3 X 660 MW Ghatampur Thermal Power Project, Kanpur: Ultrasonic Test Report

This 3 sentence summary provides the key details from the ultrasonic test report: The report documents ultrasonic testing performed on welds for the 3 x 660 MW GHATAMPUR Thermal Power Project in Kanpur, India, and indicates that the testing was done according to ASME section VIII division 1 appendix 12 acceptance standards using equipment operating at frequencies between 0 and 70 MHz. The results and any remarks from the ultrasonic testing are included in the report.

Uploaded by

MD AFZAL ALAM
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views

3 X 660 MW Ghatampur Thermal Power Project, Kanpur: Ultrasonic Test Report

This 3 sentence summary provides the key details from the ultrasonic test report: The report documents ultrasonic testing performed on welds for the 3 x 660 MW GHATAMPUR Thermal Power Project in Kanpur, India, and indicates that the testing was done according to ASME section VIII division 1 appendix 12 acceptance standards using equipment operating at frequencies between 0 and 70 MHz. The results and any remarks from the ultrasonic testing are included in the report.

Uploaded by

MD AFZAL ALAM
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

3 X 660 MW GHATAMPUR THERMAL POWER

PROJECT,KANPUR
BGR ENERGY SYSTEMS LIMITED Doc
ESQF-ME-023 Rev: 0
POWER PROJECTS DIVISION No.

DOC.TITLE ULTRASONIC TEST REPORT Page 1 of 1

REPORT NO: DATE:

PROJECT NAME: 3 X 660 MW GTTP,KANPUR PROJECT NO.: 0253

SUB-CONTRACTOR:

DRAWING NO: UT PROCEDURE NO.: ESQP-ME-023

ACCEPTANCE STD.: ASME:SEC-VIII DIV.01(APPENDIX 12) UT EQUIPMENT DETAILS:

JOB DESCRIPTION: COUPLANT: GREASE

SEARCH UNIT DETAILS :

SEARCH UNIT 0o 45o 60o 70o


FREQUENCY (MHz)
PRIMARY REFERENCE LEVEL (dB)

TRANSFER CORRECTION (dB)

SCANNING SENSITIVITY (dB)

CALIBRATION / RANGE( mm)

CALIBRATION / REF. BLOCK DETAILS IIW-V2 BLOCK


JOINT CONFIGURATION: MARK NO. : FILE NO-
WELDER NO. :
SIZE:
THICKNESS:
MATERIAL:
SURFACE CONDITION-
SCANNING PATTERN:
OBSERVATIONS:

RESULTS:
REMARKS :

GS- NDT BGRESL QC NUPPL