Time Schedule On Job Training: Elemen Kompetensi April

This document outlines a time schedule for job training for Eastor Rainhard Dogma Tambunan at PLN from April to August. It includes 23 elements of competency to be covered such as the operation of a water treatment plant, desalination plant, hydrogen plant, auxiliary boiler, fuel and gas equipment, air intake and exhaust systems, cooling systems, condensate systems, feedwater systems, lubrication systems, hydraulic systems, ash removal equipment, and firefighting equipment. The schedule assigns periods throughout the months for Tambunan to receive training on the different operational systems and equipment.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
68 views

Time Schedule On Job Training: Elemen Kompetensi April

This document outlines a time schedule for job training for Eastor Rainhard Dogma Tambunan at PLN from April to August. It includes 23 elements of competency to be covered such as the operation of a water treatment plant, desalination plant, hydrogen plant, auxiliary boiler, fuel and gas equipment, air intake and exhaust systems, cooling systems, condensate systems, feedwater systems, lubrication systems, hydraulic systems, ash removal equipment, and firefighting equipment. The schedule assigns periods throughout the months for Tambunan to receive training on the different operational systems and equipment.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Nama : Eastor Rainhard Dogma Tambunan

TIME SCHEDULE ON JOB TRAINING

APRIL
NO ELEMEN KOMPETENSI 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
PLN
1 Pemahaman Proses Bisnis di Unit Induk
2 Pembahasan workplan dengan Mentor sesuai dengan KUK
3 pengoperasian Water Treatment Plant
4 pengoperasian Desalination Plant/Reverse Osmosis
5 pengoperasian hydrogen plant Coal handling Water treatment plant
MEI
5 pengoperasian hydrogen plant
6 pengoperasian peralatan pengolahan limbah
7 Pengoperasian auxiliary boiler
8 pengoperasian peralatan auxiliary steam
9 pengoperasian pemanas udara (air heater) Mill Feeder Primary system
JUNI
10 pengoperasian peralatan bahan bakar minyak dan gas
11 Pengoperasian sistim bahan bakar minyak dan gas
LEBARAN
12 Pengoperasian peralatan udara pembakaran
13 Pengoperasian peralatan gas buang Secondary system Oil system
JULI
13 Pengoperasian peralatan gas buang
14 pengoperasian soot blower
15 pengoperasian water intake
16 pengoperasian peralatan pendingin
17 pengoperasian kondenser
18 pengoperasian peralatan air condensate Cooling system Condensate system Feedwater system
AGUSTUS
18 pengoperasian peralatan air condensate
19 pengoperasian peralatan air pengisi
20 pengoperasian peralatan pelumasan
21 pengoperasian peralatan hydraulic
22 Pengoperasian peralatan pembuangan abu
23 Pengoperasian peralatan pemadam kebakaran Fly ash K3