Daily Material Report Jan 19

This document provides a daily materials report summary as of January 2, 2019 for the Haliyapur-Kudebhar Road Project. It includes details of opening and closing balances, quantities received and issued for various construction materials including cement, aggregates, reinforcement steel, oils, admixtures, and plant production outputs. Key information reported includes the current stock levels and balances remaining to be received for different items against the bill of quantities for the project.

Uploaded by

safety apco
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
61 views

Daily Material Report Jan 19

This document provides a daily materials report summary as of January 2, 2019 for the Haliyapur-Kudebhar Road Project. It includes details of opening and closing balances, quantities received and issued for various construction materials including cement, aggregates, reinforcement steel, oils, admixtures, and plant production outputs. Key information reported includes the current stock levels and balances remaining to be received for different items against the bill of quantities for the project.

Uploaded by

safety apco
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

APCO INFRATECH PVT LTD

HALIYAPUR-KUDEBHAR ROAD PROJECT,PKG:II


DAILY MATERIALS REPORT (SUMMARY) - AS ON DATE : 01/01/2019
RECEIVED ISSUED
OPENING CLOSING BALANCE TO
SL NO ITEM DESCRIPTION UOM
BALANCE TODAY THIS MONTH CUMMULITIVE TODAY THIS MONTH CUMMULITIVE BALANCE BOQ BE RECEIVE

CEMENT
1 CEMENT GR 43 OPC BAG 1,996.000 2,100.000 2,100.000 70,835.000 470.000 470.000 67,209.000 3,626.000 111060.000 40,225.000

2 CEMENT (PPC) BAG 0.000 - - 4,490.000 - - 4,490.000 - - (4,490.000)


BOULDER - - - -
1 STONE BOULDER CUM - - - - - - - - 1,313.000 1,313.000
AGGREGATE - - - -
1 AGGREGATE 10MM MT 4,001.077 29.350 29.350 30,616.467 30.365 30.365 26,616.405 4,000.062 63,850.790 33,234.323
2 AGGREGATE 20MM MT 5,787.946 175.980 175.980 31,663.159 51.627 51.627 25,750.860 5,912.299 59,201.887 27,538.728
3 AGGREGATE 40MM MT 9,298.928 - - 43,661.094 95.935 95.935 34,458.101 9,202.993 66,639.823 22,978.729
4 STONE DUST MT 19,148.819 182.290 182.290 68,087.081 154.311 154.311 48,910.283 19,176.798 107,115.455 39,028.374
5 GSB MT 26,619.626 988.026 988.026 215,746.695 1,630.480 1,630.480 189,769.523 25,977.172 248,603.850 32,857.155
6 COARSE SAND CFT 704.538 - - 98,405.588 - - 97,701.050 704.538 308,057.681 209,652.093
7 FINE SAND CFT - - - 11,336.830 - - 11,336.830 - 20,762.280 9,425.450
REINFORCEMENT STEEL - - - -
1 TMT TOR STEEL 08MM MT 36.108 - - 69.790 0.520 0.520 34.202 35.588
2 TMT TOR STEEL 10MM MT 28.301 - - 129.862 1.040 1.040 102.601 27.261
3 TMT TOR STEEL 12MM MT 10.821 - - 20.103 - - 9.282 10.821
4 TMT TOR STEEL 16MM MT 9.678 - - 16.570 - - 6.892 9.678 542.000 296.665
5 TMT TOR STEEL 20MM MT 3.119 - - 7.990 - - 4.871 3.119
6 TMT TOR STEEL 25MM MT 0.995 - - 1.020 - - 0.025 0.995
7 TMT TOR STEEL 32MM MT - - - - - - - -
TOTAL TMT TOR STEEL MT 89.022 - - 195.605 - - 120.613 87.462 542.000 296.665
MS ROUND BAR - - - -
1 MS ROUND BAR 32MM MT 25.352 - - 60.200 - - 34.848 25.352
OIL AND LUBRICANTS - - - -
1 HIGH SPEED DIESEL (HSD) LTRS 5,017.000 12,000.000 12,000.000 888,063.000 3,243.000 3,243.000 874,289.000 13,774.000 4,050,000.000 3,161,937.000
2 FURNACE OIL REGULAR LTRS - - - - - - - - 522,000.000 522,000.000
ADMIXTURE AND CHEMICALS - - - -
1 ADMIXTURE KGS 7,179.140 - - 28,137.150 - - 20,958.010 7,179.140 47,655.000 19,517.850
2 CURRING COMPOUND FOR DLC KGS - - - - - - - - 2,925.000 2,925.000
3 CURRING COMPOUND FOR PQC KGS 200.000 - - 2,200.000 - - 2,000.000 200.000 2,437.000 237.000
BITUMINOUS PRODUCT - - - -
2 BITUMEN - VG30 MT 2.952 - - 894.585 - - 891.633 2.952 1,753.000 858.415
3 BITUMEN - VG10 MT - - - 35.439 - - 35.439 - 105.623 70.184
4 EMULSION -RS1 MT - - - 4.820 - - 4.820 - 117.121 112.301
5 EMULSION -SS1 MT 2.040 15.150 15.150 161.650 - - 144.460 17.190 170.044 8.394
6 CRMB -55 MT - - - 8.012 - - 8.012 - 1218.000 1,209.988
RED BRICKS 3RD CLASS - - - -
1 RED BRICKS 3RD CLASS NOS - - - 691,704.000 - - 691,704.000 -
HUME RCC PIPE - - - -
1 RCC HUME PIPE 1200MM X 2.5 MTR NP4 NOS - - - 120.000 - - 120.000 - 148.400 28.400
-

