Eccentric Turning
Eccentric Turning
CHAPTER NO 1
COMPANY PROFILE
1
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
COMPANY PROFILE
HISTORY
The company has long history which dates back to the year 1985, when m/s
Turner Hoare & co started it’s activity in imports and exports of traditional Indian
consumer goods. I n 1968, m/s Turner Hoare & Corporate. Took over another company,
m/s east Asiatic Corporate. and realizing market potential entered into execution of
engineering project like hydro pneumatic ash handling system, mechanical cleaning
rakes, vibroscreen travelling water screens and bagged import substitution award
twice.
The company is situated at Nashik at 180 kms. North east of Mumbai and employs
about 350 people. The constructed area is over 11000 sq meters. The company engaged in
designing and manufacturing a wide range of auto ancillary products such as
propeller shafts, clutches, UJ kits, steering joints, steering system parts, axles and
components thereof. The company is original supplier to almost all vehicles
manufacture in India.
The products are supplied as proprietary and for many of its products; the
company enjoys confidence of customers, under self-certification scheme. The
company also caters to spare parts market demands.
The unit has EOH & S management system to maintain the performance of EOH
& S and implement continual improvements. Manufacturing facilities include many CNC
2
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
machines and SPM. Inspection is carried out by latest inspection techniques & testing
equipments. The company firmly believes that the EOH & S policy and objectives
can only be achieved through the direction given by its management and the
involvement of its people. The plans now in places, which are supported by its
people, will secure a successful future for the company as for its customers.
MILESTONES OF MSL
3
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER NO 2
INTRODUCTION
4
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
INTRODUCTION
The lathe is one of the oldest machine tools and came into existence from the early tree
lathe which was then a device for rotating and machining a piece of work held between two
adjacent trees. A rope wound round the work with its one end being pulled by a man caused
the job to rotate intermittently with its further development a strip of wood called “lath” was
used to support the rope and that is how the machine came to be known as “lathe”.
This device continued to develop through centuries and in the year 1797, HENRY
MAUDSLAY an Englishman, designed the first screw cutting lathe which is the forerunner
of the present day high speed heavy duty production lathe, a machine tool which has
practically given shape to the present day civilization by building machines and industries.
Eccentric work is work that is turned off center, or not on the normal center axis. An engine
crankshaft is a good example of an eccentric workpiece. Crankshafts normally have a main
center axis, called a main journal, and offset axes, which produce the throw and the
eccentric diameters of the mechanism. An eccentric shaft may have two or more diameters
and several different center axes. The amount of eccentricity, or half of the throw, is the
linear distance that a set of center holes has been offset from the normal center axis of the
workpiece. Eccentric turning on the lathe is used for the following eccentric turning
situations. When the throw is large enough to allow all centers to located on the workpiece
at the same time. When the throw is too small allow all centers to fit into the end of a
workpiece at the same time. When the throw is largethen all centers cannot be located on
the work, or in other words, a throw larger than the largest diameter of the workpiece.
The company” MAHINDRA SONA PVT. LTD” were producing the part called flange
yoke by conventional method. For manufacturing the flange yoke they were using 5
machines
5
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
The company” MAHINDRA SONA PVT. LTD” were producing the part called
flange yoke by conventional method. For manufacturing the flange yoke they were
using 5 machines. The operations done on it are as follows:-
Cross-hole drilling
Boring
Pilot diameter turning
Bolt hole drilling
Spot facing
Bolt hole reaming
Cross hole grooving
Chamfering
Deburring
6
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
high investment and tooling cost of a CNC machine, the cutting and ideal time should be
optimize by considering the tool consumption and the non machining time cost components.
In boring and grooving the part has create more chips which is to be accomplished
effect to the tool whenever the tool life is goes decreasing. We suggest a lubrications by the
forcefully damped and also the pneumatic air gun is to be used to clean the fixture for a
improving the productivity and high quality level of product.
7
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER NO 3
NEED OF PROJECT
8
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
NEED OF PROJECT
The company has to create a challenge for whom to study the whole process
which manufactures a flange yoke 1310.We studied that the process is to be carried by
conventional machine on flange yoke 1310. The main need of project is to plan the process
in easy way for performing the operation on flange yoke 1310.which required less time and
also increasing the productivity of the company.
From these products one part of universal joints (flange yoke) was
manufactured by using conventional machines. There are nine process involved in
manufacturing of flange yoke. The process is
Cross-hole drilling
Boring
Pilot diameter turning
Bolt hole drilling
Spot facing
Bolt hole reaming
Cross hole grooving
Chamfering
Deburring
As all machines are conventional consumes more time to manufacture the part, as
cycle time of each part is increased hence it hampers productivity. Minimizing the
use of conventional machines we can increase productivity.
