PV On Buildings and Fire Safety: Recommendation For DRRG Solar PV Systems
PV On Buildings and Fire Safety: Recommendation For DRRG Solar PV Systems
1 INTRODUCTION ............................................................................................................................................ 2
1.1 Scope ................................................................................................................................2
1.2 Definitions ................................................................................................................................2
1.3 Reference documents...................................................................................................................2
1 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
1 INTRODUCTION
1.1 Scope
This document contains special considerations and measures against fire hazard to be applied when PV plants are to
be mounted on buildings.
Fire hazard prevention is considered in view of the following:
Different types of buildings are considered as regards the fire hazard, and PV plants are basically divided into
externally-mounted (BAPV) and building-integrated (BIPV).
In this document the measures adopted in countries with a high PV penetration have been considered. Particularly
useful were the following: VDE-AR-E 2100-712 (Germany), Guida CEI 82-25 (Italy), UL 1699B (US).
1.2 Definitions
AC disconnector – Switch installed on an AC line that also complies with the requirements for a
disconnector.
DC disconnector – Switch installed on a DC line that also complies with the requirements for a
disconnector.
Building-attached photovoltaic (BAPV) – Photovoltaic modules are considered to be building attached, if the PV
modules are mounted on a building envelope and do not fulfill the criteria for building integration.
Inverter – Device which converts the direct current produced by the photovoltaic modules to
alternating current in order to deliver the output power to the grid. The inverter is also capable of controlling the
quality of this output power.
Photovoltaic (PV) system / Photovoltaic (PV) plant – assembly of components that produce and supply electricity
by the conversion of solar energy.
2 Shams Dubai -PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
2 PRELIMINARY FIRE SAFETY CONSIDERATIONS ON BUILDINGS
PV plants on buildings may have several possible placements, however, visible and exposed to sunrays.
According to the UAE FIRE & LIFE SAFETY CODE OF PRACTICE, buildings are divided into:
Lowrise Buildings: Occupancies or multiple and mixed occupancies, facilities, buildings and structures having
occupiable or usable floors at or up to 15 meters from the lowest grade or lowest level of Fire Service Access into that
occupancy.
Midrise Buildings: Occupancies or multiple and mixed occupancies, facilities, buildings and structures having
occupiable or usable floors between 15 meters to 23 meters from the lowest grade or lowest level of Fire Service
Access into that occupancy.
Highrise Buildings: Occupancies or multiple and mixed occupancies, facilities, buildings and structures having
occupiable or usable floors more than 23 meters above from the lowest grade or lowest level of Fire Service Access
into that occupancy.
Hazard content and hazard evaluation for the occupancies differ based on the material involved and its burning
characteristics. The owner, consultants and contractors are asked to submit details such as occupancy description,
operation and process involved and material usage in their occupancy for Civil Defence approval.
Most of the occupancies are basically categorized as Ordinary Hazard, where materials (paper, records, books,
computers, carpets, household plastic, home appliances, electronic and electrical office equipment, hospital
equipment, furniture, wood, bedding and upholstery) are likely to burn with moderate rapidity or to give off a
considerable volume of smoke.
Occupancies may also house other associated hazards, which fall into High Hazard category such as battery storage,
flammable liquids such as Diesel in generators, laboratory chemicals, cleaning solvents in storage rooms, and fuel
gas in kitchens and pantries.
Industrial and storage occupancies usually represent an Extra High Hazard with storage of rapidly burning and dense
smoke generating materials such as plastic, tyres, highly flammable liquids and gases, combustible dust, processes
and operations involving high temperatures and flames.
Multiple or mixed occupancies are combinations of various hazard content and hazard categories. Accordingly the
code application in such occupancies is based on the most stringent requirements.
3 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
3 FIRE RESISTANT PV MODULES
The standard IEC 61730-2 includes the fire test (MST 23) for PV modules. The characteristics assessed in the fire test
establish the fundamental fire resistance of PV modules serving either as roof covering materials or mounted onto a
building over an existing roof. These modules may be exposed to fire conditions, and therefore need to indicate their
fire-resistance characteristics when exposed to a fire source originating from outside the building on which they are
installed.
The fire resistance classes range from Class C (fundamental fire resistance), to Class B to Class A (highest fire
resistance). A minimum fire resistance rating Class C is necessary for any building-mounted module (BAPV).
Certification to a higher level may be considered in order to satisfy specific conditions and requirements.
Depending on the building class, design criteria and other relevant aspects, PV modules integrated in buildings
(BIPV) may require specific, more advanced characteristics as regards fire hazard than those tested by means of IEC
61730-2. As a rule, a minimum fire resistance rating Class A or Class B is needed.
