Bestway Cement Ltd. Chakwal: BOQ As Per Drawings / Actual Work Done Report

The document is a report on the fire alarm system installation work done at Bestway Cement Ltd. Chakwal. It provides details of the actual cable and conduit work, number of sensors, pull stations, sounders installed in 27 work areas. It lists the total installed, delivered, in-stock components and percentage of work completed which is around 75%.

Uploaded by

Israr Hussain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views2 pages

Bestway Cement Ltd. Chakwal: BOQ As Per Drawings / Actual Work Done Report

The document is a report on the fire alarm system installation work done at Bestway Cement Ltd. Chakwal. It provides details of the actual cable and conduit work, number of sensors, pull stations, sounders installed in 27 work areas. It lists the total installed, delivered, in-stock components and percentage of work completed which is around 75%.

Uploaded by

Israr Hussain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Bestway Cement Ltd.

Chakwal
BOQ as per Drawings / Actual Work done Report
Date: 10-05-2018

Manual
Sub Pull LHDC
Actual Cable Base Sensor Sounder LHDC
Conduit Control Station Module
S.No Work Area used Wiring installed installed + Flasher Cable
work Panel DCP- LM-519
(Mtr) (Nos.) (Nos.) (Nos.) (Mtr)
(Nos.) AMS (Nos.)
(Nos.)
1 Raw Material Grinding L-1 450 1 1 17 17 1 2 2
2 Raw Material Grinding L-2 500 1 1 17 17 1 2 2
3 Coal Mill L-1 144 1 1 11 11 1 1 1
4 Coal Mill L-2 150 1 1 11 11 1 1 1
5 Preheater L-1 200 1 1 11 11 1 1 1
6 Preheater L-2 (*) 156 1 1 12 12 1 1 1
7 Raw Mill Feeding L-1 115 1 1 7 7 1 1 1
8 Raw Mill Feeding L-2 300 1 1 1 1 0 1 1
9 Lime stone Crusher 130 1 1 8 8 1 1 1
10 Clinker Doom L-1 45 1 1 3 3 1 1 1
11 Clinker Doom L-2 45 1 1 3 3 1 1 1
12 Sack Store L-1 500 1 1 49 49 1 1 2
13 Sack Store L-2 650 1 1 39 39 1 2 2
14 Packing Plant L-1 95 1 1 5 5 1 1 1
15 Packing Plant L-2 76 1 1 5 5 1 1 1
16 Cooler L-1 252 1 1 13 13 1 1 1
17 Cooler L-2 210 1 1 15 15 1 1 1
18 Raw Mill Proportioning L-1 83 1 1 4 4 1 1 1
19 Cement Mill L-1 195 1 1 14 14 1 1 1
20 Cement Mill L-2 (*) 185 1 1 14 14 1 1 1
21 Grid Station L-1 200 1 1 10 10 1 1 1
22 Grid Station L-2 155 1 1 6 6 1 1 1
23 Main Store 175 0.8 0.8 6 6 1 1 1
24 Store Yard
25 CCR Building 1215 0.7 0.7 79
26 Admin Building 693 1 1 48 47 1 5 6
27 Despatch Office 180 1 1 10 10 1 1 1
28 Technical Gallary
29 Clinker Doom Belts L-1 900
30 Clinker Doom Belts L-2 840
31 TG Building WHRPP 540 1 1 26 26 1 4 5
TOTAL Installed 7639 27 27 444 364 25 36 39 0 1740
TOTAL DELIVERED 13400 662 662 31 64 63 4 4800
In-Stock 5761 218 298 6 28 24 4 3060
Note:
For conduit and wiring work,
1 = Work Done,
0 = Work Not Done
Fire Alarm System Installation Work Progress
120
Percentage of work Done

100

80

60

40

20