9
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Here comes the need of our project as decided the product should be manufactured
in minimum cycle time, so to fulfil this requirement. We have designed one or
more than fixture which helps in combining the operations i.e. in past after each
operation part has to be loaded and unloaded from one machine to another. Now
company fixture uses at chamfering machines, due to which loading & unloading
time is eliminated and suggest a machines or tool used for the pilot diameter
turning operation.
Man:-
Machine:-
Five operators deployed
Operation wise five
hence chance of individual
different machines
mistake/ error
(1310 F) flange
yoke
improvement in
quality,
productivity
Material:
Method:-
No effect.
Each of five machines & each operation has its
own process chart. Loading & unloading,
setting involved. Time consuming process.
10
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER NO 4
COMPANY
SPECIFICATIONS
11
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
COMPANY SPECIFICATIONS
As the job has freedom to move in six directions, for proper machining on it,
these all motions should be restricted. Following are some parts of fixture with their
specifications.
Above discussed specifications are taken by considering flange yoke, now some
specifications of overall fixture by considering VMC
The specifications give to height of fixture is the distance between the tool
and table of machine.
Width related specifications considering according to width of bed.
12
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER NO 5
PROJECT
SPECIFICATIONS
13
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
PROJECT SPECIFICATIONS
To accomplish the project, there are certain specifications put forward to the
company on the basis of which the project is to be designed, which are as follows,
14
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER NO 6
EXISTING
MANUFACTURING
PROCESS
15
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
2 Rough cutting
3 Finish cutting
9 chamfering
10 Deburring
12 Dispatch
16
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Operation
OperationNo.1:-
no.1:-Cross
cross Hole
hole drilling
Drilling
17
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Dispatch
METHODOLOGY
The methodology adopted for present work was as follows:
Studying the existing manufacturing process of flange yoke 1310 used in light
commercial vehicle which is the assembly for in universal joint kits and also the
propeller shafts.
Determination of process plan for flange yoke 1310 in which the fault is to be
recommended at which the time will be consumed and the increase productivity.
Types of processing causing the defect in the part:
Tool used at the CNC auto lathe machine for pilot diameter turning
operation,
Suggested design fixture for chamfering machine
Deburring equipment for removing the burr from the part
Suggest process plan for the flange yoke 1310.
ANALYSIS OF DEFECTS
Analysis of data is an important task. The production data was collected of six
months and analysis of defects was for the two processes as given below:
Tool Used At the CNC Auto Lathe Machine for Pilot Diameter Turning Operation
In pilot diameter turning process, the rejection occurred due to:
Incorrect setting up of tool on the machine,
Incorrectly ground tool angles such as rake angle, clearance angle and nose
radius,
Wear of cutting tool,
Incorrect cutting conditions such as depth of cut and feed rate,
Quality of tool.
Skilled operator is required
Prevent number of accidents.
Quality of coolant.
18
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Cost of tool.
The table 1 shows the month wise description of defectives pieces of flange yoke 1310 in
pilot diameter turning process.
19
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Table no 2: Deburring Equipment for Removing the Burr from the Part
CHAPTER NO 7
MODIFYING
MANUFACTURING
PROCESS
20
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
3 Deburring
4 Rough cutting
5 Finish cutting
10 Chamfering
12 Dispatch
21
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Dispatch
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Forging Forging
Operation No.1:- Cross Hole Drilling Operation No.1:- Cross Hole Drilling
Operation No. 2:- Rough Cutting Operation No. 2:- Rough Cutting
Operation No. 4:- Pilot Diameter Operation No. 4:- Rough Cutting
Turning
Operation No. 5:- Boring And Grooving Operation No. 5:- Finish Cutting
Operation No. 6:- Four Hole Facing Operation No. 6:- Pilot Diameter
Turning
Operation No. 7:- Four Hole Drilling Operation No. 7:- Four Hole Facing
Operation No. 8:- Four Hole Tapping Operation No. 8:- Four Hole Drilling
Operation No. 9:- Chamfering Operation No. 9:- Four Hole Tapping
Operation No. 11:- Inspection and Packing Operation No.11:- Inspection and Packing
Dispatch Dispatch
23
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER NO 8
TIME CALCULATION
ACTIVITY CHARTS
24
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
1 Job Loading 8
2 Boring 30
4 Internal Grooving 28
5 Job Unloading 2
6 Inspection 10
25
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
1 Job Loading 14
2 Rough Cut 19
3 Finish Cut 10
5 Job Unloading 7
6 Inspection 10
26
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
1 Job Loading 47
5 Job Unloading 20
6 Inspection 27
27
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Operation
Sr.No Time In Sec
1 Job Loading 3
2 Chamfering 8
3 Job Unloading 3
4 Inspection 3
28
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER NO 9
MULTIPLE ACTIVITY
CHARTS
29