PLANT PRODUCTION
SL NO PRODUCT NAME UOM TODAY THIS MONTH COMMULITIVE
1 GSB MT - - -
2 WMM MT 383.740 383.740 124,472.920
3 CTSB MT - - -
4 CTB MT - - -
5 DBM MT - - 19,566.430
6 OGPS MT - - 205.740
7 BC MT - - -
8 RMC M-15 PCC M3 15.500 15.500 3,046.300
9 RMC M-20 RCC M3 - - 34.000
10 RMC M-25 RCC M3 19.500 19.500 2,588.500
11 RMC M-30 RCC M3 - - 202.000
12 RMC M-35 RCC M3 - - -
13 DLC M3 - - 1,682.000
14 PQC M3 32.000 32.000 2,443.000
APCO INFRATECH PVT LTD
HALIYAPUR-KUDEBHAR ROAD PROJECT,PKG:II
DAILY MATERIALS REPORT (SUMMARY) - AS ON DATE : 02/01/2019
RECEIVED ISSUED
OPENING CLOSING BALANCE TO
SL NO ITEM DESCRIPTION UOM
BALANCE TODAY THIS MONTH CUMMULITIVE TODAY THIS MONTH CUMMULITIVE BALANCE BOQ BE RECEIVE

CEMENT
1 CEMENT GR 43 OPC BAG 3,626.000 2,792.000 4,892.000 73,627.000 282.000 752.000 67,491.000 6,136.000 111060.000 37,433.000

