Bestway Cement Ltd. Chakwal: BOQ As Per Drawings / Actual Work Done Report
Bestway Cement Ltd. Chakwal: BOQ As Per Drawings / Actual Work Done Report
Chakwal
BOQ as per Drawings / Actual Work done Report
Date: 10-05-2018
Manual
Sub Pull LHDC
Actual Cable Base Sensor Sounder LHDC
Conduit Control Station Module
S.No Work Area used Wiring installed installed + Flasher Cable
work Panel DCP- LM-519
(Mtr) (Nos.) (Nos.) (Nos.) (Mtr)
(Nos.) AMS (Nos.)
(Nos.)
1 Raw Material Grinding L-1 450 1 1 17 17 1 2 2
2 Raw Material Grinding L-2 500 1 1 17 17 1 2 2
3 Coal Mill L-1 144 1 1 11 11 1 1 1
4 Coal Mill L-2 150 1 1 11 11 1 1 1
5 Preheater L-1 200 1 1 11 11 1 1 1
6 Preheater L-2 (*) 156 1 1 12 12 1 1 1
7 Raw Mill Feeding L-1 115 1 1 7 7 1 1 1
8 Raw Mill Feeding L-2 300 1 1 1 1 0 1 1
9 Lime stone Crusher 130 1 1 8 8 1 1 1
10 Clinker Doom L-1 45 1 1 3 3 1 1 1
11 Clinker Doom L-2 45 1 1 3 3 1 1 1
12 Sack Store L-1 500 1 1 49 49 1 1 2
13 Sack Store L-2 650 1 1 39 39 1 2 2
14 Packing Plant L-1 95 1 1 5 5 1 1 1
15 Packing Plant L-2 76 1 1 5 5 1 1 1
16 Cooler L-1 252 1 1 13 13 1 1 1
17 Cooler L-2 210 1 1 15 15 1 1 1
18 Raw Mill Proportioning L-1 83 1 1 4 4 1 1 1
19 Cement Mill L-1 195 1 1 14 14 1 1 1
20 Cement Mill L-2 (*) 185 1 1 14 14 1 1 1
21 Grid Station L-1 200 1 1 10 10 1 1 1
22 Grid Station L-2 155 1 1 6 6 1 1 1
23 Main Store 175 0.8 0.8 6 6 1 1 1
24 Store Yard
25 CCR Building 1215 0.7 0.7 79
26 Admin Building 693 1 1 48 47 1 5 6
27 Despatch Office 180 1 1 10 10 1 1 1
28 Technical Gallary
29 Clinker Doom Belts L-1 900
30 Clinker Doom Belts L-2 840
31 TG Building WHRPP 540 1 1 26 26 1 4 5
TOTAL Installed 7639 27 27 444 364 25 36 39 0 1740
TOTAL DELIVERED 13400 662 662 31 64 63 4 4800
In-Stock 5761 218 298 6 28 24 4 3060
Note:
For conduit and wiring work,
1 = Work Done,
0 = Work Not Done
Fire Alarm System Installation Work Progress
120
Percentage of work Done
100
80
60
40
20