A PV module used in place of classified roofing material or mounted to or above an existing classified roofing material
needs to comply with the following:
- Spread-of-flame test
- Burning brand test
These are based on ANSI/UL 790. Sufficient samples shall be provided to create a single test assembly for a single
spread of flame and a single burning brand test.
Products that comply with these tests are not easily flammable, afford the measurable degree of fire protection to
the roof deck, do not slip from position, and are not expected to produce flying brands
The sample area of the test material should be not less than 1 m in width for all classes, 1.82 m minimum length for
the fire safety Class A, 2.4 m minimum length for the fire safety Class B, or 3.9 m minimum length for the fire safety
Class C, as measured from the leading edge of the sample.
For the safety Class A or B test, the gas flame is to be applied continuously for 10 min or until the spread flame (flaming
of the material being tested) permanently recedes from a point of maximum spread, whichever is the shorter
duration. For a safety Class C test, the gas flame is to be applied for 4 min and then removed.
During and after the application of the test flame, the test sample is to be observed for the distance to which flaming
of the material has spread, production of flaming or glowing brands, and displacement of portions of the test sample.
The observation is to continue until the flame has permanently receded from a point of maximum spread.
4 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
Figure 1 – Spread-of-flame test (LAPI laboratory)
The fire safety Class A brand is to consist of a grid, 300 mm square and approximately 57 mm thick, made of kiln-
dried Douglas fir pine lumber that is free of knots and pitch pockets. The dry weight of the finished brand is to be 2000
±150g.
The fire safety Class B brand is to consist of a grid, 150 mm square and approximately 57 mm thick, made of kiln-dried
Douglas fir pine lumber that is free of knots and pitch pockets. The dry weight of the finished brand is to be 500 ±50 g.
The fire safety Class C brand is to consist of a piece of kiln-dried non-resinous white pine lumber that is free of knots
and pitch pockets. The dry weight of the finished brand is to be 9.25 ±1.25 g.
Before application to the test deck, the brands are to be ignited so as they burn freely in still air (times and other
details depending on safety class).
Each individual tests, whether fire safety Class A, B or C, is to be continued until the brand is consumed and until all
evidence of flame, glow or smoke has disappeared from both the exposed surface of the material being tested and
the underside of the test deck.
5 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
Figure 2 – Burning brand construction
As an example, in figure 3 shows the result of a Class A burning-brand test on a PV module that
can be certified only for a Class C fire test. The PV module fails the test
6 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
Figure 3 – Example of a Class A burning-brand test – the PV module fails the test (LAPI laboratory)
The adoption of further criteria for PV module assessment is valid, in particular, in case of BIPV, where the fire
characteristics of PV modules shall fully met the design safety criteria adopted in the building’s design. As a reference
the following international and national standards give information for tests, which could be used:
- ISO 834-1, Fire-resistance tests – Elements of building construction – Part 1: General requirements
- ISO 834-3, Fire-resistance tests – Elements of building construction – Part 3: Commentary on test method and
test data application
- ISO 5657, Reaction to fire tests – Ignitability of building products using a radiant heat source
- ISO 13501-5:2005, Fire classification of construction products and building elements – Part 5: Classification using
data from external fire exposure to roofs tests
- ENV 1187-1/4: Test methods for roof coverings under the influence of a thermal attack of burning brands and
radiant heat
- ANSI/UL 790: Standard Test Methods for Fire Tests of Roof Coverings
- ANSI/UL 1703-2013, Standard for Safety for Flat-Plate Photovoltaic Modules and Panels
The EU (ENV 1187) and the US approach to PV Fire Risk Assessment (UL 1703-2013) are described briefly in the
continuation of the text.
7 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
ENV 1187
The ENV 1187 fire test methods, parts 1 to 4, differ in terms of radiant heat, the used brands, additional air flow (wind
simulation), tilt angles, amount and size of the demanded test specimen. The pass criteria for each test method are
described in EN 13501-5.
In general buildings, integrated PV systems shall be tested in conjunction with a defined mounting system following
the installation instruction of the module manufacturer. When testing PV modules, the mounting material and the
joints be
tween modules as well as sealing materials have to be considered and included in the test set-up.
UL 1703-2013
After the changes to ANSI/UL 1703 (2013 edition), the fire classification rating approach takes into account the
module or panel in combination with the mounting system and the roof covering products over which it is installed.
Research tests demonstrated that fire class rating of the PV module alone determined according to ANSI/UL 1703-
2012 may not predict the fire performance of the PV module, mounting system, and roof assembly as a system.
