Resource Levelling & Smoothening
Resource Levelling & Smoothening
BY : PROF.VIRAJ PAREKH
Resource
1) Multiple Activity –
Same Resources
2) Simultaneous Activity
Availability
– Same Resources
3) Multiple Project –
Common Pool
Limited Unlimited
Resource Allocation
Deployment of Resources according to priority. When Resources are limited
and conflicting demands are made for the same type of resources, a
systematic method or the allocation of resources becomes essential.
Resource Smoothening
The total project duration is not changed, but some of the activities start
times are shifted by their available floats so that a uniform demand for the
resources is generated. However, the resources are considered to be
unlimited.
Resource Levelling
The activity start times are so rescheduled that the peak demand for a
particular resource does not cross the available limit of the resources. Thus,
the resources are considered to be limited. Total Project Duration may be
changed.
Activity Event Duration EST LST EFT LFT Total Float Resources
LFT-EST-D
A 1-2 2 0 0 2 2 0 3
B 2-3 5 2 2 7 13 6 2
C 2-4 6 2 2 8 8 0 3
D 2-5 4 2 2 6 9 3 4
E 3-6 3 7 13 16 16 6 3
F 4-6 8 8 8 16 16 0 2
G 5-7 8 6 9 16 17 3 3
H 6-8 3 16 16 19 19 0 2
I 7-8 2 16 17 19 19 1 3
J 8-9 3 19 19 22 22 0 5
Activity Event Duration EST LST EFT LFT Total Float Resources
LFT-EST-D
A 1-2 2 0 0 2 2 0 3
B 2-3 5 2 2 7 13 6 2
C 2-4 6 2 2 8 8 0 3
D 2-5 4 2 2 6 9 3 4
E 3-6 3 7 13 16 16 6 3
F 4-6 8 8 8 16 16 0 2
G 5-7 8 6 9 16 17 3 3
H 6-8 3 16 16 19 19 0 2
I 7-8 2 16 17 19 19 1 3
J 8-9 3 19 19 22 22 0 5
Activity Event Duration EST LST EFT LFT Total Float Resources
LFT-EST-D
A 1-2 2 0 0 2 2 0 3
B 2-3 5 2 2 7 13 6 2
C 2-4 6 2 2 8 8 0 3
D 2-5 4 2 2 6 9 3 4
E 3-6 3 7 13 16 16 6 3
F 4-6 8 8 8 16 16 0 2
G 5-7 8 6 9 16 17 3 3
H 6-8 3 16 16 19 19 0 2
I 7-8 2 16 17 19 19 1 3
J 8-9 3 19 19 22 22 0 5
Possible Solution – 1 with Activity B & E
Maximum Requirement from 9 to 7
9 Resources for 5 days and 7 resources for 1 day
only
Average consumption of 5 resources was for 9
days which is reduced by 7 days
Network Logic is intact
Project Duration is not changed