Construction of Sludge Drying Beds-Kokosi WWTW Project Inception Meeting Minutes 2
Construction of Sludge Drying Beds-Kokosi WWTW Project Inception Meeting Minutes 2
CONTRACT NO:
TIME: 9H00
Lebogang
Tlhatlhogi
LT MISA Intern 0786814961 Y Lebogang [email protected]
0119543835/
Cynthia Dlali CD Morad Consulting Civil Technician
0789554963
Y [email protected]
0119543835/
Michael Benhura MB Morad Consulting Project Manager
0815711367
Y [email protected]
0187889020/
Laetitia Joubert LJ Merafong CLM (PMU) Finance Officer
0826135511
Y [email protected]
Sekgatlane Merafong CLM (Solid
Mantjane
SM
Waste Dept)
Manager 0187889848 Y [email protected]
Manager CLM (Waste
Andre Loots AL
Water)
Manager 0827863686 Y [email protected]
PROJECT TEAM
3.1 Morad Consulting were appointed on two new projects namely: Note
- Construction of Sludge Drying Beds – Kokosi WWTW project and,
- Rehabilitation (Phase 2) – Carletonville Landfill Site
3.2.1 The Kokosi WWTW has an existing sludge drying bed of approximately 1 219 MB Oct 2017
square metres. The capacity of the drying bed area needs to be increased to a
total area of ±4 876 square metres by the construction of an additional three (3)
new drying beds with the same layout and method of operation as for the existing
drying beds.
Prepared By: Morad Consulting Engineers
All authorisations need to be in place.
3.2.2 MB Oct 2017
The existing sludge drying bed and WWTW was designed by Pro-Plan. Morad
3.2.3 can get hold of them to get information on the existing designs. MB Oct 2017
The tender document to include for extensive labour intensive work to maximise
3.2.5 the creation of EPWP work opportunities. MB Nov 2017
11 CLOSURE
At......................................................................................................................
............................................................................. ......................................................................................
FOR MERAFONG CITY LOCAL MUNICIPALITY MORAD CONSULTING