What Is Risk Management?: Dr. Zainal Arifin
What Is Risk Management?: Dr. Zainal Arifin
The origin of the word ‘risk’ is thought to be either the Arabic word risq or the
Latin word riscum (Kedar 1970).
The Arabic risq signifies ‘anything that has been given to you [by God] and from
which you draw profit’ and has connotations of a fortuitous and favorable
outcome.
The Latin riscum, however, originally referred to the challenge that a barrier reef
presents to a sailor and clearly has connotations of an equally fortuitous but
unfavorable event.
A common definition of risk – the likelihood of something undesirable happening
in a given time – is conceptually simple but difficult to apply. It provides no clues
to the overall context and how risks might be perceived. Most people think of risk
in terms of three components: something bad happening, the chances of it
happening, and the consequences if it does happen.
Typical risk parameters (Adapted from Allen 1995)
UNCERTAINTIES
Hetland (2003) believes the following assertions clarify uncertainty:
1. Risk is an implication of a phenomenon being uncertain.
2. Implications of a phenomenon being uncertain may be wanted or unwanted.
3. Uncertainties and their implications need to be understood to be managed properly.
Smith et al. (2006) suggest that risks fall in to three categories: known risks, known
unknowns and unknown unknowns.
SOURCES OF RISK
Many project management practitioners suggest the following influence the risk associated with projects:
1. Project size
2. Technology maturity (the incorporation of novel methods, techniques, materials)
3. Project structural complexity.
Figure 2.3 Financial risk timeline
Global Risks Elemental Risks
Global risks originate from sources external Elemental risks originate from sources within the project
to the project environment and although environment and are usually “controllable” within the
they are usually predictable their effect on elements of the project. The four main elemental risks are
the outcome may not always be construction/manufacture, operational, financial and
controllable within the elements of the revenue risks (Merna and Smith 1996). These types of risk
project. The four major global risks are are usually considered as controllable risks and are often
political, legal, commercial and related to the different phases of a project and mainly
environmental risks (Merna and Smith assessed at SBU and project levels.
1996). These types of risk are often
referred to as “uncontrollable risks” since
the corporate entity cannot control such
risks even though there is a high probability
of occurrence. Normally these risks are
dealt with at corporate level and often
determine whether a project will be
sanctioned.
Static Risk Dynamic Risk
1. Such circumstance is not within the reasonable control of the party affected
2. Such circumstance despite the exercise of reasonable diligence cannot be
prevented, avoided or removed by such party
3. Such event materially adversely affects the contractor to construct or
operate the facility
4. The contractor has taken all reasonable precautions in order to avoid the
effect of such event on the contractor’s ability to construct or operate the
facility
5. Such event is not the direct or indirect result of failure by the contractor to
perform any of his obligations under any of the project documents, and
6. Such party has given the other party prompt notice describing such event,
the effect thereof and the actions being taken in order to comply with this
paragraph.
Instances of Force Majeure
1. Acts of war or the public enemy whether war be declared or not
2. Public disorders, insurrections, rebellion, sabotage, riots, violent demonstrations or
vandalism
3. Explosions, fires, earthquakes, avalanche or other natural calamities
4. Strikes, lockouts, or other industrial action of workers or employees
5. Ionizing radiations or contamination by radio activity from any nu- clear fuel or nuclear
waste
6. Any order, legislation, enactment, judgments, ruling or decision made or taken by
Government or judicial authority
7. Unforeseeable unfavorable climatic or unforeseeable unsuitable ground conditions or
sub-surfaces or latent physical conditions at the site which differ materially from those
indicated in the Site Investigation Report or previously unknown physical conditions at the
site of an unusual nature which differ materially for those ordinarily encountered and
generally recognized as inherent in work of the character provided for in an agreement
8. Delays in obtaining Governmental authorizations
9. Any other event which is not within reasonable control of the party affected.
STAKEHOLDERS
If you can’t manage risk, you can’t control
it. And if you can’t control it you can’t
manage it. That means you’re just
gambling and hoping to get lucky.
(J. Hooten, Managing Partner, Arthur
Andersen & Co., 2000)