0% found this document useful (0 votes)
55 views

Job Planning Checklist

This document provides a checklist for job planning that includes identifying pre-shutdown activities, job tasks and procedures, post-completion activities, required parts and materials, tools and equipment needed, investigating job priority and obtaining relevant documents and forms. It also includes checking that the work order is completed correctly and progressed to the appropriate status.

Uploaded by

Esteban Sarli
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
55 views

Job Planning Checklist

This document provides a checklist for job planning that includes identifying pre-shutdown activities, job tasks and procedures, post-completion activities, required parts and materials, tools and equipment needed, investigating job priority and obtaining relevant documents and forms. It also includes checking that the work order is completed correctly and progressed to the appropriate status.

Uploaded by

Esteban Sarli
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

JOB PLANNING - CHECKLIST

Work Order Number: Procedure


_______________________________ (_) Identify pre-shutdown and job set up activities.
Work Order Description: (_) Identify sequenced job tasks and job procedure. (Use Job Planning Form)
_______________________________ (_) Identify post-completion activities.
Date Started:
Parts/Materials Identification
_______________________________
(_) Determine the parts required to do the job (Use Job Planning Form)
Planner:
(_) Determine material specification requirements (Use Job Planning Form)
_______________________________
Dept. / Area / Location: Tools/Equipment Identification
_______________________________ (_) Identify special tools to do the job, i.e., rigging, safety equipment and tools not normally in the
craftsmen’s possession. (Use Job Planning Form)
Investigation and Research (_) Identify mobile equipment needed to perform the job.
Determine priority for planning this job (1- Work Order
10). (_) Filled out completely and correctly
(_) Obtain appropriate documents and (_) Progressed to appropriate status
forms for planning: (_) In Planning: (Date) __________ (Duration) __________
(_) Work Order (_) Parts Shortage: (Date) __________ (Duration) __________
(_) Planner Field Checklist (_) Requisitions Approved.
(_) Ready for Scheduling: (Date) __________ (Duration) __________
(_) Job Planning Form (_) Sub-Work Orders required.
(_) Review job site (Field Check List) (_) Written (_) Planned
(_) Existing plan or procedure: (_) Ready: (Date) __________ (Duration) __________
(_) Preplan __________
(_) Repetitive __________ Planned Work Order Package Checklist
(_) SMP__________ (_) Work Order (_) Materials List (_) SMP
(_) JHA__________ (_) MEP/Venture Summary (_) Lead Time (_) JHA
(_) Work Order(s): (_) Permits (_) Parts Verification (_) LO/TO Sheet
(_) SDS (_) Tool List (_) QA/QC Forms
__________________________________
______________________________ (_) References: __________________________________________________
(_) Review equipment history: (_) Other: _______________________________________________________
(_) MTBF __________
(_) RCA __________ (_) Planned Work Order Package filed for future use.
(_) Noticeable Pattern(s):
__________________________________