Pnumatic Test Procedure R0
Pnumatic Test Procedure R0
1.0 INTRODUCTION
Abu Dhabi Oil Company (ADOC) is currently operating three offshore oilfields. These fields
are Mubarraz field, Umm Al Anbar field (referred to as AR), and Neewat Al Ghalan (referred
to as GA).
The Hydrocarbons produced from Mubarraz field are processed in Mubarraz Island (MUB),
whereas the Hydrocarbons produced from AR and GA Fields are processed at the AR site
terminal (AR) (West Mubarraz). Crude Oil from Mubarraz Oilfield along with crude oil from
West Mubarraz is stored on Mubarraz Island and is exported via a Single Point Mooring
(SPM) facility. Mubarraz Island and AR site terminals are connected by a Causeway.
ADOC intends to expand its existing facilities to increase its production targets. As part of the
Causeway project, four (4) new gas pipelines shall be laid underground in the Causeway
between Mubarraz Island, GA and the AR Site Terminal. The main objectives of these
pipelines are to transfer the excess sour gas from MUB to AR site, to supply fuel gas to new
GTGs at MUB from AR site and to increase gas injection capacity at the GA Field in future.
ADOC has awarded the EPC Contract for “EPC for Causeway Pipelines Project” to Target
Engineering Construction Co. (LLC). TARGET Engineering Construction Co. (LLC) has
subcontracted the Residual & Detailed Engineering works to Subcontractor, Amec Foster
Wheeler.
1.1 Scope
The EPC for Causeway Pipelines Project includes the Residual Engineering, Detail
Engineering, Procurement (other than free issue materials), Furnishing, Construction,
Inspection, Testing, Clean-up, Pre-commissioning and assistance for Commissioning for the
following:
The purpose of this Pneumatic procedure is to ensure that the fabricated spools threading
integrity.
For the purpose of this document, the words and expressions listed below shall have the
meanings assigned to them as follows
EPC for Causeway Pipelines Project
3.1 Definitions
3.2 Abbreviations
4.0 REFERENCES
i) Laws, Standard and Regulation of the UAE and the Emirates of Abu Dhabi
ii) ADNOC Code of Practices (ADNOC COP)
iii) Project Data Sheets and Specifications.
iv) COMPANY Engineering Specifications, Procedures and Standards
v) International codes and standards
The CONTRACTOR shall notify the COMPANY of any apparent conflict between codes and
standards and any other specifications noted herein. Resolution and/or interpretation of the
precedence shall be obtained from the COMPANY in writing before proceeding further.
In case of conflict between the various codes and standards the most stringent of the
requirements shall govern. The CONTRACTOR shall refer any such conflict and any other
matter which requires further interpretation to the attention of COMPANY and COMPANY’s
interpretation shall be final.
CONTRACTOR PROCEDURES
INTERNATIONAL STANDARDS
5.0 RESPONSIBILITIES
EPC for Causeway Pipelines Project
Project Manager together with his team is responsible for the day-to-day effective
implementation of this procedure and that all the relevant staffs are aware of their
responsibilities.
QA/QC Manager together with the QA/QC Engineer/Inspector shall ensure that the
procedure is established, and all inspection activities as mentioned relevant ITP,
Specification are carried out and recorded.
QA/QC Engineer/Inspector together with his team shall coordinate with COMPANY
representative/TPI to obtain necessary approvals and responsible for preparing all necessary
check list and documents required for carrying out activities, and responsible to prepare
Material receipt Inspection report. (MRIR)
HSE Manager together with his site based Safety Officers shall ensure the necessary work
permit is ready for the specified work and currently available at the location and safety
measures as identified are in place and followed.
Test Engineer: He is responsible for performing the hydro test as per the project specification
and line list, will be reporting Construction Manager at site. Also ensures that the particular
package is released from QA/QC department in all respect. Ensures that all the equipment
is arranged well before start, water filling, draining system all in place.
Air Compressor
Pressure Gauges (according to pressure requirements)
Pressure Relief Valve
Blinds
7.0 PROCEDURE
If required a test manifold shall be prepared and to be tested and certified for 110% of the
highest pneumatic test pressure. Same can be used for testing the pipe spools.
EPC for Causeway Pipelines Project
Before starting pressurization pressure gauges to fix as marked in the loop file. And all
blinds to be placed at test limit position.
Pressure to be applied in a controlled manner to avoid any surging in the line. Once
80 percent of the test pressure is reached, the rate of pressurization should be
reduced.
Once the desired test pressure is reached, the Compressor shall be stopped and to be
isolated.
After isolation of Compressor the loop under testing shall be kept for a sufficient time to
allow the Company / TPI to witness all the threaded joints and flanged joints for any
leak by applying soap solution.
Upon completion of the above test slowly depressurise the air by keeping the vent open.
Calibrated pressure gauges to be selected such that range of pressure gauge should
be 1.5 times the test pressure.
Pressure gauge shall be fixed at the pressure pump location or at the lowest position of
the test loop.
8.0 DOCUMENTATION
Piping QC Inspector responsible to prepare the Pneumatic test package and get it
approval from COMPANY, raising inspection request for the pneumatic test and
witnessing the same and provide pneumatic test certificates for each and every
package.