Perhitungan Tulangan Pelat Lantai

The document discusses the calculation of reinforcement bars for floor slabs. It provides the diameter, spacing, and number of reinforcement bars running in the x and y directions for different slab areas. It then calculates the length of reinforcement bars required for the top and bottom of each slab area. This includes calculations for the distance between bar centers accounting for the concrete cover and bar diameters. A table is also included listing the total theoretical and actual lengths of reinforcement bars by type and size.

Uploaded by

Anna Dewi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views6 pages

Perhitungan Tulangan Pelat Lantai

The document discusses the calculation of reinforcement bars for floor slabs. It provides the diameter, spacing, and number of reinforcement bars running in the x and y directions for different slab areas. It then calculates the length of reinforcement bars required for the top and bottom of each slab area. This includes calculations for the distance between bar centers accounting for the concrete cover and bar diameters. A table is also included listing the total theoretical and actual lengths of reinforcement bars by type and size.

Uploaded by

Anna Dewi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

2.

3 Perhitungan Tulangan Pelat Lantai


Diameter Tulangan = 10 mm
Jarak antar tulangan sumbu x = 200 mm
Jarak antar tulangan sumbu y = 200 mm
Jumlah tulangan sumbu x area 1 = 98 tulangan x 2 tulangan = 196
Jumlah tulangan sumbu x area 2 = 36 tulangan x 2 tulangan = 72
Jumlah tulangan sumbu y area 1 = 21 tulangan x 4 tulangan = 84
Jumlah tulangan sumbu y area 2 = 21 tulangan x 2 tulangan = 42
Jumlah tulangan sumbu y area 3 = 71 tulangan x 6 tulangan = 246

2.4.1 Arah Memendek (y)


1. Tulangan Atas Lapis 1 ( Area 1 )

d sengkang = 10 mm

= Jarak as ke as – Lebar balok + 2(selimut beton + dsengkang + rtulangan balok) +


1
(2(6𝐷 + 4 𝜋(𝐷𝑝𝑒𝑛 + 2𝑑𝑠𝑒𝑛𝑔𝑘𝑎𝑛𝑔) + (80 − 𝐷𝑝𝑒𝑛 − 2𝑑𝑠𝑒𝑛𝑘𝑎𝑛𝑔) +
3
𝜋(𝐷𝑝𝑒𝑛 + 2𝑑𝑠𝑒𝑛𝑔𝑘𝑎𝑛𝑔))
8
1
= 4000 − 350 + 2(40 + 10 + 11) + (2(60 + 4 𝜋(38,1 + 20) +
3
(80 − 38,1 − 20) + 𝜋(38,1 + 20))
8

= 3650 + 122 + 391,8425


= 4163,8425 mm ≈ 4164 mm = 4,164 m

2. Tulangan Atas Lapis 1 ( Area 1 )

d sengkang = 10 mm

= Jarak as ke as – Lebar balok + 2(selimut beton + dsengkang +


3
rtulangan balok) + (2(6𝐷 + 8 𝜋(𝐷𝑝𝑒𝑛 + 2𝑑𝑠𝑒𝑛𝑔𝑘𝑎𝑛𝑔))

= 4000 − 350 + 2(40 + 10 + 11) + 2(60 + 68,4)


= 4028,8 𝑚𝑚 ≈ 4028 𝑚𝑚 = 4,028 𝑚
3. Tulangan Atas Lapis 1 ( Area 1 )

diameter tulangan = 10 mm
diameter tulangan = 10 mm

= Jarak as ke as – Lebar balok + 2(selimut beton + dsengkang +


3
rtulangan balok) + (2(6𝐷 + 8 𝜋(𝐷𝑝𝑒𝑛 + 2𝑑𝑠𝑒𝑛𝑔𝑘𝑎𝑛𝑔)) + 40D

= 8000 − 350 + 2(40 + 10 + 11) + 2(60 + 68,4) + 400


= 15428.8 𝑚𝑚 ≈ 15429 𝑚𝑚 = 15,429 𝑚
a. Tulangan a
= 12 𝑚𝑒𝑡𝑒𝑟
b. Tulangan b
= 3,429 𝑚𝑒𝑡𝑒𝑟
4. Tulangan Bawah Lapis 1 ( Area 1 )

diameter tulangan = 10 mm

diameter tulangan = 10 mm

= Jarak as ke as – Lebar balok + 2(selimut beton + dsengkang + rtulangan balok) +