From a safety perspective, the objective of the work turned towards promoting stand-off-mounted PV systems
with improved performance and developing a system-based test that would differentiate high performing from
low performing designs. Thus, it was decided to pursue the development of a new fire classification test for the PV
modules, the mounting components, and the roof assembly as a system.
The new fire classification rating tests in ANSI/UL 1703-2013 involves the combination of the module or panel, the
mounting system, and the roof covering system. Because each of these three components has many products in the
marketplace, testing every possible combination of the three components could mean thousands of required tests.
8 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
4 DESIGN AND INSTALLATION CRITERIA
This is not practical and could stifle market innovation. In response, a number of considerations and provisions were
written into the new standard to reduce the number of required tests.
Basically, the installation of a PV plant on an existing building, depending on the components used and their location,
may increase the fire risk of that building. This may be a result of:
- Interferences with smoke ventilation systems (e.g. partial or total obstruction of skylights,
impediments to the opening of smoke extraction systems).
- Risk of flame propagation to external or to internal areas of the building (presence of wiring on the rooftop
of a building divided into several compartments, modification of the rapidity of fire development in a single
compartment building).
Furthermore, possible exposure of firefighters to electric-shock risk has to be considered, given the voltage present
in the daylight.
- PV modules and their interconnections placed on a roof made of non-combustible material according to ASTM
E 136 or EN 13501-3 (class A1);
- Interposition of a non-combustible layer between PV modules with their interconnections and the roof. The
non-combustible layer shall be at least one-half-hour fire-rated; and
- Preparation of a new Risk Assessment for a PV plant to be approved by UAE Civil Defence.
In case of High Hazard or Extra High Hazard buildings, a proper set of safety measures shall be adopted and a new Risk
Assessment is to be prepared for approval by the UAE Civil Defence.
9 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
4.3 Minimum distance from rooftop openings
PV modules, wirings, switchboard assemblies and other equipment shall not cover any ventilation system on the
roof, e.g. skylights, smoke extraction systems or chimneys.
In order to ensure correct operation of smoke extraction systems, PV components and wirings shall be placed at a
minimum distance of 1 m (top view) from their perimeter. The positioning of the equipment and the installation has
to be in line with manufacturer’s specifications and recommendations.
In order to avoid a sudden propagation of fire to external building areas, PV components and wirings shall be placed
at a minimum distance of 0.5 m (top view) from the perimeter of skylights, chimneys or other openings.
Components and equipment installed internally or externally shall not obstruct in any way the existing means of
egress.
Minimum elevation of the PV modules above the roof shall be 50 mm.
Figure 6 summarizes these scenarios (the manual call point is not necessary in case of One-and-Two-Family Dwelling).
The passage of cables from PV modules inside the building before the disconnector is allowed provided that inside
the building they are placed in a channel with a fire-rated protection of at least one-half-hour.
In all above mentioned buildings, except for One-and-Two-Family Dwelling, electrical disconnection shall be operated
by means of a manual call point installed at the height of 1.1 – 1.4 m above floor level and in a plain, accessible, well lit
and free of hindrance place. The manual call point shall be close to an external access in order to be easily operated
by personnel or firefighters.
The manual call point shall be in line with NFPA 72 and a proper label shall indicate that it triggers the disconnection
of the PV plant.
In case of BIPV not installed in fire compartmented areas it is necessary to adopt one of the following further
measures:
- The manual call point also disconnects or short-circuits separately each module or groups of modules each of
them having an open circuit voltage at STC not greater than 120 VDC.
- Installation of an Arc Fault Circuit Interrupter (AFCI) to protect the DC side from series arcs in accordance with
NEC Section 690.11 and UL 1699B. When AFCI detects a failure it disconnects the DC side of the PV plant and
generates an audible signal
10 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
Figure 4 – Disconnection from a manual call point in case of inverter inside the building
Figure 5 – Disconnection from a manual call point in case of inverter outside the building
11 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
Figure 6 – Possible placement of the inverter and disconnector with the manual call point (when required)
12 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
The area where PV modules, cables and other equipment is located, if accessible, shall be marked by proper signs as
indicated in Figure 8. They shall also be placed in correspondence to each PV plant access door. The same signs shall
be used to indicate cables before disconnectors and shall be placed every 5 meters along the cable.
These signs shall be UV resistant, and shall indicate the DC voltage as the Open Circuit Voltage at STC of the PV array.
Their minimum size is 200 × 200 mm (w × h).
13 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
4.6 Summary of design and installation criteria
14 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
15 Shams Dubai- PV on Buildings and Fire Safety: Recommendations for DRRG Solar PV Systems Version 1.0 – Edition 2015
Dubai Electricity & Water Authority
For generations to come