2 CEMENT (PPC) BAG 0.000 - - 4,490.000 - - 4,490.000 - - (4,490.000)


BOULDER - - - -
1 STONE BOULDER CUM - - - - - - - - 1,313.000 1,313.000
AGGREGATE - - - -
1 AGGREGATE 10MM MT 4,000.062 127.110 156.460 30,743.577 151.204 181.569 26,767.609 3,975.968 63,850.790 33,107.213
2 AGGREGATE 20MM MT 5,912.299 242.330 418.310 31,905.489 165.551 217.178 25,916.411 5,989.078 59,201.887 27,296.398
3 AGGREGATE 40MM MT 9,202.993 - - 43,661.094 - 95.935 34,458.101 9,202.993 66,639.823 22,978.729
4 STONE DUST MT 19,176.798 126.220 308.510 68,213.301 151.138 305.449 49,061.421 19,151.880 107,115.455 38,902.154
5 GSB MT 25,977.172 868.754 1,856.780 216,615.449 936.990 2,567.470 190,706.513 25,908.936 248,603.850 31,988.401
6 COARSE SAND CFT 704.538 - - 98,405.588 - - 97,701.050 704.538 308,057.681 209,652.093
7 FINE SAND CFT - - - 11,336.830 - - 11,336.830 - 20,762.280 9,425.450
REINFORCEMENT STEEL - - - -
1 TMT TOR STEEL 08MM MT 35.588 - - 69.790 - 0.520 34.202 35.588
2 TMT TOR STEEL 10MM MT 27.261 - - 129.862 - 1.040 102.601 27.261
3 TMT TOR STEEL 12MM MT 10.821 - - 20.103 - - 9.282 10.821
4 TMT TOR STEEL 16MM MT 9.678 - - 16.570 - - 6.892 9.678 542.000 296.665
5 TMT TOR STEEL 20MM MT 3.119 - - 7.990 - - 4.871 3.119
6 TMT TOR STEEL 25MM MT 0.995 - - 1.020 - - 0.025 0.995
7 TMT TOR STEEL 32MM MT - - - - - - - -
TOTAL TMT TOR STEEL MT 87.462 - - 195.605 - - 120.613 87.462 542.000 296.665
MS ROUND BAR - - - -
1 MS ROUND BAR 32MM MT 25.352 - - 60.200 - - 34.848 25.352
OIL AND LUBRICANTS - - - -
1 HIGH SPEED DIESEL (HSD) LTRS 13,774.000 - 12,000.000 888,063.000 3,946.000 7,189.000 878,235.000 9,828.000 4,050,000.000 3,161,937.000
2 FURNACE OIL REGULAR LTRS - - - - - - - - 522,000.000 522,000.000
ADMIXTURE AND CHEMICALS - - - -
1 ADMIXTURE KGS 7,179.140 - - 28,137.150 - - 20,958.010 7,179.140 47,655.000 19,517.850
2 CURRING COMPOUND FOR DLC KGS - - - - - - - - 2,925.000 2,925.000
3 CURRING COMPOUND FOR PQC KGS 200.000 - - 2,200.000 - - 2,000.000 200.000 2,437.000 237.000
BITUMINOUS PRODUCT - - - -
2 BITUMEN - VG30 MT 2.952 38.605 38.605 933.190 15.008 15.008 906.641 26.549 1,753.000 819.810
3 BITUMEN - VG10 MT - - - 35.439 - - 35.439 - 105.623 70.184
4 EMULSION -RS1 MT - - - 4.820 - - 4.820 - 117.121 112.301
5 EMULSION -SS1 MT 17.190 - 15.150 161.650 - - 144.460 17.190 170.044 8.394
6 CRMB -55 MT - - - 8.012 - - 8.012 - 1218.000 1,209.988
RED BRICKS 3RD CLASS - - - -
1 RED BRICKS 3RD CLASS NOS - - - 691,704.000 - - 691,704.000 -
HUME RCC PIPE - - - -
1 RCC HUME PIPE 1200MM X 2.5 MTR NP4 NOS - - - 120.000 - - 120.000 - 148.400 28.400
-

PLANT PRODUCTION
SL NO PRODUCT NAME UOM TODAY THIS MONTH COMMULITIVE
1 GSB MT - - -
2 WMM MT - 383.740 124,472.920
3 CTSB MT - - -
4 CTB MT - - -
5 DBM MT 375.190 375.190 19,941.620
6 OGPS MT - - 205.740
7 BC MT - - -
8 RMC M-15 PCC M3 25.500 41.000 3,071.800
9 RMC M-20 RCC M3 - - 34.000
10 RMC M-25 RCC M3 24.500 44.000 2,613.000
11 RMC M-30 RCC M3 - - 202.000
12 RMC M-35 RCC M3 - - -
13 DLC M3 3.000 3.000 1,685.000
14 PQC M3 - 32.000 2,443.000