0.95 445.20
0.72
2.79 1.11
TP1 2.42 0.89
2.06 0.68
1.70 1.90
TP2 1.44 1.54
1.18 1.17
2.59 1.45
TP3 2.10 1.18
1.59 0.95
1.60
BM2 1.35
1.25
Illustrative Problem

 Arithmetic Check
 1st Method  2nd Method
• DE1 = (ΣBSm-ΣFSm)/2 • Elev BM2 = BM1 + ΣBS - ΣFS

• DE2 = Elev BM1 – Elev BM2


Profile Leveling
Profile Leveling

 The process of determining differences in elevation


along a fixed line at designated short measured
intervals
 Design and construction of roads, railroads, canals,
culverts, bridges, sewer lines (horizontal structures)
 Usually taken along the centerline with the level set up
a convenient distance away from it so that sights of
more uniform lengths can be obtained
Profile Leveling

 Any number of foresights can be taken

 Intermediate foresights are taken where necessary to


portray accurately the existing ground surface along the
route surveyed
Profile Leveling

 Profile
 A curved line which graphically portrays the intersection
of a vertical plane with the surface of the earth
 Represent the ground elevations of selected critical
points along a surveyed line and the horizontal distances
between these points
 Stationing
 A numerical designation given in terms of horizontal
distance any point along a profile line is away from the
starting point
Profile Leveling

 Intermediate foresights (ground rod readings)


 Taken along the centerline of the proposed project to
provide an accurate representation of the ground surface
 Full stations
 Points which are established along the profile level route
at uniformly measured distances
 Plus stations
 Points established along a profile level route which is not
designated as a full station
 Points taken at breaks in the ground surface slope and at
critical points (location of culverts, bridges)
Illustrative Problem

 A schematic arrangement of a profile level route from BM3 to BM4


are shown below. The values indicated represent backsight,
foresight, and intermediate foresight readings taken on stations
along the route. Prepare and complete profile level notes for the
portrayed information. Show the customary arithmetic check and
plot the profile. 2+00 HI
1+00 2

3+00

0+00
BM4

TP1
HI1
4+50 6+70
5+50
6+00
BM3
Elev 300.50m
Illustrative Problem
STA BS HI FS IFS ELEV
BM3 2.4 300.50m
0+00 1.5
1+00 2.0
2+00 1.3
3+00 0.7
TP1 2.55 3.2
4+50 2.8
5+50 3.5
6+00 4.5
6+70 3.95
BM4 3.3
Illustrative Problem
303

302
ELEVATION (m)

301

300

299

298
0+00 1+00 2+00 3+00 4+00
STATIONINGS
Illustrative Problem

 Arithmetic Check

• Elev BM4 = BM3 + ΣBS - ΣFS


Reciprocal Leveling
Reciprocal Leveling

 Employed to determine the difference in elevation


between two points when it is difficult or impossible
to keep backsights and foresights short and equal
 Such conditions are running a line of levels across
wide rivers, lakes, and rugged terrain (deep
canyons)
 Two sets of rod readings are observed (Method of
Reversion)
 One set taken with the instrument set up close to one
point and another instrument on the other
Reciprocal Leveling

 Errors due to refraction by the atmosphere,


curvature of the earth and faulty adjustment of the
instrument are significantly reduced if not
eliminated
Reciprocal Leveling

DE1 a  b
DE2  a'b'
Instrumental errors and the effect
of curvature and refraction DE1 DE2 (a  b)  (a'b' )
DE1 ≠ DE2, » » TDE  
2 2
*Note: If TDE is negative, A is higher than B;
If TDE is positive, B is higher than A.
Illustrative Problem

 In leveling across a deep and wide river, reciprocal level


readings were taken between two points, X and Y as
follows:
a. With instrument set up near X, the rod readings on X
are 1.27 and 1.265 meters; on the distant point Y, the
rod readings are 2.50, 2.52, 2.55, and 2.49 meters.
b. With instrument set up near Y, the rod readings on Y are
3.48 and 3.47 meters; on the distant point X, the rod
readings are 2.13, 2.14, and 2.145 meters.
Determine the true difference in elevation between the two
points and the elevation of Y if the known elevation of X
is 289.90meters.
Illustrative Problem

Elev=289.90m

Instrument Set up near X Instrument Set up near Y


STA BS FS STA BS FS
X 1.27 X’ 2.13
1.265 2.14
Y 2.50 2.145
2.52 Y’ 3.48
2.55
3.47
2.49
SUM
SUM
MEAN
MEAN
Trigonometric Leveling
Trigonometric Leveling

 “Indirect Leveling”
 Determine the difference in elevation from
observed vertical angle and either horizontal or
inclined distances
 Used extensively when undertaking topographic
surveys over rugged or rolling terrain since it
provides a rapid means of determining vertical
distances and elevation of points
Trigonometric Leveling

V  dTan DEab  dTan  HI  RR


V  sSin DEab  sSin  HI  RR
ElevB  ElevA  DEab
Trigonometric Leveling

 For horizontal distance is greater than 300 meters,


effects of the earth’s curvature and refraction must
be considered in the calculation of the vertical
distances.
d 2
DEab  dTan  HI  RR  0.0675( )
1000
d 2
DEab  sSin  HI  RR  0.0675( )
1000
Illustrative Problem

 A vertical angle of +13°45’ is read to a target


1.23m above point B. the measured inclined
distance, s, is 823.29m and the elevation of A is
123.65m above datum. If the HI at A is 1.35m,
determine the difference in elevation between A
and B and the elevation of B, considering the
effects of curvature and atmospheric refraction.
Illustrative Problem
Cross-Section
Leveling
CROSS-SECTION LEVELING

 Short profiles taken perpendicular to the centerline


of projects such as a highway, railroad, irrigation
canal, or sewer line
 They may also be taken for borrow pits and
excavations required for buildings, structures, and
quarries.

Roadway Cross-Sections
Borrow-Pit Cross Sections
ROADWAY CROSS-SECTION

 This type of cross-section is


required for most route
projects such as roads and
railroads.

 Elevations of ground points


along the section are taken at
regular intervals on either side.
Where significant changes
occur in ground features,
ground elevations are also
taken.
BORROW-PIT CROSS-SECTION
 Employed in the construction of structures and buildings,
and in the excavation of borrow pits.
 Borrow pit is an open area which is usually adjacent to a
construction project where suitable fill material is
excavated.

The base line from which the GL are


referred should be established outside the
immediate project area so that reference
stakes and other markers will not be
obliterated or disturbed during the process
of excavation.

Similarly, any reference bench mark should


also be located outside the work area.

You might also like