Module Management Konstruksi
Module Management Konstruksi
Manajemen
Konstruksi
Perencanaan Biaya Proyek
04
Teknik Teknik Arsitektur 12020 Endah Mustikowati, ST, MT
Abstract Kompetensi
Pendahuluan
Latihan RAB
Latihan : Perhitungan volume dan biaya proyek sederhana (Rumah tinggal)
Format dan contoh perhitungan volume pekerjaan secara detail, dapat dilihat pada halaman
berikut ini.
This cost estimating strategy is developed based on a three-step process. These steps lead to a
more accurate cost estimate by incorporating the knowledge gained during the design phase of
the project combined with knowledge from previous projects. With the adoption of this strategy,
a strategy explanation should be included in the Project Management Plan.
Intermediate Estimate
During the Planning Phase, the project requirements will be developed by the analyst and the
project manager for the customer’s review and approval and will further clarify and define the
project estimates. More details are provided to the project team to allow them to help the project
manager with project estimates. A detailed project schedule is created by the project manager to
provide duration and effort for each task, the assignment of resources for each task, and a
complete and detailed cost estimate of the project effort.
The detailed project designs are created allowing the project manager to refine some of the
project tasks and add the estimation of costs such as hardware, software, and items such as test
equipment or additional space for the project team. At this point, the initial estimates created
for the Concept Proposal can be updated or replaced to reconcile the more accurate.
Construction cost constitutes only a fraction, though a substantial fraction, of the total project cost.
However, it is the part of the cost under the control of the construction project manager. The
required levels of accuracy of construction cost estimates vary at different stages of project
development, ranging from ball park figures in the early stage to fairly reliable figures for budget
control prior to construction. Since design decisions made at the beginning stage of a project life
cycle are more tentative than those made at a later stage, the cost estimates made at the earlier
Construction cost estimates may be viewed from different perspectives because of different
institutional requirements. In spite of the many types of cost estimates used at different stages of
a project, cost estimates can best be classified into three major categories according to their
functions. A construction cost estimate serves one of the three basic functions: design, bid and
control. For establishing the financing of a project, either a design estimate or a bid estimate is
used.
For the owner or its designated design professionals, the types of cost estimates encountered run
parallel with the planning and design as follows:
* Screening estimates (or order of magnitude estimates)
* Preliminary estimates (or conceptual estimates)
PROYEK :
DIHITUNG OLEH :
TANGGAL :
III DINDING
Pasangan
1 Bata merah m2 kolom pagar tipe 1, 24 bidang, 48 kolom
1 batu lebar 0.4 tinggi 2.5 48
17 bidang, 32 kolom, lebar 0.4 tinggi 2.5
Tali air,
4 skoneng m1 Tali air pada pagar tipe-2 (77.1*2)
nat 1. 154.2
Aci sudut pada seluruh kolom
pagar tipe-1 (24), tipe-2 (13), tipe-3 (6)
2. tot.kolom(x2) x t x 4 157
total 311.2 310
m1 besi tulangan 10
1 sloof p.tipe-1perbkan 96.85
2 sloof p.tipe-1/baru 94.4
3 kolom 7*3*2.5/baru 52.5
3a. kolom tambahan kolom 17*3*0.9/perb. 45.9