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
30
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Rough Cut(19sec)
8
9
10
11
12
13
14
15
Unloading(7sec)
16
17
Job
18
19
20
21
22
Finish Cut(10)
23
Inspection(10sec)
24
25
26
27
28
29
30
Pilot Ø & Chamfering
31
32
33
34
35
36
37
38
39
31
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
32
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Unloadin Loading
g (3sec) (3sec)
Job
2
Chamfering(8sec)
3
4
Job
5
Inspection 6
(2sec) 7
8
9
33
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER NO 10
FLOW CHARTS
34
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
FLOW CHART
Flow Chart for CNC Boring and Grooving Machine
Charted By:
Date:
Boring Operation
1
Storage = Storage = 1
1
= Transport =2
35
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Charted By:
Date:
1 Rough Cut
2
Finish Cut
1 Transport
Inspection
1
1 = Operation = 3
= Inspection = 1
Storage
1 = Storage = 1
= Transport = 1
36
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
2 Transport
Summary
1
Inspection
= Operation = 1
1 Storage
= Inspection = 1
= Storage = 1
= Transport = 1
37
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Charted By:
Date:
Chamfering
1
Transport
1
Summary
1 Inspection
= Operation = 1
Storage = Inspection = 1
1
= Storage = 1
= Transport = 1
38
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER NO 11
SUGGEST FIXTURE
DESIGN
39
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
40
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Principal of Designing:
Locating principal:
The question of properly location the supporting, and clamping the work is important since the
overall accuracy is primarily dependant on the accuracy with which the work piece is consistently
located within the fixture. There must be no movement of work piece while machining locating
surface to the establishment of proper relationship between work piece and the fixture. The function
of clamping is to exert the force to press the work piece against the locating surface and holds it
there against the action of cutting force.
The fix illustrate the body is in the free space. A body in this condition has six degree of freedom;
three of those are freedoms of translations and three are freedom of rotations. Consider the possible
movements of the free body shown, with respect to the three mutually perpendicular axes ‘X-X’, ‘Y-
Y’ and ‘Z’
41
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
The locating system must in conjunction with the clamping system, completely
constrained the work piece or eliminate as many of the six degree of freedom to complete
The work piece is resting of the tree pins 1, 2, and 3 which are inserted in the base of
body of the work. The work piece cannot rotate about the axis ‘X-X’ and ‘Z-Z’ it also cannot move
down. In this way five types of motion are restricted. Two more pins 4 and 5 are inserted in a fixed
body, in a plane perpendicular to the plane containing pins 1, 2, 3. Now the work piece cannot rotate
about the 'Y-Y' axes and also cannot move towards the left. Hence the addition of pins 4 and 5
restrict the three more types of motion. Another pin 6 the second vertical faces of the fixed body
arrest one more motion thus 9 motions are restricted. The remaining motion are restricted by
clamping devices the above method of location the work piece in a fixture is called 3-2-1 principle
of "six point" location principle.
42
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
43
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Functional Layout
VMC CNC
CNC Auto
VMC Lathe
Boring
VMC And
Grooving
Boring
VMC And
Grooving Chamfering
VMC
Deburring
VMC
44
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CNC Drilling
Machine
Vertical Milling
Machine
Chamfering
Machine
Deburring
Machine
45
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER 12
MATERIAL SELECTION
46
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
MATERIAL SELECTION
Component Material
Sr. No. Requirement & Properties
Name
47
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER NO 13
CONCLUSION
CONCLUSION
48
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Labours 6 4
From our Project we conclude that, the existing process required more time for
performing the various operations on Flange Yoke 1310.It required more material handling,
more machining time, and more chances of accident and more fatigue to operator. Then we
suggest the Modifying process for improving the productivity. Reduce the material handling
time and also reduce the chances of accident in company. We suggest the design of fixture
for Chamfering operation.
We learnt from this project improving the productivity and also the various time,
quality and quantity chart for any component like as Multiple activity chart, Gantt chart,
Flow charts, Time calculation chart etc.
49
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
CHAPTER NO 14
REFERENCES
50
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
REFERENCES
P.C.Sharma,”A Text Book of Production Engineering”, S. Chand & CO., New
Delhi, 1990.
M.Selim Akturk & Selcuk Avci,”And Integrated Process Planning Approach For
CNC Machine Tools”, The International Journal Of Advance Manufacturing
Technology, London, 1996.
51
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
DETAILED
PHOTOGRAPHS
52
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
53
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
54
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
Deburring machine
55
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
56
PROCESS PLANNING APPROACH FOR FLANGE YOKE 1310 2013
57