1
(2(6𝐷 + 4 𝜋(𝐷𝑝𝑒𝑛 + 2𝑑𝑠𝑒𝑛𝑔𝑘𝑎𝑛𝑔) + (110 − 𝐷𝑝𝑒𝑛 − 2𝑑𝑠𝑒𝑛𝑘𝑎𝑛𝑔) +
3
𝜋(𝐷𝑝𝑒𝑛 + 2𝑑𝑠𝑒𝑛𝑔𝑘𝑎𝑛𝑔)) + 40D
8
1
= 15000 − 350 + 2(40 + 10 + 11) + (2(60 + 4 𝜋(38,1 + 20) +
3
(110 − 38,1 − 20) + 𝜋(38,1 + 20)) + 400
8
= 14772 + 2(60 + 45,6 + 51,9 + 68,4) + 400
= 15623,8 mm ≈ 15624 mm = 15,624 m
a. Tulangan a
= 11 𝑚𝑒𝑡𝑒𝑟
b. Tulangan b
= 4,624 𝑚𝑒𝑡𝑒𝑟

5. Tulangan Atas Lapis 1 ( Area 3 )

diameter tulangan = 10 mm diameter tulangan = 10 mm

diameter tulangan = 10 mm

= Jarak as ke as – Lebar balok + 2(selimut beton + dsengkang +


3
rtulangan balok) + (2(6𝐷 + 8 𝜋(𝐷𝑝𝑒𝑛 + 2𝑑𝑠𝑒𝑛𝑔𝑘𝑎𝑛𝑔)) + ( 2 x 40D )

= 30000 − 350 + 2(40 + 10 + 11) + 2(60 + 68,4) + 800


= 30828,8 𝑚𝑚 ≈ 30829 𝑚𝑚 = 30,829 𝑚
a. Tulangan a
= 12 𝑚𝑒𝑡𝑒𝑟
b. Tulangan b
= 12 𝑚𝑒𝑡𝑒𝑟
c. Tulangan c
= 6,829 𝑚𝑒𝑡𝑒𝑟

6. Tulangan Bawah Lapis 1 ( Area 3 )


diameter tulangan = 10 mm

diameter tulangan = 10 mm
diameter tulangan = 10 mm

= Jarak as ke as – Lebar balok + 2(selimut beton + dsengkang + rtulangan balok) +


1
(2(6𝐷 + 𝜋(𝐷𝑝𝑒𝑛 + 2𝑑𝑠𝑒𝑛𝑔𝑘𝑎𝑛𝑔) + (110 − 𝐷𝑝𝑒𝑛 − 2𝑑𝑠𝑒𝑛𝑘𝑎𝑛𝑔) +
4
3
𝜋(𝐷𝑝𝑒𝑛 + 2𝑑𝑠𝑒𝑛𝑔𝑘𝑎𝑛𝑔)) + ( 2 x 40D )
8
1
= 30000 − 350 + 2(40 + 10 + 11) + (2(60 + 4 𝜋(38,1 + 20) +
3
(110 − 38,1 − 20) + 𝜋(38,1 + 20)) + 800
8

= 29772 + 2(60 + 45,6 + 51,9 + 68,4) + 800


= 31023,8 mm ≈ 31024 mm = 31,024 m
a. Tulangan a
= 11 𝑚𝑒𝑡𝑒𝑟
b. Tulangan b
= 12 𝑚𝑒𝑡𝑒𝑟
c. Tulangan c
= 8,024 𝑚𝑒𝑡𝑒𝑟

2.4.2 Arah Memanjang (x)


1. Tulangan Bawah Lapis 2 ( Area 1 )
d sengkang = 10 mm
b d sengkang = 10 mm
a

a. Tulangan a

= 11 𝑚𝑒𝑡𝑒𝑟
b. Tulangan b

= 12 meter

2. Tulangan Atas Lapis 2 ( Area 1 )

d sengkang = 10 mm
b d sengkang = 10 mm
a
a. Tulangan a
= 12 meter
b. Tulangan b
= 12 meter

3. Tulangan Bawah Lapis 2 ( Area 2 )

d sengkang = 10 mm
b d sengkang = 10 mm
a

a. Tulangan a
= 11 𝑚𝑒𝑡𝑒𝑟
b. Tulangan b
= 12 meter

4. Tulangan Atas Lapis 2 ( Area 2 )


d sengkang = 10 mm
b d sengkang = 10 mm
a
a. Tulangan a
= 12 meter
b. Tulangan b
= 12 meter

Tabel Bar Bending Scheduler Tulangan Pelat Lantai

PELAT LANTAI
Diameter Total Panjang Total Panjang Bentuk & Ukuran Tulangan
No. Kode Tipe Jumlah
(mm) Teoritis (m) (m) Panjang Kait

1 016 aba 8 6,533 166 1084,478

2 017 a 8 6,467 166 1073,522

3 ab 8 7,584 510 3867,84

018 c 8 11,69 510 5961,9

3 ba 8 7,584 510 3867,84

4 ab 8 7,538 510 3844,38

019 c 8 11,69 510 5961,9

4 ba 8 7,583 510 3867,33